CN215036543U - Integrative equipment is collected in piece clearance that casting part was used - Google Patents

Integrative equipment is collected in piece clearance that casting part was used Download PDF

Info

Publication number
CN215036543U
CN215036543U CN202022691522.4U CN202022691522U CN215036543U CN 215036543 U CN215036543 U CN 215036543U CN 202022691522 U CN202022691522 U CN 202022691522U CN 215036543 U CN215036543 U CN 215036543U
Authority
CN
China
Prior art keywords
piece
debris
cleaning
fixed mounting
collecting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022691522.4U
Other languages
Chinese (zh)
Inventor
李姣力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Xingyang Cast Iron Machinery Manufacturing Co ltd
Original Assignee
Xinjiang Xingyang Cast Iron Machinery Manufacturing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Xingyang Cast Iron Machinery Manufacturing Co ltd filed Critical Xinjiang Xingyang Cast Iron Machinery Manufacturing Co ltd
Priority to CN202022691522.4U priority Critical patent/CN215036543U/en
Application granted granted Critical
Publication of CN215036543U publication Critical patent/CN215036543U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Cleaning In General (AREA)

Abstract

The utility model discloses a piece cleaning and collecting integrated equipment for casting parts, which comprises a workbench, wherein two sides of the bottom end of the workbench are fixedly provided with an underframe, one side of the underframe is detachably provided with a piece processing device, one side of the piece processing device is detachably provided with a valve, the top end of the piece processing device is communicated with a feeding pipe, the surface of the feeding pipe is fixedly sleeved with a first sealing ring, the top end of the workbench is fixedly provided with a polishing pool, one side of the top end of the workbench is fixedly provided with a first supporting column, and the top end of the first supporting column is detachably provided with a rotating shaft, therefore, the cleaning device has the effects of cleaning up scraps on the workpiece without touching the workpiece, and reducing the labor intensity.

Description

Integrative equipment is collected in piece clearance that casting part was used
Technical Field
The utility model relates to a casting technical field, more specifically say, the utility model relates to an integrative equipment is collected in piece clearance that casting part used.
Background
The casting part is a workpiece formed after being demoulded through a casting mould, the surface of the workpiece which is just demoulded has flaws, and the side of the workpiece also has excessive burrs, so that the workpiece needs to be polished and polished again, certain chips are generated in the polishing and polishing process, and the chips are recovered through the chip cleaning and collecting integrated equipment, and a polishing workbench is cleaned.
The existing scrap cleaning and collecting integrated equipment can only collect floating scraps and scraps falling on a workbench in the polishing process in the working process, and due to different shapes of dies, a workpiece still has small gaps, so that time and labor are wasted due to manual cleaning, the dies are easy to scrape by cleaning the scraps in the gaps, and the working efficiency is reduced; when clastic recovery, directly stack the piece in accomodating the bag, more occupation space because clastic granule is smaller, when the bag was accomodate in the artifical clearance in later stage, also can increase the work degree of difficulty.
SUMMERY OF THE UTILITY MODEL
In order to overcome prior art's above-mentioned defect, the embodiment of the utility model provides a piece clearance that cast member used collects integrative equipment, collect integrative equipment in order to solve current piece clearance, can only retrieve showy piece and the piece that drops on the workstation, piece on the work piece need clear up through the manual work, thereby reduce work efficiency's problem, the piece relatively accounts for the space after retrieving, because the clastic granule is smaller, when the bag was accomodate in the manual clearance of later stage, also can increase the problem of the work degree of difficulty.
In order to solve the technical problem, the utility model provides a following technical scheme: the utility model provides an integrative equipment is collected in piece clearance that casting part was used, comprises a workbench, the both sides fixed mounting of workstation bottom has the chassis, one side demountable installation of chassis has piece processing apparatus, one side demountable installation of piece processing apparatus has the valve, piece processing apparatus's top intercommunication has the pan feeding pipe, the fixed surface cover of pan feeding pipe has connect first sealing ring, the top fixed mounting of workstation has the pond of polishing, one side fixed mounting on workstation top has first support column, the top demountable installation of first support column has the pivot, the burnishing roll has been cup jointed in the surface activity of pivot, the top demountable installation in the pond of polishing has piece collecting bin, one side fixed mounting in piece collecting bin has the air suction hopper, one side fixed mounting who inhales the air hopper has the suction fan, the top fixed mounting of workstation has the second support column, the surface activity of pivot has cup jointed the bearing.
Wherein, one side on workstation top demountable installation has main motor, and the inside of second support column, burnishing roll and bearing is run through to the one end of main motor.
Wherein, the inside top demountable installation of piece processing apparatus has the heating chamber, and the bottom intercommunication of heating chamber has the discharging pipe.
Wherein, the fixed surface of discharging pipe has cup jointed the second sealing ring, and the inside bottom demountable installation of piece processing apparatus has the cooler bin, and the cooling bath has been seted up to the bottom of cooler bin, and one side fixed mounting of cooler bin has the grab handle.
Wherein, the inside to the cooler bin is run through to the one end of discharging pipe, and the bottom of discharging pipe is connected with the inside of cooling bath.
Wherein, the inside top fixed mounting in piece collection storehouse has the rack, and the mounting hole has been seted up in the front of rack, and the fixed cover in inside of mounting hole has connect the dead lever.
Wherein, the inside fixed mounting of heating chamber has the heat preservation, and the inside both sides demountable installation of heat preservation has the heater, and the connecting hole has been seted up to the bottom of heating chamber, and the internal surface of connecting hole is laminated with the surface of discharging pipe mutually.
The utility model discloses an above-mentioned technical scheme's beneficial effect as follows:
1. in the above scheme, integrative equipment is collected in piece clearance utilizes the suction fan to absorb the piece in the storehouse is collected to the piece through the wind scoop and in the piece processing apparatus, has reached the effect of collecting the piece from a plurality of positions fast, utilizes rack and dead lever to reached the effect of conveniently placing the work piece, thereby played not touching with the work piece, cleaned the piece on the work piece totally, thereby reduced intensity of labour's effect.
2. In the above scheme, integrative equipment is collected in piece clearance utilizes mutually supporting between heating chamber, heater and the heat preservation to reached the effect that melts the piece fast, through mutually supporting between cooler bin and the cooling bath, thereby reached the fashioned effect of piece cooling that will melt fast, thereby the effect of the later stage clearance piece degree of difficulty that alleviates.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic side view of the whole structure of the present invention;
FIG. 3 is a schematic structural view of the scrap handling apparatus of the present invention;
FIG. 4 is a schematic view of the debris collection bin of the present invention;
fig. 5 is a schematic view of the structure of the heating chamber of the present invention.
[ reference numerals ]
1. A work table; 2. a chassis; 3. a debris handling device; 4. a valve; 5. a feeding pipe; 6. a first seal ring; 7. a polishing pool; 8. a first support column; 9. a rotating shaft; 10. a polishing roll; 11. a debris collection bin; 12. a suction hopper; 13. a suction fan; 14. a second support column; 15. a bearing; 16. a main motor; 17. a heating chamber; 18. a discharge pipe; 19. a second seal ring; 20. a cooling tank; 21. a cooling tank; 22. a handle; 23. placing a rack; 24. mounting holes; 25. fixing the rod; 26. a heat-insulating layer; 27. a heater; 28. and connecting the holes.
Detailed Description
In order to make the technical problems, technical solutions and advantages to be solved by the present invention clearer, the following detailed description will be given with reference to the accompanying drawings and specific embodiments.
The embodiment of the utility model provides an embodiment of the utility model provides a piece clearance collection integrative equipment for cast member as attached figure 1-5, including workstation 1, the both sides fixed mounting in workstation 1 bottom has chassis 2, one side demountable installation of chassis 2 has piece processing apparatus 3, one side demountable installation of piece processing apparatus 3 has valve 4, the top intercommunication of piece processing apparatus 3 has pan feeding pipe 5, the fixed cover of surface of pan feeding pipe 5 is connected with first sealing ring 6, the top fixed mounting of workstation 1 has polishing pond 7, one side fixed mounting of workstation 1 top has first support column 8, the top demountable installation of first support column 8 has pivot 9, the surface activity of pivot 9 has cup jointed polishing roller 10, the top demountable installation of polishing pond 7 has piece collection storehouse 11, one side fixed mounting of piece collection storehouse 11 has air suction hopper 12, one side fixed mounting of air suction hopper 12 has suction fan 13, the top fixed mounting of workstation 1 has second support column 14, the surface activity of pivot 9 has cup jointed bearing 15, one side demountable installation on workstation 1 top has main motor 16, the one end of main motor 16 runs through in the inside of second support column 14, burnishing roll 10 and bearing 15, the inside top demountable installation of piece processing apparatus 3 has heating chamber 17, the bottom intercommunication of heating chamber 17 has discharging pipe 18, the fixed cover in surface of discharging pipe 18 has second sealing ring 19, the inside bottom demountable installation of piece processing apparatus 3 has cooling tank 20, cooling tank 21 has been seted up to the bottom of cooling tank 20, one side fixed mounting of cooling tank 20 has grab handle 22, the one end of discharging pipe 18 runs through to the inside of cooling tank 20, the bottom of discharging pipe 18 with the inside of cooling bath 21 is connected, the inside top fixed mounting in storehouse 11 is collected to the piece has rack 23, mounting hole 24 has been seted up in rack 23's front, dead lever 25 has been cup jointed to the inside fixed of mounting hole 24, the inside fixed mounting of heating chamber 17 has heat preservation 26, the inside both sides demountable installation of heat preservation 26 has heater 27, connecting hole 28 has been seted up to the bottom of heating chamber 17, the internal surface of connecting hole 28 is laminated with the surface of discharging pipe 18 mutually.
As shown in fig. 3, a second sealing ring 19 is fixedly sleeved on the surface of the discharge pipe 18, a cooling tank 20 is detachably mounted at the bottom end inside the debris processing device 3, a cooling groove 21 is formed at the bottom end of the cooling tank 20, and a handle 22 is fixedly mounted at one side of the cooling tank 20.
Specifically, the mutual cooperation between integrative equipment utilization cooling tank 21 and the cooling tank 20 is collected in the piece clearance to reach and solidify the piece that melts fast, and made things convenient for the effect that workman later stage was retrieved.
Wherein the main motor 16 is other brand, model YE 2; the heater 27 is Yunpenkewei, KEW-QSG model.
The working process of the utility model is as follows:
the suction fan 13 of the integrated equipment for cleaning and collecting the scraps is started to absorb the scraps in the scrap collecting bin 11 into the scrap processing device 3 through the suction hopper 12, and the polished casting piece is placed on the placing frame 23 and the fixing rod 25, so that the effects of quickly cleaning the scraps on the casting piece, preventing time and labor waste caused by manual cleaning and scraping the casting piece are achieved; collect the piece in the piece processing apparatus 3, start heater 27 and heat the piece, prevent thermal loss through heat preservation 26, the piece that melts flows to the cooling tank 21 in the cooler bin 20 through discharging pipe 18, after the cooling, the workman can directly pull out cooler bin 20 from the piece processing apparatus 3 through grab handle 22, just can take out the piece to convenient clearance has been reached and has been retrieved clastic effect.
According to the scheme, the debris cleaning and collecting integrated equipment utilizes the mutual matching among the suction fan 13, the suction hopper 12, the debris collecting bin 11, the debris processing device 3, the placing frame 23 and the fixing rod 25, so that the problems that only floating debris and debris falling on the workbench 1 can be recovered and the debris on a workpiece needs to be cleaned manually are solved, and the working efficiency is improved; integrative equipment is collected in piece clearance utilizes mutually supporting between heating chamber 17, heater 27, heat preservation 26, cooler bin 20 and the cooling bath 21, has avoided the piece to retrieve the back and comparatively account for the space, because clastic granule is smaller, the artifical clearance in later stage is accomodate the problem that the bag was more wasted time and energy to reduce the work degree of difficulty.
The points to be finally explained are: first, in the description of the present application, it should be noted that, unless otherwise specified and limited, the terms "mounted," "connected," and "connected" should be understood broadly, and may be a mechanical connection or an electrical connection, or a communication between two elements, and may be a direct connection, and "upper," "lower," "left," and "right" are only used to indicate a relative positional relationship, and when the absolute position of the object to be described is changed, the relative positional relationship may be changed;
secondly, the method comprises the following steps: in the drawings of the disclosed embodiments of the present invention, only the structures related to the disclosed embodiments are referred to, and other structures can refer to the common design, and under the condition of no conflict, the same embodiment and different embodiments of the present invention can be combined with each other;
and finally: the above description is only for the preferred embodiment of the present invention and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. The utility model provides an integrative equipment is collected in piece clearance that casting piece was used, includes workstation (1), the both sides fixed mounting of workstation (1) bottom has chassis (2), its characterized in that, one side demountable installation of chassis (2) has piece processing apparatus (3), one side demountable installation of piece processing apparatus (3) has valve (4), the top intercommunication of piece processing apparatus (3) has pan feeding pipe (5), the fixed surface of pan feeding pipe (5) has cup jointed first sealing ring (6), the top fixed mounting of workstation (1) has polishing pond (7), one side fixed mounting on workstation (1) top has first support column (8), the top demountable installation of first support column (8) has pivot (9), the surface activity of pivot (9) has cup jointed polishing roller (10), the top demountable installation of pond (7) of polishing has piece collection storehouse (11), one side fixed mounting that the piece was collected storehouse (11) has air suction hopper (12), one side fixed mounting of air suction hopper (12) has suction fan (13), the top fixed mounting of workstation (1) has second support column (14), bearing (15) have been cup jointed in the surface activity of pivot (9).
2. A casting debris cleaning and collecting integrated device as claimed in claim 1, wherein a main motor (16) is detachably mounted on one side of the top end of the working table (1), and one end of the main motor (16) penetrates through the inside of the second support column (14), the polishing roller (10) and the bearing (15).
3. A casting debris cleaning and collecting integrated device as claimed in claim 1, wherein a heating chamber (17) is detachably mounted at the top end of the interior of the debris processing device (3), and a discharge pipe (18) is communicated with the bottom end of the heating chamber (17).
4. The integrated equipment for cleaning and collecting the debris for the cast member as claimed in claim 3, wherein a second sealing ring (19) is sleeved on the surface of the discharge pipe (18), a cooling tank (20) is detachably mounted at the bottom end inside the debris treatment device (3), a cooling groove (21) is formed in the bottom end of the cooling tank (20), and a handle (22) is fixedly mounted at one side of the cooling tank (20).
5. A casting debris cleaning and collecting integrated apparatus as claimed in claim 4, wherein one end of the discharge pipe (18) extends through to the interior of the cooling box (20), and the bottom end of the discharge pipe (18) is connected to the interior of the cooling bath (21).
6. The integrated equipment for cleaning and collecting the debris for the casting parts as claimed in claim 1, wherein a placing frame (23) is fixedly installed at the top end inside the debris collecting bin (11), a mounting hole (24) is formed in the front face of the placing frame (23), and a fixing rod (25) is fixedly sleeved inside the mounting hole (24).
7. The integrated equipment for cleaning and collecting the scraps used for casting parts as claimed in claim 3, wherein an insulating layer (26) is fixedly arranged inside the heating chamber (17), heaters (27) are detachably arranged on two sides inside the insulating layer (26), a connecting hole (28) is formed in the bottom end of the heating chamber (17), and the inner surface of the connecting hole (28) is attached to the surface of the discharge pipe (18).
CN202022691522.4U 2020-11-19 2020-11-19 Integrative equipment is collected in piece clearance that casting part was used Expired - Fee Related CN215036543U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022691522.4U CN215036543U (en) 2020-11-19 2020-11-19 Integrative equipment is collected in piece clearance that casting part was used

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022691522.4U CN215036543U (en) 2020-11-19 2020-11-19 Integrative equipment is collected in piece clearance that casting part was used

Publications (1)

Publication Number Publication Date
CN215036543U true CN215036543U (en) 2021-12-07

Family

ID=79160791

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022691522.4U Expired - Fee Related CN215036543U (en) 2020-11-19 2020-11-19 Integrative equipment is collected in piece clearance that casting part was used

Country Status (1)

Country Link
CN (1) CN215036543U (en)

Similar Documents

Publication Publication Date Title
CN113547094B (en) Die-casting molding equipment for intelligent manufacturing
CN210817422U (en) Cooling system for casting machine
CN215036543U (en) Integrative equipment is collected in piece clearance that casting part was used
CN211639281U (en) Cylinder barrel end face polishing device for collecting debris
CN114833584B (en) Numerical control spinning device capable of processing large-batch copper kettles and application method
CN115609051A (en) Vertical milling machine
CN213379629U (en) Band sawing machine
CN219907727U (en) Steel smelting waste slag cooling device
CN216728608U (en) Steam paraffin removal cleaning machine
CN207238760U (en) A kind of device for removing slag of aluminium casting-rolling mill
CN207480228U (en) A kind of machining center of quick recycling cooling oil
CN220056946U (en) Quenching device for die manufacturing
CN215091129U (en) Scrap recovery device for gear shaping machine
CN212551941U (en) Sweeps recovery unit of milling machine processing usefulness
CN109807295B (en) Crystallizer capable of automatically feeding
CN211708805U (en) Numerical control lathe water tank
CN215967761U (en) Bearing ring processing device
CN215748472U (en) Steel rust removing device convenient to collect and used for constructional engineering
CN215430845U (en) High-speed wire finishing mill with water cooling device
CN217493913U (en) Precision casting revises polishes and uses dust collector
CN217553119U (en) Embossing device for embossing PET (polyethylene terephthalate) composite color steel plate
CN220388113U (en) Cutting device for construction engineering machinery
CN211805134U (en) Efficient cooling and cutting equipment for nonferrous metal
CN220128321U (en) Dust collector of cylindrical grinder
CN216574309U (en) Auxiliary supporting and positioning frame for cast iron welding

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211207

CF01 Termination of patent right due to non-payment of annual fee