CN215857777U - Vertical high slope pile anchor and internal support composite supporting system - Google Patents

Vertical high slope pile anchor and internal support composite supporting system Download PDF

Info

Publication number
CN215857777U
CN215857777U CN202121711630.1U CN202121711630U CN215857777U CN 215857777 U CN215857777 U CN 215857777U CN 202121711630 U CN202121711630 U CN 202121711630U CN 215857777 U CN215857777 U CN 215857777U
Authority
CN
China
Prior art keywords
support
pile
supporting
anchor
high slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202121711630.1U
Other languages
Chinese (zh)
Inventor
夏体波
安健
杨磊
吕明
胡森
杨凡
叶剑华
罗朝虎
徐光明
孙灵
张中
刘强
陈本宽
颜斌
黎吉龙
吴孟玄
龙应华
赵勇
姚志刚
王文胜
梁德斌
杜典祥
杨正茂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 4 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Original Assignee
No 4 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 4 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group filed Critical No 4 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Priority to CN202121711630.1U priority Critical patent/CN215857777U/en
Application granted granted Critical
Publication of CN215857777U publication Critical patent/CN215857777U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model provides a vertical high slope pile anchor and inner support composite support system, which relates to the technical field of slope protection and solves the problems that the slope is very easy to collapse and cause personal casualties as a support structure is not made in time after the existing support device is excavated, and the consequence is very serious.

Description

Vertical high slope pile anchor and internal support composite supporting system
Technical Field
The utility model belongs to the technical field of slope protection, and particularly relates to a vertical high slope pile anchor and internal support composite supporting system.
Background
The service life of the side slope is not less than the service life of the proposed road and is a permanent side slope; the side slope is in a vertical side slope form, the height of the side slope is very large, the timing of excavation and support is very important, and if a support structure is not made in time after excavation, the side slope is very easy to collapse, so that casualties are caused, and the consequences are very serious.
Therefore, in view of the above, research and improvement are made for the existing structure and defects, and a vertical high slope pile anchor and an internal support composite supporting system are provided, so as to achieve the purpose of higher practical value.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problems, the utility model provides a vertical high slope pile anchor and an inner support composite supporting system, which aims to solve the problem that the slope is very easy to collapse to cause personal injury and death and the consequence is very serious because the existing supporting device cannot be used for supporting structures in time after excavation.
The utility model relates to a vertical high slope pile anchor and inner support composite support system, which is achieved by the following specific technical means:
the utility model provides a compound system of strutting of perpendicular high slope stake anchor and internal stay, include bearing mechanism includes:
the waist beam is arranged at the inner side positions of the two inner supporting pieces.
Further, the guard mechanism includes:
the main body of the guide component is a cross-shaped block which is connected to the inner side of the inner supporting piece in a sliding manner, and the inner side of the guide component is also provided with a bearing mechanism.
Further, the guard mechanism includes:
and the anchor cable is hinged at the front side position of the support pile.
Further, a support mechanism;
the main body of the supporting mechanism is of a cuboid structural design, the front side of the supporting mechanism is further provided with a protection mechanism, the inner side of the protection mechanism is further provided with a bearing mechanism, and the stand oblique beam is installed at the top end face of the waist beam.
Further, the support mechanism includes:
the anti-slide piles are arranged at the inner side positions of the two support piles and form a shape like a Chinese character 'pin' together with the support piles, and a protection mechanism is further arranged on the front side of each anti-slide pile.
Further, the guard mechanism includes:
the inner supporting piece is characterized in that the main body of the inner supporting piece is of a cuboid structure with a hollow interior, the inner supporting piece and the supporting pile form an L-shaped structure together, and an elastic assembly is arranged inside the inner supporting piece.
Further, the support mechanism includes:
the main body of the support pile is of a cuboid structure design, and the two support piles are arranged in a transverse array.
Compared with the prior art, the utility model has the following beneficial effects:
the construction technology of the vertical high slope pile anchor and inner support composite system adopts the slope pile anchor and cast-in-place reinforced concrete truss inner support composite system, greatly improves the stability of a slope, has novel, unique and attractive appearance, reduces the waste of materials and saves the construction time, can shorten the construction period by 20 percent, saves the labor cost by 20 percent, saves the materials by 20 percent and has very obvious economic benefit compared with a single support form.
Additional advantages, objects, and features of the utility model will be set forth in part in the description which follows and in part will become apparent to those having ordinary skill in the art upon examination of the following or may be learned from practice of the utility model.
Drawings
Fig. 1 is a schematic side view of the present invention.
Fig. 2 is a schematic front side view of the present invention.
Fig. 3 is a schematic top side view of the present invention.
Fig. 4 is a left side view of the present invention.
In the drawings, the corresponding relationship between the component names and the reference numbers is as follows:
1. a support mechanism; 101. supporting piles; 102. anti-slide piles; 2. a protection mechanism; 201. an inner support member; 202. an anchor cable; 203. a guide assembly; 3. a carrying mechanism; 301. a wale; 302. and (5) an upright column oblique beam.
Detailed Description
The embodiments of the present invention will be described in further detail with reference to the drawings and examples. The following examples are intended to illustrate the utility model but are not intended to limit the scope of the utility model.
In the description of the present invention, "a plurality" means two or more unless otherwise specified; the terms "upper", "lower", "left", "right", "inner", "outer", "front", "rear", "head", "tail", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, are only for convenience in describing and simplifying the description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed in a particular orientation, and be operated, and thus, should not be construed as limiting the utility model. Furthermore, the terms "first," "second," "third," and the like are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "connected" and "connected" are to be interpreted broadly, e.g., as being fixed or detachable or integrally connected; can be mechanically or electrically connected; may be directly connected or indirectly connected through an intermediate. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Example (b):
as shown in figures 1 to 4:
the utility model provides a vertical high slope pile anchor and internal support composite support system, which comprises a support mechanism 1; the main part of supporting mechanism 1 is cuboid structural design, and the front side of supporting mechanism 1 still is provided with protection machanism 2, still is provided with in protection machanism 2 inboard and bears mechanism 3, and the top face position at waist rail 301 is installed to stand sloping 302, props 101, and the main part of props 101 is cuboid structural design, and two props 101 is horizontal array setting, and supporting mechanism 1 includes: the anti-slide piles 102 are arranged at the inner sides of the two support piles 101, the anti-slide piles 102 and the support piles 101 form a Chinese character 'pin', and the front side of the anti-slide piles 102 is further provided with a protection mechanism 2.
Referring to fig. 1-2, the shielding mechanism 2 includes: interior support piece 201, the main part of interior support piece 201 is inside hollow cuboid structural design, and interior support piece 201 constitutes "L" shape structure with a fender pile 101 jointly, still is provided with elastic component in the inside of interior support piece 201, and protection machanism 2 includes: an anchor line 202, the anchor line 202 is hinged at the front side position of the support pile 101, and the protection mechanism 2 comprises: the main body of the guide assembly 203 is a cross-shaped block, the guide assembly 203 is slidably connected to the inner side of the inner support member 201, and the inner side of the guide assembly 203 is further provided with a bearing mechanism 3.
Referring to fig. 3-4, the carrier mechanism 3 includes: the wale 301, the wale 301 is installed at the inner side position of the two inner supporting pieces 201.
The specific use mode and function of the embodiment are as follows:
when the device is used, 1, the slide-resistant pile 102 is constructed: excavating the anti-slide pile 102 by subsection jump holes, sealing the bottom in time after the excavation is in place to prevent a foundation bearing layer from being damaged, constructing the support pile 101 and the anti-slide pile 102 at the same time, pouring concrete to a position 14m above the road pavement elevation, and constructing the upper part when horizontal support construction is carried out; two difficulties exist in pile foundation construction:
constructing an ultra-close pile foundation, wherein the minimum distance between a support pile 101 and an anti-slide pile 102 is 0.3cm, the minimum distance between the anti-slide pile 102 is 1m, the support pile 101 and the anti-slide pile 102 are in a finished product shape, and the construction process adopts a jumping excavation mode of firstly lengthening, then shortening, firstly enlarging, then reducing and separating holes, namely firstly constructing the anti-slide pile 102, then jumping excavation construction, then constructing an adjacent anti-slide pile 102, and finally constructing the support pile 101, so that the construction safety and the pile forming quality are ensured;
and secondly, constructing an overlength half pile, wherein the supporting pile 101 is only constructed to the position with the pavement elevation of 14m, a longer empty pile exists in the supporting pile 101, the maximum empty pile length is more than 10m, and the elevation of the pile top is controlled by adopting a pressure sensor on the engineering site, so that the effective pile length and the over-poured concrete amount are ensured.
2. And (3) side slope support construction: slope excavation, anchor cables 202 and inter-pile plates are alternately and circularly performed, the grading height is 0.5m below the anchor cables 202, and next-level slope excavation can be performed after the anchor cables 202 are supported; the anchor cable 202 adopts pressure grouting, the prestressed anchor cable 202 tensioning can be carried out after the strength of cement mortar reaches 85 percent, and the prestressed anchor cable 202 tensioning is carried out according to secondary four-level cluster tensioning; before the side slope is excavated to the road surface elevation, all anchor cables 202 are not required to be anchored; after the slope excavation is finished, unified anchor sealing can be carried out; in the construction and operation period of the side slope, the internal force of the anchor cable 202 is monitored regularly, and abnormal conditions are found and fed back in time
3. Internal stay, couple roof beam, waist rail 301, stand construction: when the road surface is excavated to the position with the elevation of 14m, the excavation operation is suspended, the first inner support, the longitudinal connecting beam, the upright post, the oblique beam, the waist beam 301 and the second inner support are constructed, a special construction scheme is compiled before construction, and expert demonstration is organized, so that the lower slope construction can be carried out when the strength of the member reaches more than 90% of the design strength.
The construction technology of the vertical high slope pile anchor and internal support composite system comprises the following process flows: surveying and paying off → field leveling → construction of slope top water intercepting ditch → anti-slide pile 102 and support pile 101 construction → crown beam construction → excavation of earth and stone (layering, 50cm below anchor rope 202) above 14m of road surface elevation → construction of anchor rope 202 → construction of inter-pile plate → excavation, anchor rope 202 and inter-pile plate are circularly constructed to 14m above road surface elevation → construction of inner support, connecting beam, waist beam 301, column construction of second (top) inner support, connecting beam, waist beam 301 and column construction → excavation of earth and stone below 14m of road surface elevation → construction of inter-pile plate (excavation and alternate construction of inter-pile plate).
And graded and segmented excavation is adopted, the length of each segment is preferably 10-15m, the graded excavation height is 0.5m below the anchor cable 202, and the next procedure can be carried out after the supporting structure reaches the design strength. The method comprises the steps of adopting a pile anchor and an inner support supporting part, firstly adopting a reverse construction method to construct a position 14m above the elevation of a road surface, then constructing a stand column, a connecting beam and a counter support by a forward construction method, and carrying out lower slope construction when the strength of a component reaches more than 90% of the design strength.
The embodiments of the present invention have been presented for purposes of illustration and description, and are not intended to be exhaustive or limited to the utility model in the form disclosed. Many modifications and variations will be apparent to those of ordinary skill in the art. The embodiment was chosen and described in order to best explain the principles of the utility model and the practical application, and to enable others of ordinary skill in the art to understand the utility model for various embodiments with various modifications as are suited to the particular use contemplated.

Claims (7)

1. The utility model provides a compound support system of perpendicular high slope stake anchor and internal stay which characterized in that: comprises a supporting mechanism;
the main body of the supporting mechanism is of a cuboid structural design, the front side of the supporting mechanism is further provided with a protection mechanism, the inner side of the protection mechanism is further provided with a bearing mechanism, and the stand oblique beam is installed at the top end face of the waist beam.
2. The vertical high slope pile anchor and internal support composite supporting system of claim 1, which is characterized in that: the support mechanism includes:
the main body of the support pile is of a cuboid structure design, and the two support piles are arranged in a transverse array.
3. The vertical high slope pile anchor and internal support composite supporting system of claim 2, characterized in that: the support mechanism includes:
the anti-slide piles are arranged at the inner side positions of the two support piles and form a shape like a Chinese character 'pin' together with the support piles, and a protection mechanism is further arranged on the front side of each anti-slide pile.
4. The vertical high slope pile anchor and internal support composite supporting system of claim 3, wherein: the guard mechanism includes:
the inner supporting piece is characterized in that the main body of the inner supporting piece is of a cuboid structure with a hollow interior, the inner supporting piece and the supporting pile form an L-shaped structure together, and an elastic assembly is arranged inside the inner supporting piece.
5. The vertical high slope pile anchor and internal support composite supporting system of claim 4, which is characterized in that: the guard mechanism includes:
and the anchor cable is hinged at the front side position of the support pile.
6. The vertical high slope pile anchor and internal support composite supporting system of claim 5, which is characterized in that: the guard mechanism includes:
the main body of the guide component is a cross-shaped block which is connected to the inner side of the inner supporting piece in a sliding manner, and the inner side of the guide component is also provided with a bearing mechanism.
7. The vertical high slope pile anchor and internal support composite supporting system of claim 6, which is characterized in that: the bearing mechanism comprises:
the waist beam is arranged at the inner side positions of the two inner supporting pieces.
CN202121711630.1U 2021-07-27 2021-07-27 Vertical high slope pile anchor and internal support composite supporting system Expired - Fee Related CN215857777U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121711630.1U CN215857777U (en) 2021-07-27 2021-07-27 Vertical high slope pile anchor and internal support composite supporting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121711630.1U CN215857777U (en) 2021-07-27 2021-07-27 Vertical high slope pile anchor and internal support composite supporting system

Publications (1)

Publication Number Publication Date
CN215857777U true CN215857777U (en) 2022-02-18

Family

ID=80331890

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121711630.1U Expired - Fee Related CN215857777U (en) 2021-07-27 2021-07-27 Vertical high slope pile anchor and internal support composite supporting system

Country Status (1)

Country Link
CN (1) CN215857777U (en)

Similar Documents

Publication Publication Date Title
CN103306289B (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN203905018U (en) Supporting and protecting system with combined double-row piles in combination with oblique anchors
CN109629576B (en) Suspension protection system for water supply pipe crossing foundation pit and construction method
CN111779025A (en) In-situ protection structure crossing foundation pit municipal pipe network box culvert and construction method
CN204919602U (en) Compound anchored retaining wall by tie rods
CN211816193U (en) Anchor draws formula steel sheet pile supporting construction
CN212129160U (en) Oblique-pulling foundation pit supporting structure for pile top
CN215857777U (en) Vertical high slope pile anchor and internal support composite supporting system
CN209779640U (en) foundation pit supporting pile top crown beam construction structure
CN112411615A (en) Design method of assembled debris flow drainage groove retaining wall
CN113389212A (en) Vertical high slope pile anchor and internal support composite support system and technological process
CN110685287A (en) Double-row pile foundation pit supporting system with drainage ditch and retaining wall and construction method
CN216765941U (en) Tunnel decompression load shedding structure under bias voltage state
CN110029685A (en) A kind of pile drawing anchor barricade fabricated construction
CN213897211U (en) Assembled debris flow drainage groove retaining wall
CN211772495U (en) Light embankment structure built on high and steep hillside
CN111503373A (en) Underground pipeline protection structure and construction method thereof
EP1061177A2 (en) Cantilevered structure for the protection of a communication route
CN113982004A (en) Anchor cable-reinforced soil combined soil retaining member and construction method thereof
CN210288408U (en) Foundation pit supporting structure
CN112323816A (en) Unloading type combined retaining structure and construction method thereof
CN205742292U (en) A kind of to the protection structure of existing tunnel below newly-built underground engineering
CN211200424U (en) Splicing prefabricated mountain slope supporting structure
CN218479820U (en) Supporting construction of surveying footrill
CN216193941U (en) Novel abutment structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220218

CF01 Termination of patent right due to non-payment of annual fee