CN215052153U - Device for preventing bridge closure template falls - Google Patents

Device for preventing bridge closure template falls Download PDF

Info

Publication number
CN215052153U
CN215052153U CN202120482416.7U CN202120482416U CN215052153U CN 215052153 U CN215052153 U CN 215052153U CN 202120482416 U CN202120482416 U CN 202120482416U CN 215052153 U CN215052153 U CN 215052153U
Authority
CN
China
Prior art keywords
steel
template
square steel
bridge
closure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120482416.7U
Other languages
Chinese (zh)
Inventor
张振钛
张予欣
施文龙
张学斌
袁国涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Railway Survey & Design Institute Co ltd
Original Assignee
Xinjiang Railway Survey & Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Railway Survey & Design Institute Co ltd filed Critical Xinjiang Railway Survey & Design Institute Co ltd
Priority to CN202120482416.7U priority Critical patent/CN215052153U/en
Application granted granted Critical
Publication of CN215052153U publication Critical patent/CN215052153U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a device for preventing bridge closure template falls, include the bracket base that is setting up on the box girder roof and the box girder bottom plate of bridge closure section both sides, set up closure section steel template subassembly in the bridge closure section, set up the anchor reinforcing bar in the bracket base of coaxial arrangement respectively, anchor reinforcing bar outside end is fixed respectively and is setting up square steel supporting seat, a square steel is being coaxial suit in the square steel supporting seat between two bracket bases of coaxial arrangement, set up the steel wedge between square steel one end and one of them square steel supporting seat, level respectively is setting up the prestressing force pore canal in the bridge box girder of closure section both sides, the prestressing force pore canal fit in setting up the prestressing force reinforcing bar, through the prestressing force reinforcing bar and bracket base, square steel accomplish the location locking of closure section steel template subassembly. The device can demolish the template and prevent that the template from falling and provide reliable performance after closing the dragon for the bridge, stops that the template falls.

Description

Device for preventing bridge closure template falls
Technical Field
The utility model relates to a prevent device that bridge closure template falls, specifically speaking relate to a prevent device that formwork support falls after being applicable to large-span bridge closure, belong to bridge and culvert engineering technical field.
Background
Traditional large-span bridge need be with locking device fixed closure section space when closing up, installs the steel template, and the ligature closes up a section reinforcing bar, lays closure section prestressing force pore canal, pours the concrete, demolishs the steel template after treating the concrete reaches design strength, and stretch-draw closure prestressing steel bar accomplishes the bridge and closes the dragon. The construction method has the advantages that when the closure steel template is detached, the falling problem often occurs due to improper operation or aging failure of the template, pedestrians or vehicles are hit very often, and even the major accident that the running of a railway line under a bridge is interrupted is caused.
Disclosure of Invention
The utility model aims at providing a prevent device that bridge closure template falls can prevent that the template from falling and providing reliable performance for demolising the template after the bridge closure, stops the accident potential of template falling.
The utility model discloses a realize above-mentioned purpose, the technical solution who adopts is: the utility model provides a device for preventing bridge closure template falls, includes that the bracket base that is setting up about being dorsad interval respectively on the box girder roof and the box girder bottom plate of bridge closure section both sides, setting up closure section steel template subassembly in the bridge closure section the vertical inner wall in both sides and the bottom surface of closure section steel template subassembly respectively set up the shear resistant member, set up anchor bar in the bracket base of coaxial arrangement respectively, anchor bar outside end is fixed respectively and is being set up square steel supporting seat, a square steel is being coaxial suit in the square steel supporting seat between two bracket bases of coaxial arrangement, is setting up the steel wedge between square steel one end and one of them square steel supporting seat, respectively the level is setting up the prestressing force pore canal in the bridge box girder of closure section both sides, the prestressing force pore canal fit in and is setting up the prestressing force muscle, through prestressing force muscle and bracket base, And the square steel completes the positioning and locking of the steel template assembly at the closure section.
Pouring closure section concrete, and removing the square steel supporting seat, the steel wedge, the square steel, the bracket base and the anchoring steel bar after the concrete reaches the designed strength; the steel template assembly at the closure section is not removed, so that the steel template assembly is connected with the beam body concrete into a whole through the shear resistant piece, a steel-concrete composite beam structure is formed after closure, and the closure template is not dropped through the non-removal of the closure template. The utility model provides an anchoring point and a supporting point of the rigid square steel by arranging the bracket base, and provides fastening force for the rigid support of the square steel; through setting up prestressing steel strand wires, locking square steel supporting seat. Through setting up the shear resistant member, strengthened being connected of steel template and concrete. The steel structure with the steel-concrete composite structure is formed by arranging the steel inner template and the steel outer template. The steel inner template and the steel outer template are coated with the anticorrosive paint, so that the durability of the template is ensured.
Drawings
The present invention will be described in further detail with reference to the accompanying drawings.
Fig. 1 is a schematic front view of the present invention;
FIG. 2 is a schematic side sectional view of the structure of FIG. 1;
fig. 3 is a front view structure schematic diagram of a steel formwork assembly of a closure section.
Detailed Description
The utility model provides a prevent device that bridge closure template falls, as shown in fig. 1, 2, 3, includes that it sets up the bracket base 1 to be left and right back of the body interval respectively on box girder roof 12 and the box girder bottom plate 13 of bridge closure section both sides, is setting up closure section steel template subassembly 11 in the bridge closure section the outer mould 8 of closure section steel template subassembly 11, the vertical inner wall in centre form 9 both sides and the outer mould 8 bottom surface on set up shear 10 respectively. Anchor reinforcing bar 2 is being set up respectively in the bracket base 1 of coaxial arrangement, and anchor reinforcing bar 2 outside end is fixed respectively and is being set up square steel supporting seat 3, and coaxial suit is being a square steel 4 in the square steel supporting seat 3 between two bracket bases of coaxial arrangement, is setting up steel wedge 5 between 4 one end of square steel and one of them square steel supporting seat 3 for it is spacing and fixed to carry out square steel 4. Prestressed channels 6 are horizontally arranged in the bridge box girders on two sides of the closure section respectively, prestressed reinforcements 7 are arranged in the prestressed channels 6 in a matching manner, and the positioning and locking of the closure section steel formwork assembly 11 are completed through the prestressed reinforcements 7, the bracket base 1 and the square steel 4.
Pouring closure section concrete, and removing the square steel supporting seat 3, the steel wedge 5, the square steel 4, the bracket base 1 and the anchoring steel bar 2 after the concrete reaches the designed strength; the steel formwork assembly 11 at the closure section is not removed, so that the steel formwork assembly is connected with the beam body concrete into a whole through the shear resistant piece 10, a steel-concrete composite beam structure is formed after closure, and the closure formwork does not fall off through the non-removal of the closure formwork assembly 11.

Claims (1)

1. The utility model provides a device that prevents bridge closure template from falling, includes the bracket base that is setting up about being respectively on the box girder roof and the box girder bottom plate of bridge closure section both sides dorsad interval, setting up closure section steel template subassembly in the bridge closure section the vertical inner wall in both sides and the bottom surface of closure section steel template subassembly on set up respectively and shearing characterized by: the anchor reinforcing steel bars are respectively arranged in the corbel bases which are coaxially arranged, the outer side ends of the anchor reinforcing steel bars are respectively fixedly provided with square steel supporting seats, one piece of square steel is coaxially sleeved in the square steel supporting seat between the two corbel bases which are coaxially arranged, a steel wedge is arranged between one end of the square steel and one of the square steel supporting seats, prestressed ducts are horizontally arranged in the bridge box girders of the two closure sections respectively, prestressed reinforcing steel bars are arranged in the prestressed ducts in a matched mode, and the corbel bases and the square steel are used for positioning and locking the steel template assemblies of the closure sections.
CN202120482416.7U 2021-03-06 2021-03-06 Device for preventing bridge closure template falls Active CN215052153U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120482416.7U CN215052153U (en) 2021-03-06 2021-03-06 Device for preventing bridge closure template falls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120482416.7U CN215052153U (en) 2021-03-06 2021-03-06 Device for preventing bridge closure template falls

Publications (1)

Publication Number Publication Date
CN215052153U true CN215052153U (en) 2021-12-07

Family

ID=79255123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120482416.7U Active CN215052153U (en) 2021-03-06 2021-03-06 Device for preventing bridge closure template falls

Country Status (1)

Country Link
CN (1) CN215052153U (en)

Similar Documents

Publication Publication Date Title
CN210636312U (en) Prefabricated structure of assembling of assembled bridge of high-speed railway
CN105839510A (en) Steel-ultra-high-performance concrete combined continuous beam bridge structure and construction method thereof
CN102587267A (en) Tension-fabricated bridge with prestressed hollow-plate-girders and middle transverse partitions and construction method of tension-fabricated bridge with prestressed hollow-plate-girder and middle transverse partitions
CN111877182B (en) Novel construction method for upper structure of multi-chamber continuous UHPC box girder bridge
CN102146658A (en) Locally uncombined suspension bridge steel-concrete combined bridge deck system and construction method of combined bridge deck system
CN102852276A (en) Large-tonnage prestressed superposed crane beam and construction method
CN108951399A (en) A kind of Single-box multi-chamber box beam bridge and its construction method
CN111074772A (en) Improved T-shaped steel prefabricated hollow slab beam bridge hinge joint structure and construction process thereof
CN109895239B (en) Fabricated concrete stair slow platform beam slab and construction method thereof
KR101762374B1 (en) Method for constructing platform
CN215052153U (en) Device for preventing bridge closure template falls
CN106087692A (en) A kind of Simply supported non-uniform T negative moment of girder section structure and construction method
CN212865473U (en) Prefabricated assembled type lane plate
KR100564351B1 (en) Steel prestressed concrete grider utilizing a steel pipe as a mold and construction method of bridge using the girder
CN210621476U (en) Segment prefabricated bent cap cantilever assembling construction device
CN108678248A (en) A kind of modular unit transverse connection structure and its construction technology
CN215669083U (en) T roof beam cross slab reinforced structure
CN110924303B (en) Steel beam and built-in steel reinforced concrete slab continuous combination beam and construction method
CN110067198A (en) A kind of steel reinforced concrete composite beam bridge and its construction method
CN214883001U (en) Bridge side span closure device
CN205474785U (en) Steel - ultra high performance concrete combination continuous bridge structure
CN108978490B (en) Construction method of continuous beam-arch combined beam body and continuous beam-arch combined beam body
CN211447283U (en) Connecting beam of main building and skirt house
KR20060017949A (en) Field-fabricated prestressing steel-composed girder and construction method of continuous bridge using the girder
CN108708285B (en) By adjusting temporary rest pier improvement combination beam internal force at bridge method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant