CN215594856U CN202121731122.XU CN202121731122U CN215594856U CN 215594856 U CN215594856 U CN 215594856U CN 202121731122 U CN202121731122 U CN 202121731122U CN 215594856 U CN215594856 U CN 215594856U
Authority
CN
China
Prior art keywords
hanging basket
baffle
fence
hanging
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121731122.XU
Other languages
Chinese (zh)
Inventor
田野
张尧华
周昕宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN202121731122.XU priority Critical patent/CN215594856U/en
Application granted granted Critical
Publication of CN215594856U publication Critical patent/CN215594856U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a hanging basket for house building safety construction, which comprises a hanging basket body (1), a fence (2), a sliding assembly, a baffle (3), a positioning assembly, a hanging piece (8) and a balance hoisting assembly, wherein the hanging basket body is fixedly connected with the fence; the fence is arranged at the top of the hanging basket body to form a hanging basket main body, and one end of the fence is open; the two ends of the baffle are respectively connected with the pair of sliding assemblies, the baffle can be slidably arranged on the basket body through the sliding assemblies and is positioned at the opening end of the fence, and the two ends of the baffle are connected with the basket body through the pair of positioning assemblies; a plurality of hangs a symmetry dress in rail top edge, and a pair of balanced lifting components symmetry dress is in rail top both sides, and balanced lifting components one end of every group hangs a plurality of and is connected with rail top one side, and the other end all is connected to the equipment of lifting by crane. The utility model can improve the integral stress uniformity and stability of the hanging basket main body in the lifting and construction processes, reserve construction operation space as much as possible and ensure the efficient and safe implementation of house construction.

Description

Hanging basket for house construction safety construction
Technical Field
The utility model relates to auxiliary equipment for building engineering, in particular to a hanging basket for safe construction of house construction.
Background
The hanging basket is also called a hanging basket, is a building tool for high-altitude operation of building engineering, can be used for curtain wall installation, outer wall cleaning and the like, is erected on a building or a structure through a cantilever mechanism, utilizes a lifting mechanism to drive a hanging platform, and is used as an operation platform for operators through a construction facility running up and down along the vertical surface of the building or the structure through a steel wire rope.
The utility model discloses a Chinese utility model ZL202021444831.5 discloses a be applied to safety of building construction and hang basket, including hanging the basket body and installing at the workstation that hangs the basket body, the workstation lower extreme has been installed and has been prevented the box that falls, a plurality of supporting legs has been installed to the workstation lower extreme, be equipped with the spout on the supporting legs, prevent falling the box two sides and have installed the slider, slider sliding fit spout, prevent falling box one side and have installed a plurality of hydraulic lifting column, hydraulic lifting column dress is established on hanging the basket body, it is equipped with the hydraulic pump to hang basket body facial make-up, the hydraulic pump facial make-up is equipped with defeated oil pipe, defeated oil pipe one side is installed on the hydraulic lifting column, prevent falling the box facial make-up and be equipped with a plurality of stopper, the stopper is installed on the workstation. This safety hangs basket in the work progress, reserves for the space of construction less, and inconvenient a plurality of operating personnel are under construction simultaneously, and need frequently adjust the position of safety hanging basket according to the process of construction. In addition, the safety hanging basket is only provided with hanging pieces in the middle parts of two sides, the safety hanging basket is easy to be stressed unevenly in the lifting process, the operator needs to walk in the safety hanging basket or concentrate on one side of the hanging basket in the construction process, the instability of the safety hanging basket is further aggravated, and certain potential safety hazards exist.
Disclosure of Invention
The utility model aims to provide a hanging basket for house building safety construction, which can improve the integral stress uniformity and stability of a hanging basket main body in the lifting and construction processes, reserve construction operation space as much as possible and ensure the efficient and safe house building construction.
The utility model is realized by the following steps:
a hanging basket for house construction safety construction comprises a hanging basket body, a fence, a sliding assembly, a baffle plate, a positioning assembly, a hanging piece and a balance hoisting assembly; the fence is fixedly arranged at the top of the hanging basket body to form a hanging basket main body, and one end of the fence is open; the two ends of the baffle are respectively connected with the pair of sliding assemblies, the baffle is slidably mounted on the basket main body through the sliding assemblies and is positioned at the opening end of the fence, and the two ends of the baffle are respectively fixedly connected with the basket main body through the pair of positioning assemblies; a plurality of hangs the piece and symmetrically installs respectively in the top edge of rail, and a pair of balanced lifting components symmetrically installs respectively in the top both sides of rail, and the one end of every group of balanced lifting components all hangs the piece through a plurality of and is connected with rail top one side, and the other end of every group of balanced lifting components all is connected to the equipment of lifting by crane.
Each group of balance hoisting components comprises a steel wire rope, a pulley and a hoisting rope; the pulleys are of a double-pulley structure, and the steel wire rope is wound around the plurality of hanging pieces positioned on one side of the top of the fence and the lower pulleys of the pulleys, so that the steel wire rope forms a triangular annular structure; one end of the lifting rope is wound around the upper pulley of the pulley, and the other end of the lifting rope is connected to the lifting equipment.
Each group of sliding assemblies comprises a sliding block and a sliding groove; the spout is vertical to be installed on the inner wall of hanging basket body and rail, and the slider setting is at the tip of baffle, and the slider can match the embedding and slide in the spout and along the spout, makes the baffle can pass through the spout and hang basket main part slidable connection.
Each group of positioning assemblies comprises a limiting piece; a plurality of limiting holes are formed in the inner walls of the hanging basket body and the fence at intervals, through holes are formed in the end portions of the baffles, and the limiting pieces fixedly connect the end portions of the baffles to the hanging basket main body through the through holes and one of the limiting holes; a plurality of limiting holes are longitudinally arranged at the side of the sliding component.
The bottom of the baffle is connected with an elastic net, the inner wall of the hanging basket body is provided with a plurality of hanging rings, and the bottom of the elastic net is hung on the hanging basket body through the hanging rings, so that the elastic net covers the opening end of the fence.
The outer wall of the hanging basket body is provided with a plurality of reflective strips.
The bottom of the inner wall of the hanging basket body is provided with an anti-slip pad.
The bottom surface of the cradle body is provided with a plurality of universal wheels, and each universal wheel is internally provided with a shock absorber.
Compared with the prior art, the utility model has the following beneficial effects:
1. the utility model is provided with the slidable and fixed baffle, so that an operator can adjust the height of the baffle according to the height of a construction position and the height of the operator, the baffle can ensure the shielding protection effect and simultaneously does not influence the construction operation, and the construction area is ensured to be reserved as much as possible so as to ensure the construction efficiency; meanwhile, the baffle is fixed after sliding positioning and cannot fall off, the effectiveness of the protection effect of the baffle is ensured, and the safety of operators in the construction process is ensured.
2. The hanging basket is provided with the hanging pieces and the balance hoisting assembly, the hanging pieces arranged at the four corners can increase the lifting stability of the hanging basket main body, and meanwhile, the automatic adjustment of the steel wire rope and the double-pulley structure is matched, so that external forces such as shaking and vibration and the like applied to the hanging basket main body can be automatically counteracted, the stress uniformity of each hanging piece is effectively improved, the integral stress of the hanging basket main body is uniform, the hanging basket main body is prevented from inclining in the lifting and construction processes, and the construction safety of operators is ensured.
Drawings
FIG. 1 is an exploded view of the hanging basket for house construction safety construction of the present invention;
FIG. 2 is an enlarged schematic view at A in FIG. 1;
FIG. 3 is an enlarged schematic view of point B in FIG. 1;
FIG. 4 is a perspective view of the hanging basket for house building safety construction of the present invention;
FIG. 5 is an enlarged schematic view at C in FIG. 4;
FIG. 6 is a perspective view of a balance lifting assembly in the hanging basket for house building safety construction according to the present invention;
fig. 7 is a perspective view of the baffle and the elastic net in the hanging basket for the safe construction of the house building.
In the figure, 1, a hanging basket body; 2. a fence; 3. a baffle plate; 4. an elastic net; 5. a limiting hole; 6. a through hole; 7. a limiting member; 8. a hanger; 9. a wire rope; 10. a pulley; 11. lifting a lifting rope; 12. a slider; 13. a chute; 14. a light-reflecting strip; 15. a non-slip mat; 16. hanging a ring; 17. a universal wheel.
Detailed Description
The utility model is further described with reference to the following figures and specific examples.
Referring to fig. 1 and 4, the hanging basket for the house building safety construction comprises a hanging basket body 1, a fence 2, a sliding assembly, a baffle 3, a positioning assembly, a hanging piece 8 and a balance lifting assembly; the fence 2 is fixedly arranged at the top of the hanging basket body 1 to form a hanging basket main body, and one end of the fence 2 is open; the two ends of the baffle 3 are respectively connected with the pair of sliding assemblies, the baffle 3 is slidably mounted on the basket body through the sliding assemblies and is positioned at the opening end of the fence 2, and the two ends of the baffle 3 are respectively fixedly connected with the basket body through the pair of positioning assemblies; a plurality of hangs piece 8 and symmetrically installs respectively in the top edge of rail 2, and a pair of balanced lifting components symmetrically installs respectively in the top both sides of rail 2, and the one end of every group of balanced lifting components all is connected with rail 2 top one side through a plurality of hanging pieces 8, and the other end of every group of balanced lifting components all is connected to the equipment of lifting by crane. Preferably, the sliding assembly, the positioning assembly and the balance hoisting assembly are two groups and are symmetrically arranged relative to the hanging basket main body, so that the uniform stress and the good overall balance performance of the hanging basket main body are ensured.
Referring to fig. 1, 4 and 6, each group of the balance hoisting assembly comprises a steel wire rope 9, a pulley 10 and a hoisting rope 11; the pulley 10 is of a double-pulley structure, and the steel wire rope 9 is wound through the plurality of hanging pieces 8 positioned on one side of the top of the fence 2 and the lower pulley of the pulley 10, so that the steel wire rope 9 forms a triangular annular structure; one end of the lifting rope 11 is wound around the upper pulley of the pulley 10, and the other end of the lifting rope 11 is connected to the lifting equipment. Preferably, the front end and the rear end of one side of the top of the fence 2 are both provided with a hanging part 8, the steel wire rope 9 is tensioned between the two hanging parts 8 and the lower pulleys of the pulleys 10 to form an isosceles triangle structure, and the lifting force is uniformly dispersed to the fence 2 through the steel wire rope 9, so that the stress uniformity and the lifting stability are ensured. Because the pulley 10 adopts a double-pulley structure and is installed in a non-fixed mode, automatic sliding adjustment can be realized between the lifting rope 11 and the steel wire rope 9, tensioning and force transmission of the steel wire rope 9 are further ensured, the stress stability of the basket body is ensured, the lifting and the construction process are not inclined, and the stability of the basket body 1 can be ensured even if an operator concentrates on a certain position of the basket body 1 or frequently walks in the basket body 1. The number of the hanging members 8 can be increased according to the actual conditions such as the width of the side end of the fence 2 and the load-bearing requirement.
Referring to fig. 2, 3 and 5, each set of the sliding components includes a sliding block 12 and a sliding groove 13; the spout 13 is vertical to be installed on the inner wall of hanging basket body 1 and rail 2, and slider 12 sets up the tip at baffle 3, and slider 12 can match and imbed in spout 13 and slide along spout 13, makes baffle 3 can pass through spout 13 and hang basket main part sliding connection. Slide through slider 12 makes baffle 3 slide from top to bottom in spout 13 to satisfy different work progress, constructor to the high requirement of sheltering from of baffle 3, ensure that baffle 3 plays effectual guard action, leave sufficient construction space in order to satisfy the construction requirement of great area sheltering from rail 2 opening part simultaneously. The slider 12 imbeds in spout 13, can prevent that baffle 3 from droing from hanging the basket main part, and baffle 3 can be stably slided from top to bottom under the restriction of both sides slider 12 and spout 13.
Each group of positioning components comprises a limiting piece 7; a plurality of limiting holes 5 are formed in the inner walls of the hanging basket body 1 and the fence 2 at intervals, through holes 6 are formed in the end portions of the baffles 3, and the limiting pieces 7 fixedly connect the end portions of the baffles 3 to the hanging basket main body through the through holes 6 and one of the limiting holes 5; a plurality of limiting holes 5 are longitudinally arranged at the side of the sliding chute 13 of the sliding component. Preferably, the limiting part 7 can adopt a bolt, the limiting hole 5 can adopt a screw hole matched with the specification of the limiting part 7, the limiting part 7 is convenient to lock the baffle 3 on the hanging basket main body through the limiting hole 5, and both ends of the baffle 3 are reliably fixed through the positioning assembly. According to the selection of the limiting holes 5 at different heights, the height adjusting requirements of the baffle 3 can be met, the baffle 3 is fixed, and the baffle 3 can provide effective safety guarantee for the construction process at a proper height.
Referring to fig. 7, the bottom of the baffle 3 is connected with an elastic net 4, the inner wall of the basket body 1 is provided with a plurality of hanging rings 16, the bottom of the elastic net 4 is hooked on the basket body 1 through the hanging rings 16, and the elastic net 4 covers the opening end of the fence 2. The opening part of the closed fence 2 is arranged through the elastic net 4, so that an operator can be prevented from falling from the opening part of the fence 2 in the lifting process, and the use safety of the hanging basket main body is further improved.
The outer wall of the hanging basket body 1 is provided with the plurality of light reflecting strips 14, so that the warning effect can be achieved, and the safety of building construction is further improved.
Hang basket body 1's inner wall bottom be equipped with slipmat 15, preferred, slipmat 15 can adopt materials such as rubber to make, can play skid-proof effect, the work progress is difficult to avoid involving liquid materials such as water, can effectively avoid constructing and make the inside standing facade of hanging basket body 1 wet and smooth and influence operating personnel's safe construction through slipmat 15.
The bottom surface of the cradle body 1 is provided with a plurality of universal wheels 17, and each universal wheel 17 is internally provided with a shock absorber (not shown in the figure). Preferably, the shock absorber can adopt damping spring, attenuator etc. and play the effect of shock attenuation, reduce the injury that the accident falls and lead to. The universal wheel 17 can realize the free sliding of the cradle body 1 on the ground, so that the utility model can be conveniently moved to a construction position, and the universal wheel 17 can adopt a roller with a brake pedal, so that the utility model can be positioned on the ground.
The using method of the utility model is as follows:
1. when building the surface construction, with baffle 3 through slider 12 along spout 13 drop to the minimum, make operating personnel can follow the opening position entering of rail 2 hang basket body 1 in, operating personnel is according to the height of construction position and operating personnel's height, adjust baffle 3 to suitable height along spout 13 gliding slider 12 that makes progress, make the position mutual interference of the height of baffle 3 and required construction, enlarge the construction reserved area as far as possible, and can play the guard action that prevents personnel and material and fall.
2. The two ends of the baffle 3 penetrate through the through hole 6 by using limiting pieces 7 such as bolts and the like and are in threaded connection with the limiting hole 5 at the height of the baffle 3, the baffle 3 is fixed on the hanging basket main body, and the opening part of the fence 2 is covered by the elastic net 4. The basket body is slid to a construction position by the universal wheel 17.
3. Through the lifting device of prior art lift by crane and hang basket main part, pulley 10's upper and lower pulley realizes freely sliding and adjustment between wire rope 9 and lifting rope 11, make wire rope 9 and lifting rope 11 realize automatic adjustment and reliable tensioning, reach the purpose of dispersion atress and even atress, effectively resist the vibrations of hanging basket main part, rock, wire rope 9 tensioning forms isosceles triangle's stable form, it is even to make 8 stress points of every piece of hanging, prevent to hang basket body 1 atress inequality and lead to slope and rock.
4. The opening part through rail 2 is under construction, and after the construction is completed, the opening part of rail 2 is covered by elastic net 4, so that the height and position of the basket body can be adjusted.
The present invention is not limited to the above embodiments, and any modifications, equivalent replacements, improvements, etc. within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (8)

1. The utility model provides a hang basket for safe construction is built in room which characterized by: the hanging basket comprises a hanging basket body (1), a fence (2), a sliding assembly, a baffle (3), a positioning assembly, a hanging piece (8) and a balance hoisting assembly; the fence (2) is fixedly arranged at the top of the hanging basket body (1) to form a hanging basket main body, and one end of the fence (2) is opened; the two ends of the baffle (3) are respectively connected with the pair of sliding assemblies, the baffle (3) is slidably mounted on the basket body through the sliding assemblies and is positioned at the opening end of the fence (2), and the two ends of the baffle (3) are respectively fixedly connected with the basket body through the pair of positioning assemblies; a plurality of hangs piece (8) and symmetrically installs respectively in the top edge of rail (2), and a pair of balanced lifting components symmetrically installs respectively in the top both sides of rail (2), and the one end of every group of balanced lifting components all hangs piece (8) and is connected with rail (2) top one side through a plurality of, and the other end of every group of balanced lifting components all is connected to the equipment of lifting by crane.
2. The hanging basket for the safe construction of the house building according to claim 1, which is characterized in that: each group of balance hoisting assemblies comprises a steel wire rope (9), a pulley (10) and a hoisting rope (11); the pulley (10) is of a double-pulley structure, and the steel wire rope (9) passes through a plurality of hanging pieces (8) positioned on one side of the top of the fence (2) and a lower pulley of the pulley (10) in a winding manner, so that the steel wire rope (9) forms a triangular annular structure; one end of the lifting rope (11) is wound around the upper pulley of the pulley (10), and the other end of the lifting rope (11) is connected to lifting equipment.
3. The hanging basket for the safe construction of the house building according to claim 1, which is characterized in that: each group of sliding components comprises a sliding block (12) and a sliding groove (13); spout (13) vertical installation is on the inner wall of hanging basket body (1) and rail (2), and slider (12) set up the tip at baffle (3), and slider (12) can match the embedding and slide in spout (13) and along spout (13), make baffle (3) can pass through spout (13) and hang basket main part sliding connection.
4. The hanging basket for the safe construction of the house building according to claim 1, which is characterized in that: each group of positioning components comprises a limiting piece (7); a plurality of limiting holes (5) are formed in the inner walls of the hanging basket body (1) and the fence (2) at intervals, through holes (6) are formed in the end portions of the baffles (3), and the limiting pieces (7) fixedly connect the end portions of the baffles (3) to the hanging basket main body through the through holes (6) and one of the limiting holes (5); a plurality of limiting holes (5) are longitudinally arranged at the side of the sliding component.
5. The hanging basket for the safe construction of the house building according to the claim 1, 3 or 4, characterized in that: the bottom of baffle (3) be connected with elasticity net (4), be equipped with a plurality of link (16) on the inner wall of string basket body (1), the bottom of elasticity net (4) is hung on string basket body (1) through a plurality of link (16), makes elasticity net (4) shroud in the open end department of rail (2).
6. The hanging basket for the safe construction of the house building according to the claim 1, 3 or 4, characterized in that: the outer wall of the hanging basket body (1) is provided with a plurality of light reflecting strips (14).
7. The hanging basket for the safe construction of the house building according to the claim 1, 3 or 4, characterized in that: the bottom of the inner wall of the hanging basket body (1) is provided with an anti-skid pad (15).
8. The hanging basket for the safe construction of the house building according to the claim 1, 3 or 4, characterized in that: the bottom surface of the cradle body (1) is provided with a plurality of universal wheels (17), and a shock absorber is arranged in each universal wheel (17).
CN202121731122.XU 2021-07-28 2021-07-28 Hanging basket for house construction safety construction Active CN215594856U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121731122.XU CN215594856U (en) 2021-07-28 2021-07-28 Hanging basket for house construction safety construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121731122.XU CN215594856U (en) 2021-07-28 2021-07-28 Hanging basket for house construction safety construction

Publications (1)

Publication Number Publication Date
CN215594856U true CN215594856U (en) 2022-01-21

Family

ID=79879307

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121731122.XU Active CN215594856U (en) 2021-07-28 2021-07-28 Hanging basket for house construction safety construction

Country Status (1)

Country Link
CN (1) CN215594856U (en)

Similar Documents

Publication Publication Date Title
CA1287025C (en) Perimeter safety net system for multi-story buildings under construction
CN111591932B (en) System and method for carrying people along anti-falling track on power transmission line
KR101975293B1 (en) The elevated workbench equipped with safety equipment for safety work and its safety equipment
CN108996421B (en) Finished furniture hoisting machine and finished furniture hoisting method
CN215594856U (en) Hanging basket for house construction safety construction
CN203128099U (en) Slipping type pipeline lifting device
CN111962854B (en) Scaffold with safety protection mechanism and building method
CN204827251U (en) Novel suit derrick upright
CN207829430U (en) Lifting type operation platform for suspension operation
CN210594945U (en) Movable hoisting operation frame for bridge floor wet joint construction
US20070267249A1 (en) Roof safety system
CN215889430U (en) Anti-falling device for structural engineering
CN204643664U (en) A kind of building tower crane
CN211058271U (en) Working platform
CN108222486A (en) A kind of building external application safety hanging cradle
CN211622541U (en) Domatic construction scaffold frame
CN210888772U (en) Safety device for electrical construction
KR20190033737A (en) Safety system for going up and down of tower-crane
CN208201644U (en) Suspension type safety work hanger
CN215052002U (en) Prevent roof beam dog that falls convenient to installation
CN219753908U (en) Sliding rack adherence operation platform for dismantling chimney and water tower
CN206539332U (en) Rigger's escape device
CN217027121U (en) Auxiliary device for high-altitude construction of foundation pit
CN206280720U (en) A kind of derrick low level installation and removal falling proof device
CN217079644U (en) Building construction ladder of ascending a height with protective structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant