CN215669462U - Auxiliary device for installing reinforcing cage of bored pile - Google Patents

Auxiliary device for installing reinforcing cage of bored pile Download PDF

Info

Publication number
CN215669462U
CN215669462U CN202122213816.0U CN202122213816U CN215669462U CN 215669462 U CN215669462 U CN 215669462U CN 202122213816 U CN202122213816 U CN 202122213816U CN 215669462 U CN215669462 U CN 215669462U
Authority
CN
China
Prior art keywords
plate
vertical plate
bored pile
guide
fixing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122213816.0U
Other languages
Chinese (zh)
Inventor
李山
柴峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Expressway Project Management Co ltd
Original Assignee
Shandong Expressway Project Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Expressway Project Management Co ltd filed Critical Shandong Expressway Project Management Co ltd
Priority to CN202122213816.0U priority Critical patent/CN215669462U/en
Application granted granted Critical
Publication of CN215669462U publication Critical patent/CN215669462U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses an auxiliary device for installing a steel reinforcement cage of a bored pile, which comprises a guide mechanism for guiding the steel reinforcement cage and an installation mechanism for fixing the guide mechanism on a pile casing, wherein the installation mechanism comprises a fixing mechanism for fixing on the pile casing, and the fixing mechanism is connected with the guide mechanism through a connecting piece. This device is in pile central point all the time and puts when making the steel reinforcement cage installation, need not adjust the position constantly when the steel reinforcement cage is transferred in the installation, increases the efficiency of construction, shortens construction period.

Description

Auxiliary device for installing reinforcing cage of bored pile
Technical Field
The utility model relates to the field of drilling and pouring, in particular to an auxiliary device for installing a reinforcing cage of a drilling and pouring pile.
Background
The cast-in-situ bored pile is a pile formed by forming a pile hole in foundation soil through mechanical drilling, steel pipe soil extrusion or manual excavation and the like on an engineering site, placing a reinforcement cage in the pile hole and pouring concrete into the pile hole. When the reinforcement cage is installed, workers mostly install and lower the reinforcement cage by experience and visual inspection in the construction process. This procedure has the disadvantage: 1. the steel bar worker needs to be closely matched with the crane, the position needs to be slowly adjusted when the steel bar cage is put down, and the efficiency is slow. 2. The steel reinforcement worker generally adjusts the position of the steel reinforcement cage by experience and visual inspection, and has operation errors and low precision. 3. The protecting wall is frequently scratched, so that mud clamping, sediment thickening and the like of the steel reinforcement cage can be caused, and the retreatment cost is higher.
SUMMERY OF THE UTILITY MODEL
Aiming at the defects, the utility model provides the auxiliary device for installing the reinforcement cage of the bored pile, so that the reinforcement cage can be positioned when entering the pile casing, the retaining wall cannot be scratched, and the construction is convenient.
The technical scheme of the utility model is as follows: the utility model provides a bored concrete pile steel reinforcement cage installation auxiliary device, is including being used for the guiding mechanism to the steel reinforcement cage direction and being used for fixing the installation mechanism at a section of thick bamboo that protects with guiding mechanism, installation mechanism including being used for fixing the fixed establishment who protects a section of thick bamboo, fixed establishment passes through the connecting piece and is connected with guiding mechanism. The guide mechanism can prevent the reinforcement cage from being scratched on the wall of the protective cylinder and also plays a role in guiding the reinforcement cage to enter the protective cylinder.
The guide mechanism comprises a guide pipe, and guide wheels are arranged at two ends of the guide pipe. The diameter of the guide wheel is larger than the outer diameter of the guide pipe. The outer diameter of the guide pipe is 4cm, and the diameter of the guide wheel is 5 cm. The guide wheels can play a role in sliding.
The fixing mechanism comprises a U-shaped clamping plate clamped on the protective cylinder, a locking bolt used for locking the wall of the protective cylinder is arranged in the U-shaped clamping plate, and the U-shaped clamping plate is fixed with the guide pipe through a connecting plate. The U-shaped clamping plate is used for fixing the wall of the protective cylinder and plays a supporting role in the guide mechanism.
The U-shaped cardboard includes first riser and second riser, and first riser and second riser are all fixed on the diaphragm, and the one end that the connecting plate is close to at the diaphragm is set up to the first riser, and the one end of connecting plate is kept away from at the diaphragm to the second riser setting, and the width of second riser is less than the width of first riser. The diaphragm contacts with the wall top of a casing, and the second riser is outside protecting the section of thick bamboo, and the first riser is inside protecting the section of thick bamboo.
The length of the first vertical plate is 6cm, and the width of the first vertical plate is 6 cm; the length of the second vertical plate is 6cm, the width of the second vertical plate is 4cm, the length of the transverse plate is 6cm, the width of the transverse plate is 5cm, and the 4cm side of the second vertical plate is fixed with the 6cm side of the transverse plate.
The locking bolt passes first riser and second riser, and the partial cover that is located between first riser and the second riser at the locking bolt is equipped with adjusting nut, and the bolt and nut combination can make fixed establishment fix on the protection wall, and the quantity of bolt can set up according to the in-service use needs.
The connecting plate is two, and the stand pipe is fixed between two connecting plates. The guide pipe is fixed with the connecting plate through a fixing bolt, the length of the connecting plate is 6.5cm, the width of the connecting plate is 4cm, and the long side of the connecting plate, which is 6.5cm, is fixed with the U-shaped clamping plate.
Can see through above-mentioned description, the U-shaped cardboard of this scheme can block at the wall top of protecting the section of thick bamboo, then fixes through the bolt, and guiding mechanism can lead by many steel reinforcement cages, avoids steel reinforcement cage to touch and protects a section of thick bamboo wall.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are only one embodiment of the present invention, and it is obvious for those skilled in the art to obtain other drawings without inventive exercise.
Fig. 1 is a schematic structural diagram of an embodiment of the present invention.
Fig. 2 is a bottom view of fig. 1.
In the figure: 1 is the second riser, 2 is the first riser, 3 is the diaphragm, 4 is the connecting plate, 5 is the leading wheel, 6 is locking bolt, 7 is fixing bolt, 8 is adjusting nut, 9 is the stand pipe.
Detailed Description
The following further describes embodiments of the present invention with reference to the drawings. It should be noted that the description of the embodiments is provided to help understanding of the present invention, but the present invention is not limited thereto. In addition, the technical features involved in the embodiments of the present invention described below may be combined with each other as long as they do not conflict with each other.
The auxiliary device for installing the steel reinforcement cage of the bored pile can be seen from the attached drawing, and comprises a guide mechanism for guiding the steel reinforcement cage and an installation mechanism for fixing the guide mechanism on a pile casing, wherein the installation mechanism comprises a fixing mechanism for fixing the pile casing, and the fixing mechanism is connected with the guide mechanism through a connecting piece.
The guide mechanism comprises a guide pipe 9, and guide wheels 5 are arranged at two ends of the guide pipe 9; the diameter of the guide wheel 5 is larger than the outer diameter of the guide pipe 9; in this embodiment the guide tube 9 has an outer diameter of 4cm and the guide wheel 5 has a diameter of 5 cm.
The fixing mechanism comprises a U-shaped clamping plate clamped on the protective cylinder, a locking screw 6 bolt used for locking the wall of the protective cylinder is arranged in the U-shaped clamping plate, and the U-shaped clamping plate is fixed with the guide pipe 9 through a connecting plate 4. The U-shaped cardboard includes first riser 2 and second riser 1, and first riser 2 and second riser 1 are all fixed on diaphragm 3, and first riser 2 sets up the one end that is close to connecting plate 4 at diaphragm 3, and second riser 1 sets up the one end of keeping away from connecting plate 4 at diaphragm 3, and the width of second riser 1 is less than the width of first riser 2. The length of the first vertical plate 2 is 6cm, and the width of the first vertical plate is 6 cm; the length of the second vertical plate 1 is 6cm, the width is 4cm, the length of the transverse plate 3 is 6cm, the width of the transverse plate is 5cm, and the 4cm side of the second vertical plate 1 is fixed with the 6cm side of the transverse plate 3. The locking bolt 6 passes through the first vertical plate 2 and the second vertical plate 1, and an adjusting nut 8 is sleeved on the part, located between the first vertical plate 2 and the second vertical plate 1, of the locking bolt 6. The number of the connecting plates 4 is two, and the guide pipe 9 is fixed between the two connecting plates 4. The guide pipe 9 is fixed with the connecting plate 4 through the fixing bolt 7, the length of the connecting plate 4 is 6.5cm, the width of the connecting plate 4 is 4cm, and the long side of 6.5cm of the connecting plate 4 is fixed with the U-shaped clamping plate.
When the device is used, holes are punched at the top of the wall of the protective cylinder, the number of the punched holes is the same as that of the locking bolts 6, the punched holes are matched with the locking bolts 6, then the U-shaped clamping plate is clamped on the protective cylinder, the second vertical plate 1 is arranged outside the protective cylinder, the first vertical plate 2 is arranged inside the protective cylinder, then the locking bolts 6 penetrate through the first vertical plate, the adjusting nuts 8 are arranged on the locking bolts 6, and then the locking bolts penetrate through the protective cylinder and the second vertical plate 1 to be fixed, so that the whole device can be fixed at the top of the protective cylinder to finish the installation of the device; the number of the devices arranged on the wall of the protective cylinder can be set and installed according to actual use requirements; be in pile central point all the time and put when making the steel reinforcement cage installation, need not adjust the position constantly when the steel reinforcement cage is transferred in the installation, increase the efficiency of construction, reduction of construction period.
The embodiments of the present invention have been described in detail with reference to the accompanying drawings, but the present invention is not limited to the described embodiments. It will be apparent to those skilled in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, and the scope of protection is still within the scope of the utility model.

Claims (10)

1. An auxiliary device for installing a reinforcement cage of a bored pile is characterized by comprising a guide mechanism for guiding the reinforcement cage and an installation mechanism for fixing the guide mechanism on a pile casing,
the mounting mechanism comprises a fixing mechanism for fixing the protective cylinder, and the fixing mechanism is connected with the guide mechanism through a connecting piece.
2. The bored pile cage installation aid of claim 1, wherein,
the guide mechanism comprises a guide pipe (9), and guide wheels (5) are arranged at two ends of the guide pipe (9).
3. The bored pile cage installation aid of claim 2, wherein,
the diameter of the guide wheel (5) is larger than the outer diameter of the guide pipe (9).
4. The bored pile cage installation aid of claim 3, wherein,
the outer diameter of the guide pipe (9) is 4cm, and the diameter of the guide wheel (5) is 5 cm.
5. The bored pile cage installation aid of claim 2, wherein,
the fixing mechanism comprises a U-shaped clamping plate clamped on the protective cylinder, a locking bolt (6) used for locking the wall of the protective cylinder is arranged in the U-shaped clamping plate, and the U-shaped clamping plate is fixed with the guide pipe (9) through a connecting plate (4).
6. The bored pile cage installation aid of claim 5, wherein,
the U-shaped clamping plate comprises a first vertical plate (2) and a second vertical plate (1), the first vertical plate (2) and the second vertical plate (1) are fixed on the transverse plate (3), the first vertical plate (2) is arranged at one end, close to the connecting plate (4), of the transverse plate (3), the second vertical plate (1) is arranged at one end, far away from the connecting plate (4), of the transverse plate (3), and the width of the second vertical plate (1) is smaller than that of the first vertical plate (1).
7. The bored pile cage installation aid of claim 6, wherein,
the length of the first vertical plate (2) is 6cm, and the width of the first vertical plate is 6 cm; the length of the second vertical plate (1) is 6cm, the width of the second vertical plate is 4cm, the length of the transverse plate is 6cm, the width of the transverse plate is 5cm, and the 4cm side of the second vertical plate (1) is fixed with the 6cm side of the transverse plate (3).
8. A bored pile cage installation aid according to claim 5 or 7, wherein,
the locking bolt (6) passes through the first vertical plate (2) and the second vertical plate (1), and the part of the locking bolt (6) between the first vertical plate (2) and the second vertical plate (1) is sleeved with the adjusting nut (8).
9. The bored pile cage installation aid of claim 5, wherein,
the number of the connecting plates (4) is two, and the guide pipe (9) is fixed between the two connecting plates (4).
10. The bored pile cage installation aid of claim 9, wherein,
the guide pipe (9) is fixed with the connecting plate (4) through a fixing bolt (7), the connecting plate (4) is 6.5cm long and 4cm wide, and the 6.5cm long side of the connecting plate (4) is fixed with the U-shaped clamping plate.
CN202122213816.0U 2021-09-14 2021-09-14 Auxiliary device for installing reinforcing cage of bored pile Active CN215669462U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122213816.0U CN215669462U (en) 2021-09-14 2021-09-14 Auxiliary device for installing reinforcing cage of bored pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122213816.0U CN215669462U (en) 2021-09-14 2021-09-14 Auxiliary device for installing reinforcing cage of bored pile

Publications (1)

Publication Number Publication Date
CN215669462U true CN215669462U (en) 2022-01-28

Family

ID=79963024

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122213816.0U Active CN215669462U (en) 2021-09-14 2021-09-14 Auxiliary device for installing reinforcing cage of bored pile

Country Status (1)

Country Link
CN (1) CN215669462U (en)

Similar Documents

Publication Publication Date Title
CN107700533B (en) A kind of box quick assembly and disassembly mould piping lane construction technology
CN109024571B (en) Method for installing and positioning reinforcement cage of bored pile and auxiliary device thereof
CN109577342B (en) Swift supporting device of circular pit construction
CN102493471A (en) Suspending installation construction process method of structural foot margin anchor bolt
CN215669462U (en) Auxiliary device for installing reinforcing cage of bored pile
KR20070093255A (en) Underground wall earth retaining structure by prestressed steel pipe and excavation construction method of having used this
CN212104105U (en) Deep foundation pit prestress support replacing and supporting system
CN204435361U (en) Arc iron and adopt the stake reinforcement installation structure of this arc iron
CN103850434A (en) Template capable of finishing construction of shear wall tension screw at one side
KR102315382B1 (en) Numerical Analysis Method for Determining the Decompression Size of Preload for Stability of Securing Wall
CN212455784U (en) Pipeline suspension structure
CN211547694U (en) Bored concrete pile steel reinforcement cage location centering device
CN210459229U (en) Support assembled in deep basal pit and trade and prop construction frock
CN210597281U (en) Bridge pile foundation in-situ binding reinforcement cage deviation control die carrier
CN209923971U (en) Suspension connecting device for steel pipe column and steel reinforcement cage in reverse construction
CN209854730U (en) Foundation ditch construction support for railway engineering
CN219137647U (en) Temporary fixing and centering tool for pile foundation reinforcement cage
CN208280644U (en) Open caisson and inverse device is installed as internal model
CN211974417U (en) Building structure reinforcing assembly
CN210263994U (en) Adjustable protection device for reserved line pipe returned below top plate
CN216142043U (en) Foundation pit support system
CN210507462U (en) Foundation ditch temporary support structure convenient to usefulness of speedily carrying out rescue work
CN205591545U (en) Instrument is consolidated to log template
CN219219046U (en) Underground diaphragm wall reinforcing and protecting structure
CN110700574A (en) Post-cast strip supporting structure and construction method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant