- CN216587972U CN216587972U CN202122341638.XU CN202122341638U CN216587972U CN 216587972 U CN216587972 U CN 216587972U CN 202122341638 U CN202122341638 U CN 202122341638U CN 216587972 U CN216587972 U CN 216587972U
- Authority
- CN
- China
- Prior art keywords
- platform
- frame
- assembly
- construction
- mounting structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model relates to the field of construction auxiliary equipment, in particular to a construction derrick installation structure, wherein a bottom platform is a structural base, a bottom inclined strut unit is fixed on the bottom platform, a frame structure is fixedly erected on the bottom inclined strut unit, a top platform is arranged at the top end of a frame assembly, and an overhauling assembly is arranged at the outer edge of the frame assembly; the hoisting assembly is hoisted and arranged inside the frame assembly through the top platform; by adopting the utility model, each modularized platform is matched with the frame type mechanism, so that the rapid erection of the construction derrick is realized, and the efficient and safe maintenance operation is ensured by arranging abundant safety and warning devices; the lifting transportation of a construction site is realized through overhead lifting equipment; overall structure is firm, and the good reliability, the installation is erect fast, improves whole efficiency of construction.
Description
Technical Field
The utility model relates to the field of construction auxiliary equipment, in particular to a construction derrick mounting structure.
Background
The inclined support of the traditional steel structure derrick not only needs to bear the inclined lifting load when a mine works, but also needs to bear the gravity load of the derrick, the inclined support is a multi-stress component, a large box-shaped section is mostly adopted, and in order to ensure the stability of a box-shaped wall plate, longitudinal and transverse reinforced rib plates are additionally arranged inside the inclined support, so that the weight of the inclined support is overlarge, the box-shaped section is a closed section, the structure is complex, the welding workload is large, and the processing and manufacturing period is long; the inclined frame is installed by adopting an integral hoisting or reverse construction mode, and the installation difficulty is high.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a derrick structure which is modularly erected, has excellent structural strength and is free from area limitation.
A construction derrick mounting structure comprises a bottom platform, a lifting platform, a bottom inclined strut unit, a frame assembly, an overhaul assembly, a top platform and a hoisting assembly;
the bottom platform is a structural base, the bottom inclined strut unit is fixed on the bottom platform, the frame assembly is fixedly erected on the bottom inclined strut unit, the top platform is arranged at the top end of the frame assembly, and the maintenance assembly is arranged at the outer edge of the frame assembly; the hoisting assembly is hoisted and arranged inside the frame assembly through the top platform;
furthermore, the frame assembly comprises an outer frame inclined frame, a cross brace connecting rod and a connecting inclined brace; the outer frame inclined frames extend upwards from the bottom inclined strut units, a plurality of cross strut connecting rods are horizontally erected between two adjacent outer frame inclined frames, and the connecting inclined struts are connected with the upper cross strut connecting rods and the lower cross strut connecting rods; the maintenance assembly is fixedly arranged on the outer frame inclined frame;
furthermore, the hoisting assembly comprises a hoisting elevator, a pulley lock catch and a traction shaft sleeve; the hoisting machine is arranged on the top platform and is connected with and drives the pulley lock catch through a rope, and the traction shaft sleeve is used for connecting the pulley lock catch and the lifting platform.
Further, the maintenance assembly comprises a climbing frame ladder and a protective net ring; the climbing frame ladder is fixedly arranged on the frame assembly, and the protective net ring is arranged on the outer side of the climbing frame ladder;
furthermore, the middle part of the outer frame inclined frame is also provided with an overhaul platform;
furthermore, a warning lamp is arranged on the top platform;
furthermore, an illuminating lamp box is arranged at the edge of the bottom platform;
furthermore, the lower end face of the bottom platform is also provided with a fixed foot support, and the bottom of the bottom inclined support unit penetrates through the bottom platform to be connected with the fixed foot support;
the utility model has the beneficial effects that:
by adopting the utility model, each modularized platform is matched with the frame type mechanism, so that the construction derrick is quickly erected, and the efficient and safe maintenance operation is ensured by arranging abundant safety and warning devices; the lifting and transportation of a construction site are realized through overhead lifting equipment; overall structure is firm, and the good reliability, the installation is erect fast, improves whole efficiency of construction.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic front view of the present invention;
FIG. 3 is an enlarged partial schematic view at A of the present invention;
FIG. 4 is an enlarged view of a portion of the present invention at B;
reference numerals: 1-bottom platform, 2-lifting platform, 3-lighting lamp box, 4-bottom inclined strut unit, 5-outer frame inclined frame, 6-cross strut connecting rod, 7-connecting inclined strut, 8-maintenance platform, 9-maintenance component, 10-top platform, 11-hoisting elevator, 12-warning lamp, 13-pulley lock catch, 14-traction shaft sleeve and 15-fixing foot strut.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Referring to fig. 1-2, a construction derrick installation structure includes a bottom platform 1, a lifting platform 2, a bottom bracing unit 4, a frame assembly, an overhaul assembly 9, a top platform 10 and a hoisting assembly;
the bottom platform 1 is a structural base, the bottom inclined strut unit 4 is fixed on the bottom platform 1, the frame assembly is fixedly erected on the bottom inclined strut unit 4, the top platform 10 is arranged at the top end of the frame assembly, and the maintenance assembly 9 is arranged at the outer edge of the frame assembly; the hoisting assembly is hoisted and arranged inside the frame assembly through the top platform 10;
further, the frame assembly comprises an outer frame inclined frame 5, a cross brace connecting rod 6 and a connecting inclined brace 7; the outer frame inclined frames 5 extend upwards from the bottom inclined strut units 4, a plurality of cross strut connecting rods are horizontally erected between two adjacent outer frame inclined frames 5, and the connecting inclined struts 7 are connected with upper and lower adjacent cross strut connecting rods 6; the maintenance assembly 9 is fixedly arranged on the outer frame inclined frame 5;
in this embodiment, frame subassembly is the derrick main part, and frame 5 is connected bracing 7 through the cooperation of stull connecting rod 6 as the skeleton of supporting usefulness, and every stull connecting rod 6 is used for accepting and is connected two sets of bracing connecting rod 7 that link, realizes a plurality of triangle steady connection structure, and every stull connecting rod 6 is used for accepting and is connected two sets of bracing connecting rod 7 that link.
Further, the hoisting assembly comprises a hoisting elevator 11, a pulley lock catch 13 and a traction shaft sleeve 14; the hoisting elevator 11 is arranged on the top platform 10, is connected with and drives the pulley lock catch 13 through a rope, and the traction shaft sleeve 14 is used for connecting the pulley lock catch 13 with the lifting platform 2;
in this embodiment, the hoisting of overhead type is adopted, and the pulley hasp 13 is cooperated to realize the maximum utilization of lifting performance, so that the integral lifting load efficiency is improved.
Further, the service assembly 9 comprises a climbing frame ladder 92 and a protective net ring 91; the climbing frame ladder 92 is fixedly arranged on the frame assembly, and the protective net ring 91 is arranged on the outer side of the climbing frame ladder 92;
furthermore, the middle part of the outer frame inclined frame 5 is also provided with an overhaul platform 8;
in this embodiment, erect maintenance platform 8 in the middle part position of derrick and can be convenient for the staff to maintain whole derrick structure, its installation position corresponds with the hoist and mount subassembly, also can further improve holistic hoist and mount and overhaul work's work efficiency.
Further, a warning light 12 is further arranged on the top platform 10; the edge of the bottom platform 1 is also provided with an illuminating lamp box 3;
in this embodiment, can play the warning effect through warning light 12 on top platform 10, the cooperation need not light colour, realizes quick information transfer to lighting lamp house 3 can assist the illumination to the frame main part and the bottom of derrick, improves night operating efficiency and security.
Further, a fixed foot support 15 is further arranged on the lower end face of the bottom platform 1, and the bottom of the bottom inclined support unit 4 penetrates through the bottom platform 1 and is connected with the fixed foot support 15;
in this embodiment, the installation angle of the fixed foot brace 15 can be adjusted to adapt to headframes of different specifications and weights, so that the bottom inclined brace unit 4 can be fixed and stabilized better, and the stability of the whole drilling is improved.
By adopting the utility model, each modularized platform is matched with the frame type mechanism, so that the construction derrick is quickly erected, and the efficient and safe maintenance operation is ensured by arranging abundant safety and warning devices; the lifting and transportation of a construction site are realized through overhead lifting equipment; overall structure is firm, and the good reliability, the installation is erect fast, improves whole efficiency of construction.
The specific embodiments described herein are merely illustrative of the spirit of the utility model. Various modifications, additions and substitutions for the described embodiments may be made by those skilled in the art without departing from the scope and spirit of the utility model as defined by the accompanying claims.
Claims (8)
1. A construction derrick mounting structure is characterized in that a bottom platform (1), a lifting platform (2), a bottom inclined strut unit (4), a frame assembly, an overhaul assembly (9), a top platform (10) and a hoisting assembly are wrapped;
the bottom platform (1) is a structural base, the bottom inclined strut unit (4) is fixed on the bottom platform (1), the frame assembly is fixedly erected on the bottom inclined strut unit (4), the top platform (10) is arranged on the top end of the frame assembly, and the maintenance assembly (9) is arranged on the outer edge of the frame assembly; the hoisting assembly is hoisted and arranged inside the frame assembly through the top platform (10).
2. A construction derrick mounting structure according to claim 1, characterised in that the frame assembly comprises an outer frame ramp (5), a cross brace connecting rod (6) and a connecting ramp (7); the outer frame inclined frames (5) extend upwards from the bottom inclined strut units (4), a plurality of cross strut connecting rods are horizontally erected between two adjacent outer frame inclined frames (5), and the connecting inclined struts (7) are connected with the upper and lower adjacent cross strut connecting rods (6); and the maintenance assembly (9) is fixedly arranged on the outer frame inclined frame (5).
3. A construction derrick mounting structure according to claim 1, characterised in that the hoisting assembly comprises a hoisting hoist (11), a pulley lock (13) and a traction sleeve (14); the hoisting hoister (11) is arranged on the top platform (10), connected with the pulley lock catch (13) through a rope and drives the pulley lock catch (13), and the traction shaft sleeve (14) is used for connecting the pulley lock catch (13) with the lifting platform (2).
4. A construction derrick mounting structure according to claim 2, characterised in that the service assembly (9) comprises a climbing frame ladder (92) and a protective netting (91); the climbing frame ladder (92) is fixedly arranged on the frame assembly, and the protective net ring (91) is arranged on the outer side of the climbing frame ladder (92).
5. A construction derrick mounting structure as claimed in claim 2, characterised in that the outer frame ramp (5) is also provided with an access platform (8) in the middle.
6. A construction derrick mounting structure according to claim 1, characterised in that a warning light (12) is also arranged on the top platform (10).
7. A construction derrick mounting structure according to claim 1, characterised in that the edge of the bottom platform (1) is also provided with a light box (3).
8. A construction derrick mounting structure according to claim 1, characterised in that the lower end surface of the bottom platform (1) is further provided with a fixed foot brace (15), and the bottom of the bottom sprag unit (4) is connected with the fixed foot brace (15) through the bottom platform (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122341638.XU CN216587972U (en) | 2021-09-27 | 2021-09-27 | Construction derrick mounting structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122341638.XU CN216587972U (en) | 2021-09-27 | 2021-09-27 | Construction derrick mounting structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216587972U true CN216587972U (en) | 2022-05-24 |
Family
ID=81637801
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202122341638.XU Active CN216587972U (en) | 2021-09-27 | 2021-09-27 | Construction derrick mounting structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216587972U (en) |
-
2021
- 2021-09-27 CN CN202122341638.XU patent/CN216587972U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201670702U (en) | Manual lifting operation equipment | |
CN101734560B (en) | High-altitude dismantling method of inside-climbing tower crane for towering structure construction | |
CN211923476U (en) | Electric hoist lifting system attached to lifting scaffold | |
CN204899274U (en) | Prefabricated concrete structure goes along with sb. to guard him frame outward | |
CN216587972U (en) | Construction derrick mounting structure | |
CN107720569A (en) | One kind is removed inner climbing crane tower and hung with masts type roofing | |
CN108466968A (en) | Firm multifunctional lifting platform | |
CN205500579U (en) | Moving die carrier for lock | |
CN210735910U (en) | Self-lifting hoisting equipment suitable for assembly type additional elevator construction | |
CN201330506Y (en) | Spreader climbing mechanism | |
CN209778122U (en) | Jacking sleeve frame for mounting standard knot | |
CN214941062U (en) | Structure for improving layering reverse order of hollow steel gallery | |
CN113494127A (en) | Construction method for layered lifting of large-span open-web corridor steel platform | |
CN211499699U (en) | Ladder-climbing type operation rack for hanging cage | |
CN113585860A (en) | Device and method for mounting and dismounting double-arm holding pole | |
CN201619965U (en) | Climbing lift | |
CN201980890U (en) | Herringbone hoisting mast for hoisting under special situation of high altitude | |
CN111170131A (en) | Installation equipment for elevator without machine room | |
CN220787874U (en) | Special tower group for wind power installation | |
RU2677507C2 (en) | Derrick-winch unit of drilling unit with built-in device for lifting tower | |
CN103225390A (en) | Hollow facade pulley guide attached-type lifting scaffold | |
CN215801098U (en) | Cable-stay bridge king-tower cable construction operation platform | |
CN214879597U (en) | Hanging and lowering device | |
CN214167047U (en) | Building elevator convenient to installation just has raising and lowering functions | |
CN218809724U (en) | Foldable vertical shaft safety maintenance platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |