CN216516853U - Cast-in-place structure reserves tenon fourth of twelve earthly branches and decorates roof beam construction equipment - Google Patents
Cast-in-place structure reserves tenon fourth of twelve earthly branches and decorates roof beam construction equipment Download PDFInfo
- Publication number
- CN216516853U CN216516853U CN202123222923.6U CN202123222923U CN216516853U CN 216516853 U CN216516853 U CN 216516853U CN 202123222923 U CN202123222923 U CN 202123222923U CN 216516853 U CN216516853 U CN 216516853U
- Authority
- CN
- China
- Prior art keywords
- support plate
- mortise
- tenon
- support
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及混凝土砼浇筑的技术领域,尤其涉及一种现浇结构预留榫卯装饰梁施工装置。The utility model relates to the technical field of concrete pouring, in particular to a construction device for a cast-in-place structure reserved tenon and mortise decorative beam.
背景技术Background technique
预制装配式剪力墙结构是一种现代化的建筑结构模式,与传统的混泥土建筑方式不同的是,这种建筑采用组装的方式,水耗、能耗相对较少,不会产生固体废物垃圾、污水等污染。同时,这种建筑方式还有助于实现住宅产业化,有利于建筑节能节排。采用装配式结构,主要是通过厂商预定、现场组装的方式来完成建筑的主体结构,在一些施工条件不好的地带有着良好的适应性。The prefabricated shear wall structure is a modern building structure model. Different from the traditional concrete building method, this building adopts the assembly method, which consumes relatively less water and energy, and does not generate solid waste. , sewage and other pollution. At the same time, this construction method is also conducive to the realization of residential industrialization, which is conducive to building energy conservation and emission reduction. The prefabricated structure is mainly used to complete the main structure of the building by pre-ordering and on-site assembly. It has good adaptability in some areas with poor construction conditions.
随着建筑施工工艺的不断优化,采用铝膜、爬架施工工艺,装饰梁往往不在建筑物最上端,施工过程爬架需要提升,故未能与楼层主体结构一次成型。With the continuous optimization of building construction technology, the use of aluminum film and climbing frame construction technology, the decorative beam is often not at the top of the building, and the climbing frame needs to be lifted during the construction process, so it cannot be formed at one time with the main floor structure.
在现有技术中,如中国发明专利“CN201911338756.6”公开的基于榫卯结构的装配式混凝土剪力墙连接方法,使用了榫卯式连接结构保证装饰梁的连接便捷性和稳定性。In the prior art, as disclosed in the Chinese invention patent "CN201911338756.6", the mortise-and-mortise structure-based prefabricated concrete shear wall connection method uses the mortise-and-mortise joint structure to ensure the convenience and stability of the connection of the decorative beams.
然而,现有的榫卯结构一般是使用套筒进行浇筑得到,不利于装配式预制施工,且为一次性结构,无法进行循环利用,因此,需要设置一种可循环利用的榫卯装饰梁施工装置,方便装饰梁与剪力墙之间的连接。However, the existing tenon-and-mortise structure is generally obtained by casting using a sleeve, which is not conducive to prefabricated construction, and is a one-time structure that cannot be recycled. Therefore, a recyclable tenon-and-mortise decorative beam construction is required. The device facilitates the connection between the decorative beam and the shear wall.
实用新型内容Utility model content
针对现有剪力墙与装饰梁进行榫卯结构连接时存在的不利于装配式施工和循环利用性差的技术问题,本实用新型提出一种现浇结构预留榫卯装饰梁施工装置,通过第一支撑板和第二支撑板组成中空四面体结构,用于在剪力墙模板的缺口处即预留榫卯连接处对上下左右四个方向进行支撑,将浇筑支撑组件设置剪力墙浇筑模板与预留榫卯连接处之间,保证剪力墙浇筑时,混凝土不会流入预留榫卯连接处,在剪力墙浇筑完成后,通过张紧拉伸机构拉动第一支撑板,使第一支撑板与剪力墙混凝土结构相分离,使用移动支撑机构带动第二支撑板与剪力墙混凝土结构相分离,最后在第一支撑板和第二支撑板的带动下使得浇筑支撑组件与剪力墙混凝土结构相分离,实现预留榫卯装饰梁施工装置的拆卸,方便下次使用,循环再利用性好,且浇筑完成的榫卯结构方便预制装饰梁的安装和浇筑。Aiming at the technical problems that the existing shear wall and the decorative beam are connected by the tenon and mortise structure, which is not conducive to the prefabricated construction and the poor recycling, the utility model proposes a cast-in-place structure reserved tenon and mortise decorative beam construction device. A support plate and a second support plate form a hollow tetrahedron structure, which is used to support the four directions of up, down, left and right at the gap of the shear wall formwork, that is, the reserved tenon and mortise joint, and set the pouring support component to the shear wall pouring formwork Between the reserved mortise and tenon joints, ensure that the concrete will not flow into the reserved mortise and tenon joints when the shear wall is poured. A support plate is separated from the shear wall concrete structure, the second support plate is driven to separate from the shear wall concrete structure by the moving support mechanism, and finally the pouring support assembly and the shear wall are driven by the first support plate and the second support plate. The concrete structure of the force wall is separated from each other, realizing the disassembly of the reserved mortise-and-mortise decorative beam construction device, which is convenient for the next use, and has good recycling and reuse.
为了达到上述目的,本实用新型的技术方案是这样实现的:In order to achieve the above object, the technical scheme of the present utility model is achieved in this way:
一种现浇结构预留榫卯装饰梁施工装置,安装在剪力墙浇筑模板的装饰梁榫卯连接处,包括第一支撑板,第一支撑板通过可拆卸组件与第二支撑板相连接,第一支撑板分别位于榫卯连接处的上下两侧,第二支撑板位于榫卯连接处的左右两侧,第二支撑板之间通过移动支撑机构相连接,相邻的第一支撑板和第二支撑板之间通过张紧拉伸机构相连接,第一支撑板和第二支撑板的同一侧设置有浇筑支撑组件,浇筑支撑组件与剪力墙浇筑模板相配合。A cast-in-place structure reserved tenon and mortise decorative beam construction device, installed at the mortise and tenon joint of the decorative beam of a shear wall casting template, comprising a first support plate, the first support plate is connected with a second support plate through a detachable component The first support plates are located on the upper and lower sides of the tenon-and-mortise joint respectively, the second support plates are located on the left and right sides of the tenon-and-mortise joint, the second support plates are connected by a moving support mechanism, and the adjacent first support plates are It is connected with the second support plate through a tensioning and stretching mechanism, and a pouring support assembly is arranged on the same side of the first support plate and the second support plate, and the pouring support assembly is matched with the shear wall pouring template.
进一步的,移动支撑机构包括齿轮,齿轮的上下两侧与直齿条相配合,直齿条的端部与第二支撑板相连接,直齿条之间通过限位组件活动连接,限位组件位于齿轮和第二支撑板之间。Further, the moving support mechanism includes gears, the upper and lower sides of the gears are matched with the spur gear racks, the ends of the spur gear racks are connected with the second support plate, and the spur gear racks are movably connected through a limit component, and the limit component between the gear and the second support plate.
进一步的,限位组件包括限位块,限位块的两端设置有通孔,直齿条活动设置在通孔内。Further, the limit component includes a limit block, two ends of the limit block are provided with through holes, and the straight rack is movably arranged in the through holes.
进一步的,直齿条与第二支撑板相垂直,直齿条与第二支撑板之间设置有斜撑杆,斜撑杆的两端分别与直齿条和第二支撑板固定连接。Further, the straight rack is perpendicular to the second support plate, a diagonal brace is arranged between the straight rack and the second support plate, and two ends of the diagonal brace are respectively fixedly connected to the straight rack and the second support plate.
进一步的,张紧拉伸机构包括螺纹杆,螺纹杆的一端与第一支撑板铰接,螺纹杆的另一端通过活动组件与第二支撑板相连接。Further, the tensioning and stretching mechanism includes a threaded rod, one end of the threaded rod is hinged with the first support plate, and the other end of the threaded rod is connected with the second support plate through a movable assembly.
进一步的,活动组件包括拉杆,拉杆的一端通过螺栓与螺纹杆的另一端活动连接,拉杆的另一端与第二支撑板铰接。Further, the movable assembly includes a pull rod, one end of the pull rod is movably connected with the other end of the threaded rod through a bolt, and the other end of the pull rod is hinged with the second support plate.
进一步的,浇筑支撑组件包括活动支撑板,活动支撑板的两端与第二支撑板固定连接,活动支撑板与剪力墙浇筑模板相配合。Further, the pouring support assembly includes a movable support plate, two ends of the movable support plate are fixedly connected with the second support plate, and the movable support plate is matched with the shear wall pouring template.
进一步的,活动支撑板包括两个支撑板,支撑板之间铰接,支撑板与第二支撑板固定连接。Further, the movable support plate includes two support plates, the support plates are hinged, and the support plate is fixedly connected with the second support plate.
进一步的,可拆卸组件包括合页板,合页板分别设置在第二支撑板和第一支撑板的端部,合页板之间通过销轴可拆卸连接。Further, the detachable assembly includes a hinge plate, the hinge plates are respectively arranged on the ends of the second support plate and the first support plate, and the hinge plates are detachably connected by a pin shaft.
本实用新型的有益效果:The beneficial effects of the present utility model:
1.本实用新型通过第一支撑板和第二支撑板组成中空四面体结构,用于在剪力墙模板的缺口处即预留榫卯连接处对上下左右四个方向进行支撑,将活动支撑板设置剪力墙浇筑模板与预留榫卯连接处之间,保证剪力墙浇筑时,混凝土不会流入预留榫卯连接处,剪力墙浇筑完成后,能够在剪力墙与装饰梁连接处设置榫卯连接结构,方便预制装饰梁的安装和浇筑。1. The utility model forms a hollow tetrahedral structure through the first support plate and the second support plate, which is used to support the four directions of up, down, left and right at the gap of the shear wall formwork, that is, the reserved tenon-and-mortise joint, and the movable support The plate is set between the shear wall pouring formwork and the reserved tenon-and-mortise joint to ensure that the concrete will not flow into the reserved tenon-and-mortise joint when the shear wall is poured. The mortise and tenon joint structure is set at the joint to facilitate the installation and pouring of the prefabricated decorative beams.
2.本实用新型在相邻的第一支撑板和第二支撑板之间设置螺纹杆和拉杆组成的张紧拉伸机构,实现第一支撑板的快速拆卸,在第一支撑板拆卸完成后,使用齿轮、直齿条和限位块组成的移动支撑机构实现两个第二支撑板的相对运动,实现第二支撑板与混凝土结构的快速分离,进而保证整个施工装置的快速拆卸并用于下次榫卯连接结构的施工,循环再利用性好。2. In the present invention, a tensioning and stretching mechanism composed of a threaded rod and a tie rod is arranged between the adjacent first support plates and the second support plates to realize the rapid disassembly of the first support plate. After the disassembly of the first support plate is completed , use the mobile support mechanism composed of gears, spur racks and limit blocks to realize the relative movement of the two second support plates, realize the rapid separation of the second support plate and the concrete structure, and then ensure the rapid disassembly of the entire construction device and use it for lowering The construction of the mortise and tenon joint structure has good recyclability.
附图说明Description of drawings
为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the following briefly introduces the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description These are just some embodiments of the present invention, and for those of ordinary skill in the art, other drawings can also be obtained from these drawings without creative effort.
图1为本实用新型的剪力墙浇筑前的结构示意图。Fig. 1 is the structural schematic diagram of the shear wall of the utility model before pouring.
图2为本实用新型的剪力墙浇筑后的结构示意图。FIG. 2 is a schematic structural diagram of the shear wall of the utility model after pouring.
图中,1-合页板,2-斜撑杆,3-限位块,4-拉杆,5-第二支撑板,6-直齿条,7-齿轮,8-活动支撑板,9-螺纹杆,11-第一支撑板。In the figure, 1-hinge plate, 2-diagonal strut, 3-limiting block, 4-tie rod, 5-second support plate, 6-straight rack, 7-gear, 8-movable support plate, 9- Threaded rod, 11-first support plate.
具体实施方式Detailed ways
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有付出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the implementations. example. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
一种现浇结构预留榫卯装饰梁施工装置,安装在剪力墙浇筑模板的装饰梁榫卯连接处,如图1所示,包括第一支撑板11,第一支撑板11通过可拆卸组件与第二支撑板5相连接,第一支撑板11分别位于榫卯连接处的上下两侧,第二支撑板5位于榫卯连接处的左右两侧,第二支撑板5之间通过移动支撑机构相连接,相邻的第一支撑板11和第二支撑板5之间通过张紧拉伸机构相连接,第一支撑板11和第二支撑板5的同一侧设置有浇筑支撑组件,浇筑支撑组件与剪力墙浇筑模板相配合。A cast-in-place structure reserved tenon and mortise decorative beam construction device, installed at the mortise and tenon joint of the decorative beam of the shear wall casting template, as shown in Figure 1, comprising a
预制装配式建筑能够提升施工的效率,在预制装配式剪力墙结构的施工过程中,需要在剪力墙之间安装装饰梁,为了提升装饰梁与剪力墙之间的连接稳定性,在剪力墙上设置有榫卯连接结构,通过榫卯连接结构使得装饰梁与剪力墙稳定连接,或者直接在榫卯连接结构之间设置模板,浇筑装饰梁。因此,在浇筑剪力墙时就需要预留榫卯连接结构,这就需要在剪力墙模板的一侧设置榫卯结构的施工装置,使得剪力墙浇筑完成时,榫卯连接结构也预设完成。Prefabricated buildings can improve the efficiency of construction. During the construction of prefabricated shear wall structures, decorative beams need to be installed between the shear walls. In order to improve the connection stability between the decorative beams and the shear walls, the The shear wall is provided with a tenon-and-mortise connection structure, through which the decorative beam is stably connected to the shear wall, or a template is directly set between the tenon-and-mortise connection structure to pour the decorative beam. Therefore, it is necessary to reserve the tenon-and-mortise connection structure when pouring the shear wall, which requires a construction device of the tenon-and-mortise structure on one side of the shear wall formwork, so that when the shear wall is poured, the tenon-and-mortise connection structure is also pre-set. set complete.
在本实施例中,将现浇结构预留榫卯装饰梁施工装置安装在剪力墙浇筑模板的缺口处即装饰梁榫卯连接处,其中,如图1所示,首先,将浇筑支撑组件、第一支撑板11和第二支撑板5依次安装在剪力墙浇筑模板的缺口处,浇筑支撑组件保证剪力墙模板浇筑混凝土时不会从缺口水平方向流出,浇筑支撑组件两侧的第二支撑板5保证剪力墙模板浇筑混凝土时不会从缺口左右两侧流出,浇筑支撑组件上下两侧的第一支撑板11保证剪力墙模板浇筑混凝土时不会从缺口上下两侧流出,在剪力墙浇筑模板内浇筑混凝土完成后,在剪力墙的装饰梁连接处形成一个榫卯连接缺口,方便将预制的装饰梁的两端搭接在榫卯连接处,方便后续固定,方便装配式施工,或在榫卯连接处之间设置模板,榫卯连接处对模板进行支撑,方便直接浇筑装饰梁,方便现场直接施工;其次,在剪力墙浇筑模板内浇筑混凝土完成后,需要将施工装置拆除,将第一支撑板11和第二支撑板5之间的可拆卸组件拆下,调节张紧拉伸机构,拉动拆下可拆卸组件的第一支撑板11,如图2所示,使第一支撑板11与剪力墙混凝土结构相分离,控制移动支撑机构带动第二支撑板5与剪力墙混凝土结构相分离,最后,拉动第一支撑板11和第二支撑板5,在二者的带动下使得浇筑支撑组件与剪力墙混凝土结构相分离,实现施工装置的拆卸,方便下次使用,循环再利用性好。In this embodiment, the cast-in-place structure reserved mortise-and-mortise decorative beam construction device is installed at the notch of the shear wall casting template, that is, the mortise-and-mortise joint of the decorative beam, wherein, as shown in FIG. 1, first, the casting support assembly is , The
具体的说,如图1所示,移动支撑机构包括齿轮7,齿轮7的上下两侧与直齿条6相配合,直齿条6的端部与第二支撑板5相连接,直齿条6之间活动连接有限位组件,限位组件位于齿轮7和第二支撑板5之间;限位组件包括限位块3,限位块3的两端设置有通孔,直齿条6位于通孔内。Specifically, as shown in FIG. 1 , the moving support mechanism includes a gear 7, the upper and lower sides of the gear 7 are matched with the
在进行第二支撑板5的安装时,如图1所示,调节齿轮7,使得齿轮7上下两侧的直齿条6在限位块3上移动,进而推动第二支撑板5,使得第二支撑板5之间的距离满足卯榫连接处的需要,限位块3通过两端的通孔分别与直齿条6相连接,保证直齿条6移动的稳定性;在进行第二支撑板5的拆卸时,如图2所示,第一支撑板11此时已与混凝土剪力墙相分离,旋转齿轮7,使得上下两侧的直齿条6运动,拉动两个第二支撑板5相对移动,实现第二支撑板5与混凝土结构的分离,保证拆卸的便捷性。When installing the second support plate 5, as shown in FIG. 1, adjust the gear 7 so that the
值得说明的是,在本实施例中,如图1所示,为了进一步保证直齿条6运动的稳定性和结构的强度,直齿条6与第二支撑板5相垂直,直齿条6与第二支撑板5之间设置有斜撑杆2,斜撑杆2的两端分别与直齿条6和第二支撑板5固定连接。在直齿条6推动或者拉动第二支撑板5移动时,斜撑杆2对直齿条6和第二支撑板5均有支撑作用,提升结构的稳定性。It is worth noting that, in this embodiment, as shown in FIG. 1 , in order to further ensure the movement stability and structural strength of the
进一步的,如图1所示,张紧拉伸机构包括螺纹杆9,螺纹杆9的一端与第一支撑板11铰接,螺纹杆9的另一端通过活动组件与第二支撑板5相连接。Further, as shown in FIG. 1 , the tensioning and stretching mechanism includes a threaded rod 9 , one end of which is hinged to the
在需要进行第一支撑板11的拆卸时,将可拆卸组件卸下后,第一支撑板11的一端与第二支撑板5的一端不再连接,此时,调节螺纹杆9在活动组件中的长度,使得第一支撑板11与第二支撑板5之间的距离缩短,进而在第二支撑板5未与混凝土结构分离的前提下,将第一支撑板11与混凝土结构相分离,实现第一支撑板11的快速拆卸。When the
具体的说,如图2所示,活动组件包括拉杆4,拉杆4的一端通过螺栓与螺纹杆9的另一端活动连接,拉杆4的另一端与第二支撑板5铰接;可拆卸组件包括合页板1,合页板1分别设置在第二支撑板5和第一支撑板11的端部,合页板1之间通过销轴可拆卸连接。Specifically, as shown in Figure 2, the movable assembly includes a
在进行第一支撑板11的拆卸时,将合页板1之间的销轴拔掉,旋转螺栓,螺纹杆9和拉杆4的端部发生旋转,使得螺纹杆9和拉杆4发生相对移动,进而使得第一支撑板11与第二支撑板5之间的距离缩短,实现第一支撑板11的快速拆卸。When the
值得说明的是,在本实施例中,如图2所示,只拆掉了第一支撑板11一侧的销轴,使得第一支撑板11能够绕另一侧的销轴旋转,实现快速拆卸。在本实用新型的其他实施例中,还可以将第一支撑板11两侧的销轴同时拆掉,只要达到本实用新型快速拆卸的目的即可。It is worth noting that, in this embodiment, as shown in FIG. 2 , only the pin on one side of the
进一步的,如图1所示,浇筑支撑组件包括活动支撑板8,活动支撑板8的两端与第二支撑板5固定连接,活动支撑板8与剪力墙浇筑模板相配合。在混凝土结构浇筑完成后,第二支撑板5与混凝土结构分离后,拉动第二支撑板5,第二支撑板5带动活动支撑板8与混凝土结构发生分离,实现活动支撑板8的快速拆卸。Further, as shown in FIG. 1 , the pouring support assembly includes a
具体的说,活动支撑板8包括两个支撑板,支撑板之间铰接,支撑板与第二支撑板5固定连接。在进行活动支撑板8的拆卸时,拉动第二支撑板5,进而带动两个支撑板,两个支撑板绕相互铰接处发生旋转,实现活动支撑板8的快速拆卸。Specifically, the
以上仅为本实用新型的较佳实施例而已,并不用以限制本实用新型,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the present invention. within the scope of the new protection.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202123222923.6U CN216516853U (en) | 2021-12-21 | 2021-12-21 | Cast-in-place structure reserves tenon fourth of twelve earthly branches and decorates roof beam construction equipment |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202123222923.6U CN216516853U (en) | 2021-12-21 | 2021-12-21 | Cast-in-place structure reserves tenon fourth of twelve earthly branches and decorates roof beam construction equipment |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN216516853U true CN216516853U (en) | 2022-05-13 |
Family
ID=81501426
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202123222923.6U Active CN216516853U (en) | 2021-12-21 | 2021-12-21 | Cast-in-place structure reserves tenon fourth of twelve earthly branches and decorates roof beam construction equipment |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN216516853U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115043092A (en) * | 2022-07-22 | 2022-09-13 | 天元建设集团有限公司 | Mortise and tenon type steel pipe bundle capable of being positioned |
-
2021
- 2021-12-21 CN CN202123222923.6U patent/CN216516853U/en active Active
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115043092A (en) * | 2022-07-22 | 2022-09-13 | 天元建设集团有限公司 | Mortise and tenon type steel pipe bundle capable of being positioned |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO2021147256A1 (en) | Single-side integral hoisted large-span overbridge crossing over multiple railway lines, and construction method therefor | |
| CN208122301U (en) | A kind of floor support plate supporting apparatus | |
| WO2020244268A1 (en) | Variable cross-section pipe gallery structure suitable for rapid construction and construction method therefor | |
| CN115772911A (en) | A construction method for a comprehensive pipe gallery | |
| CN223423636U (en) | Combined device for single-side template support | |
| CN204983661U (en) | Light steel is framed greatly, integrative -in -place mould support system is decorated in protection that keeps warm | |
| CN221989398U (en) | Basement post-cast strip permanently faces and combines constructional column construction structure | |
| CN115853314B (en) | Parapet top overhanging component supporting device and construction method | |
| CN220580181U (en) | Novel assembled umbrella-shaped structure | |
| CN219298754U (en) | Two-way prestressing force template structure of narrow space concrete construction | |
| CN206829428U (en) | A kind of light steel lightweight concrete exempts from form removal wall body structure | |
| CN115853261A (en) | High-altitude independent beam assembly type formwork reinforcing and supporting system and construction method thereof | |
| CN212773578U (en) | A kind of prefabricated building quick dismantling independent support system | |
| CN110056005B (en) | Subway side wall construction is to top braced system | |
| CN211691514U (en) | A prefabricated top leveling device for laminated slab beams | |
| CN209975803U (en) | Ecological composite wall structure | |
| CN210086296U (en) | Opposite-top supporting system for subway side wall construction | |
| CN112982618A (en) | Construction process for cast-in-situ cover plate of drainage ditch | |
| CN217859683U (en) | Auxiliary positioning tool for flexible steel dam construction | |
| CN112878362A (en) | Comprehensive pipe gallery slip form device and construction method | |
| CN113524399A (en) | Movable prefabricated hollow slab beam base | |
| CN216664503U (en) | A retractable fixing device for forming a kitchen and bathroom countersill at one time | |
| CN207512968U (en) | A kind of splicing node of steel plate combined shear wall | |
| CN218563671U (en) | Assembled utility tunnel major structure construction formwork trolley | |
| CN217859684U (en) | Welding auxiliary tool for flexible steel dam construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |