CN215859000U - Hanging basket for construction of outer wall of building area - Google Patents

Hanging basket for construction of outer wall of building area Download PDF

Info

Publication number
CN215859000U
CN215859000U CN202121185858.1U CN202121185858U CN215859000U CN 215859000 U CN215859000 U CN 215859000U CN 202121185858 U CN202121185858 U CN 202121185858U CN 215859000 U CN215859000 U CN 215859000U
Authority
CN
China
Prior art keywords
hanging basket
wall
basket
coating
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121185858.1U
Other languages
Chinese (zh)
Inventor
朱洪涛
杨小铃
刘俊
瞿懿
夏维成
高永峰
曾良雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 22nd Bureau Group Co Ltd
Electrification Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd
Original Assignee
China Railway 22nd Bureau Group Co Ltd
Electrification Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 22nd Bureau Group Co Ltd, Electrification Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd filed Critical China Railway 22nd Bureau Group Co Ltd
Priority to CN202121185858.1U priority Critical patent/CN215859000U/en
Application granted granted Critical
Publication of CN215859000U publication Critical patent/CN215859000U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model discloses a hanging basket for building area outer wall construction, which comprises a main hanging basket platform, wherein a front protective baffle and a door plate are arranged at the upper end of the main hanging basket platform, the front protective baffle and the door plate are respectively positioned at the front end and the rear end of the main hanging basket platform, an outer fixed rod is arranged on the outer wall of the front protective baffle, a movable sleeve block is sleeved on the outer wall of the outer fixed rod, a coating material placing basket is arranged at the front end of the movable sleeve block, and connectors are arranged on two sides of the coating material placing basket. This district is built in room outer wall construction is with hanging flower basket sets up outer dead lever through guard flap's outer wall in the front, establish movable sleeve piece at outer dead lever outer wall cover, it puts the thing basket to set up coating at activity sleeve piece front end, thereby can put the position of thing basket to coating at any time and remove through the movable sleeve piece that removes on the outer dead lever, make things convenient for the workman to use coating, can put the locking screw of thing basket left and right sides through coating simultaneously and put thing basket position to coating and lock, guarantee from this that coating puts the stability of the material on the thing basket.

Description

Hanging basket for construction of outer wall of building area
Technical Field
The utility model relates to the technical field of house construction equipment, in particular to a hanging basket for outer wall construction of a building construction area.
Background
The house building engineering refers to various house buildings and auxiliary facilities thereof, and lines, pipelines, equipment installation engineering and indoor and outdoor decoration engineering matched with the house buildings; the 'house building' refers to a project which is provided with a top cover, a beam column, a wall, a foundation and can form an internal space and meet the requirements of people on production, living, study, public activities and the like; the building construction engineering is generally called building engineering for short, and refers to engineering entities for surveying, planning, designing, constructing, installing, maintaining and the like performed by newly building, rebuilding or expanding building and auxiliary structures and the completed engineering entities.
The construction of building outer wall needs use the hanging flower basket supplementary to go on at present, and current hanging flower basket adopts wire rope hoist and mount, has the phenomenon of rocking in the use, has increased the degree of difficulty of workman's operation from this, and the rigidity of scribbling the skip bucket on current hanging flower basket simultaneously needs the workman to go repeatedly same position and dips in and get coating, has reduced work efficiency from this, needs to improve.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a hanging basket for construction of an outer wall of a building area, which solves the problem that construction of workers is inconvenient due to the fact that a material coating barrel is fixed in the placing position of a material coating barrel in the hanging basket in the background technology.
In order to achieve the purpose, the utility model provides the following technical scheme that the hanging basket for the construction of the outer wall of the building area comprises a main hanging basket platform, wherein a front protective baffle and a door plate are arranged at the upper end of the main hanging basket platform and are respectively positioned at the front end and the rear end of the main hanging basket platform, an outer fixed rod is arranged on the outer wall of the front protective baffle, a movable sleeve block is sleeved on the outer wall of the outer fixed rod, a paint storage basket is arranged at the front end of the movable sleeve block, connectors are arranged on two sides of the paint storage basket, a locking screw is arranged on each connector, and the rear end of each locking screw is inserted into the outer fixed rod.
Preferably, one side of the main hanging basket platform is provided with a first splice plate, and the other side of the main hanging basket platform is provided with a second splice plate.
Preferably, the second splice plate and the first splice plate are rotationally connected with the main hanging basket platform, and chutes are formed in the second splice plate, the first splice plate and the main hanging basket platform.
Preferably, the second splice plate and the first splice plate are both provided with side baffle plates, the bottoms of the side baffle plates are provided with sliding blocks, and the lower ends of the sliding blocks are located in the sliding grooves.
Preferably, the side baffle all constitutes sliding connection with second splice plate, first splice plate and main hanging flower basket platform, and the side baffle left and right sides outer wall all is provided with the fixed head.
Preferably, the rear end of the front protective baffle is provided with a sleeve rod, the rear end of the sleeve rod is inserted with a telescopic rod, the telescopic rod is fixedly connected with the sleeve rod through a bolt, and the rear end of the telescopic rod is provided with a bonding pad.
Compared with the prior art, the utility model has the beneficial effects that: this district is built in room outer wall construction is with hanging flower basket sets up outer dead lever through guard flap's outer wall in the front, establish movable sleeve piece at outer dead lever outer wall cover, it puts the thing basket to set up coating at activity sleeve piece front end, thereby can put the position of thing basket to coating at any time and remove through the movable sleeve piece that removes on the outer dead lever, make things convenient for the workman to use coating, can put the locking screw of thing basket left and right sides through coating simultaneously and put thing basket position to coating and lock, guarantee from this that coating puts the stability of the material on the thing basket.
Drawings
FIG. 1 is a schematic structural view of a hanging basket for construction of an outer wall of a building area according to the present invention;
FIG. 2 is a schematic view of a connection structure of a hanging basket sleeve rod and a telescopic rod for the construction of an outer wall of a building area;
FIG. 3 is a side view of the hanging basket side retaining and protecting baffle for the construction of the outer wall of the building area.
In the figure: 1. the device comprises a first splicing plate, a main hanging basket platform, a door plate, a laminating pad, a bolt, a sleeve rod, a second splicing plate, a side blocking protective baffle plate, a fixing head, a sliding groove, a front protective baffle plate, a coating placing basket, a movable sleeve block, a connecting head, a locking screw, an outer fixing rod, a telescopic rod, a sliding block and a connecting head, wherein the side blocking protective baffle plate is 8, the fixing head is 9, the sliding groove is 10, the sliding groove is 11, the front protective baffle plate is 12, the coating placing basket is 13, the movable sleeve block is 14, the connecting head is 15, the locking screw is 16, the outer fixing rod is 17, the telescopic rod is 18, and the sliding block is arranged on the outer fixing rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: a hanging basket for construction of an outer wall of a building area comprises a main hanging basket platform 2, a front protective baffle 11 and a door plate 3 are arranged at the upper end of the main hanging basket platform 2, the main hanging basket platform 2 and the front protective baffle 11 are welded and fixed, the front protective baffle 11 and the door plate 3 are respectively arranged at the front end and the rear end of the main hanging basket platform 2, the door plate 3 is connected to the front protective baffle 11 at the rear end through a hinge, the door plate 3 is convenient for workers to enter, a first splice plate 1 is arranged on one side of the main hanging basket platform 2, the left side of the main hanging basket platform 2 is connected with the first splice plate 1 through a hinge, a second splice plate 7 is arranged on the other side of the main hanging basket platform 2, the right side of the main hanging basket platform 2 is connected with a second splice plate 7 through a hinge, so that the second splice plate 7 and the first splice plate 1 can rotate downwards, the second splice plate 7 and the first splice plate 1 are folded, only the main gondola platforms 2 are used; the second splice plate 7 and the first splice plate 1 are rotationally connected with the main hanging basket platform 2, the second splice plate 7, the first splice plate 1 and the main hanging basket platform 2 are all provided with a chute 10, and the second splice plate 7, the first splice plate 1 and the main hanging basket platform 2 are all integrally connected with the chute 10; the second splicing plate 7 and the first splicing plate 1 are both provided with a side baffle 8, the side baffle 8 can transversely move on the second splicing plate 7, the first splicing plate 1 and the main hanging basket platform 2 through a chute 10, so that the size of a use space can be adjusted, a sliding block 18 is arranged at the bottom of the side baffle 8, the side baffle 8 and the sliding block 18 are fixedly connected through a bolt, the lower end of the sliding block 18 is positioned in the chute 10, and the sliding block 18 is in sliding connection with the chute 10; the side baffle 8 and the second splice plate 7, the first splice plate 1 and the main hanging basket platform 2 are in sliding connection, the outer walls of the left side and the right side of the side baffle 8 are provided with fixing heads 9, and the side baffle 8 and the fixing heads 9 are fixedly connected through bolt pieces; an outer fixed rod 16 is arranged on the outer wall of a front protective baffle 11, the front protective baffle 11 and the outer fixed rod 16 are fixed through a support, a movable sleeve block 13 is sleeved on the outer wall of the outer fixed rod 16, the diameter of the outer fixed rod 16 is smaller than the inner diameter of the movable sleeve block 13, a sleeve rod 6 is arranged at the rear end of the front protective baffle 11, the front protective baffle 11 and the sleeve rod 6 are welded and fixed, an expansion rod 17 is inserted at the rear end of the sleeve rod 6, the sleeve rod 6 and the expansion rod 17 form an expansion structure, the expansion rod 17 and the sleeve rod 6 are fixedly connected through a bolt 5, so that the lengths of the expansion rod 17 and the sleeve rod 6 can be adjusted, a bonding pad 4 is bonded with a wall in the using process of the device, the shaking of a main hanging basket platform 2 is reduced, a bonding pad 4 is arranged at the rear end of the expansion rod 17, and the expansion rod 17 and the bonding pad 4 are fixed through glue; the coating material containing basket 12 is arranged at the front end of the movable sleeve block 13, the movable sleeve block 13 and the coating material containing basket 12 are fixed through a bolt, connectors 14 are arranged on two sides of the coating material containing basket 12, the coating material containing basket 12 and the connectors 14 are fixed through bolts, locking screws 15 are arranged on the connectors 14, the connectors 14 and the locking screws 15 are in threaded connection, the rear ends of the locking screws 15 are inserted on the outer fixing rods 16, threaded holes are formed in the outer walls of the outer fixing rods 16, and therefore the coating material containing basket 12 can be conveniently reinforced by inserting the locking screws 15; this district is built in room outer wall construction and is used hanging flower basket sets up outer dead lever 16 through the outer wall of guard flap 11 in the front, establish movable sleeve 13 at outer dead lever 16 outer wall cover, set up coating at movable sleeve 13 front end and put thing basket 12, thereby can put the position of thing basket 12 to coating at any time and remove through movable sleeve 13 on the outer dead lever 16, make things convenient for the workman to use coating, can put the locking screw 15 of thing basket 12 left and right sides to coating through coating and put thing basket 12 position and lock, guarantee the stability of the material on the coating thing basket 12 from this.
The working principle is as follows: when the hanging basket for the construction of the outer wall of the building area is used, firstly, the main hanging basket platform 2 is hung outside the outer wall, the door plate 3 of the main hanging basket platform 2 faces the wall surface, the bolt 5 is loosened after the hanging is finished, then the telescopic rod 17 is drawn out from the inside of the sleeve rod 6, the attaching pad 4 is slowly close to the wall, the attaching pad 4 is contacted with the wall, then the telescopic rod 17 and the sleeve rod 6 are fixed by the bolt 5, at the moment, the attaching pad 4 can play a role of supporting the main hanging basket platform 2, the front and back shaking of the main hanging basket platform 2 is reduced, in the process of using the device, the position of the paint storage basket 12 can be moved along with the movement of workers, the movable sleeve block 13 is pushed to move on the outer fixed rod 16 during the movement, so that the purpose of moving the position of the paint storage basket 12 is achieved, and the paint storage basket 12 is moved to a proper position and then the paint storage basket 12 is reinforced if needed, the locking screw 15 can be rotated into the inside of the outer fixing rod 16 for reinforcement, which is the working principle of the hanging basket for the construction of the outer wall of the building area.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that various changes in the embodiments and/or modifications of the utility model can be made, and equivalents and modifications of some features of the utility model can be made without departing from the spirit and scope of the utility model.

Claims (6)

1. The utility model provides a district is built in room hanging flower basket for outer wall construction, includes main hanging flower basket platform (2), its characterized in that: the hanging basket platform is characterized in that a front protective baffle (11) and a door plate (3) are arranged at the upper end of the main hanging basket platform (2), the front protective baffle (11) and the door plate (3) are respectively located at the front end and the rear end of the main hanging basket platform (2), an outer fixed rod (16) is arranged on the outer wall of the front protective baffle (11), a movable sleeve block (13) is sleeved on the outer wall of the outer fixed rod (16), a coating placing basket (12) is arranged at the front end of the movable sleeve block (13), connectors (14) are arranged on the two sides of the coating placing basket (12), locking screw rods (15) are arranged on the connectors (14), and the rear ends of the locking screw rods (15) are inserted into the outer fixed rods (16).
2. The hanging basket for the construction of the outer wall of the building area according to claim 1, wherein: a first splice plate (1) is arranged on one side of the main hanging basket platform (2), and a second splice plate (7) is arranged on the other side of the main hanging basket platform (2).
3. The hanging basket for construction of the outer wall of the building area according to claim 2, wherein: the second splice plate (7) and the first splice plate (1) are rotatably connected with the main hanging basket platform (2), and the second splice plate (7), the first splice plate (1) and the main hanging basket platform (2) are provided with chutes (10).
4. The hanging basket for construction of the outer wall of the building area according to claim 2, wherein: the second splicing plate (7) and the first splicing plate (1) are both provided with side baffle plates (8), the bottoms of the side baffle plates (8) are provided with sliding blocks (18), and the lower ends of the sliding blocks (18) are located in the sliding grooves (10).
5. The hanging basket for construction of the outer wall of the building area according to claim 4, wherein: the side baffle (8) and the second splice plate (7), the first splice plate (1) and the main hanging basket platform (2) all form sliding connection, and the outer walls of the left side and the right side of the side baffle (8) are provided with fixing heads (9).
6. The hanging basket for the construction of the outer wall of the building area according to claim 1, wherein: preceding guard flap (11) rear end is provided with telescopic link (6), and its telescopic link (6) rear end is inserted and is equipped with telescopic link (17), and telescopic link (17) pass through bolt (5) fixed connection with telescopic link (6) to telescopic link (17) rear end is provided with laminating pad (4).
CN202121185858.1U 2021-05-31 2021-05-31 Hanging basket for construction of outer wall of building area Active CN215859000U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121185858.1U CN215859000U (en) 2021-05-31 2021-05-31 Hanging basket for construction of outer wall of building area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121185858.1U CN215859000U (en) 2021-05-31 2021-05-31 Hanging basket for construction of outer wall of building area

Publications (1)

Publication Number Publication Date
CN215859000U true CN215859000U (en) 2022-02-18

Family

ID=80313668

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121185858.1U Active CN215859000U (en) 2021-05-31 2021-05-31 Hanging basket for construction of outer wall of building area

Country Status (1)

Country Link
CN (1) CN215859000U (en)

Similar Documents

Publication Publication Date Title
CN106894510B (en) Assembly for assembling house cabinet system
CN206916774U (en) The tool bracing system of spigot-and-socket piping lane bellmouth deformation slit formwork
CN210798308U (en) Reinforcing device for steel backing ridges of aluminum alloy templates of outer walls
CN215859000U (en) Hanging basket for construction of outer wall of building area
CN205134527U (en) Three -dimensional building module
CN212002439U (en) A consolidate bearing structure for building engineering
CN216552693U (en) Large-span assembly type building crossbeam
CN216340631U (en) Modular passing-through stone structure
CN215406722U (en) Steel house
CN212896972U (en) Steel construction assembled wallboard is built in room
CN212002185U (en) Construction equipment is increased to landing leg behind hanging flower basket
CN212957792U (en) Container house
CN210530292U (en) Scaffold for building
CN212105071U (en) House building engineering's construction platform
CN217924727U (en) Functional foot rest
CN213952887U (en) Scaffold frame for building engineering convenient to carry
CN215168322U (en) Adjustable anti-seismic reinforcing plate for constructional engineering
CN215167770U (en) Supporting framework for architectural decoration
CN214696062U (en) Platform frame modular structure of green steel construction
CN218029294U (en) Steel construction communication computer lab that can build fast
CN205296565U (en) Fast -assembling environmental protection combination wallboard
CN214220534U (en) Scaffold for plastering heat-insulating coating of building interior wall
CN214498626U (en) Building construction protective fence
CN213774380U (en) Strutting arrangement is used in building engineering construction
CN216588029U (en) Building engineering construction safety control rail

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant