CN215801105U CN202122232177.2U CN202122232177U CN215801105U CN 215801105 U CN215801105 U CN 215801105U CN 202122232177 U CN202122232177 U CN 202122232177U CN 215801105 U CN215801105 U CN 215801105U
Authority
CN
China
Prior art keywords
scaffold
bridge body
construction
hanging basket
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122232177.2U
Other languages
Chinese (zh)
Inventor
许涛
吴金水
芶作武
赵杨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Wujiang Construction Co ltd
Original Assignee
Fujian Wujiang Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Wujiang Construction Co ltd filed Critical Fujian Wujiang Construction Co ltd
Priority to CN202122232177.2U priority Critical patent/CN215801105U/en
Application granted granted Critical
Publication of CN215801105U publication Critical patent/CN215801105U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to the field of bridge construction, in particular to an operating platform for disassembling a hanging basket construction sliding frame. The scaffold is detachably connected to the outer guide beam, two ends of the outer guide beam are respectively arranged on a bottom die and a sliding frame of the hanging basket on the bridge body, and finish rolling deformed steel bars at the top of the sliding frame penetrate through the bridge body and then are connected to the hanging basket. The bottom plate is arranged at the bottom of the scaffold, and workers stand and walk on the bottom plate. The two protective doors are respectively hinged at two ends of the scaffold. The ejector rod is arranged on one side of the construction frame close to the bridge body, and when the construction frame is installed on the bridge body, the ejector rod butts against the side wall of the bridge body. In operation, a worker may stand on the floor of the scaffold to remove the carriage. The carriage is not required to be dismounted in a hanging mode, risks caused by high-altitude operation are avoided, potential safety hazards are eliminated, and due to the arrangement of the ejector rods, the situation that the scaffold is toppled due to unbalanced stress of the scaffold when a worker walks on the scaffold can be avoided, so that the safety of the scaffold and the worker is guaranteed.

Description

A operation platform for hanging basket construction balladeur train is dismantled
Technical Field
The utility model relates to the field of bridge construction, in particular to an operating platform for disassembling a hanging basket construction sliding frame.
Background
The hanging basket construction refers to the operation of segmenting the cantilever on site by adopting a hanging basket method when pouring a cantilever beam bridge with larger span. It does not need to erect a support and does not use a large crane. The hanging basket is manufactured in a factory, prepressing is carried out after field installation, after the safety of the hanging basket is checked and the deflection of an outer guide beam is detected, a template of a box beam, binding steel bars, installing corrugated pipes and pouring concrete can be erected, prestress paving is carried out after a pair of beam sections are poured, then the hanging basket is moved forwards, pouring of the next section of box beam is carried out until a cantilever end is reached, before the hanging basket is moved, in order to avoid abrasion of a poured bridge body caused by a bottom die on the hanging basket, the bottom die needs to be moved downwards firstly, so that the bottom die and the bridge body can move without obstacles after a certain gap is formed between the bottom die and the bridge body, but in order to enable the bottom die to be more balanced in the installation of the traditional hanging basket bottom die, the outer guide beam on the bottom die penetrates through a sliding frame and is hung on the hanging basket through the sliding frame, therefore, the sliding frame hanging the outer guide beam needs to be detached before the bottom die is moved, but because the sliding frame is in a suspended state, accidents easily occur in the disassembly process, and great potential safety hazards exist.
Disclosure of Invention
In view of the above-mentioned shortcomings of the background art, the present invention provides an operation platform for dismounting a cradle construction carriage.
The utility model adopts the following technical scheme that:
the construction frame is detachably connected to an outer guide beam, the head end of the outer guide beam is connected to a bottom die of the hanging basket, the tail end of the outer guide beam is erected on the sliding frame, the hanging basket is arranged on the bridge body, and finish rolling threaded steel at the top of the sliding frame penetrates through the bridge body and then is connected to the hanging basket;
the bottom plate is arranged at the bottom of the scaffold, and workers stand and walk on the bottom plate;
the two protective doors are respectively arranged at two ends of the scaffold and are hinged with the scaffold;
and the ejector rod is arranged on one side of the construction frame close to the bridge body, and when the construction frame is installed on the bridge body, the ejector rod props against the side wall of the bridge body.
As a further improvement, be equipped with fixed frame on one side that the scaffold is close to the pontic, this fixed frame comprises connecting rod and clamping bar, the connecting rod level sets up, and this connecting rod head end fixed connection to on the scaffold, and tail end one side of connecting rod is equipped with the clamping bar, the connecting rod below is located to the clamping bar, and the clamping bar removes about can the scaffold relatively, and this clamping bar is used for compressing tightly outer nose girder on the scaffold lateral wall.
As a further improvement, a screw rod is arranged between the clamping rod and the scaffold, and the screw rod penetrates through the clamping rod and then is fixed on the scaffold through a nut.
As a further improvement, a coaming is arranged on one side of the scaffold far away from the fixed frame and used for protecting workers.
As a further improvement, one end of the ejector rod close to the bridge body is provided with a roller wheel, and the roller wheel can cover the side wall of the bridge body in a rolling manner.
From the above description of the structure of the present invention, compared with the prior art, the present invention has the following advantages: the operation platform comprises a scaffold, a bottom plate, a protective door and a top rod. The scaffold is detachably connected to the outer guide beam, two ends of the outer guide beam are respectively arranged on the bottom die and the sliding frame of the hanging basket, the hanging basket is arranged on the bridge body, and the finish rolling deformed steel bar at the top of the sliding frame is connected to the hanging basket after penetrating through the bridge body. The bottom plate is arranged at the bottom of the scaffold, and workers stand and walk on the bottom plate. The two protective doors are respectively hinged at two ends of the scaffold. The ejector rod is arranged on one side of the construction frame close to the bridge body, and when the construction frame is installed on the bridge body, the ejector rod abuts against the side wall of the bridge body. In operation, a worker may stand on the floor of the scaffold to remove the carriage. The carriage is not required to be dismounted in a hanging mode, risks caused by high-altitude operation are avoided, potential safety hazards are eliminated, and due to the arrangement of the ejector rods, the situation that the scaffold is toppled due to unbalanced stress of the scaffold when a worker walks on the scaffold can be avoided, so that the safety of the scaffold and the worker is guaranteed.
Drawings
Fig. 1 is a schematic side view of the present invention mounted to a bridge.
Fig. 2 is a schematic perspective view of a scaffold and an outer guide beam.
Fig. 3 is a perspective view of the scaffold, floor, guard gate and ram 46.
Fig. 4 is a side view of the construction frame, the outer guide beam and the outer guide beam.
Fig. 5 is a schematic structural view of the upper prop of the scaffold abutting against the side wall of the bridge body.
Detailed Description
The following describes embodiments of the present invention with reference to the drawings.
As shown in fig. 1 and 2, an operation platform for detaching a cradle construction carriage comprises a scaffold 4, a bottom plate 42, a protective door 44 and a top bar 46.
As shown in fig. 1, 2 and 3, the head end of the outer guide beam 3 is connected to the bottom die 21 of the cradle 2, the tail end of the outer guide beam 3 is mounted on the carriage 5, the cradle 2 is disposed on the bridge 1, and the top finish-rolled thread steel of the carriage 5 passes through the bridge 1 and then is connected to the cradle 2, the scaffold 4 is detachably connected to the outer guide beam 3, specifically, a fixing frame 45 is disposed on one side of the scaffold 4 close to the bridge 1, the fixing frame 45 is composed of a connecting rod 451 and a clamping rod 452, the connecting rod 451 is horizontally disposed, the head end of the connecting rod 451 is fixedly connected to the scaffold 4, a clamping rod 452 is disposed on one side of the tail end of the connecting rod 451, the clamping rod 452 is disposed below the connecting rod 451, and the clamping rod 452 can move left and right relative to the scaffold 4, specifically, a lead screw 453 is disposed between the clamping rod 452 and the scaffold 4, the lead screw 453 is fixed to the scaffold 4 through a nut after passing through the clamping rod 452, during operation, make outer nose girder 3 place in earlier between clamping bar 452 and scaffold 4, rethread swivel nut makes clamping bar 452 remove along lead screw 453 and is close to outer nose girder 3, compresses tightly outer nose girder 3 on scaffold 4 lateral wall to realize the fixed connection of outer nose girder 3 and scaffold 4, avoid scaffold 4 to appear rotating in the use.
As shown in fig. 2 and 3, the bottom plate 42 is arranged at the bottom of the construction frame 4, when the sliding frame 5 for hanging the outer guide beam 3 needs to be disassembled, a worker can stand and walk on the bottom plate 42 to operate, the sliding frame 5 does not need to be disassembled in a hanging manner, the risk generated by high-altitude operation is avoided, and the potential safety hazard is eliminated.
As shown in fig. 3 and 4, two protection doors 44 are provided, two protection doors 44 are respectively provided at two ends of the scaffold 4, and the protection doors 44 are hinged to the scaffold 4, so that a worker can conveniently enter the scaffold 4 to operate by rotating the protection door 44 at one end of the scaffold 4 during operation. Further, be equipped with bounding wall 43 on the one side that fixed frame 45 was kept away from to scaffold 4, this bounding wall 43 is used for protecting the workman, avoids the workman to drop from scaffold 4, further ensures workman's safety.
As shown in fig. 4 and 5, the ejector rod 46 is disposed on one side of the scaffold 4 close to the bridge body 1, when the scaffold 4 is installed on the bridge body 1, the ejector rod 46 butts against the side wall of the bridge body 1, so as to enhance the stress bearing point of the scaffold 4, make the stress of the scaffold 4 more balanced, and avoid the situation that the scaffold 4 is toppled over due to unbalanced stress of the scaffold 4 when a worker walks on the scaffold 4, thereby ensuring the safety of the scaffold 4 and the worker. And the ejector rod 46 is equipped with the gyro wheel 461 near one end of the pontic 1, and this gyro wheel 461 can roll cover on the pontic 1 lateral wall, the setting of gyro wheel 461 for in-process that the scaffold 4 removed following the outer nose girder 3 and hanging the basket 2, be rolling friction between ejector rod 46 and the pontic 1 lateral wall, be favorable to scaffold 4 and ejector rod 46's steady movement.
Before the cradle 2 and the outer guide beam 3 are installed on the bridge body 1, the outer guide beam 3 on the cradle 2 is firstly placed between the clamping rod 452 and the construction frame 4, then the clamping rod 452 moves to be close to the outer guide beam 3 along the lead screw 453 by rotating the nut, the outer guide beam 3 is tightly pressed on the side wall of the construction frame 4, so as to realize the fixed connection of the outer guide beam 3 and the construction frame 4, the construction frame 4 is prevented from rotating in the using process, then the cradle 2 assembled with the construction frame 4 is installed on the bridge body 1, the box girder pouring is carried out, when the cradle 2 needs to move forwards, the protective door 44 at one end of the construction frame 4 can be opened, a worker enters the bottom plate 42 of the construction frame 4 to operate on the bottom plate 42, the carriage 5 hanging the outer guide beam 3 is detached, then the cradle 2 is moved according to the traditional mode, so as to continue to pour other box girders, the structure is simple, the operation is convenient, and the carriage 5 does not need to be detached in a suspended way, avoid the risk that high altitude construction produced, eliminated the potential safety hazard, and when scaffold 4 installed to outer nose girder 3 on, ejector pin 46 supported the bridge 1 lateral wall, can strengthen the atress bearing point of scaffold 4, made scaffold 4 atress more balanced, avoided the workman to cause the uneven scaffold 4 atress of scaffold 4 to topple over when walking about on scaffold 4 to guarantee scaffold 4 and workman's safety.
The above description is only an embodiment of the present invention, but the design concept of the present invention is not limited thereto, and any insubstantial modifications made by using the design concept should fall within the scope of infringing the present invention.

Claims (5)

1. The utility model provides an operation platform that is used for hanging basket construction balladeur train to dismantle which characterized in that, including:
the construction frame is detachably connected to an outer guide beam, the head end of the outer guide beam is connected to a bottom die of the hanging basket, the tail end of the outer guide beam is erected on the sliding frame, the hanging basket is arranged on the bridge body, and finish rolling threaded steel at the top of the sliding frame penetrates through the bridge body and then is connected to the hanging basket;
the bottom plate is arranged at the bottom of the scaffold, and workers stand and walk on the bottom plate;
the two protective doors are respectively arranged at two ends of the scaffold and are hinged with the scaffold;
and the ejector rod is arranged on one side of the construction frame close to the bridge body, and when the construction frame is installed on the bridge body, the ejector rod props against the side wall of the bridge body.
2. An operating platform for the disassembly of a cradle construction carriage as set forth in claim 1, characterized in that: the scaffold is equipped with fixed frame on one side of being close to the pontic, and this fixed frame comprises connecting rod and clamping bar, the connecting rod level sets up, and this connecting rod head end fixed connection to on the scaffold, and tail end one side of connecting rod is equipped with the clamping bar, the connecting rod below is located to the clamping bar, and the clamping bar removes about can the scaffold relatively, and this clamping bar is used for compressing tightly outer nose girder on the scaffold lateral wall.
3. An operation platform for the disassembly of a cradle construction carriage as set forth in claim 2, characterized in that: and a screw rod is arranged between the clamping rod and the scaffold, and the screw rod penetrates through the clamping rod and then is fixed on the scaffold through a nut.
4. An operation platform for the disassembly of a cradle construction carriage as set forth in claim 2, characterized in that: be equipped with the bounding wall on one side of fixed frame is kept away from to the scaffold, this bounding wall is used for protecting the workman.
5. An operating platform for the disassembly of a cradle construction carriage as set forth in claim 1, characterized in that: and one end of the ejector rod, which is close to the bridge body, is provided with a roller wheel, and the roller wheel can be covered on the side wall of the bridge body in a rolling manner.
CN202122232177.2U 2021-09-15 2021-09-15 A operation platform for hanging basket construction balladeur train is dismantled Active CN215801105U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122232177.2U CN215801105U (en) 2021-09-15 2021-09-15 A operation platform for hanging basket construction balladeur train is dismantled

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122232177.2U CN215801105U (en) 2021-09-15 2021-09-15 A operation platform for hanging basket construction balladeur train is dismantled

Publications (1)

Publication Number Publication Date
CN215801105U true CN215801105U (en) 2022-02-11

Family

ID=80160561

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122232177.2U Active CN215801105U (en) 2021-09-15 2021-09-15 A operation platform for hanging basket construction balladeur train is dismantled

Country Status (1)

Country Link
CN (1) CN215801105U (en)

Similar Documents

Publication Publication Date Title
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN101922143B (en) Construction method of bent cap
CN205077845U (en) Hydraulic intelligent climbing operation scaffold for core barrel well of building
CN102877637B (en) Method for implementing operating platform in bottom wall construction of cantilever beam
CN104695337B (en) Self-lifting sliding and turnover construction system and construction method
CN104196222B (en) The suspension scaffold of tools type section steel builder's jack
CN110259088B (en) Method for erecting external protection scaffold of building with twisted vertical face
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN107338727A (en) A kind of overall demolition, installation anticollision wall form and its walking track crane move system
CN205036072U (en) A shaped steel formwork support that encorbelments for high altitude structure of encorbelmenting
CN102912996B (en) Steel tube concrete column high-altitude construction safety protection system
CN206233541U (en) A kind of interior top external climbing mould bases operation platform for construction of super highrise building
CN105952133A (en) Suspended large-span reinforced concrete structure construction steel platform and construction method
CN215801105U (en) A operation platform for hanging basket construction balladeur train is dismantled
CN202954552U (en) Steel tube concrete column high-altitude construction safety protection system
CN206888904U (en) A kind of cat ladder for bridge pier column construction
CN203452375U (en) Hydraulic self-jacking oblique creeping formwork
CN211689948U (en) Suspension operation platform device for construction of suspension cable at tower part of cable-stayed bridge
CN111827648A (en) Construction device and method for down-supporting type overhanging scaffold
CN211006343U (en) Assembled steel structure ladder cage
CN208380058U (en) Removable hanging basket suspension scaffold
CN105776092A (en) Stretching type basket device and construction method thereof
CN106284989A (en) The sliding form bracing system of double track and complete construction method
CN105887884A (en) Single-side type rock anchor beam concrete pouring trolley
CN111979925B (en) Construction method for pouring diaphragm plate in hollow thin-wall pier by using fabricated construction platform

Legal Events

Date Code Title Description
GR01 Patent grant