CN216583923U - Movable ALC partition wall board hanging bracket capable of being used as construction operation frame - Google Patents

Movable ALC partition wall board hanging bracket capable of being used as construction operation frame Download PDF

Info

Publication number
CN216583923U
CN216583923U CN202123119744.XU CN202123119744U CN216583923U CN 216583923 U CN216583923 U CN 216583923U CN 202123119744 U CN202123119744 U CN 202123119744U CN 216583923 U CN216583923 U CN 216583923U
Authority
CN
China
Prior art keywords
chassis
scaffold
partition wall
construction
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123119744.XU
Other languages
Chinese (zh)
Inventor
桑泽优
李树文
廖丽芳
卢磊
张海龙
张洋
李强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Bureau Group Co Ltd
Original Assignee
China Construction Third Bureau Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Bureau Construction Engineering Co Ltd filed Critical China Construction Third Bureau Construction Engineering Co Ltd
Priority to CN202123119744.XU priority Critical patent/CN216583923U/en
Application granted granted Critical
Publication of CN216583923U publication Critical patent/CN216583923U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a movable ALC partition wall board hanger capable of being used as a construction operation frame, which comprises a construction frame assembly and a hanger assembly detachably mounted with the construction frame assembly, wherein the hanger assembly comprises a middle chassis, two sides of the middle chassis are respectively provided with an overturning chassis, the lower side of the middle chassis is provided with a plurality of universal wheels, the upper side of the middle chassis is provided with a winch and two vertically arranged oil cylinders, the two oil cylinders are commonly connected with a top end pulley bracket, the end part of the top end pulley bracket is provided with a first pulley, the winch is wound and connected with a steel wire rope, and one end of the steel wire rope is connected with a lifting hook through the first pulley; the partition wall is transported by the crane component, the problem of hoisting the partition plate in a special environment is solved, meanwhile, the partition plate can be installed in an auxiliary mode, the crane component can be used as a construction operation frame, and the crane component has the advantages of being movable, convenient for workers to operate and high in construction efficiency.

Description

Movable ALC partition wall board hanging bracket capable of being used as construction operation frame
Technical Field
The utility model relates to the technical field of building construction, in particular to a movable ALC partition wall board hanging bracket capable of being used as a construction operation frame.
Background
In the building construction field, the application of partition plate is more and more extensive, and partition plate has the efficiency of construction height, and the effectual advantage of shaping, but its monolithic size is big, and length is longer can't be transported through the construction elevator, and it is also inconvenient to carry through the stair.
Chinese utility model with application number CN202021098922.8 specially adapted for 2021 year 03 month 26 discloses a portable partition plate hoisting construction device, include: the quick connection frame body is erected on one side of the partition board to be installed; the hoisting mechanism is used for hoisting the partition wall, and a hoisting point of the hoisting mechanism extends out of the top of the quick connection frame body; and the counterweight mechanism is used for keeping the quick-connection frame body stable during hoisting. The partition board mounting and assembling device is simple in structure, can fully and reasonably utilize materials according to actual construction needs on site, can be manufactured and adjusted automatically at any time according to needs, is high in convenience and flexibility in mounting, dismounting and using, saves cost, and can be used for realizing the lifting of the partition board through the lifting mechanism and then mounting and constructing the partition board during construction.
Chinese utility model with application number CN201721270767.1 specially adapted to 2018, 04, 27 discloses a high and large space light partition plate hoisting frame, include: the door-shaped frame body comprises two vertical rods and a first cross rod arranged at the tops of the vertical rods; the first ends of the inclined struts are connected with the door-shaped frame body, and the second ends of the inclined struts are supported on the ground; the second cross rod is connected between the two inclined struts; the electric hoist is arranged on the second cross rod; the fixed pulley is arranged on the first cross rod; the steel wire rope penetrates through the fixed pulley, the first end of the steel wire rope is connected with the electric hoist, and the second end of the steel wire rope is connected with a lifting hook; usable lifting hook is connected the partition plate of treating the hoist and mount, and after restarting electric block slowly promoted light partition plate to being close 90 degrees, the manual work was stood on the handling frame and is lightly pushed away the board top, and the same manual work of lower extreme is supplementary, makes light partition plate accurate removal to the assigned position, later gets the lifting hook and accomplishes preliminary installation.
The defect of two above current patents lies in, can only realize hoist and mount function, and the function is comparatively single, can not remove, dismantles comparatively inconvenient with the installation, inconvenient operator operation construction.
Disclosure of Invention
The utility model aims to solve the problems in the prior art, provides a movable ALC partition board hanging bracket which can be used as a construction operation frame, solves the problem of hanging partition boards in special environments by using the hanging bracket assembly to transfer partition boards, can assist in installing partition boards, is also used as the construction operation frame, and has the advantages of being movable, convenient for workers to operate and high in construction efficiency.
In order to achieve the purpose, the utility model adopts the technical scheme that:
the utility model provides a portable ALC partition wall board gallows that can be used as construction handling frame, including the construction frame subassembly and with scaffold subassembly demountable installation's gallows subassembly, the gallows subassembly includes middle chassis, the both sides on middle chassis respectively are equipped with a upset chassis, the downside on middle chassis is equipped with a plurality of universal wheel, the upside on middle chassis is equipped with the hydro-cylinder of hoist engine and two vertical settings, two the top pulley support is connected jointly to the hydro-cylinder, the tip of top pulley support is equipped with first pulley, wire rope is connected in the hoist engine winding, and wire rope's one end process the lifting hook is connected to first pulley.
Above-mentioned scheme is with gallows subassembly and scaffold subassembly demountable installation, transfers the baffle wall with the gallows subassembly, has solved the problem of special environment partition plate handling, can assist simultaneously to carry out the partition plate installation to do the construction handling frame concurrently, have portable, make things convenient for workman's operation, advantage that the efficiency of construction is high.
Wherein, through the flexible control top pulley height of hydro-cylinder, the universal wheel is convenient for the workman to promote the partition plate gallows and remove.
Further, the scaffold subassembly includes a plurality of scaffold pole setting, a plurality of scaffold horizontal pole and a plurality of scaffold vertical cross pole, a plurality of scaffold horizontal pole and a plurality of the both ends end to end of scaffold vertical cross pole is consecutive, and scaffold horizontal pole with the both ends of scaffold vertical cross pole are all connected the scaffold pole setting. The scaffold assembly is used for facilitating standing construction of construction personnel.
Furthermore, a plurality of the bottom welding of scaffold frame pole setting has two connecting plates, be equipped with on the upset chassis with the reservation bolt hole that the connecting plate corresponds. Through can dismantle the connection with middle chassis and upset chassis and scaffold frame pole setting bottom, easy to assemble and load.
Further, the horizontal pole of scaffold frame with the vertical horizontal pole of scaffold frame is welded connection, the both ends of the horizontal pole of scaffold frame are equipped with U type draw-in groove, U type draw-in groove with the scaffold frame pole setting is run through fixedly through the bolt. The height of the transverse cross rod of the scaffold can be adjusted according to the field situation.
Further, the middle chassis is hinged with the turnover chassis through hinges, and when the middle chassis and the turnover chassis are in a flat state, bolts are inserted at the joint of the middle chassis and the turnover chassis. When the partition board hanging bracket moves, the bolts are taken down, and the two side overturning chassis are overturned and folded through the hinges.
Furthermore, two jacking supports are respectively arranged at the lower side corners of the two turnover chassis. Before the installation, adjustment top support upper portion handle makes the top support top tightly ground, improves the stability of partition plate gallows.
Furthermore, a second pulley is arranged on the middle chassis, and the steel wire rope sequentially passes through the first pulley and the second pulley and then is connected with the lifting hook. The steel wire rope led out from the winch bypasses the two pulleys to be connected with the lifting hook, so that the partition board can be conveniently lifted by controlling the winch to work.
Compared with the prior art, the utility model has the beneficial effects that:
with gallows subassembly and scaffold subassembly demountable installation, transfer the baffle wall with the gallows subassembly, solved the problem of special environment partition plate handling, can assist simultaneously to carry out the partition plate installation to do the construction handling frame concurrently, have portable, make things convenient for workman's operation, advantage that the efficiency of construction is high.
Drawings
FIG. 1 is a schematic view of a partition wall hanger of the present invention;
FIG. 2 is a schematic view of the connection between the intermediate chassis and the turnover chassis according to the present invention;
FIG. 3 is a side view of the construction rack assembly of the present invention;
fig. 4 is a top view of the inventive scaffold uprights and transverse scaffolding crossbars;
figure 5 is a top plan view of the connection of the scaffold upright and the inverted base plate of the present invention;
figure 6 is a side view of the connection of the scaffold upright to the inverted chassis of the present invention;
in the figure: 1. a middle chassis; 2. a universal wheel; 3. an oil cylinder; 4. a top pulley support; 5. a winch; 6. a first pulley; 7. a wire rope; 8. a hook; 9. turning over the chassis; 10. jacking; 11. erecting a scaffold; 12. a transverse cross bar of the scaffold; 13. longitudinal cross bars of the scaffold; 14. profiled steel sheets; 15. loose leaves; 16. and (4) bolts.
Detailed Description
The technical solutions of the present invention will be described clearly and completely with reference to the accompanying drawings, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "left", "right", "top", "bottom", "inner", "outer", "horizontal", "vertical", and the like indicate orientations or positional relationships that are based on the orientations or positional relationships shown in the drawings, and are only used for convenience in describing the present invention and simplifying the description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention.
As shown in fig. 1 to 6, a portable ALC partition wall board gallows that can be used as construction handling frame, including the construction frame subassembly and with scaffold subassembly demountable installation's gallows subassembly, the gallows subassembly includes middle chassis 1, the both sides of middle chassis 1 respectively are equipped with a upset chassis 9, the downside of middle chassis 1 is equipped with a plurality of universal wheel 2, the upside of middle chassis 1 is equipped with hoist engine 5 and two vertical setting's hydro-cylinder 3, two top pulley bracket 4 is connected jointly to hydro-cylinder 3, the tip of top pulley bracket 4 is equipped with first pulley 6, hoist engine 5 twines and connects wire rope 7, and wire rope 7's one end is passed through first pulley 6 connects lifting hook 8.
Above-mentioned scheme is with gallows subassembly and scaffold subassembly demountable installation, transfers the baffle wall with the gallows subassembly, has solved the problem of special environment partition plate handling, can assist simultaneously to carry out the partition plate installation to do the construction handling frame concurrently, have portable, make things convenient for workman's operation, advantage that the efficiency of construction is high.
Wherein, through the flexible control top pulley height of hydro-cylinder 3, universal wheel 2 is convenient for the workman to promote the partition plate gallows and remove.
Further, the scaffold subassembly includes a plurality of scaffold pole setting 11, a plurality of scaffold horizontal pole 12 and a plurality of scaffold vertical cross-bar 13, a plurality of scaffold horizontal cross-bar 12 and a plurality of the both ends of scaffold vertical cross-bar 13 are consecutive, and scaffold horizontal cross-bar 12 with the both ends of scaffold vertical cross-bar 13 are all connected scaffold pole setting 11. The scaffold assembly is used for facilitating standing construction of construction personnel.
Furthermore, a plurality of two connecting plates are welded at the bottom of the scaffold upright rod 11, and reserved bolt holes corresponding to the connecting plates are arranged on the turnover chassis 9. The middle chassis 1 and the turnover chassis 9 are detachably connected with the bottom of the scaffold upright rod 11, so that the installation and the bearing are convenient.
Further, the horizontal pole 12 of scaffold with the vertical horizontal pole 13 of scaffold is welded connection, the both ends of the horizontal pole 12 of scaffold are equipped with U type draw-in groove, U type draw-in groove with the scaffold pole setting 11 is through the bolt fixed. The height of the scaffold transverse cross bar 12 can be adjusted according to the field situation.
Further, the middle chassis 1 is hinged to the turnover chassis 9 through hinges 15, and when the middle chassis 1 and the turnover chassis 9 are in a flat state, bolts 16 are inserted into the joints of the middle chassis 1 and the turnover chassis 9. When the partition board hanging bracket moves, the bolts 16 are taken down, and the two side overturning chassis 9 is overturned and folded through the hinges 15.
Furthermore, two jacking brackets 10 are respectively arranged at the lower corners of the two turnover chassis 9. Before installation, the handle at the upper part of the jacking 10 is adjusted to enable the jacking 10 to tightly jack the ground, so that the stability of the partition board hanging bracket is improved.
Furthermore, a second pulley is arranged on the middle chassis 1, and the steel wire rope 7 sequentially passes through the first pulley 6 and the second pulley and then is connected with the lifting hook 8. The steel wire rope 7 led out from the winch 5 is connected with the lifting hook 8 by bypassing the two pulleys, so that the partition board can be conveniently lifted by controlling the winch 5 to work.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a portable ALC partition wall board gallows that can be used as construction handling frame, its characterized in that, including the construction frame subassembly and with scaffold subassembly demountable installation's gallows subassembly, the gallows subassembly includes middle chassis, the both sides on middle chassis respectively are equipped with a upset chassis, the downside on middle chassis is equipped with a plurality of universal wheel, the upside on middle chassis is equipped with the hydro-cylinder of hoist engine and two vertical settings, two the top pulley support is connected jointly to the hydro-cylinder, the tip of top pulley support is equipped with first pulley, wire rope is connected in the hoist engine winding, and wire rope's one end process the lifting hook is connected to first pulley.
2. The mobile ALC partition wall hanging bracket of claim 1, wherein the construction rack assembly comprises a plurality of scaffold uprights, a plurality of scaffold transverse crossbars and a plurality of scaffold longitudinal crossbars, wherein a plurality of scaffold transverse crossbars are connected end to end with the ends of a plurality of scaffold longitudinal crossbars, and wherein the ends of the scaffold transverse crossbars and the scaffold longitudinal crossbars are connected to the scaffold uprights.
3. The mobile ALC partition wall board hanging bracket as claimed in claim 2, characterized in that two connecting plates are welded to the bottom of several said scaffold upright stanchions, and the turning chassis is equipped with corresponding reserved bolt holes connected with said connecting plates.
4. The mobile ALC partition wall hanging bracket as claimed in claim 2, characterized in that the horizontal cross-bar and the vertical cross-bar are welded, and the two ends of the horizontal cross-bar are equipped with U-shaped slots, and the U-shaped slots are fixed with the vertical rods by bolts.
5. The mobile ALC partition wall board hanging bracket capable of being used as a construction operation frame of claim 1, characterized in that the middle chassis is hinged with the turnover chassis through hinges, and when the middle chassis and the turnover chassis are in a flat state, bolts are inserted at the connection of the middle chassis and the turnover chassis.
6. The mobile ALC partition wall panel hanger useful as a construction handling frame of claim 1, wherein two jacking legs are provided at each of the lower corners of the two tilt-out chassis.
7. The mobile ALC partition wall hanging bracket as recited in claim 1, characterized in that said intermediate chassis is equipped with a second pulley, and said wire rope passes through said first pulley and said second pulley in turn and then connects to said hook.
CN202123119744.XU 2021-12-13 2021-12-13 Movable ALC partition wall board hanging bracket capable of being used as construction operation frame Active CN216583923U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123119744.XU CN216583923U (en) 2021-12-13 2021-12-13 Movable ALC partition wall board hanging bracket capable of being used as construction operation frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123119744.XU CN216583923U (en) 2021-12-13 2021-12-13 Movable ALC partition wall board hanging bracket capable of being used as construction operation frame

Publications (1)

Publication Number Publication Date
CN216583923U true CN216583923U (en) 2022-05-24

Family

ID=81612454

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123119744.XU Active CN216583923U (en) 2021-12-13 2021-12-13 Movable ALC partition wall board hanging bracket capable of being used as construction operation frame

Country Status (1)

Country Link
CN (1) CN216583923U (en)

Similar Documents

Publication Publication Date Title
CN212689520U (en) Quick butt-joint type operation platform
CA2143813A1 (en) Lifting scaffold
CN210636796U (en) High-rise elevator shaft jacking formwork system
CN216583923U (en) Movable ALC partition wall board hanging bracket capable of being used as construction operation frame
CN212201223U (en) Vertically lifting large-span multi-group multi-layer bridge type lifting platform truss system
CN213418531U (en) Supporting and adjusting device for connecting steel members with prefabricated wall panels
CN213923863U (en) Indoor mobilizable piece together formula lifts by crane instrument
CN216971830U (en) A hoist device for ALC partition plate
CN217128907U (en) Scaffold frame for building engineering construction convenient to material loading
JP3841242B2 (en) Elevator parking elevating work table and construction method using it
CN220432195U (en) Ladder type device for dismounting anti-falling device of elevator
CN205777434U (en) A kind of hoistway operation rack device
CN218507434U (en) Assembled component hoisting device
CN216264199U (en) A safe operation panel for steel sheet wall vertical welding seam welding
CN216638734U (en) Lifting appliance for bridge anti-net-throwing construction
CN218434631U (en) Can dismantle self-control crane that can remove
CN218521644U (en) Movable and height-adjustable steel arch suspender connecting construction device
CN217924769U (en) Novel simple scaffold lifting platform
CN219469634U (en) Simple and easy convenient many pipe fittings automatic lifting device
CN217867701U (en) A auxiliary device for installation of ALC slat
CN217458499U (en) Movable lifting machine
CN212336763U (en) Curtain wall installation guide rail device fixed on roof flower frame beam
CN214364852U (en) Integrated device for mounting steel jacking structure of high and large concrete column
CN218667143U (en) Bridge pier column reinforcing bar installation auxiliary stand
CN214935404U (en) Device for hoisting skylight keel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant