CN2604485Y - combined scaffold for building - Google Patents

combined scaffold for building Download PDF

Info

Publication number
CN2604485Y
CN2604485Y CN 03220113 CN03220113U CN2604485Y CN 2604485 Y CN2604485 Y CN 2604485Y CN 03220113 CN03220113 CN 03220113 CN 03220113 U CN03220113 U CN 03220113U CN 2604485 Y CN2604485 Y CN 2604485Y
Authority
CN
China
Prior art keywords
vertical rod
screw rod
base
rod
plug
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 03220113
Other languages
Chinese (zh)
Inventor
杨秉法
曹永忠
成军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 03220113 priority Critical patent/CN2604485Y/en
Application granted granted Critical
Publication of CN2604485Y publication Critical patent/CN2604485Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model belongs to a combined scaffold for building, it contains pole setting 1, base 2, oblique pull rod 3, horizontal pole 4. The upper end and the lower end of the upright post are respectively provided with a round pin through hole 14, and the upper end is provided with four plug bushes 6. The base consists of a base plate 7 and a screw rod 8, the screw rod is firmly connected with the base plate, and a nut 9 is screwed on the screw rod. The upright stanchion is sleeved on the screw rod of the base. The two ends of the cross rod are respectively provided with a wedge-shaped plug 11, and the two ends of the diagonal draw bar are also respectively provided with a wedge-shaped plug 12. The vertical rods are connected into a firm whole by the cross rods and the inclined rods. The utility model discloses the dismouting is easy very much, and the materials are few moreover, and material utilization is high, can make the figurative roof-rack of scaffold frame or prefabricated plate of construction and indoor and outdoor fitment.

Description

Assembly scaffold for building
Assembly scaffold for building belongs to building machinery.
Existing building can be divided into two kinds with scaffold, and a kind of is rod cluster structure, and another is that metal tube is by fastening cuff stationary structure.The rod structure exists fragile, the shortcoming that wastes natural resources, and metal tube cuff fastening structure exists the material effective rate of utilization low.More than two kinds of structures also all have the shortcomings of dismounting trouble.
The purpose of this utility model is a kind of employing standard metal spare fabricated structure of design, and the scaffold that adopts inserting mode is installed, and it has easy accessibility, the advantage that stock utilization is high.
For achieving the above object, the utility model comprises vertical rod, base, diagonal member, cross bar.Respectively there is a round pin through hole at the two ends up and down of vertical rod, and the upper end also has four sleeves.Base is made up of chassis, screw rod, and there is a nut on screw rod and chassis for firmly to be connected on the screw rod.The screw rod of vertical rod and base adopts pegs graft, a wedge shape plug respectively is with at the cross bar two ends, with cross bar with about, the vertical rod of front and back connects into framework, the wedge shape plug of cross bar is inserted in the two ends of the interior diagonal member of sleeve of vertical rod and also respectively is with a wedge shape plug, the plug of diagonal member lower end is inserted in the sleeve in the vertical rod outside, and the plug of upper end is inserted in the sleeve in another adjacent vertical rod outside.Make scaffold form firm general frame like this.
The utility model dismounting is easy especially, and materials are few, the stock utilization height, and steadiness and fastness are all good, and load-bearing can arbitrarily be adjusted.Can be used as the scaffold of building operations and indoor and outdoor decoration or the upper frame of precast plate moulding.
Fig. 1 is the utility model overall structure schematic diagram, Fig. 2 is the enlarged drawing that Figure 1A orders, Fig. 3 is the structural representation of vertical rod 1, Fig. 4 is the structural representation of the sleeve 6 in the vertical rod, Fig. 5 is the structural representation of cross bar 4, Fig. 6 is the structural representation of pedal, and Fig. 7 is the structural representation of diagonal member, and Fig. 8 is the structural representation of base.
Embodiment: present embodiment is made up of vertical rod 1, base 2, diagonal member 3, cross bar 4, pedal 5, and the two ends up and down of vertical rod respectively have a round pin through hole 14, and the upper end has four sleeves 6, and the angle between adjacent two sleeves 6 in the left and right sides all is 90 °.Base 2 is made up of chassis 7 and screw rod 8, and screw rod 8 and chassis 7 are rotary with nut 9 for firmly to be connected on the screw rod 8, also be with one handle 10 on the nut 9.Vertical rod 1 is enclosed within on the screw rod 8 of base, adjusts nut 9 and can make the vertical rod lifting, and vertical rod and vertical rod are pegged graft the back with fixing in the pin reeve round pin through hole 14.Cross bar is divided into long and short two kinds, and a wedge shape plug 11 respectively is with at cross bar 4 two ends, with cross bar with about, the vertical rod of front and back connects into framework, the wedge shape plug 11 of cross bar is inserted in the sleeve 6 of vertical rod.A wedge shape plug 12 also respectively is with at the two ends of diagonal member 3, and the plug of diagonal member lower end is inserted in the sleeve in the vertical rod outside, and the plug of upper end is inserted in the sleeve in another adjacent vertical rod outside.Pedal 5 is a rectangular frame, is connected with wire lath 13 in framework, and the two ends, the left and right sides of framework respectively are with two connections to collude 15, will collude 15 during application and ride on the cross bar and get final product.

Claims (5)

1, assembly scaffold for building is characterized in that it comprises vertical rod (1), base (2), diagonal member (3), cross bar (4); Respectively there is a round pin through hole (14) at the two ends up and down of vertical rod (1), and the upper end has four sleeves (6); Base (2) is made up of chassis (7) and screw rod (8), and screw rod (7) and chassis (8) are rotary with nut (9) for firmly to be connected on the screw rod (8); Vertical rod (1) is enclosed within on the screw rod (8) of base (2); A wedge shape plug (11) respectively is with at cross bar (4) two ends, and the wedge shape plug (11) of cross bar (4) is inserted in the sleeve (6) of vertical rod (1), with cross bar (4) vertical rod of all around is connected into framework; A wedge shape plug (12) also respectively is with at the two ends of diagonal member (3), the plug (12) of the lower end of diagonal member (3) is inserted in the sleeve (6) in vertical rod (1) outside, the plug of upper end (12) is inserted in the sleeve (6) in another adjacent vertical rod (1) outside, makes scaffold form firm general frame.
2, assembly scaffold for building according to claim 1 is characterized in that the nut (9) on the screw rod (8) also is with one handle (10).
3, assembly scaffold for building according to claim 1 is characterized in that it also includes pedal (5), and pedal (5) is a rectangular frame, is connected with wire lath (13) in framework, and the two ends, the left and right sides of framework respectively have two connections and collude (15).
4, assembly scaffold for building according to claim 1, it is characterized in that vertical rod (1) and vertical rod (1) are pegged graft after, inject in the round pin through hole (14) fixing with pin.
5, assembly scaffold for building according to claim 1 is characterized in that four sleeves (6) in the vertical rod (1), and the angle between adjacent two sleeves in the left and right sides (6) all is 90 °.
CN 03220113 2003-02-28 2003-02-28 combined scaffold for building Expired - Fee Related CN2604485Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 03220113 CN2604485Y (en) 2003-02-28 2003-02-28 combined scaffold for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 03220113 CN2604485Y (en) 2003-02-28 2003-02-28 combined scaffold for building

Publications (1)

Publication Number Publication Date
CN2604485Y true CN2604485Y (en) 2004-02-25

Family

ID=34161673

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 03220113 Expired - Fee Related CN2604485Y (en) 2003-02-28 2003-02-28 combined scaffold for building

Country Status (1)

Country Link
CN (1) CN2604485Y (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104453195A (en) * 2014-11-14 2015-03-25 重庆市喜植机械设备有限公司 Scaffold
CN104453194A (en) * 2014-11-12 2015-03-25 重庆市喜植机械设备有限公司 Building structure frame
CN106677507A (en) * 2017-02-20 2017-05-17 李欣 Operation platform for building construction
CN110159059A (en) * 2019-06-03 2019-08-23 蔚孜电子商务(上海)有限公司 Break camp with attachment hanging device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104453194A (en) * 2014-11-12 2015-03-25 重庆市喜植机械设备有限公司 Building structure frame
CN104453195A (en) * 2014-11-14 2015-03-25 重庆市喜植机械设备有限公司 Scaffold
CN106677507A (en) * 2017-02-20 2017-05-17 李欣 Operation platform for building construction
CN110159059A (en) * 2019-06-03 2019-08-23 蔚孜电子商务(上海)有限公司 Break camp with attachment hanging device

Similar Documents

Publication Publication Date Title
CN202299199U (en) Assembled type balcony guardrail
CN2604485Y (en) combined scaffold for building
CN2192688Y (en) Combined scaffold for building
CN207846810U (en) A kind of novel ceiling applied on steel construction ceiling framework
CN206385884U (en) A kind of extra-high performance concrete electric pole
CN213476900U (en) Combined splayed support
CN211422025U (en) Assembling structure of power grid line iron tower
CN203742030U (en) Stone curtain wall keel structure
CN2215545Y (en) Steel tower made from steel pipes
CN218375659U (en) Assembled pylon
CN217151259U (en) Steel pipe supporting structure at building door opening
CN215858794U (en) Novel steel keel device for house building
CN216041723U (en) Stable form braced truss for three-layer steel structure room
CN221355031U (en) Vertical waxberry picking steel frame
CN215629426U (en) Cast-in-place box girder steel pipe support that stability is good
CN211201259U (en) High-strength alloy frame structure
CN211818593U (en) Quick mounting structure of cement fence encryption net
CN221024858U (en) Combined spliced water storage equipment
CN214993386U (en) Assembled guardrail convenient to connect
CN220928197U (en) Wood structure beam column connection node device
CN215907417U (en) Combined type building template fixing structure
CN215122535U (en) Planting greenhouse skeleton with hang function
CN2262340Y (en) Combined greenhouse frame
CN201485860U (en) Steel structural house foundation framework
CN218623497U (en) Novel superimposed sheet support frame

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee