CN216109621U - Double-layer operation platform for truss installation and construction system - Google Patents

Double-layer operation platform for truss installation and construction system Download PDF

Info

Publication number
CN216109621U
CN216109621U CN202122459920.8U CN202122459920U CN216109621U CN 216109621 U CN216109621 U CN 216109621U CN 202122459920 U CN202122459920 U CN 202122459920U CN 216109621 U CN216109621 U CN 216109621U
Authority
CN
China
Prior art keywords
truss
frame
double
platform
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202122459920.8U
Other languages
Chinese (zh)
Inventor
罗超伟
王宁
宋小成
张少北
高飞扬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Bureau Installation Engineering Co Ltd
Original Assignee
China Construction Second Bureau Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Bureau Installation Engineering Co Ltd filed Critical China Construction Second Bureau Installation Engineering Co Ltd
Priority to CN202122459920.8U priority Critical patent/CN216109621U/en
Application granted granted Critical
Publication of CN216109621U publication Critical patent/CN216109621U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a double-layer operating platform for truss installation and a construction system, which comprise an attachment frame and an operating frame, wherein a hook bent towards the back side of the attachment frame is fixedly installed at the top end of the attachment frame, the middle part and the bottom of the front side of a frame body of the attachment frame are respectively provided with one operating frame, and the two operating frames are parallel to each other and are arranged in a penetrating manner along the left and right directions of the attachment frame. The utility model is provided with two open walking streets corresponding to the construction position of the truss, hoisting equipment is adopted to hoist the truss structure, and then the two walking streets are hung at the upper chord of the truss through the hooks, the truss chord is embraced through the locking rope, so that the platform is prevented from falling off, a plurality of platforms can be used in parallel, a steel springboard is erected among the platforms, personnel can climb into the platform from one side of the truss, and can reach any required construction position of the truss through the platform walkway for construction, the space is open, the protection measures are tight, the construction efficiency is improved, the safety of constructors is ensured, and the utility model has the advantages of simple structure, convenient installation and convenient turnover.

Description

Double-layer operation platform for truss installation and construction system
Technical Field
The utility model relates to the technical field of truss installation, in particular to a double-layer operating platform and a construction system for truss installation.
Background
Along with the increase of space steel structure engineering, the structural style of the space steel structure engineering is gradually complicated, the span is gradually enlarged, and the installation requirement is higher and higher. The installation that single cage carried out the truss in the traditional construction of using more, the operation is very inconvenient, needs additionally to set up interim packway moreover, and the efficiency of construction is low, and the cage need be moved again when personnel change the construction position, removes interim packway, is under construction in the cage, and personnel move limitedly, and inefficiency seriously influences the construction progress, and has safe risk.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a double-layer operating platform for truss installation and a construction system, so as to solve the technical problems in the background technology.
In order to achieve the technical purpose, the utility model adopts the following technical scheme:
the utility model provides a double-deck operation platform for truss installation, is including adhering to frame and handling frame, adhere to frame top end fixed mounting to its dorsal part crooked couple, and its support body front side middle part and bottom are provided with an handling frame respectively, and two handling frames are parallel to each other to link up the setting along the left and right sides direction of adhering to the frame.
Preferably, the hook opening is provided with a locking rope, the locking rope is made of a steel wire rope, one end of the locking rope is bound at the tail end of the hook, and the other end of the locking rope is provided with a rope sleeve matched with the clamping ring.
Preferably, the attaching frame comprises a plurality of upright columns arranged at intervals, the upright columns are parallel to each other, and the upright columns are connected into a whole through a plurality of transverse struts vertically fixed with the upright columns.
Preferably, the handling frame comprises two passing lanes fixedly arranged on the front side of the attachment frame and a guard rail arranged on the front side of the passing lanes.
Preferably, a skirting board is arranged at the bottom of the protection railing in a whole length mode.
In addition, the utility model also provides a construction system of the double-layer operation platform for truss installation, which comprises a plurality of double-layer operation platforms arranged at intervals along the extending direction of the truss, wherein the double-layer operation platforms are hung on the upper chord of the main truss through hooks, two operation frames are respectively and correspondingly arranged below the upper chord and the lower chord of the main truss, two adjacent double-layer operation platforms are respectively hung on two sides of the secondary truss, and a steel springboard is fixedly paved between the two operation frames and is hung with a safety rope serving as a temporary guardrail.
Preferably, constructors on the operation frame wear safety belts, and connecting ropes of the safety belts are sleeved on the upper chord members or the lower chord members of the main truss in a sliding mode.
Compared with the prior art, the utility model has the beneficial effects that:
1. the truss structure is manufactured according to the span and the section size of the truss, two wide walking streets are arranged corresponding to the construction position of the truss, hoisting equipment is adopted to hoist the truss structure and then hung at the upper chord of the truss through a hook, the chord of the truss is embraced through a locking rope, the platforms are prevented from falling off, a plurality of platforms can be used in parallel, a steel springboard is arranged between the platforms, personnel can climb into the platforms from one side of the truss, and can reach any required construction position of the truss through the platform walkway for construction, the space is wide, the protection measures are strict, the construction efficiency is improved, and the safety of the constructors is ensured;
2. the operation platform is simple in structure and convenient to install, can be integrally hoisted, installed and circulated after being manufactured, is high in erection and transportation efficiency, saves construction cost, avoids material waste, and is in accordance with a green construction concept.
Drawings
The above and/or other aspects and advantages of the present invention will become more apparent and more readily appreciated from the detailed description taken in conjunction with the following drawings, which are meant to be illustrative, not limiting of the utility model, and in which:
FIG. 1 is a schematic structural diagram of the present invention.
Reference numerals: 1-main truss, 2-secondary truss, 3-attachment frame, 4-operation frame, 5-hook, 6-locking rope, 7-upright post, 8-cross brace, 9-passing sidewalk, 10-guard rail, 11-skirting board, 12-steel springboard and 13-safety rope.
Detailed Description
Hereinafter, an embodiment of a double deck work platform and a construction system for truss installation according to the present invention will be described with reference to the accompanying drawings. The examples described herein are specific embodiments of the present invention, are intended to be illustrative and exemplary in nature, and are not to be construed as limiting the scope of the utility model. In addition to the embodiments described herein, those skilled in the art will be able to employ other technical solutions which are obvious based on the disclosure of the claims and the specification of the present application, and these technical solutions include technical solutions which make any obvious replacement or modification for the embodiments described herein.
In the description of the present invention, it should be noted that the terms "front", "back", "left", "right", "lateral", "vertical", "up", "down", "top", "bottom", "inside", "outside", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention.
The drawings in the present specification are schematic views to assist in explaining the concept of the present invention, and schematically show the shapes of respective portions and their mutual relationships. It is noted that the drawings are not necessarily to the same scale so as to clearly illustrate the structures of the various elements of the embodiments of the utility model. Like reference numerals are used to denote like parts.
The principles and features of this invention are described below in conjunction with the following drawings, which are set forth to illustrate, but are not to be construed to limit the scope of the utility model. The preferred embodiment of the present invention is described in further detail below with reference to fig. 1:
as shown in fig. 1, the preferred double-layer operating platform for truss installation of the present invention comprises an attachment frame 3 and an operating frame 4, wherein a hook 5 bent toward the back side of the attachment frame 3 is fixedly installed at the top end of the attachment frame 3, the middle part and the bottom of the front side of the frame body are respectively provided with one operating frame 4, and the two operating frames 4 are parallel to each other and are arranged in a penetrating manner along the left-right direction of the attachment frame 3;
the attachment frame 3 comprises a plurality of stand columns 7 which are arranged at intervals, the stand columns 7 are parallel to each other, and the stand columns 7 are connected into a whole through a plurality of cross braces 8 which are vertically fixed with the stand columns;
the operation frame 4 comprises two passing corridors 9 fixedly arranged on the front side of the attachment frame 3 and a protective barrier 10 arranged on the front side of the passing corridors 9, the passing corridors 9 comprise a corridor beam vertically arranged on the front side of the attachment frame 3 and a steel springboard 12 laid above the corridor beam, the steel springboard 12 is laid on the corridor beam and firmly tied by iron wires, the protective barrier 10 comprises a guardrail vertical rod and a guardrail cross beam which are fixedly connected, and a skirting board 11 for preventing scattered small pieces from falling is arranged on the bottom of the guardrail vertical rod in a through manner;
the opening position of the hook 5 is provided with a locking rope 6, the locking rope 6 is made of a steel wire rope, one end of the locking rope is bound at the tail end of the hook 5, and the other end of the locking rope is provided with a rope sleeve matched with the clamping ring.
When the safety guard is used, the construction system is set up according to the following steps that firstly, a plurality of double-layer operation platforms are arranged at intervals along the extending direction of a truss, each double-layer operation platform is hung on the upper chord of a main truss 1 through a hook 5, at the moment, two operation frames 4 are correspondingly arranged below the upper chord and the lower chord of the main truss 1 respectively, two adjacent double-layer operation platforms are hung on two sides of a secondary truss 2 respectively, then, a locking rope 6 at the position of the hook 5 is wound on a column 7 of an attachment frame 3 for one circle and then a rope sleeve and the locking rope are clamped through a snap ring, a steel springboard 12 is fixedly laid between passing railways 9 of two adjacent double-layer operation platforms in sequence, two safety ropes 13 are hung at the tail ends of two connected safety railways 10 to serve as temporary guardrails, when a constructor operates, the platform is climbed from one side of the passing truss, the connecting rope of the safety belt is slidingly sleeved on the upper chord or the lower chord of the main truss 1 at a construction position after the platform railways 9 reach the construction position to be constructed The construction can be started. Through the double-layer operating platform construction system, the personnel construction requirements of all installation positions of the trusses can be met, the welding work of upper and lower chord connection nodes of the main trusses in truss steel structure construction can be solved, the installation of the secondary trusses between two adjacent main trusses can be met, the requirement of simultaneous construction of the upper and lower chords of the trusses can be met through one-time installation, and the construction efficiency is improved.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the utility model, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (7)

1. A double-deck operation platform for truss installation which characterized in that: including attaching to frame (3) and handling frame (4), attach to hook (5) of frame (3) top fixed mounting to its dorsal part bending, and its support body front side middle part and bottom are provided with one handling frame (4) respectively, and two handling frames (4) are parallel to each other to link up the setting along the left and right sides direction of attaching to frame (3).
2. The double deck work platform for truss installation of claim 1, wherein: the hook is characterized in that a locking rope (6) is arranged at the opening position of the hook (5), the locking rope (6) is made of a steel wire rope, one end of the locking rope is bound at the tail end of the hook (5), and the other end of the locking rope is provided with a rope sleeve matched with the clamping ring.
3. The double deck work platform for truss installation of claim 1, wherein: the attaching frame (3) comprises a plurality of stand columns (7) which are arranged at intervals, the stand columns (7) are parallel to each other, and the stand columns (7) are connected into a whole through a plurality of cross braces (8) which are vertically fixed with the stand columns.
4. A double deck work platform for truss installations as claimed in claim 3 wherein: the operation frame (4) comprises two passing streets (9) fixedly arranged on the front side of the attachment frame (3) and a protective railing (10) arranged on the front side of the passing streets (9).
5. The double deck work platform for truss installation of claim 4, wherein: the bottom of the protective barrier (10) is provided with a skirting board (11) throughout.
6. A construction system comprising a double deck work platform for truss installation as claimed in any one of claims 1 to 5, wherein: including the double-deck operation platform of a plurality of that sets up along truss extending direction interval, double-deck operation platform articulates on main truss (1) upper chord through couple (5), and its twice operation rack (4) correspond respectively and set up in the upper chord and lower chord below of main truss (1), and two adjacent double-deck operation platform articulate respectively in secondary truss (2) both sides, and fixed the having laid steel springboard (12) between the two operation rack (4) and articulate safety rope (13) as interim guardrail.
7. A construction system according to claim 6, wherein: constructors on the operation frame (4) wear safety belts on the bodies, and connecting ropes of the safety belts are sleeved on the upper chord or the lower chord of the main truss (1) in a sliding mode.
CN202122459920.8U 2021-10-13 2021-10-13 Double-layer operation platform for truss installation and construction system Expired - Fee Related CN216109621U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122459920.8U CN216109621U (en) 2021-10-13 2021-10-13 Double-layer operation platform for truss installation and construction system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122459920.8U CN216109621U (en) 2021-10-13 2021-10-13 Double-layer operation platform for truss installation and construction system

Publications (1)

Publication Number Publication Date
CN216109621U true CN216109621U (en) 2022-03-22

Family

ID=80692162

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122459920.8U Expired - Fee Related CN216109621U (en) 2021-10-13 2021-10-13 Double-layer operation platform for truss installation and construction system

Country Status (1)

Country Link
CN (1) CN216109621U (en)

Similar Documents

Publication Publication Date Title
CN100590277C (en) High-altitude bridge type cantilever scaffold
CN104763109B (en) Quick construction method for pressed bottom tile of large-span steel structure factory building roof
US10458079B2 (en) Bridging system
CN209942196U (en) Cantilever support system for large-volume concrete structure
CN210507141U (en) Movable tensioning platform
CN110685226A (en) Hydraulic integral self-climbing construction platform
CN101215928B (en) Attached lifting scaffold trolley type inclining-proof device and method of use thereof
CN215291322U (en) Integrally assembled attached scaffold
CN216109621U (en) Double-layer operation platform for truss installation and construction system
CN218434640U (en) Telescopic tower crane escape way
CN205955164U (en) Portable steel truss operation platform
CN211775606U (en) Regularization assembled that can have enough to meet need climbs frame and goes up people's passageway
CN114108480A (en) Full-section downward-sliding erection structure of suspension bridge catwalk and construction method thereof
CN205591115U (en) Suspension type catwalk veil installing the system
CN212129859U (en) Detachable steel structure aerial work operating platform
CN211312215U (en) Hydraulic integral self-climbing construction platform
CN217145966U (en) Track foundation and suspension type track system convenient for transferring personnel
CN210767926U (en) Safety protection platform
CN210658052U (en) Crawling ladder for road and bridge
CN219622223U (en) Novel scaffold structure
CN217125923U (en) Track foundation with corridor and suspension type track system
CN219823484U (en) Attached tower crane pedestrian passageway
CN211421800U (en) Lower operating platform for hanging basket
CN216615518U (en) Bridge decoration construction platform
CN215629425U (en) Suspension operation platform device for subsequent operation of T-beam erection

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220322

CF01 Termination of patent right due to non-payment of annual fee