CN214834324U - A anchor clamps that is used for hanging stone material roughness survey and regulate futilely - Google Patents

A anchor clamps that is used for hanging stone material roughness survey and regulate futilely Download PDF

Info

Publication number
CN214834324U
CN214834324U CN202120146179.7U CN202120146179U CN214834324U CN 214834324 U CN214834324 U CN 214834324U CN 202120146179 U CN202120146179 U CN 202120146179U CN 214834324 U CN214834324 U CN 214834324U
Authority
CN
China
Prior art keywords
stone
dry
hanging
screw
clamping piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120146179.7U
Other languages
Chinese (zh)
Inventor
康建军
陈钢
程永水
郑贤好
高俊
江然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Sanjian Engineering Co Ltd
Original Assignee
Anhui Sanjian Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Sanjian Engineering Co Ltd filed Critical Anhui Sanjian Engineering Co Ltd
Priority to CN202120146179.7U priority Critical patent/CN214834324U/en
Application granted granted Critical
Publication of CN214834324U publication Critical patent/CN214834324U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses an anchor clamps for hanging stone material roughness measure and regulate futilely, including the tight system of stone material back clamp, the positive tight system of clamp of stone material. The stone back clamping system consists of a screw and a clamping piece, the clamping piece is connected with the screw through a circular shaft, and the clamping piece can move around the circular shaft. The stone front clamping system consists of a clamping sheet, a nut and a gasket. When the dry-hanging stone is installed, the next row of installed stones is used as a reference, the clamp clamps the reference stone and the stone to be installed, and the stone to be installed and the surface of the reference stone are tightly attached to the clamping sheet by adjusting the back bolt hanging piece of the stone to be installed, so that the flatness of the stone meets the requirement. By using the clamp, only one person is needed to operate, and the construction efficiency and the installation precision of the dry hanging stone are improved. Provides a new construction method for high-precision installation and construction of dry-hanging stone on the outer vertical surface of the building.

Description

A anchor clamps that is used for hanging stone material roughness survey and regulate futilely
Technical Field
The utility model relates to a building engineering building veneer construction technical field especially relates to an anchor clamps that is used for hanging stone material roughness measure and regulate futilely.
Background
Along with the development of social economy, people have higher and higher requirements on the attractiveness of buildings, and a large amount of stone decoration on the outer vertical surfaces of the buildings appears, wherein compared with the traditional wet operation process, the dry hanging stone process avoids a grouting process, can shorten the construction period, reduce the self weight of the buildings, improve the anti-seismic performance, more importantly, effectively prevent the permeation pollution of pigments such as salt alkali in grouting and the like to the stone, improve the decoration quality and the impression effect, and is widely used.
The dry hanging method of stone is also called empty hanging method. The method uses metal hanging pieces to directly hang the facing stone on the wall surface or hang the facing stone on a steel frame in the air. The stone is fixed on the building through the metal hanging piece to form the stone decorative curtain wall.
The method for installing the stone plate on the outer vertical surface generally comprises the following steps: the method is carried out from bottom to top, firstly, two horizontal control lines are pulled at the upper opening and the lower opening of the lowest row of plate mounting positions on the outer wall surface to control the levelness of the plates, the verticality of the plates is based on a preset ash cake, the plates are hung straight by lines, and the plates are fixed after being mounted and calibrated. And after the installation of the lowest row of boards is finished, the boards are used as a reference, the last row of boards are installed, the last row of stone is repeatedly installed, the horizontal line is drawn at the upper opening and the lower opening of the board to be installed, and the vertical and the flatness of the board are hung by using a line drop. And the stones are installed upwards row by row until the end. This is inefficient.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a be used for hanging stone material roughness measure and regulate anchor clamps in order to compensate prior art's defect futilely.
The utility model discloses a realize through following technical scheme:
the utility model provides an anchor clamps for hanging stone material roughness survey and regulate futilely, includes stone material back clamping system, the positive clamping system of stone material and screw rod, screw rod top and the tight swing joint of stone material back clamping system, the tight system of the positive clamping system of stone material is screwed on the screw rod, presss from both sides the stone material tight between the tight system of stone material back clamping and the tight system of the positive clamping of stone material.
The screw rod top forging and pressing be trapezoidal, open between two parties at trapezoidal long limit end department has the round hole.
The stone back clamping system comprises two back clamping pieces, through holes are formed in the centers of the two back clamping pieces, the two back clamping pieces are located on two sides of the trapezoidal section of the screw respectively, the circular shaft penetrates through the circular hole in the screw and the through holes in the back clamping pieces and is riveted in a pier mode, the screw and the clamping pieces are integrated, and the back clamping pieces and the screw can rotate mutually through the circular shaft.
The back clamping piece is rectangular, and a groove is formed in the middle of the bottom edge of the back clamping piece, so that the back clamping piece is convenient to clamp the stone.
The stone front clamping system comprises a front clamping piece, a nut and a gasket, wherein a round hole is formed in the center of the front clamping piece, and the front clamping piece and the gasket are sequentially sleeved on a screw rod and screwed down through the nut.
The front clamping piece is a square steel plate, and the nut is a butterfly-shaped nut, so that the front clamping piece is convenient to twist by hands.
The screw rod is 5mm in diameter and 120mm in length; the outer package size of the back clamping sheet is 50mm multiplied by 25mm multiplied by 1.5 mm; the front clamping piece has an outer envelope dimension of 40mm x 3 mm.
The clamp for measuring and adjusting the flatness of the dry-hanging stone is suitable for dry-hanging granite stones with the thickness of 20-30 mm, and if the conditions of constructing other types of platy stones with different specifications and the like are met, the corresponding size of the clamp is adjusted, but the clamp device is unchanged.
When the dry-hanging stone is installed, the next row of installed plates is used as a reference, one person operates, the back bolt hanging piece of the stone to be installed is adjusted, the surfaces of the installed stone and the reference stone are tightly attached to the clamping piece in a consistent mode, and the clamp is used for verifying the verticality and the flatness of the stone to be installed.
The utility model has the advantages that: the utility model discloses when hanging the stone material futilely in the installation, operating personnel utilizes anchor clamps, only needs one man to operate, improves and hangs stone material efficiency of construction and installation accuracy futilely, and the quality assurance provides new construction method for the outer facade of building is hung stone material high accuracy erection construction futilely.
Drawings
Fig. 1 is a construction elevation view of the present invention.
Fig. 2 is a side view of the structure of the present invention.
Fig. 3 is a structural bottom view of the present invention.
Fig. 4 is a big picture of the stone back surface clamping sheet of the utility model.
In the figure, 1, a stone back clamping system, 11, a back clamping sheet, 12, a screw, 13, a round shaft, 2, a stone front clamping system, 21, a front clamping sheet, 22, a gasket, 23, a nut, 3, a stone, 31, a reference stone, 32 and a stone to be installed.
Detailed Description
As shown in fig. 1-4, a clamp for measuring and adjusting the flatness of dry-hanging stone comprises a stone back clamping system 1, a stone front clamping system 2 and a screw 12. The stone back clamping system 1 is composed of two back clamping pieces 11, the back clamping pieces 11 are connected with a screw 12 through a round shaft 13, and the back clamping pieces 11 can move around the round shaft 13. One end of the screw 12 is forged and pressed to be trapezoidal, and a round hole is formed near the long side end of the trapezoidal shape. The back clamping sheet 11 is rectangular, and one side of the long side is provided with a special-shaped groove, so that the stone 3 can be clamped conveniently. The back clamping piece 11 is provided with a round hole at the center. The two back clamping pieces 11 are respectively arranged at two sides of the trapezoidal section of the screw 12, the round shaft 13 penetrates through round holes formed in the screw 12 and the back clamping pieces 11 and is riveted, so that the screw 12 and the back clamping pieces 11 are integrated, and the back clamping pieces 11 and the screw 12 can rotate mutually through the round shafts 13. The stone front clamping system 2 is composed of a front clamping sheet 21, a nut 23 and a gasket 22. The front clamping piece 21 of the stone front clamping system 2 is a square steel plate, and a round hole capable of penetrating through the screw 12 is formed in the center of the square steel plate. The nut 23 is matched with the screw thread of the screw 12, and the nut 23 is butterfly-shaped, so that the nut can be screwed by hands conveniently. The washer 22 is mated with the nut 23.
The construction steps of the fixture for measuring and adjusting the flatness of the dry-hanging stone are as follows:
1. manufacturing clamp
Selecting a screw rod with the diameter of 5mm and steel plates with the diameter of 1.5mm and 3mm, and blanking according to the size. One end of the screw rod is forged into a trapezoid shape, and a hole is drilled. Two back clamping pieces 11 are manufactured on a 1.5mm steel plate according to the size, holes are drilled in the middle of the back clamping pieces 11, and the back clamping pieces 11 and the screw rods 12 are forged and anchored into a whole through round shafts 13. The 2mm steel plate is manufactured into a front clamping piece 21 of the stone according to the size, and a hole is formed in the middle. The front clamping piece 21 and the gasket 22 of the stone front clamping system 2 are sequentially placed in the screw 12, and the screw is screwed in by the nut 23.
2. Testing and adjusting the flatness of the simulated stone
And (3) installing a clamp on the installed and adjusted reference stone 31, inserting the stone 32 to be installed into the clamp, adjusting the back bolt hanging piece of the stone 32 until the front sides of the reference stone 31 and the stone 32 to be installed are tightly attached to the front side clamping piece 21 of the stone front side system 2, ensuring that the verticality and the flatness of the stone 32 meet the requirements, and finally fixing the stone 32 for next construction.
The above, only be the preferred example of the utility model discloses, not be used for the restriction the utility model discloses, all basis the utility model discloses a technical entity is any slight modification, equivalent replacement and improvement to do the above embodiment, all should be contained within the technical scheme's of the utility model protection within range.

Claims (6)

1. The utility model provides an anchor clamps that is used for hanging stone material roughness futilely and surveys and transfer which characterized in that: the stone front clamping system is screwed on the screw rod, and the stone is clamped between the stone back clamping system and the stone front clamping system.
2. The fixture for measuring and adjusting the flatness of the dry-hung stone as claimed in claim 1, wherein: the screw rod top forging and pressing be trapezoidal, open between two parties at trapezoidal long limit end department has the round hole.
3. The fixture for measuring and adjusting the flatness of the dry-hung stone as claimed in claim 2, wherein: the stone back clamping system comprises two back clamping pieces, through holes are formed in the centers of the two back clamping pieces, the two back clamping pieces are located on two sides of the trapezoidal section of the screw respectively, a circular shaft penetrates through a circular hole in the screw and the through holes in the back clamping pieces and is riveted in a pier mode, and the back clamping pieces and the screw rotate mutually through the circular shaft.
4. The fixture for measuring and adjusting the flatness of the dry-hung stone as claimed in claim 3, wherein: the back clamping piece is rectangular, and a groove is formed in the middle of the bottom edge of the back clamping piece.
5. The fixture for measuring and adjusting the flatness of the dry-hung stone as claimed in claim 1, wherein: the stone front clamping system comprises a front clamping piece, a nut and a gasket, wherein a round hole is formed in the center of the front clamping piece, and the front clamping piece and the gasket are sequentially sleeved on a screw rod and screwed down through the nut.
6. The fixture for measuring and adjusting the flatness of the dry-hung stone as claimed in claim 5, wherein: the front clamping piece is a square steel plate, and the nut is a butterfly-shaped nut.
CN202120146179.7U 2021-01-20 2021-01-20 A anchor clamps that is used for hanging stone material roughness survey and regulate futilely Active CN214834324U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120146179.7U CN214834324U (en) 2021-01-20 2021-01-20 A anchor clamps that is used for hanging stone material roughness survey and regulate futilely

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120146179.7U CN214834324U (en) 2021-01-20 2021-01-20 A anchor clamps that is used for hanging stone material roughness survey and regulate futilely

Publications (1)

Publication Number Publication Date
CN214834324U true CN214834324U (en) 2021-11-23

Family

ID=78954635

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120146179.7U Active CN214834324U (en) 2021-01-20 2021-01-20 A anchor clamps that is used for hanging stone material roughness survey and regulate futilely

Country Status (1)

Country Link
CN (1) CN214834324U (en)

Similar Documents

Publication Publication Date Title
CN102493622A (en) Wallboard installing component and method for installing decorative wallboard by using same
CN216109175U (en) Shaped steel fossil fragments dry-hanging ceramic tile and mixed partition wall of gypsum board
CN214834324U (en) A anchor clamps that is used for hanging stone material roughness survey and regulate futilely
CN201087487Y (en) Back-tied type metal sheet dry hanging curtain wall
CN212224513U (en) Assembled fitment wall top surface T type levelling device
CN201241453Y (en) Stone or ceramic tile wire cable or bar steel prestress pulling and hanging glue implant paste installation apparatus
CN2806629Y (en) Rapid multidimensionally-adjustable dry-hanging framework component device
CN202299212U (en) Integration device of stone and keel
CN213868520U (en) Light steel keel frame with stable structure for indoor suspended ceiling
CN212453240U (en) Large-specification energy-saving ceramic plate curtain wall structure
CN112663886A (en) Hanging composite wallboard installation system and installation method thereof
CN211899408U (en) Building outer wall dry-hanging stone structure
CN112663828A (en) Hidden caulking design structure of steel skeleton concrete partition wall and mounting method thereof
CN213572776U (en) Anti-drop stone paving and reinforcing structure capable of improving flatness
CN219471421U (en) Rock plate and ceramic sheet structure convenient for wall hanging
CN210857678U (en) Pottery tile and GRC board curtain connection structure
CN212129758U (en) Vitrified micro bubble energy-saving heat-insulating veneer integrated board
CN210216833U (en) Dry hanging fixing device for stone curtain wall
CN211783432U (en) Level bar for dry hanging stone installation measurement
CN214575252U (en) Hang dress composite wall panel installing the system
CN220247465U (en) Green construction mounting structure of assembled stone material
CN214658028U (en) Hidden caulking design structure of steel skeleton concrete partition wall
CN217205061U (en) Light microlite wall material pre-buried with back bolt
CN112681658B (en) Fast-assembly wallboard structure and mounting method
CN210767639U (en) Adjustable keel for installing dado

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant