CN214996596U - Isolation railing for landscaping - Google Patents

Isolation railing for landscaping Download PDF

Info

Publication number
CN214996596U
CN214996596U CN202120103107.4U CN202120103107U CN214996596U CN 214996596 U CN214996596 U CN 214996596U CN 202120103107 U CN202120103107 U CN 202120103107U CN 214996596 U CN214996596 U CN 214996596U
Authority
CN
China
Prior art keywords
groove
diameter
landscaping
connecting piece
clamping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120103107.4U
Other languages
Chinese (zh)
Inventor
郭明媛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Dijian Real Estate Development Group Co ltd
Original Assignee
Shaanxi Dijian Real Estate Development Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Dijian Real Estate Development Group Co ltd filed Critical Shaanxi Dijian Real Estate Development Group Co ltd
Priority to CN202120103107.4U priority Critical patent/CN214996596U/en
Application granted granted Critical
Publication of CN214996596U publication Critical patent/CN214996596U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model belongs to the technical field of landscaping protection equipment, in particular to an isolation railing for landscaping, which comprises a support post, an elevation rod, a fixing part and a connecting part, wherein a threaded post is fixedly arranged at the top end of the support post, four foundation bolts are uniformly and symmetrically and fixedly connected with the bottom end of the support post, a through groove is formed at the bottom end of the elevation rod, a threaded groove is formed above the through groove, the through groove is communicated with the threaded groove, and the support post penetrates through the through groove; this device is through setting up the pillar, heightening pole and rag bolt, uses through the three cooperation, and the fixed height of adjusting between pillar and the heightening pole is used for matching the mounting height requirement, and adjusting rag bolt is used for keeping the level, has improved the suitability to mounting height and installation environment to be provided with mounting and connecting piece and be used for carrying out the fixed connection of guardrail, can accomplish the installation fast and dismantle, easy operation, and the concatenation installation is accomplished the back, be difficult for breaking away from, firm in connection brings the facility for the staff.

Description

Isolation railing for landscaping
Technical Field
The utility model belongs to the technical field of afforestation protective apparatus, concretely relates to afforestation is with keeping apart railing.
Background
Landscaping is a beautiful natural environment and rest area created by applying engineering technology and artistic means in a certain region and modifying the terrain (or further building mountains, stacking stones and managing water) to plant trees, flowers and plants, building buildings, arranging garden roads and the like.
Adopt isolation railing to protect often in afforestation's in-service use, can keep apart dangerous area, also can keep apart the crowd with trees flowers and plants, play the effect that the protection trees flowers and plants are not trampled, but present afforestation is comparatively troublesome with isolation railing concatenation mounting means to because the topography in gardens is different, also there is the difference to the mounting height requirement of isolation railing, present afforestation is with isolation railing suitability is lower.
In order to solve the problem, the application provides an isolation railing for landscaping.
SUMMERY OF THE UTILITY MODEL
To solve the problems set forth in the background art described above. The utility model provides an afforestation is with keeping apart railing has extensive applicability, the characteristics of being convenient for installation.
In order to achieve the above object, the utility model provides a following technical scheme: an isolation railing for landscaping comprises a support, heightening rods, a fixing part and a connecting part, wherein a threaded column is fixedly arranged at the top end of the support, four foundation bolts are uniformly and symmetrically and fixedly connected to the bottom end of the support, a through groove is formed in the bottom end of each heightening rod, a thread groove is formed above the through groove and communicated with the thread groove, the support penetrates through the through groove and extends to the thread groove, the threaded column is in threaded connection with the thread groove, the top end of the fixing part is fixedly connected with the outer side wall of each heightening rod, a clamping groove is formed in the bottom end of the fixing part, pressing blocks are symmetrically and fixedly arranged on the outer side wall of the fixing part and penetrate through the outer side wall of the fixing part and extend to the inside of the clamping groove, guardrails are arranged between the two heightening rods, and four ends of each guardrail are respectively fixedly connected with the bottom ends of the connecting part, the bottom of connecting piece has seted up the screw thread mouth, the spout has been seted up to the top of screw thread mouth, the fixed stopper that is equipped with in center department of spout, the both sides of stopper are equipped with the fixture block respectively, fixedly connected with spring between the fixture block, the bottom of mounting with the top fixed connection of connecting piece.
As the utility model relates to an afforestation is with keeping apart railing is preferred, the even symmetry in bottom of pillar is fixed and is equipped with four reinforcement pieces.
As the utility model relates to an afforestation is with keeping apart railing is preferred, the diameter of screw thread post is greater than the diameter of pillar bottom, the diameter of thread groove is greater than the diameter that leads to the groove.
As the utility model relates to an afforestation is with keeping apart railing is preferred, the top diameter of draw-in groove is greater than its opening diameter, just the diameter of connecting piece keeps unanimous with its opening diameter.
As the utility model relates to an afforestation is with keeping apart that railing is preferred, the mounting is equipped with four altogether, and even symmetric distribution is in the lateral wall of heightening the pole.
As the utility model relates to an afforestation is with keeping apart railing is preferred, the top of fixture block is the circular arc type setting, and goes up narrow width down, two under the uncompressed state the distance between the most prominent point of fixture block surpasss the opening diameter of draw-in groove.
As the utility model relates to an afforestation is with keeping apart that railing is preferred, press the briquetting with the fixture block is in same horizontal plane.
Compared with the prior art, the beneficial effects of the utility model are that: this device is through setting up the pillar, heightening pole and rag bolt, uses through the three cooperation, and the fixed height of adjusting between pillar and the heightening pole is used for matching the mounting height requirement, and adjusting rag bolt is used for keeping the level, has improved the suitability to mounting height and installation environment to be provided with mounting and connecting piece and be used for carrying out the fixed connection of guardrail, can accomplish the installation fast and dismantle, easy operation, and the concatenation installation is accomplished the back, be difficult for breaking away from, firm in connection brings the facility for the staff.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic view of the connection structure of the guardrail of the present invention;
FIG. 3 is a schematic view of the internal structure of the fixing member of the present invention;
FIG. 4 is a schematic view of the internal structure of the connecting member of the present invention;
in the figure: 1. a pillar; 101. a threaded post; 102. a reinforcing block; 2. a height adjusting rod; 201. a through groove; 202. a thread groove; 3. a fixing member; 301. a card slot; 302. a pressing block; 4. a connecting member; 401. a threaded opening; 402. a chute; 403. a limiting block; 404. a clamping block; 405. a spring; 5. a guardrail; 6. and (7) anchor bolts.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
Referring to fig. 1-4, the present invention provides an isolation railing for landscaping, which comprises a support 1, a height-adjusting rod 2, a fixing member 3 and a connecting member 4, wherein a threaded post 101 is fixed on the top of the support 1, four anchor bolts 6 are uniformly and symmetrically fixedly connected to the bottom of the support 1, a through groove 201 is formed on the bottom of the height-adjusting rod 2, a threaded groove 202 is formed above the through groove 201, the through groove 201 is communicated with the threaded groove 202, the support 1 penetrates through the through groove 201 and extends to the threaded groove 202, the threaded post 101 is in threaded connection with the threaded groove 202, the top of the fixing member 3 is fixedly connected with the outer side wall of the height-adjusting rod 2, a clamping groove 301 is formed on the bottom of the fixing member 3, a pressing block 302 is symmetrically fixed on the outer side wall of the fixing member 3, the pressing block 302 penetrates through the outer side wall of the fixing member 3 and extends to the inside of the clamping groove 301, a guardrail 5 is arranged between the two height-adjusting rods 2, four ends of guardrail 5 respectively with the bottom fixed connection of connecting piece 4, screw thread mouth 401 has been seted up to the bottom of connecting piece 4, spout 402 has been seted up to the top of screw thread mouth 401, the fixed stopper 403 that is equipped with in center department of spout 402, the both sides of stopper 403 are equipped with fixture block 404 respectively, fixedly connected with spring 405 between the fixture block 404, the bottom of mounting 3 and the top fixed connection of connecting piece 4.
In this embodiment: when the garden isolation railing is installed, a worker places the support 1 on a mounting point, rotates the heightening rod 2 according to the required installation height to change the fixed position of the threaded column 101 in the threaded groove 202, further adjusts the height of the heightening rod 2 to meet the installation height requirement, and can keep the device horizontal by adjusting the foundation bolt 6 when the bottom surface of the mounting point is uneven, so that the subsequent cement pouring work is facilitated, and the applicability to the installation height and the installation environment is improved; the four end heads of the guardrail 5 are respectively connected with the connecting piece 4 through threads, the top end of the connecting piece 4 and the bottom end of the clamping groove 301 are inserted into the clamping groove, in the process of inserting into the clamping groove 301, the two clamping blocks 404 are extruded by the side wall of the clamping groove 301 to be converged towards the limiting block 403 in the sliding groove 402, the spring 405 is extruded to be compressed, the clamping blocks 404 enter the top of the clamping groove 301, after the clamping blocks 404 enter the top of the clamping groove 301, the two clamping blocks 404 are reset under the action of the spring 405 to complete the clamping of the connecting piece 4 and the fixing piece 3, when the guardrail 5 needs to be disassembled, the pressing blocks 302 on the two sides of the fixing piece 3 are pressed to extrude the clamping blocks 404, the connecting piece 4 can be pulled out from the clamping groove 301, the disassembly of the guardrail 5 is completed, in the assembling and disassembling processes, the assembling can be completed quickly, the operation is simple, the assembling is not easy to break away, and the connection is firm, brings convenience to the working personnel.
In an alternative embodiment, four reinforcing blocks 102 are uniformly and symmetrically fixed on the bottom end of the supporting column 1.
In this embodiment: because the bottom of pillar 1 is evenly fixed with four reinforcing blocks 102 symmetrically, can strengthen the stability of pillar 1 to improve the stable support of this device.
In an alternative embodiment, the diameter of the threaded post 101 is greater than the diameter of the bottom end of the stanchion 1, and the diameter of the threaded groove 202 is greater than the diameter of the through groove 201.
In this embodiment: because the diameter of screw thread post 101 is greater than the diameter of pillar 1 bottom, and the diameter of thread groove 202 is greater than the diameter of logical groove 201, and accessible screw thread post 101 is spacing to the connection between pillar 1 and the pole 2 of increaseing.
In an alternative embodiment, the top end of the slot 301 has a diameter larger than the opening diameter thereof, and the diameter of the connector 4 is the same as the opening diameter thereof.
In this embodiment: because the diameter of the top end of the clamping groove 301 is larger than the diameter of the opening of the clamping groove, and the diameter of the connecting piece 4 is consistent with the diameter of the opening of the clamping groove, the fixing piece 3 and the connecting piece 4 can be tightly clamped.
In an alternative embodiment, the number of the fixing members 3 is four, and the fixing members are evenly and symmetrically distributed on the outer side wall of the height-adjusting rod 2.
In this embodiment: because of mounting 3 is equipped with four altogether, and even symmetric distribution is at the lateral wall of heightening pole 2, can make heightening pole 2 both sides all connect, makes things convenient for this device combination of multiunit to use.
In an alternative embodiment, the top end of the latch 404 is arc-shaped, and has a narrow top and a wide bottom, and the distance between the most protruding points of the two latches 404 in the uncompressed state exceeds the opening diameter of the slot 301.
In this embodiment: because the top of fixture block 404 is the arc type setting, and narrow-end-up is wide, and the distance between two fixture block 404 most prominent points surpasses the opening diameter of draw-in groove 301 under the uncompressed state for behind the installation of fixed part 3 and the completion of connecting piece 4 concatenation, difficult break away from, firm in connection.
In an alternative embodiment, the pressing block 302 and the latch 404 are in the same horizontal plane.
In this embodiment: because the pressing block 302 and the clamping block 404 are positioned on the same horizontal plane, the pressing block 302 on the two sides of the fixing part 3 is pressed to extrude the clamping block 404, so that the connecting piece 4 can be pulled out from the clamping groove 301, the guardrail 5 is disassembled, and the operation is simple and rapid.
The utility model discloses a theory of operation and use flow: when the garden isolation railing is installed, a worker places the support 1 on a mounting point, rotates the heightening rod 2 according to the required installation height to change the fixed position of the threaded column 101 in the threaded groove 202, further adjusts the height of the heightening rod 2 to meet the installation height requirement, and can keep the device horizontal by adjusting the foundation bolt 6 when the bottom surface of the mounting point is uneven, so that the subsequent cement pouring work is facilitated, and the applicability to the installation height and the installation environment is improved; the four end heads of the guardrail 5 are respectively connected with the connecting piece 4 through threads, the top end of the connecting piece 4 and the bottom end of the clamping groove 301 are inserted into the clamping groove, in the process of inserting into the clamping groove 301, the two clamping blocks 404 are extruded by the side wall of the clamping groove 301 to be converged towards the limiting block 403 in the sliding groove 402, the spring 405 is extruded to be compressed, the clamping blocks 404 enter the top of the clamping groove 301, after the clamping blocks 404 enter the top of the clamping groove 301, the two clamping blocks 404 are reset under the action of the spring 405 to complete the clamping of the connecting piece 4 and the fixing piece 3, when the guardrail 5 needs to be disassembled, the pressing blocks 302 on the two sides of the fixing piece 3 are pressed to extrude the clamping blocks 404, the connecting piece 4 can be pulled out from the clamping groove 301, the disassembly of the guardrail 5 is completed, in the assembling and disassembling processes, the assembling can be completed quickly, the operation is simple, the assembling is not easy to break away, and the connection is firm, brings convenience to the working personnel.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. The utility model provides an afforestation is with keeping apart railing, includes pillar (1), heightening pole (2), mounting (3) and connecting piece (4), its characterized in that: the top end of the strut (1) is fixedly provided with a threaded column (101), the bottom end of the strut (1) is uniformly and symmetrically fixedly connected with four foundation bolts (6), the bottom end of the heightening rod (2) is provided with a through groove (201), a thread groove (202) is arranged above the through groove (201), the through groove (201) is communicated with the thread groove (202), the strut (1) penetrates through the through groove (201) and extends to the thread groove (202), the threaded column (101) is in threaded connection with the thread groove (202), the top end of the fixing piece (3) is fixedly connected with the outer side wall of the heightening rod (2), the bottom end of the fixing piece (3) is provided with a clamping groove (301), the outer side wall of the fixing piece (3) is symmetrically and fixedly provided with pressing blocks (302), and the pressing blocks (302) penetrate through the outer side wall of the fixing piece (3), and extend to the inside of draw-in groove (301), two be equipped with guardrail (5) between increasement pole (2), four ends of guardrail (5) respectively with the bottom fixed connection of connecting piece (4), screw thread mouth (401) have been seted up to the bottom of connecting piece (4), spout (402) have been seted up to the top of screw thread mouth (401), the fixed stopper (403) that is equipped with in center department of spout (402), the both sides of stopper (403) are equipped with fixture block (404) respectively, fixedly connected with spring (405) between fixture block (404), the bottom of mounting (3) with the top fixed connection of connecting piece (4).
2. The isolation rail for landscaping as in claim 1, wherein: four reinforcing blocks (102) are uniformly and symmetrically fixed at the bottom end of the strut (1).
3. The isolation rail for landscaping as in claim 1, wherein: the diameter of the threaded column (101) is larger than that of the bottom end of the strut (1), and the diameter of the threaded groove (202) is larger than that of the through groove (201).
4. The isolation rail for landscaping as in claim 1, wherein: the diameter of the top end of the clamping groove (301) is larger than the diameter of the opening of the clamping groove, and the diameter of the connecting piece (4) is consistent with the diameter of the opening of the clamping groove.
5. The isolation rail for landscaping as in claim 1, wherein: the number of the fixing pieces (3) is four, and the fixing pieces are evenly and symmetrically distributed on the outer side wall of the heightening rod (2).
6. The isolation rail for landscaping as in claim 1, wherein: the top ends of the clamping blocks (404) are arranged in an arc shape, the top ends of the clamping blocks are narrow and wide, and the distance between the most protruding points of the two clamping blocks (404) in an uncompressed state exceeds the opening diameter of the clamping groove (301).
7. The isolation rail for landscaping as in claim 1, wherein: the pressing block (302) and the fixture block (404) are positioned on the same horizontal plane.
CN202120103107.4U 2021-01-14 2021-01-14 Isolation railing for landscaping Expired - Fee Related CN214996596U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120103107.4U CN214996596U (en) 2021-01-14 2021-01-14 Isolation railing for landscaping

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120103107.4U CN214996596U (en) 2021-01-14 2021-01-14 Isolation railing for landscaping

Publications (1)

Publication Number Publication Date
CN214996596U true CN214996596U (en) 2021-12-03

Family

ID=79140611

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120103107.4U Expired - Fee Related CN214996596U (en) 2021-01-14 2021-01-14 Isolation railing for landscaping

Country Status (1)

Country Link
CN (1) CN214996596U (en)

Similar Documents

Publication Publication Date Title
CN205040350U (en) Ornamental trees and shrubs strutting arrangement
CN214996596U (en) Isolation railing for landscaping
CN212642313U (en) Gardens are with reinforcement type security fence
CN204888166U (en) Novel climbing support of tendril plant
CN206722357U (en) A kind of construction scaffold
CN104996198A (en) Novel climbing rack for climbing plants
CN215594050U (en) Row pile foundation pit supporting device for building engineering
CN212087175U (en) Ecological frame of afforestation
CN211649521U (en) Adjustable force bearing device for building construction
CN211960276U (en) Plant climbing frame is used in gardens convenient to adjust
CN210959714U (en) Gardens are vwatched branch and are prevent wind and consolidate support
CN210202572U (en) City afforestation is with roadside flower case convenient to installation
CN219269704U (en) Planting is transplanted with support to view trunk
CN208563177U (en) A kind of railway guardrail installation pillar construction
CN105941081A (en) Demountable seedling standard production support rack and support method thereof
CN217389555U (en) Landscape newly-transplanted tree lodging-resistant support device
CN219060848U (en) Inclined support structure for stable scaffold
CN220081050U (en) Lawn guardrail with improved structure
CN217176103U (en) Gardens are with concatenation guardrail
CN209780422U (en) Novel garden fence
CN219919863U (en) Novel tree supporting device
CN2604485Y (en) combined scaffold for building
CN108834665A (en) A kind of climbing plant efficient stable climbing bracket
CN212728283U (en) Support frame is transplanted with trees in gardens construction
CN218117449U (en) Foundation ditch safety device for municipal road engineering

Legal Events

Date Code Title Description
GR01 Patent grant