CN217128907U - Scaffold frame for building engineering construction convenient to material loading - Google Patents

Scaffold frame for building engineering construction convenient to material loading Download PDF

Info

Publication number
CN217128907U
CN217128907U CN202220954632.1U CN202220954632U CN217128907U CN 217128907 U CN217128907 U CN 217128907U CN 202220954632 U CN202220954632 U CN 202220954632U CN 217128907 U CN217128907 U CN 217128907U
Authority
CN
China
Prior art keywords
scaffold
platform
fixedly connected
winch
engineering construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220954632.1U
Other languages
Chinese (zh)
Inventor
杨卓君
庞楷晔
杨桐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Bureau Northwest Construction Co ltd
First Construction Co ltd Of China Construction Sixth Engineering Bureau
Original Assignee
China Construction Sixth Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Installation Engineering Co Ltd filed Critical China Construction Sixth Installation Engineering Co Ltd
Priority to CN202220954632.1U priority Critical patent/CN217128907U/en
Application granted granted Critical
Publication of CN217128907U publication Critical patent/CN217128907U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a construction technical field specifically is a scaffold frame for building engineering construction convenient to material loading, which comprises a column, fixedly connected with crossbeam between the stand, the universal wheel is installed to the bottom of stand, fixedly connected with support frame between the stand. The utility model has the advantages that: the winch has the advantages that the maximum load bearing capacity is kilogram, most of materials can be hooked up to be lifted, feeding of workers is assisted, manpower is greatly saved, further, the installation stability of the winch is improved through the arrangement of the jacking columns, the installation beams, the platform and the support plates, the support plates provide powerful support for the platform below, and the winch can work stably; the top of shelf bears the weight balancing piece for this scaffold frame focus when the hoist engine promotes the heavy object remains stable, and the position of balancing piece can be adjusted, and the balancing piece is placed on lower shelf, conveniently places, can prevent effectively that this scaffold frame from empting, the shakiness.

Description

Scaffold frame for building engineering construction convenient to material loading
Technical Field
The utility model relates to a construction technical field, especially a scaffold frame for building engineering construction convenient to material loading.
Background
The scaffold is a working platform which is erected for ensuring that each construction process is smoothly carried out. The scaffold is divided into an outer scaffold and an inner scaffold according to the erected positions; the scaffold can be divided into a wood scaffold, a bamboo scaffold and a steel pipe scaffold according to different materials; the scaffold is divided into a vertical rod type scaffold, a bridge type scaffold, a door type scaffold, a suspension type scaffold, a hanging type scaffold, a lifting type scaffold and a climbing type scaffold according to the structural form. The mobile scaffold refers to various supports erected on a construction site for workers to operate and solve vertical and horizontal transportation. The movable scaffold has the characteristics of simple assembly and disassembly, good bearing performance, safe and reliable use and the like, the development speed is high, the movable scaffold is developed earliest in various novel scaffolds, and the use amount is the largest. The mobile scaffold is firstly developed and succeeded by the United states, and the mobile scaffold is successively applied and developed in Europe, Japan and other countries by the early 60 s. The scaffold is introduced and used from the countries of Japan, America, UK and the like in the beginning of the 70 s in China. The movable scaffold mainly comprises a main frame, a transverse frame, cross inclined struts, scaffold boards, an adjustable base and the like. The cross pull rod is also called a diagonal pull rod and is a cross pull rod for longitudinally connecting two auxiliary door frames. The two ends of the rod piece are punched with pin holes, and the pin holes are firmly locked with the lock pins on the vertical rod of the door frame during assembly. The effect of scaffold frame is exactly to make the workman be under construction at the eminence, and this has just led to being inconvenient at the required material loading of the construction of height, and although there is the structure of installing the hoist engine on scaffold frame now, scaffold frame generally is lighter, and the hoist engine installation is firm inadequately, and when the hoist engine hung the heavy object, scaffold frame was easy unstable.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to overcome prior art's shortcoming, provide a scaffold frame for building engineering construction convenient to material loading.
The purpose of the utility model is realized through the following technical scheme: a scaffold convenient for loading for building engineering construction comprises upright posts, wherein cross beams are fixedly connected between the upright posts, universal wheels are mounted at the bottoms of the upright posts, and a support frame is fixedly connected between the upright posts;
a shelf is fixedly connected between the two upright columns, the top of the shelf bears a balancing weight, the tops of the other two upright columns are fixedly connected with a top column, the top of the top column is fixedly connected with an installation beam, one end of the installation beam is fixedly connected with a platform, and a support plate is fixedly connected between one side of one of the upright columns and the bottom of the platform;
the top of the platform is provided with a winch, a reel of the winch is wound with a steel wire rope, and the bottom end of the steel wire rope is movably connected with a hook;
the top of the cross beam is lapped with a scaffold board.
Optionally, the support frame is integrally in an X shape, and the shelf is integrally in a U shape.
Optionally, the welding between shelf and the stand, the bottom of shelf is located five centimetres of ground top department, and this scaffold frame focus remains stable when the hoist engine promotes the heavy object, and the position of balancing weight can be adjusted, and the balancing weight is placed on lower shelf, conveniently places, can prevent effectively that this scaffold frame from empting, the shakiness.
Optionally, the top pillar, the upright column, the mounting beam, the platform and the support plate are of an integrated structure, and the platform is located on one side of the top of the upright column.
Optionally, the platform is located above the scaffold board, and the platform is provided with a through groove.
Optionally, an operating handle is integrated on the winch, the maximum bearing capacity of the winch is five hundred kilograms, most materials can be hooked up to be lifted, feeding of workers is assisted, and manpower is greatly saved.
Optionally, the scaffold board is in lap joint with the cross beam through the lap rings on the two sides, so that the scaffold is assembled and is convenient to disassemble and assemble.
The utility model has the advantages of it is following:
1. this scaffold frame for building engineering construction convenient to material loading, the integration has a hoist engine on this scaffold frame's the stand, specifically be at the top fixedly connected with fore-set of stand, the top fixedly connected with installation roof beam of fore-set, the one end fixedly connected with platform of installation roof beam, fixedly connected with extension board between one side of one of them stand and the bottom of platform, the hoist engine is installed at the top of platform, the winding has wire rope on the spool of hoist engine, wire rope's bottom swing joint has the hook, the biggest bearing of this hoist engine is the kilogram, can hook most material and promote, supplementary workman's material loading, the manpower has been saved greatly, and is further, through the fore-set, the installation roof beam, the setting of platform and extension board, the stationarity of hoist engine installation has been improved, the extension board gives the platform powerful support in the below, make this hoist engine structure can the steady work.
2. This scaffold frame for building engineering construction convenient to material loading, this scaffold frame are reliable and stable from hoist engine structure work in area, specifically are fixedly connected with shelf between the stand, and the balancing weight is born the weight of at the top of shelf for this scaffold frame is when the hoist engine promotes the heavy object focus remain stable, and the position of balancing weight can be adjusted, and the balancing weight is placed on lower shelf, conveniently places, can prevent effectively that this scaffold frame from empting, the shakiness.
Drawings
Fig. 1 is a schematic structural view of a first viewing angle of the present invention;
fig. 2 is a schematic structural view of a second viewing angle of the present invention;
fig. 3 is an enlarged schematic view of a portion a in fig. 2 according to the present invention.
In the figure: 1-upright column, 2-cross beam, 3-universal wheel, 4-support frame, 5-shelf, 6-counterweight block, 7-top column, 8-mounting beam, 9-platform, 10-support plate, 11-winch, 12-steel wire rope, 13-hook and 14-scaffold plate.
Detailed Description
The invention will be further described with reference to the accompanying drawings, but the scope of the invention is not limited to the following description.
As shown in fig. 1-3, a scaffold for building engineering construction convenient for loading comprises upright posts 1, cross beams 2 fixedly connected between the upright posts 1, universal wheels 3 mounted at the bottom of the upright posts 1, and support frames 4 fixedly connected between the upright posts 1;
a shelf 5 is fixedly connected between the two upright posts 1, the top of the shelf 5 is loaded with a balancing weight 6, the tops of the other two upright posts 1 are fixedly connected with a top post 7, the top of the top post 7 is fixedly connected with an installation beam 8, one end of the installation beam 8 is fixedly connected with a platform 9, and a support plate 10 is fixedly connected between one side of one upright post 1 and the bottom of the platform 9;
a winch 11 is installed at the top of the platform 9, a steel wire rope 12 is wound on a reel of the winch 11, and a hook 13 is movably connected to the bottom end of the steel wire rope 12;
the top of the beam 2 is lapped with a scaffold board 14.
As an optimal technical solution of the utility model: the support frame 4 is integrally in an X shape, the shelf 5 is integrally in a U shape, the shelf 5 and the upright post 1 are welded, the bottom of the shelf 5 is positioned at five centimeters above the ground, the gravity center of the scaffold is kept stable when the winch 11 lifts a heavy object, the position of the balancing weight 6 can be adjusted, the balancing weight 6 is placed on the lower shelf 5, the scaffold is convenient to place, and the scaffold can be effectively prevented from toppling and being unstable;
the support pillar 7, the upright post 1, the mounting beam 8, the platform 9 and the support plate 10 are of an integral structure, the platform 9 is located on one side of the top of the upright post 1, the platform 9 is located above the scaffold plate 14, a through groove is formed in the platform 9, an operating handle is integrated on the winch 11, the maximum bearing capacity of the winch 11 is five hundred kilograms, most of materials can be hooked up to be lifted, feeding of workers is assisted, and manpower is greatly saved;
the scaffold board 14 is lapped with the cross beam 2 through the lapping rings on two sides, so that the scaffold is assembled and is convenient to disassemble and assemble.
Example 1: the balancing weight 6 can be divided into a plurality of blocks to be stacked and placed, and each block is set to be 25 kilograms, so that manual stacking is facilitated, and labor is saved.
Example 2: the position of the balancing weight 6 can be adjusted, so that the center of gravity of the scaffold is more stable.
The working process of the utility model is as follows:
s1, moving the scaffold to a using position, braking the universal wheels 3 and building the scaffold board 15;
s2, standing on the scaffold board 15 for construction by workers, and placing the balancing weight 6 on the shelf 5 when feeding materials;
s3, controlling the winch 11 through the handle of the winch 11, hooking the material by the hook 14 to wind the steel wire rope 12, driving the material to ascend by the hook 14, and manually taking down the material on the hook 14 on the scaffold board 15.
In conclusion, when the scaffold convenient for loading in constructional engineering construction is used, a winch 11 is integrated on the upright post 1 of the scaffold, specifically, the top of the upright post 1 is fixedly connected with a top post 7, the top of the top post 7 is fixedly connected with a mounting beam 8, one end of the mounting beam 8 is fixedly connected with a platform 9, a support plate 10 is fixedly connected between one side of one upright post 1 and the bottom of the platform 9, the top of the platform 9 is provided with the winch 11, a steel wire rope 12 is wound on a reel of the winch 11, and the bottom end of the steel wire rope 12 is movably connected with a hook 13, the winch 11 has a maximum bearing capacity of 500 kilograms, can hook up most of materials to lift, assists workers in loading, greatly saves manpower, further, improves the installation stability of the winch 11 through the arrangement of the top post 7, the mounting beam 8, the platform 9 and the support plate 10, and the support plate 10 provides powerful support for the platform 9 below, the structure of the winch 11 can work stably; this scaffold puts up 11 structure work from hoist engine in area is reliable and stable, specifically is fixedly connected with shelf 5 between stand 1, and the balancing weight 6 is born the weight of at the top of shelf 5 for this scaffold puts up the focus when hoist engine 11 promotes the heavy object and remains stable, and the position of balancing weight 6 can be adjusted, and balancing weight 6 is placed on lower shelf 5, conveniently places, can prevent effectively that this scaffold from empting, the unstability.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a scaffold frame for building engineering construction convenient to material loading which characterized in that: the device comprises upright columns (1), wherein cross beams (2) are fixedly connected between the upright columns (1), universal wheels (3) are mounted at the bottoms of the upright columns (1), and supporting frames (4) are fixedly connected between the upright columns (1);
a shelf (5) is fixedly connected between the two upright posts (1), the top of the shelf (5) is loaded with a balancing weight (6), the tops of the other two upright posts (1) are fixedly connected with ejection posts (7), the top of each ejection post (7) is fixedly connected with an installation beam (8), one end of each installation beam (8) is fixedly connected with a platform (9), and a support plate (10) is fixedly connected between one side of one upright post (1) and the bottom of the platform (9);
a winch (11) is installed at the top of the platform (9), a steel wire rope (12) is wound on a reel of the winch (11), and a hook (13) is movably connected to the bottom end of the steel wire rope (12);
the top of the cross beam (2) is lapped with a scaffold board (14).
2. The scaffold convenient for building engineering construction loading of claim 1, wherein: the support frame (4) is integrally X-shaped, and the shelf (5) is integrally U-shaped.
3. The scaffold convenient to material loading for building engineering construction of claim 1, characterized in that: the shelf (5) is welded with the upright post (1), and the bottom of the shelf (5) is positioned at the top five centimeters of the ground.
4. The scaffold convenient to material loading for building engineering construction of claim 1, characterized in that: the support column (7), the upright column (1), the mounting beam (8), the platform (9) and the support plate (10) are of an integral structure, and the platform (9) is located on one side of the top of the upright column (1).
5. The scaffold convenient to material loading for building engineering construction of claim 1, characterized in that: the platform (9) is located above the scaffold board (14), and a through groove is formed in the platform (9).
6. The scaffold convenient to material loading for building engineering construction of claim 1, characterized in that: an operating handle is integrated on the winch (11), and the maximum bearing capacity of the winch (11) is five hundred kilograms.
7. The scaffold convenient to material loading for building engineering construction of claim 1, characterized in that: the scaffold board (14) is lapped with the cross beam (2) through lapping rings on two sides.
CN202220954632.1U 2022-04-24 2022-04-24 Scaffold frame for building engineering construction convenient to material loading Active CN217128907U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220954632.1U CN217128907U (en) 2022-04-24 2022-04-24 Scaffold frame for building engineering construction convenient to material loading

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220954632.1U CN217128907U (en) 2022-04-24 2022-04-24 Scaffold frame for building engineering construction convenient to material loading

Publications (1)

Publication Number Publication Date
CN217128907U true CN217128907U (en) 2022-08-05

Family

ID=82649001

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220954632.1U Active CN217128907U (en) 2022-04-24 2022-04-24 Scaffold frame for building engineering construction convenient to material loading

Country Status (1)

Country Link
CN (1) CN217128907U (en)

Similar Documents

Publication Publication Date Title
CN110616891A (en) Lift truck operated stacking template table system and method of operation thereof
CN212689520U (en) Quick butt-joint type operation platform
CN111502215A (en) Movable scaffold
CN215441501U (en) Cantilever steel structure combined construction hanging basket
CN216587766U (en) Hoisting facility and hoisting structure of large-span overhanging steel structural member
CN212957538U (en) Roof flower frame beam and outer wall decoration construction movable operation platform
CN217128907U (en) Scaffold frame for building engineering construction convenient to material loading
CN110847031A (en) Movable hanging basket for bridge construction
CN112573341B (en) Column top hoisting mechanism and construction method thereof
CN213865193U (en) Lifting device for small and medium-sized equipment
CN213204913U (en) Modular prefabricated staircase operation platform
CN210438301U (en) Light slat lifting device for building partition wall
CN217458499U (en) Movable lifting machine
CN217299872U (en) Shaft hydraulic comprehensive distribution platform
CN217867701U (en) A auxiliary device for installation of ALC slat
CN213294440U (en) Lifting device for integral frame of upright post and roof girder
CN214989751U (en) Combined small-sized portal frame
CN220485176U (en) Hoisting device without counterweight
CN209975990U (en) Scaffold convenient to set up and encorbelment that road engineering construction used
CN217461400U (en) Large-span steel beam mounting cantilever frame
CN220014395U (en) Can have enough to meet need mounting bracket by intelligent integrated platform system bailey frame of equipping
CN218290156U (en) Lifting device for lifting auxiliary unit plate from interlayer position
CN217921335U (en) A device of taking one's place fast back to steel-pipe column for basement roof is consolidated
CN212270670U (en) Movable hanging basket for bridge construction
CN211622697U (en) Anti-falling device for building construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.

Address before: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd.

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: The First Construction Co.,Ltd. of China Construction Sixth Engineering Bureau

Address before: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee before: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.