CN215402619U - Temporary supporting node for steel beam hoisting - Google Patents
Temporary supporting node for steel beam hoisting Download PDFInfo
- Publication number
- CN215402619U CN215402619U CN202121605295.7U CN202121605295U CN215402619U CN 215402619 U CN215402619 U CN 215402619U CN 202121605295 U CN202121605295 U CN 202121605295U CN 215402619 U CN215402619 U CN 215402619U
- Authority
- CN
- China
- Prior art keywords
- embedded
- steel
- plate
- steel beam
- hoisting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a temporary support node for hoisting a steel beam, which comprises an embedded steel plate, an embedded part, a triangular support plate and a height adjusting gasket, wherein one end of the embedded part is fixedly connected with the embedded steel plate, and the other end of the embedded part is embedded into concrete of an external mounting structure, so that the embedded steel plate is attached and fixed to the surface of the concrete of the external mounting structure in a way that the plate surface is vertical; two triangular support plates are arranged on the outer surface of the embedded steel plate on two sides of the lap joint position of the web plate of the external H-shaped steel beam. According to the utility model, the triangular support plates are arranged in front of the embedded structures for installing the steel beams, so that the lap joint bracket for temporarily supporting the steel beams is formed, when the steel beams are basically hoisted in place, the steel beams can be temporarily placed on the top surfaces of the two triangular support plates, the hoisting can be removed after the position accuracy is verified, and the problem that the time consumed by hoisting a tower crane during the operation of hoisting the steel beams is too long is solved.
Description
Technical Field
The utility model belongs to the field of building construction structures, and particularly relates to a temporary support node for steel beam hoisting.
Background
In the steel structure construction process, the girder steel hoist and mount operation step is usually: ground steel beam hoisting preparation work → hoisting air movement → hoisting in place, then steel beam welding installation → crane resetting after hoisting is removed. For example, in the utility model patent of application number CN200920157328.9, disclose a whole through steel core concrete column of girder steel, girder steel connected node, it is slotted according to the girder steel size on steel core concrete column, wholly pass through steel core concrete column with the girder steel in succession to melt the groove welding thoroughly with girder steel and steel pipe completely, then pour the concrete, splice girder steel and girder steel on-the-spot. In the steel beam hoisting scheme, after the tower crane is hoisted in place, the crane needs to be hoisted after the steel beam and the structural embedded steel plate are welded, the time of occupying the tower crane is long, and the project construction progress is directly influenced.
Therefore, how to ensure the safety of steel beam hoisting construction and reduce the time consumption of tower crane hoisting during steel beam hoisting operation is a technical problem to be solved urgently at present.
Disclosure of Invention
The utility model aims to solve the problem that in the prior art, the hoisting time of a tower crane is too long during the steel beam hoisting operation, and provides a temporary support node for steel beam hoisting.
The utility model adopts the following specific technical scheme:
a temporary support node for hoisting a steel beam comprises an embedded steel plate, an embedded part, a triangular support plate and a height adjusting gasket, wherein one end of the embedded part is fixedly connected with the embedded steel plate, and the other end of the embedded part is embedded into concrete of an external mounting structure, so that the embedded steel plate is attached and fixed to the surface of the concrete of the external mounting structure in a manner that the surface of the embedded steel plate is vertical; two triangular support plates are arranged on the outer surface of the embedded steel plate on two sides of the lap joint position of the web plate of the external H-shaped steel beam, the triangular support plates are right-angled triangular steel plates, one right-angled side of each triangular support plate is fixedly welded with the outer surface of the embedded steel plate, and the other right-angled side of each triangular support plate is kept horizontal and used for placing the height adjusting gasket; the elevations of the horizontal right-angle sides of the two triangular supporting plates are the same and are respectively used for supporting the upper flanges on the two sides of the external H-shaped steel beam.
Preferably, the welding seam between the triangular support plate and the outer surface of the embedded steel plate is in the form of an intermittent welding seam or a continuous full-length welding seam.
Preferably, the embedded part is an L-shaped steel bar.
Preferably, 4 embedded parts are uniformly arranged on the embedded steel plate.
Preferably, the height adjusting shim has a plurality of pieces with different thicknesses, and is selectively placed on the triangular support plate.
Preferably, the height adjusting shim is laid on the horizontal edge of the triangular support plate in a non-fixed manner.
Preferably, the thickness of the triangular supporting plate is not less than 6 mm.
Preferably, the embedded steel plate and the embedded part are fixed through welding.
Preferably, the embedded steel plate, the embedded part, the triangular support plate and the height adjusting gasket are all made of steel.
Preferably, the external mounting structure is a shear wall or a structural beam.
Compared with the prior art, the utility model has the following beneficial effects:
according to the utility model, the triangular support plates are arranged in front of the embedded structure for installing the steel beams, so that the lap joint bracket for temporarily supporting the steel beams is formed, when the steel beams are basically hoisted in place, the steel beams can be temporarily placed on the top surfaces of the two triangular support plates, and the hoisting can be removed after the position accuracy is verified. Practice proves that the time consumed by lifting each steel beam tower crane is reduced from the original 25 minutes to the current 18 minutes after the method is adopted, and the lifting time of the tower crane is greatly reduced. Therefore, the method can be widely applied to steel structure hoisting operation, and the problem that the hoisting time of the tower crane is too long during the steel beam hoisting operation is solved.
Drawings
FIG. 1 is a bottom view of a steel beam hoisting temporary support node;
FIG. 2 is a front view of a temporary support node for hoisting steel beams;
FIG. 3 is a schematic view of a gusset;
fig. 4 is a schematic view of the installation of the H-shaped steel beam on the support node.
The reference numbers in the figures are: the steel plate height adjusting device comprises an embedded steel plate 1, an embedded part 2, a triangular support plate 3, a height adjusting gasket 4, an H-shaped steel beam 5, a vertical welding line 6 and a horizontal welding line 7.
Detailed Description
The utility model will be further elucidated and described with reference to the drawings and the detailed description. The technical features of the embodiments of the present invention can be combined correspondingly without mutual conflict.
For convenience of description, the building structure for mounting the steel beam is referred to as an external mounting structure in the present invention, and the external mounting structure may be a shear wall or a structural beam, etc. in practical applications.
As shown in fig. 1, in a preferred embodiment of the present invention, a temporary supporting node for steel beam hoisting is provided, which mainly comprises an embedded steel plate 1, an embedded part 2, a triangular supporting plate 3 and a height adjusting shim 4, wherein the embedded steel plate 1, the embedded part 2, the triangular supporting plate 3 and the height adjusting shim 4 are made of steel.
The embedded steel plates 1 and the embedded parts 2 are used for forming an embedded structure on an external mounting structure and providing fixing points for the end portions of the steel beams. The embedded part 2 can generally adopt L shaped steel muscle to replace, and the one end and the embedded steel sheet 1 fixed connection of embedded part 2, inside the concrete of the external installation structure of other end embedding, make embedded steel sheet 1 with the laminating of the vertically form of face be fixed in external installation structure's concrete surface. The embedded structure can be embedded in a reinforcement cage in advance before concrete of the external mounting structure is poured, and can be combined with the external mounting structure into a whole after subsequent concrete is poured. However, it should be noted that the outer surface of the embedded steel plate 1 needs to protrude out of the concrete surface of the external mounting structure, so as to facilitate the subsequent welding operation.
In consideration of the stability of the embedded structure, a plurality of embedded parts 2 can be uniformly distributed on the embedded steel plate 1, and 4 embedded parts 2 are shown in the figure and are respectively positioned at four corners of the embedded steel plate 1.
In the utility model, the temporary supporting function provided by the embedded structure is realized by the two triangular supporting plates 3, the two triangular supporting plates 3 are fixed on the outer surface of the embedded steel plate 1, and the specific positions of the two triangular supporting plates 3 are determined according to the lap joint position of the web plate of the H-shaped steel beam 5 to be installed subsequently. The two triangular support plates 3 are fixed on two sides of the lap joint position of the web plate of the H-shaped steel beam 5 and the embedded steel plate 1. The two triangular support plates 3 are both right-angled triangular steel plates which are provided with two right-angled sides. One right-angle side of each triangular support plate 3 is welded and fixed with the outer surface of the embedded steel plate 1, the other right-angle side is kept horizontal, the elevations of the horizontal right-angle sides of the two triangular support plates 3 are the same, and the two right-angle sides are respectively used for supporting the upper flanges of the two sides of the external H-shaped steel beam 5. H shaped steel roof beam 5 is in hoist and mount in-process, and the web of its tip inserts between two triangular support board 3, and the both sides top flange can interim overlap joint at the horizontal right angle edge of two triangular support board 3, need not welding process and can form interim load-carrying structure.
Although the elevations of the horizontal right-angle sides of the two triangular support plates 3 are the same, the height adjusting gaskets 4 are placed on the horizontal right-angle sides of the triangular support plates 3 to solve the problem in consideration of inevitable error factors in the field construction process and machining error factors of the H-shaped steel beam 5, and the top flanges on the two sides of the H-shaped steel beam 5 still can not be attached to the top sides of the two triangular support plates 3 in the hoisting process. Height adjustment gasket 4 can adopt the steel sheet to replace, and its effect is that the level is shelved on the horizontal right angle edge of triangular support plate 3 to this changes and to the support plane height on the edge of a wing on the H shaped steel roof beam 5, guarantees that the both sides top edge of a wing of H shaped steel roof beam 5 can both just laminate the horizontal right angle edge in top of both sides triangular support plate 3.
Therefore, it should be noted that the height adjusting shim 4 is set according to actual construction needs on site, and only needs to be set aside when a gap exists between the upper flange of the H-shaped steel beam 5 and the top horizontal right-angle side of the triangular support plate 3 on one side or two sides. Moreover, the height adjusting shim 4 can be directly placed on the horizontal edge of the triangular support plate 3, and the height adjusting shim and the triangular support plate need to be welded and fixed, because the upper flange of the H-shaped steel beam 5 is pressed on the height adjusting shim 4 and then the height adjusting shim, the H-shaped steel beam and the H-shaped steel beam can be naturally and stably fixed under the action of pressure. Because the clearance between the upper flange of H shaped steel roof beam 5 and the top level right-angle side of triangular support plate 3 changes along with different job site conditions, consequently can realize preparing the high adjustment gasket 4 of multiple-disc different thickness, on-the-spot alternative as required places in triangular support plate 3.
In addition, since the triangular support plate 3 needs to temporarily bear the load of the H-shaped steel beam 5 before the H-shaped steel beam 5 is formally welded and fixed, the welded and fixed connection between the triangular support plate 3 and the outer surface of the embedded steel plate 1 should maintain high strength, and the form of the welding line should be an intermittent welding line or a continuous full-length welding line. The thickness of the triangular support plate 3 is not too small, and should not be less than 6 mm.
The concrete installation process of the steel beam hoisting temporary support node and the H-shaped steel beam 5 is as follows:
the first step is as follows: according to a design drawing, pre-buried steel plates 1 and pre-buried parts 2 for welding steel beams are pre-buried at the positions of the shear walls or the structural beams.
The second step is that: after concrete pouring and template dismantling are completed, the elevation of the embedded steel plate 1 is controlled by using a total station according to a floor datum point, the welding height of the triangular support plate 3 corresponding to the layer of H-shaped steel beam 5, namely the height of the floor steel beam minus the thickness of the upper flange of the steel beam, is determined, and marking is performed; and then lofting the axial position of the steel beam, wherein the measurement lofting related error meets the standard requirement.
The third step: preparing two triangular support plates 3 in advance, wherein the triangular support plates 3 have rigidity for bearing the weight of the steel beam and are not less than 6mm, welding the two triangular support plates 3 with the outer surface of the embedded steel plate 1 according to the lofting position, and welding seams can be in the form of intermittent welding or continuous full welding and are forbidden to be spot-welded.
The fourth step: lifting the H-shaped steel beam 5, after the H-shaped steel beam 5 is lifted basically in place, temporarily placing one end of the H-shaped steel beam 5 on the top horizontal right-angle edges of the two triangular support plates 3, and verifying the position accuracy. If there is the clearance at this moment can add height adjustment gasket 4, guarantee that the both sides top flange of H shaped steel roof beam 5 can both just laminate the horizontal right-angle side in top of both sides triangular support plate 3.
The fifth step: and (3) dismantling the shackle of the tower crane hook connected with the H-shaped steel beam 5, rechecking the accuracy of the installation position of the steel beam through a total station after the tower crane is unhooked, removing the crane and performing formal welding operation on the H-shaped steel beam 5. The vertical lap joints of the web plate of the H-shaped steel beam 5 and the horizontal lap joints of the upper flange and the lower flange are required to be welded to form vertical welding seams 6 and horizontal welding seams 7, and the final structure is shown in figure 4.
During the operation of hoisting conventional steel beams, after the steel beams are hoisted in place by the tower crane, the hoisting can be removed after the welding of the steel beams and the embedded steel plates is completed, and the time consumption of the tower crane is long. By adopting the utility model, the time consumption of the tower crane can be greatly reduced, and after the steel beam is hoisted in place, the steel beam can be temporarily placed on the two triangular support plates 3 to be hoisted.
The above-described embodiments are merely preferred embodiments of the present invention, which should not be construed as limiting the utility model. Various changes and modifications may be made by one of ordinary skill in the pertinent art without departing from the spirit and scope of the present invention. Therefore, the technical scheme obtained by adopting the mode of equivalent replacement or equivalent transformation is within the protection scope of the utility model.
Claims (10)
1. A steel beam hoisting temporary support node is characterized by comprising an embedded steel plate (1), an embedded part (2), a triangular support plate (3) and a height adjusting gasket (4), wherein one end of the embedded part (2) is fixedly connected with the embedded steel plate (1), and the other end of the embedded part is embedded into concrete of an external mounting structure, so that the embedded steel plate (1) is attached and fixed to the surface of the concrete of the external mounting structure in a manner that the surface of the embedded steel plate is vertical; two triangular support plates (3) are arranged on the outer surface of the embedded steel plate (1) on two sides of the web plate lap joint position of the external H-shaped steel beam (5), each triangular support plate (3) is a right-angled triangular steel plate, one right-angled side of each triangular support plate is fixedly welded with the outer surface of the embedded steel plate (1), and the other right-angled side of each triangular support plate is kept horizontal and used for placing the height adjusting gasket (4); the elevations of the horizontal right-angle sides of the two triangular supporting plates (3) are the same and are respectively used for supporting the flanges on the two sides of the external H-shaped steel beam (5).
2. The steel beam hoisting temporary support node as claimed in claim 1, wherein the welding seam between the triangular support plate (3) and the outer surface of the embedded steel plate (1) is in the form of an intermittent welding seam or a continuous full-length welding seam.
3. The steel beam hoisting temporary support node of claim 1, wherein the embedded part (2) is an L-shaped steel bar.
4. The steel beam hoisting temporary support node of claim 1, wherein 4 embedded parts (2) are uniformly arranged on the embedded steel plate (1).
5. The steel beam hoisting temporary support node of claim 1, wherein the height adjusting shim (4) has a plurality of pieces with different thicknesses, and is selectively placed on the triangular support plate (3).
6. The steel beam hoisting temporary support node of claim 1, wherein the height adjusting shim (4) rests in a non-fixed manner on the horizontal side of the triangular support plate (3).
7. The steel beam hoisting temporary support node of claim 1, wherein the triangular support plate (3) has a thickness of not less than 6 mm.
8. The steel beam hoisting temporary support node as claimed in claim 1, wherein the embedded steel plate (1) and the embedded part (2) are fixed by welding.
9. The steel beam hoisting temporary support node of claim 1, wherein the embedded steel plate (1), the embedded part (2), the triangular support plate (3) and the height adjusting gasket (4) are made of steel.
10. The steel beam-hoisting temporary support node of claim 1, wherein the external mounting structure is a shear wall or a structural beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121605295.7U CN215402619U (en) | 2021-07-14 | 2021-07-14 | Temporary supporting node for steel beam hoisting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121605295.7U CN215402619U (en) | 2021-07-14 | 2021-07-14 | Temporary supporting node for steel beam hoisting |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215402619U true CN215402619U (en) | 2022-01-04 |
Family
ID=79649591
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121605295.7U Active CN215402619U (en) | 2021-07-14 | 2021-07-14 | Temporary supporting node for steel beam hoisting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215402619U (en) |
-
2021
- 2021-07-14 CN CN202121605295.7U patent/CN215402619U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100572256C (en) | The installation method of giant crane beam | |
CN102296728A (en) | Double-steel plate structure shear wall and construction method thereof | |
CN108678398B (en) | Pre-assembly method for steel structure truss of reinforced layer of super high-rise building | |
CN103410322A (en) | Large-span parallel truss steel connective corridor construction method | |
CN105401732A (en) | Assembling method of large steel structure module of nuclear power plant | |
CN113401309B (en) | Segmented construction method for bottom side cabin of bulk cargo ship | |
CN104674665A (en) | Installation method for corridor bridge of large space steel structure | |
CN102777044B (en) | Hoisting method of steel-structured spraying layer of urea prilling tower | |
CN107795005A (en) | A kind of steel core concrete column and reinforced concrete column concrete core cylinder mixed structure and installation method | |
CN215402619U (en) | Temporary supporting node for steel beam hoisting | |
CN211340840U (en) | Tower crane foundation of internal climbing tower crane | |
CN215594551U (en) | Steel bar truss carrier plate lift plate node | |
CN103615058B (en) | A kind of constraint steel plate construction of super high-rise steel plate concrete shear wall and construction method thereof | |
CN107938854A (en) | A kind of steel girder erection method using built-in fitting | |
CN210482709U (en) | Lifting plate node structure of steel bar truss floor bearing plate | |
CN107366232A (en) | Steel box-girder chooses the embedding section of mending of arm decorative panel and integrally faces upward dress method | |
CN114382202A (en) | Integral pre-assembly hoisting construction method suitable for external wall heat insulation integration | |
CN113668706A (en) | Installation and construction method for connecting node area of steel reinforced concrete column and steel beam | |
KR20130106982A (en) | Steel connection structure for self-positioning of composite precast concrete member and construction method thereof | |
CN112962945A (en) | Corner bracket structure and construction method | |
CN221318823U (en) | Prefabricated platform for adjusting foundation height difference of elevator | |
CN105088960B (en) | A kind of tower crane method to set up being applied on bridge | |
CN217268230U (en) | Steel bar truss floor support plate structure in steel structure frame | |
CN220954534U (en) | High-altitude overlength cantilever supporting system based on BIM | |
CN220644885U (en) | Lower hanging beam roof steel bar support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |