CN215563028U - Vertical interim water supply pipe device of floor - Google Patents

Vertical interim water supply pipe device of floor Download PDF

Info

Publication number
CN215563028U
CN215563028U CN202121957514.8U CN202121957514U CN215563028U CN 215563028 U CN215563028 U CN 215563028U CN 202121957514 U CN202121957514 U CN 202121957514U CN 215563028 U CN215563028 U CN 215563028U
Authority
CN
China
Prior art keywords
water supply
floor
pipe
water receiving
receiving pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121957514.8U
Other languages
Chinese (zh)
Inventor
马磊
袁堃
沈兴东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN202121957514.8U priority Critical patent/CN215563028U/en
Application granted granted Critical
Publication of CN215563028U publication Critical patent/CN215563028U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provides a vertical temporary water supply pipeline device for floors, and belongs to the technical field of temporary water supply construction of high-rise buildings. The utility model comprises a plurality of water supply steel pipes which are pre-embedded in the concrete structural columns of the floors, the water supply steel pipes are connected with the rear water receiving pipes A in the construction floors through the reserved boxes, and the rear water receiving pipes A are mutually communicated, so that the communication among the water supply steel pipes in all the floors can be ensured. The rear water receiving pipe A in each construction floor is connected with the rear water receiving pipe B provided with a valve, the other end of the rear water receiving pipe B is connected with a water supply hose, and the water supply hose is laid on the floor plate and used by workers. The utility model uses different pipelines to install and connect aiming at different installation positions, adopts the water supply mode of combining various types of pipeline sections, effectively ensures the vertical water demand of high floors, solves the problems of slow vertical water supply efficiency of floors, easy damage of pipelines and low water supply efficiency, and has convenient integral installation and durability of the pipelines.

Description

Vertical interim water supply pipe device of floor
Technical Field
The utility model belongs to the technical field of temporary water supply construction of high-rise buildings, and particularly relates to a vertical temporary water supply pipeline device for floors.
Background
In recent years, with the continuous development of society and economy and the acceleration of urbanization construction process in China, high-rise and super-high-rise buildings in each large city emerge endlessly. Economic development enters the express way, high-rise buildings are driven to develop towards high-efficiency construction, and the engineering construction efficiency is required to be faster and faster under the condition of ensuring safety and quality.
In the work construction process, the floor all needs interim water when structure construction, fitment construction, electromechanical construction, and the floor is vertical higher, and interim water transports the difficulty more. Traditional interim water mode is that whole single type pipelines that adopt lay, wherein, when adopting the steel pipe to lay, the cycle length, cost are high, the dismouting is loaded down with trivial details, and the cost is lower when adopting the hose to lay, construction convenience, but the hose fragile, the water supply efficiency is low, can't solve the vertical water demand of high floor.
SUMMERY OF THE UTILITY MODEL
Aiming at the defects in the prior art, the utility model provides a floor vertical temporary water supply pipeline device, which is used for installing and connecting different pipelines aiming at different installation positions, and effectively solves the problems of low floor vertical water supply efficiency, easiness in pipeline damage and low water supply efficiency.
The present invention achieves the above-described object by the following technical means.
A floor vertical temporary water supply pipeline device comprises a plurality of water supply steel pipes pre-embedded in a floor concrete structure column, wherein a reserved box is further installed at a position of the side edge of the concrete structure column corresponding to the position of a pipe orifice of each water supply steel pipe, and each water supply steel pipe is connected with one end of the reserved box;
the other end of the reserved box is connected with a rear water receiving pipe A positioned in a construction floor, and a plurality of water supply steel pipes are communicated through the rear water receiving pipe A; the rear water receiving pipe A in each construction floor is connected with a rear water receiving pipe B provided with a valve, the other end of the rear water receiving pipe B is connected with a water supply hose, and the water supply hose is laid on a floor plate of the construction floor.
Furthermore, the water supply steel pipe is composed of a plurality of seamless steel pipes with the model number of DN20 and the material of Q235b in sections, and the sections are connected through mantle fiber.
Further, the water supply steel pipe is pre-buried at a position 5cm away from the side edge of the concrete structure column.
Furthermore, the reserved boxes on the side edge of the concrete structure column are uniformly arranged along the vertical direction at intervals, and the distance between the reserved boxes is 10 cm.
Further, the reserved box on the side edge of the concrete structure column close to the floor slab is 50cm away from the floor slab.
Furthermore, the rear water receiving pipe A and the rear water receiving pipe B are both PPR plastic pipes.
The utility model has the following beneficial effects:
according to the floor vertical temporary water supply pipeline device, different pipelines are used for installation and connection aiming at different installation positions, the water supply steel pipes are vertically pre-embedded in the concrete structural column, the water pipes are horizontally installed in the floor and then the water supply hoses are laid for constructors to use, the water supply mode of combining various types of pipe sections is adopted, the high floor vertical water demand is effectively guaranteed, the problems that the floor vertical water supply efficiency is low, the pipelines are easy to damage and the water supply efficiency is low are solved, the pipeline is convenient to integrally install and durable, the construction period can be shortened, and the floor vertical temporary water supply pipeline device has good economic benefits.
Drawings
Fig. 1 is a schematic structural view of a vertical temporary water supply pipeline device for a floor.
In the figure: 1-water supply steel pipe; 2-concrete structural column; 3-reserving a box; 4-the rear part is connected with a water pipe A; 5-connecting the water pipe B to the rear; 6-water supply hose; 7-a valve; 8-floor plate.
Detailed Description
The utility model will be further described with reference to the following figures and specific examples, but the scope of the utility model is not limited thereto.
As shown in fig. 1, the temporary water supply pipeline device for the vertical floor of the utility model comprises a water supply steel pipe 1, a water supply hose 6, a rear water receiving pipe a4, a rear water receiving pipe B5, a valve 7 and a reserved box 3.
The water supply steel pipe 1 is composed of a plurality of seamless steel pipes with the model number of DN20 and the material of Q235b in sections, and the sections are connected by mantle fiber. Pre-buried many water supply steel pipe 1 in the floor concrete structure post 2, specifically, the post reinforcing bar ligature of concrete structure post 2 is accomplished the back, with water supply steel pipe 1 location in the position department of 5cm apart from concrete structure post 2 side, be convenient for with reserve box 3 intercommunication, then will supply water steel pipe 1 and vertical post reinforcing bar ligature firm, carry out the installation of template after that.
A plurality of preformed holes are uniformly formed in the formwork on the side edge of the concrete structural column 2 at intervals along the vertical direction, the positions of the preformed holes correspond to the positions of pipe orifices of the water supply steel pipes 1, and the preformed boxes 3 are pre-embedded in the preformed holes; both ends of the reserved box 3 are provided with openings for installing pipelines, and the water supply steel pipe 1 is connected with one end of the reserved box 3. The distance between the preformed holes is 10cm, and the distance between the preformed holes at the bottom layer close to the floor plate 8 and the floor plate 8 is 50 cm. And the reserved box 3 is temporarily blocked during concrete pouring, so that concrete is prevented from entering the reserved box 3. And after the strength of the concrete meets the requirement, the concrete structural column is demolded, and the reserved box 3 can be stably fixed on the side edge of the concrete structural column 2.
The rear water receiving pipe A4 and the rear water receiving pipe B5 are both arranged in a construction floor outside the concrete structure column 2 and are both made of PPR plastic pipes. The other end of the reserved box 3 is connected with a rear water receiving pipe A4, so that the water supply steel pipe 1 is communicated with the rear water receiving pipe A4 through the reserved box 3; the back water receiving pipe A4 other end in each floor all passes through mantle fiber interconnect together, can realize the intercommunication between the water supply steel pipe 1 in each floor, and then realizes the water supply transportation of each floor.
The rear water receiving pipe A4 in each construction floor is connected with a rear water receiving pipe B5 through a three-way pipe fitting, a valve 7 is installed on the rear water receiving pipe B5, the other end of the rear water receiving pipe B5 is connected with a water supply hose 6, and the water supply hose 6 is laid on a floor plate 8 of the corresponding construction floor and used by construction workers.
The present invention is not limited to the above-described embodiments, and any obvious improvements, substitutions or modifications can be made by those skilled in the art without departing from the spirit of the present invention.

Claims (6)

1. A floor vertical temporary water supply pipeline device is characterized by comprising a plurality of water supply steel pipes (1) pre-embedded in a floor concrete structure column (2), wherein a reserved box (3) is further installed at the side position of the concrete structure column (2) corresponding to the position of a pipe orifice of each water supply steel pipe (1), and each water supply steel pipe (1) is connected with one end of the reserved box (3);
the other end of the reserved box (3) is connected with a rear water receiving pipe A (4) positioned in a construction floor, and the plurality of water supply steel pipes (1) are communicated through the rear water receiving pipe A (4); the rear water receiving pipe A (4) in each construction floor is connected with a rear water receiving pipe B (5) provided with a valve (7), the other end of the rear water receiving pipe B (5) is connected with a water supply hose (6), and the water supply hose (6) is laid on a floor plate (8) of the construction floor.
2. The temporary water supply pipeline device for the vertical floor of claim 1, wherein the water supply steel pipe (1) is composed of a plurality of seamless steel pipe sections with the model number of DN20 and the material of Q235b, and the sections are connected by mantle fiber.
3. The temporary water supply pipeline device for the vertical floor of claim 1, wherein the water supply steel pipe (1) is pre-buried at a distance of 5cm from the side of the concrete structural column (2).
4. Temporary water supply pipe installation according to claim 1, characterised in that the preformed boxes (3) on the side of the concrete structural column (2) are vertically evenly spaced at intervals of 10 cm.
5. Temporary water supply installation according to floor level according to claim 4, characterized in that the reserved boxes (3) on the sides of the concrete structural columns (2) close to the floor level (8) are 50cm from the floor level (8).
6. The device of claim 1, wherein the rear water receiving pipe A (4) and the rear water receiving pipe B (5) are PPR plastic pipes.
CN202121957514.8U 2021-08-19 2021-08-19 Vertical interim water supply pipe device of floor Active CN215563028U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121957514.8U CN215563028U (en) 2021-08-19 2021-08-19 Vertical interim water supply pipe device of floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121957514.8U CN215563028U (en) 2021-08-19 2021-08-19 Vertical interim water supply pipe device of floor

Publications (1)

Publication Number Publication Date
CN215563028U true CN215563028U (en) 2022-01-18

Family

ID=79839724

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121957514.8U Active CN215563028U (en) 2021-08-19 2021-08-19 Vertical interim water supply pipe device of floor

Country Status (1)

Country Link
CN (1) CN215563028U (en)

Similar Documents

Publication Publication Date Title
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN210712751U (en) Aqueduct trough body post-cast strip concrete formwork mounting structure
CN104631674A (en) Composite floor slab and construction method thereof
CN215563028U (en) Vertical interim water supply pipe device of floor
CN210263131U (en) Assembled is from stagnant water underground pipe gallery structure
CN205399773U (en) Assembled floor of light -duty building structure
CN202117320U (en) Floating-resistant device for inner circle mold of circulation water pipe trench
CN109518857B (en) Bidirectional laminated slab side splicing joint connecting structure and laminated slab construction method
CN209723346U (en) A kind of firm energy-saving building laminated floor slab
CN109137984A (en) Assembled integral mixes prefabricated pipe gallery
CN211285692U (en) Corrugated steel pipe gallery based on prestressed tendons
CN114809512A (en) Oversized prefabricated bare concrete hanging plate and manufacturing and mounting process
CN211286164U (en) Self-compaction regeneration block concrete superimposed shear wall
CN210685112U (en) Steel-concrete combined prefabricated bottom plate assembly for laminated slab and wall
CN204491663U (en) Prestressed structure function formula underground pipe gallery combined system
CN203346950U (en) Hidden laying structure for temporary water supply pipes of high-rise building
CN113653239A (en) Construction method of self-supporting steel bar truss template system
CN204850188U (en) One -way superimposed sheet piece connection structure
CN112127541A (en) Assembled floor veneer integrated board convenient to handling
CN220166993U (en) Post-pouring belt structure at junction part of basement outer wall and underground continuous wall
CN211773870U (en) Prefabricated assembly structure of underground pipe gallery
CN203213393U (en) Ribbed plate provided with longitudinal and transversal ribs
CN110847960A (en) Three-arch tunnel drainage device and construction method thereof
CN201826364U (en) Combined installation structure of flexible cast iron drain pipe in toilets of high-rise buildings
CN212427796U (en) Prefabricated floor slab

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant