CN214832779U - Construction structure for emergency rescue and disposal of soil landslide through high polymer grouting - Google Patents

Construction structure for emergency rescue and disposal of soil landslide through high polymer grouting Download PDF

Info

Publication number
CN214832779U
CN214832779U CN202120858150.1U CN202120858150U CN214832779U CN 214832779 U CN214832779 U CN 214832779U CN 202120858150 U CN202120858150 U CN 202120858150U CN 214832779 U CN214832779 U CN 214832779U
Authority
CN
China
Prior art keywords
grouting
pipe
landslide
high polymer
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120858150.1U
Other languages
Chinese (zh)
Inventor
张智超
卢贤锥
林启达
柳侃
叶龙珍
齐昌广
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Longyan Zijinshan Sports Park Investment And Development Co ltd
Fujian Geological Engineering Investigation Institute
Original Assignee
Longyan Zijinshan Sports Park Investment And Development Co ltd
Fujian Geological Engineering Investigation Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Longyan Zijinshan Sports Park Investment And Development Co ltd, Fujian Geological Engineering Investigation Institute filed Critical Longyan Zijinshan Sports Park Investment And Development Co ltd
Priority to CN202120858150.1U priority Critical patent/CN214832779U/en
Application granted granted Critical
Publication of CN214832779U publication Critical patent/CN214832779U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model relates to a construction structure for disposing soil landslide in polymer grouting emergency rescue, which comprises an operation platform arranged on the landslide body, a plurality of grouting reinforcement holes arranged on the operation platform and a composite pipe arranged in the grouting reinforcement holes; the composite pipe comprises a steel floral pipe and a recovery steel pipe, wherein the steel floral pipe is provided with a plurality of spray holes in the side wall, the recovery steel pipe is detachably connected with the top end of the steel floral pipe, and the bottom of the steel floral pipe is flush with the bottom surface of the grouting reinforcement hole; each grouting reinforcing hole at least extends into a sliding belt 1m inside the landslide; the downthehole injection thick liquid of slip casting reinforcement is the high polymer material, and this utility model has the reduction to the destruction of massif and ecological environment, and construction convenience and slope stability and intensity are showing the advantage that improves.

Description

Construction structure for emergency rescue and disposal of soil landslide through high polymer grouting
Technical Field
The utility model relates to a relief of disaster rescue technical field, concretely relates to polymer slip casting emergency rescue handles construction structures of soil property landslide.
Background
Landslide is one of the most common geological hazards. China is vast, a large number of mountain slope sections exist, the range of areas deeply affected by landslides is quite considerable, and buildings in mountain areas are mostly built according to mountains, so that landslides frequently occur in front of or behind houses, personal and property safety of people in the mountain areas is seriously threatened, and geological disaster emergency and prevention tasks are very severe for many years. In rainy seasons, emergency treatment work on landslides causes disaster relief personnel to be overwhelmed and untimely. At present, the commonly used landslide disposal means mainly comprise landslide body clearing, drainage engineering construction, weight reduction and back pressure, retaining engineering and the like, and various methods have respective defects, such as: the landslide removal is only suitable for small soil slopes, the economy is low, the original landform and landform are easy to damage, water and soil loss is caused, and the environment is protected; drainage measures belong to indirect treatment schemes and are often matched with other disposal means; the weight reduction back pressure earthwork engineering is complicated and the efficiency is lower; the supporting measures (retaining walls, anti-slide piles and the like) are inconvenient to construct, large in disturbance, high in manufacturing cost and long in construction period, the urgency of landslide disposal is difficult to meet, and the anti-slide piles widely used at present often have the problem of excessive treatment on shallow-surface landslides.
The landslide is dealt with through the reinforced mode of slip casting now, adopts the excavation of the reducible side slope of slip casting method reinforcing side slope and to the destruction of environment, and domatic need not to carry out traditional fender protection again, can remain original slope table to easily ecological restoration. However, the grouting reinforcement effect is not obvious due to the drying shrinkage property of the conventional cement during hardening; in addition, moisture in the slurry is easy to cause additional adverse effects on slope stability in the initial stage of grouting; meanwhile, the conventional cement grout has a disadvantage of relatively long setting time, which makes it difficult to satisfy the urgency of emergency disposal of landslide.
In the aspect of innovative application research of high polymer grouting, the high polymer grouting is mainly applied to the fields of road, foundation, dam, tunnel seepage prevention, leakage stoppage and the like, and is not applied to the treatment of soil landslide.
Therefore, a construction structure for emergency treatment of soil landslide by polymer grouting is urgently needed, so that emergency treatment of landslide can be effectively, rapidly and conveniently carried out.
SUMMERY OF THE UTILITY MODEL
The utility model aims at the above-mentioned problem that exists among the prior art, provide a construction structures of handling soil landslide is speedily carried out rescue work to polymer slip casting emergency.
In order to realize the purpose of the utility model, the utility model adopts the following technical scheme: a construction structure for emergency rescue disposal of soil landslide by high polymer grouting comprises an operation platform arranged on a landslide body, a plurality of grouting reinforcement holes arranged on the operation platform and composite pipes arranged in the grouting reinforcement holes; the composite pipe comprises a steel floral pipe and a recovery steel pipe, wherein the steel floral pipe is provided with a plurality of spray holes in the side wall, the recovery steel pipe is detachably connected with the top end of the steel floral pipe, and the bottom of the steel floral pipe is flush with the bottom surface of the grouting reinforcement hole; each grouting reinforcing hole at least extends into a sliding belt 1m inside the landslide; and the grout injected into the grouting reinforcement holes is a high polymer material.
The construction steps of the structure are as follows:
s100, carrying out slope cleaning on the potential landslide body, and sorting out an operation platform;
s200, drilling a slope surface of the landslide body to form a plurality of grouting reinforcing holes, wherein the plurality of grouting reinforcing holes are arranged in a quincuncial pile shape;
s300, inserting a composite pipe into each grouting reinforcement hole, wherein the composite pipe comprises a steel floral pipe and a recovery steel pipe detachably connected with the steel floral pipe, and the steel floral pipe is positioned at the bottom of each grouting reinforcement hole;
s400, grouting each composite pipe through a grouting pipe, wherein the grouting pipe is made of a two-component expansive high polymer material, a grout stop valve is arranged at the pipe orifice of the grouting pipe, high polymer grout is sprayed out of a hole through the grout stop valve and the hole in the steel perforated pipe, a surrounding rock-soil body is cut, the volume of the rock-soil body is rapidly expanded and solidified, and the rock-soil body is compacted and reinforced;
s500, lifting the grouting pipe according to a set speed, stopping for a set time when the grouting pipe is lifted to a sliding belt, continuing to lift the grouting pipe, and simultaneously performing grouting uninterruptedly;
s600, stopping grouting operation when the elevation of the bottom of the grouting pipe exceeds the steel perforated pipe;
s700, pulling out the grouting pipe, and detaching the recovery steel pipe;
and S800, performing grouting operation on each grouting reinforcing hole again to form the high polymer micro pile.
The working principle and the beneficial effects are as follows: compared with the prior art, 1, the high polymer grouting material has the advantage of quick setting, can reach 90 percent of the final strength in about 15 minutes, greatly shortens the construction period, and is very suitable for emergency treatment of disaster situations and emergencies, while the scheme adopts the two-component expandable high polymer material, can be solidified within 10 seconds at the fastest to generate an effect, and is very suitable for emergency treatment;
2. the high polymer material has good expansibility: the expansion ratio of the high polymer material can reach 20:1, the high polymer material can effectively fill cavities and cracks, squeeze surrounding rock and soil mass media and improve bearing capacity, and is different from cement slurry, the high polymer does not contain moisture, the strength of the rock and soil mass cannot be reduced at the initial stage of grouting, the high polymer material has lighter weight, has smaller additional load on the side slope with the existing diseases and cannot influence the stability of the slope body, so the method adopting the high polymer material has better performance compared with the prior art;
3. by arranging the composite pipe, the grouting operation of high polymers can be facilitated, the recovery steel pipe in the composite pipe can be conveniently recovered and reused, and the construction cost is reduced;
4. the grout stop valve is equivalent to a check valve and prevents the grout from flowing back into the grouting pipe, so that the grout can be intelligently ejected from the holes of the steel perforated pipe;
5. in the process of lifting the grouting pipe, the grouting pipe is lifted according to a preset speed, so that more grout can be sprayed out of the hole of the steel perforated pipe, the grouting pipe is stopped near the sliding belt for a set time, the high-pressure grout has sufficient time to reinforce soft rock soil, the soil quality at the sliding belt can be further reinforced, and the strength of the whole landslide is obviously improved; the set time and the set rate are changed according to the actual operation.
6. The high polymer micro-pile is formed, and the sliding resistance of a landslide body can be obviously improved.
Furthermore, a plurality of detection holes which are uniformly arranged at intervals by taking the grouting reinforcement holes as circle centers are arranged around each grouting reinforcement hole, and the permeation condition of the high polymer slurry in the stratum is observed through each detection hole, so that whether the grouting of the corresponding grouting reinforcement holes is qualified or not is judged, and the inspection steps are as follows:
s900, drilling around each grouting reinforcing hole, and taking a plurality of detection holes;
s1000, observing the penetration condition of the high polymer slurry in each detection hole;
s1100, if all the detection holes have high polymer condensate, the corresponding grouting reinforcement holes are qualified;
and S1100, otherwise, performing grouting operation on the detection holes without the high polymer condensate until each grouting reinforcing hole is qualified in detection.
Through the inspection steps, the unqualified situation of each grouting reinforcement hole can be completely avoided, so that hidden dangers are eliminated, the stability of the slope body is further improved, and the steps are simple and reliable to operate.
Furthermore, a row of grouting water-intercepting holes are densely arranged on the rear edge of the landslide in a distributed manner, every two adjacent grouting water-intercepting holes are split and run through in the grouting process to form a water-tight high polymer water-intercepting plate, the thickness of the high polymer water-intercepting plate is consistent with the inner diameter of each grouting water-intercepting hole, and the processing steps are as follows:
s1200, densely arranging and erecting a row of grouting water intercepting holes on the rear edge of the landslide body, wherein two adjacent grouting water intercepting holes form split through;
s1300, performing grouting operation on each grouting water intercepting hole to form a waterproof high polymer water intercepting plate, wherein the plate thickness of the high polymer water intercepting plate is consistent with the inner diameter of the grouting water intercepting hole.
According to the steps, the water blocking holes are split and communicated when grouting is carried out, so that a high polymer water blocking plate which can be connected together is generated, underground water outside the rear edge of the landslide can be effectively blocked from permeating into the landslide body, the stability of the landslide body is prevented from further deteriorating, compared with a water blocking plate which is directly inserted and processed, the water blocking plate is more convenient to construct, and the water blocking plate does not need to be additionally transported to the rear edge of the landslide body.
And further, S1400, spraying a layer of high polymer thin layer on the surface of the landslide body after construction is completed. Due to the water-resisting property of the high polymer, rainwater and surface water are prevented from permeating into the landslide body, and the stability of the landslide body is prevented from further deteriorating.
Furthermore, the aperture of the grouting reinforcement hole is 25-41 mm, the pitch of the holes is 5-10 m, and the depth of the grouting reinforcement hole at least extends into the position 1m below the sliding belt. The arrangement can ensure that the high polymer micro pile formed by grouting has enough strength, so that the sliding belt and the landslide soil body are better reinforced, the sliding resistance of the slope body is improved, and the grouting reinforcement hole of the size does not need to be provided with a large drilling machine, and a portable backpack drilling machine can be adopted.
Further, the steel perforated pipe is in threaded connection with the recovery steel pipe. The device can conveniently take the recovery steel pipe off from the steel perforated pipe or install the recovery steel pipe on the steel perforated pipe, and is convenient to operate.
Furthermore, when each composite pipe is subjected to grouting operation through a grouting pipe, the pipe orifice of the grouting pipe is flush with the bottom of the steel perforated pipe, and the diameter of the grout stop valve is consistent with the inner diameter of the steel perforated pipe. This setting can guarantee better that the high polymer can follow the hole of steel floral tube and spout, especially the bottom position of steel floral tube, ends the thick liquid valve and can cooperate with steel floral tube inner wall better, reduces to reveal and leads to the thick liquid can't impact on the ground around the steel floral tube.
Furthermore, when the grouting operation is performed on each composite pipe through the grouting pipe, the grouting pressure is 18 MPa. The arrangement can ensure that the slurry can impact rock soil to form better high polymer condensate under the pressure, and the high polymer can penetrate and permeate to a farther position, so that the sliding resistance and the strength of the slope are obviously enhanced.
Furthermore, the hole distance of each grouting water stopping hole is less than 0.2m, and the depth of each grouting water stopping hole at least extends into 1m below the sliding belt. Under this setting, when stopping the water hole slip casting to the slip casting for the slip casting cuts the water hole and can be broken the splitting by the thick liquid, leads to adjacent slip casting to cut the water hole and link together, and last row slip casting cuts the water hole and has formed a waterproof high polymer board that cuts water, and the structure is ingenious, and construction convenience.
Further, a backpack drilling machine is adopted in the whole process to carry out drilling operation. For soil landslide, the backpack drilling machine can penetrate through a submerged landslide body, the equipment is light, the construction is simple, a single person can operate on a mountain slope, and the influence on the stability of the slope body is small or even zero. The backpack drilling machine is adopted for sampling, and the traditional sampling such as manual excavation, groove detection, well detection and the like can be replaced. It can not only accelerate the sampling work speed, but also reduce the damage of vegetation in a large number and protect the environment.
Drawings
FIG. 1 is a flow chart of the construction of an embodiment of the present invention;
FIG. 2 is a construction structure diagram obtained by the construction method of the present invention;
FIG. 3 is a schematic structural view of a composite pipe;
FIG. 4 is a schematic view of an embodiment of the high polymer water intercepting panel.
In the figure, 1, an operation platform; 2. a landslide body; 3. a sliding belt; 4. grouting reinforcement holes; 5. a steel floral tube; 6. recovering the steel pipe; 10. polymer micro-piles; 11. grouting water stopping holes; 12. a high polymer water interception plate; 13. a thin polymer layer on the slope; 14. a slurry stop valve; 15. and (4) grouting pipes.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art all belong to the protection scope of the present invention.
It will be understood by those skilled in the art that in the present disclosure, the terms "longitudinal," "lateral," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like are used in an orientation or positional relationship indicated in the drawings for ease of description and simplicity of description, and do not indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and thus, are not to be considered limiting.
The landslide is a natural phenomenon that soil or rock mass on a slope slides downwards along the slope integrally or dispersedly under the action of gravity along a certain weak surface or a weak zone under the influence of factors such as river scouring, underground water activity, rainwater immersion, earthquake, artificial slope cutting and the like. The moving rock (earth) body is called a displaced body or a sliding body, and the unmoved underburden rock (earth) body is called a sliding bed. The landslide body 2 refers to the whole sliding part of the landslide, called the landslide body for short.
The sliding belt 3 is one of the important components of landslide landscape and refers to the gliding interface of the landslide body 2. The sliding surface is generally steep upward and gentle downward, and is approximately circular arc-shaped. The slide belt 3 is sometimes only one, sometimes several, and can be divided into a main slide belt 3 and a secondary slide belt 3. The polished surface and scratches were clearly visible on the slide belt 3, and sometimes, there were noticeable disturbances and trailing wrinkles.
Referring to fig. 2 and 3, the construction structure for emergency treatment of soil landslide by polymer grouting comprises an operation platform 1 arranged on a landslide body, a plurality of grouting reinforcement holes 4 arranged on the operation platform 1, and composite pipes arranged in the grouting reinforcement holes 4; the composite pipe comprises a steel perforated pipe 5 and a recovery steel pipe 6, wherein the steel perforated pipe 5 is provided with a plurality of spray holes in the side wall, the recovery steel pipe 6 is detachably connected with the top end of the steel perforated pipe 5, and the bottom of the steel perforated pipe 5 is flush with the bottom surface of the grouting reinforcement hole 4; each grouting reinforcement hole 4 at least extends into a sliding belt 3 in the landslide 2 by one meter; the grout injected into the grouting reinforcement holes 4 is a high polymer material, please refer to fig. 1, wherein the construction steps include the following steps:
step one, carrying out slope surface cleaning on a potential landslide body 2, sorting out an operation platform 1 for a worker to walk, and after the landslide emergency work is finished, subsequently carrying out deep engineering management by using the operation platform 1, wherein the specific operation during cleaning is a conventional technical means and is not repeated;
step two, a backpack drilling machine is adopted to drill holes of grouting reinforcement holes 4 on the slope surface, the hole diameter is 25-41 mm, the drill holes are arranged in quincuncial piles, the distance is 5-10 m, the depth is more than 1m below a sliding belt 3, the backpack drilling machine can be a Shore drilling machine, the drilling sampling depth can reach 23 m, the caliber of an underground part can be selected from 26mm and 41mm, and the backpack drilling machine can be used for sampling to replace traditional manual excavation, groove detection, well detection and other sampling; the sampling device not only can accelerate the sampling working speed, but also can greatly reduce the damage of vegetation and protect the environment;
step three, connecting the steel perforated pipe 5 and the recovery steel pipe 6 through a screw to form a composite pipe, wherein the length of the steel perforated pipe 5 is about 2m, the steel perforated pipe 5 is left in the landslide body 2 after construction is finished, the recovery steel pipe 6 can be recycled, the steel perforated pipe 5 is a commercially available product and is provided with a plurality of holes for grouting injection operation, and the structure of the steel perforated pipe is not described again;
fourthly, firstly putting the composite pipe down to enable the steel perforated pipe 5 to be positioned at the bottom of the hole;
inserting a grouting pipe 15 into the composite pipe to the bottom of the composite pipe, namely a bottom pipe opening of the steel perforated pipe 5, wherein a rubber grout stop valve 14 with the same inner diameter as the composite pipe is fixed at the pipe opening of the grouting pipe 15, the rubber grout stop valve 14 is equivalent to a one-way valve or a check valve and prevents grout from flowing back, the rubber grout stop valve 14 can be purchased from the market, the installation mode is also the prior art, other types of grout stop valves 14 can be purchased, and the specific structure is not described again;
injecting a two-component expansive high polymer material into each grouting reinforcement hole 4, grouting under the pressure of 18MPa, and enabling slurry to be firstly ejected from a hole of the steel perforated pipe 5 close to a pipe orifice due to a slurry stop valve at the pipe orifice of the grouting pipe 15, cutting surrounding rock-soil bodies, rapidly expanding and solidifying the volume, and compacting and reinforcing the rock-soil bodies;
lifting the grouting pipe 15 at a speed of 1-2 m/min to gradually increase the elevation of the bottom of the grouting pipe 15 (namely the elevation of a slurry outlet), so that more holes of the steel perforated pipe 5 can spray slurry; slightly staying when the slurry is lifted to the vicinity of the sliding belt 3, so that the high-pressure slurry has sufficient time to reinforce the soft rock-soil body; at this time, the high polymer slurry will form three states in the weak rock-soil body: the three types of the interwoven mesh split grouting slurry pulse, the compacted grouting slurry bubble and the slurry permeating into the pores of the rock-soil body can greatly improve the strength of the slope body and the sliding belt and enhance the skid resistance;
step eight, continuing grouting, stopping grouting when the elevation of the bottom of the grouting pipe 15 exceeds the elevation of the steel perforated pipe 5, wherein the elevation of the bottom of the grouting pipe 15 exceeds the elevation of the sliding belt 3 by about 1m, and facilitating the dismantling of the recovery steel pipe 6;
step nine, pulling out the grouting pipe, simultaneously screwing off and pulling out the recovery steel pipe 6 from the screw port of the steel flower pipe 5, and independently leaving the steel flower pipe 5 near the sliding belt 3 for improving the anti-sliding force;
step ten, grouting in the original drilled hole again to enable the high polymer slurry to fill the drilled hole, and simultaneously enabling the high polymer slurry to automatically block the hole opening, so that the expansive high polymer slurry can be solidified within 10 seconds at the fastest speed due to the rapid solidification of the high polymer to form a pile body with the strength of about 5MPa, and therefore the slip resistance of the slope body can be rapidly improved, the further development of the landslide is resisted, the method is quite suitable for emergency rescue disposal, and gaps can be continuously filled by utilizing surrounding rock soil;
eleven, drilling detection: adopting a backpack drilling machine, drilling 4 detection holes in the distance of 1m around the grouting reinforcement hole 4 to obtain an original sample, observing the permeation condition of the polymer slurry in the stratum, if the original samples obtained by drilling 4 holes all have polymer condensate, indicating that the polymer reinforcement has effectively diffused to the range with the radius of 1m, and can approximately meet the landslide emergency reinforcement requirement, determining that the grouting reinforcement hole 4 is qualified, otherwise, performing grouting by using the detection holes until the detection is qualified;
step twelve, adopting a backpack drilling machine, densely arranging and arranging a row of grouting water-intercepting holes 11 at the rear edge of the landslide body 2, wherein the distance between the drilling holes is preferably smaller than 0.2m, so that the grout in two adjacent holes can be split and communicated, the hole position range needs to exceed the width of the landslide body 2 by more than 5m, and the depth needs to exceed the sliding belt 3 by more than 1 m;
thirteen, please refer to fig. 4, a high polymer grouting machine is adopted to split and grout in the row of grouting water intercepting holes 11, so that grout in two adjacent holes is split and communicated, at the moment, only a grout outlet parallel to the arrangement direction of the grouting water intercepting holes 11 is required to be arranged on the wall of the grouting pipe 15, so that the cutting direction of fluid directly sprayed by the grout is also parallel to the arrangement direction of the grouting water intercepting holes 11, as shown in the arrow direction in the figure, the grout in the two adjacent water intercepting holes is split and communicated along the weak direction of a soil body, a waterproof high polymer water intercepting plate 12 is formed, the thickness of the high polymer water intercepting plate 12 is equivalent to the aperture, the groundwater outside the rear edge of the landslide can be effectively prevented from permeating into the landslide body 2, the landslide rock-soil body is prevented from being softened due to water soaking, the stability of the landslide body is prevented from further deteriorating, wherein the range of the aperture needs to exceed the width of the landslide body 2 by more than 5m, and the depth of the aperture needs to exceed the depth of the sliding belt 3 by more than 1m, so that the landslide body 2 in both width and depth directions can be completely isolated from the ground water;
fourteen, spraying a layer of polymer thin layer on the surface of the landslide body 2, and blocking rainwater and surface water from permeating into the landslide body 2 through the water-resisting property of the polymer to prevent the stability of the landslide body from further deteriorating.
The utility model discloses a method has following advantage: 1. for soil landslide, the potential landslide body 2 can be penetrated by a backpack drilling machine, the equipment is light, the construction is simple, the operation can be carried out on the mountain slope by a single person, and the stability of the slope body cannot be influenced. 2. The adopted high polymer grouting material has the advantage of quick setting, can be set within 10 seconds at the fastest speed, greatly shortens the construction period, and is very suitable for emergency treatment of disaster situations and emergencies. 3. The high polymer material has good expansibility: different from the drying shrinkage property of the conventional cement during hardening, the expansion ratio of the high polymer material can reach 20:1, so that cavities and cracks can be effectively filled, the surrounding rock and soil mass medium can be compacted, and the bearing capacity is improved. 4. And (3) water-free: different from cement grout, the high polymer does not contain moisture, and the strength of the rock-soil body cannot be reduced at the initial stage of grouting. 5. The weight is lighter: the additional load generated on the slope with the existing diseases is small, and the stability of the slope body cannot be influenced. 6. The same equipment (a backpack drilling machine and a high polymer grouting machine) is adopted, so that the reinforcement of the soft rock-soil body of the landslide and the separation of underground water, surface water and rainwater of the landslide body 2 can be realized, the stability of the landslide body is improved from multiple angles, and the effect is instant.
The part of the utility model which is not described in detail is the prior art, so the utility model does not detail the part.
It is understood that the terms "a" and "an" should be interpreted as meaning that a number of one element or element is one in one embodiment, while a number of other elements is one in another embodiment, and the terms "a" and "an" should not be interpreted as limiting the number.
Although the terms of the operating platform 1, the sliding body 2, the sliding belt 3, the grouting reinforcement holes 4, the steel floral tubes 5, the recycled steel tubes 6, the polymer micro-piles 10, the grouting cutoff holes 11, the polymer cutoff plates 12, the sloping polymer thin layers 13, the grout stop valves 14, the grouting pipes 15, etc. are used more frequently, the possibility of using other terms is not excluded. These terms are used merely to more conveniently describe and explain the nature of the present invention; they are to be construed in a manner that is inconsistent with the spirit of the invention.
The present invention is not limited to the above-mentioned preferred embodiments, and any other products in various forms can be obtained by the teaching of the present invention, but any changes in the shape or structure thereof, which have the same or similar technical solutions as the present invention, fall within the protection scope of the present invention.

Claims (9)

1. A construction structure for emergency rescue and disposal of soil landslide by high polymer grouting is characterized by comprising an operation platform arranged on a landslide body, a plurality of grouting reinforcement holes arranged on the operation platform and composite pipes arranged in the grouting reinforcement holes; the composite pipe comprises a steel floral pipe and a recovery steel pipe, wherein the steel floral pipe is provided with a plurality of spray holes in the side wall, the recovery steel pipe is detachably connected with the top end of the steel floral pipe, and the bottom of the steel floral pipe is flush with the bottom surface of the grouting reinforcement hole; each grouting reinforcing hole at least extends into a sliding belt 1m inside the landslide; and the grout injected into the grouting reinforcement holes is a high polymer material.
2. The construction structure for emergency rescue and disposal of soil landslide through high polymer grouting according to claim 1, wherein a plurality of detection holes are formed around each grouting reinforcement hole and are uniformly spaced around the grouting reinforcement hole, and the penetration condition of high polymer grout in a stratum is observed through each detection hole, so that whether grouting of the corresponding grouting reinforcement hole is qualified is judged.
3. The construction structure of the high polymer grouting emergency rescue disposal soil landslide of claim 1, wherein a row of grouting water intercepting holes are densely arranged at the rear edge of the landslide, two adjacent grouting water intercepting holes are split and communicated in the grouting process to form a water-tight high polymer water intercepting plate, and the plate thickness of the high polymer water intercepting plate is consistent with the inner diameter of the grouting water intercepting holes.
4. The construction structure of the high polymer grouting emergency rescue disposal soil landslide as claimed in claim 2, wherein the diameter of each grouting reinforcement hole is 25-41 mm, the hole distance between two adjacent grouting reinforcement holes is 5-10 m, and the depth of each grouting reinforcement hole at least extends into the sliding belt by 1 m.
5. The construction structure for the emergency rescue and disposal of the soil landslide by polymer grouting according to claim 1, wherein the steel perforated pipe is in threaded connection with a recycled steel pipe.
6. The construction structure for emergency rescue and disposal of soil landslide through high polymer grouting according to claim 1, wherein when each composite pipe is subjected to grouting operation through a grouting pipe, a pipe orifice of the grouting pipe is flush with the bottom of the steel perforated pipe, and a diameter of a grout stop valve on the grouting pipe is consistent with an inner diameter of the steel perforated pipe.
7. The construction structure for the emergency rescue and disposal of the soil landslide by polymer grouting according to claim 1, wherein when the grouting operation is performed on each composite pipe through a grouting pipe, the grouting pressure is 18 MPa.
8. The construction structure of the high polymer grouting emergency rescue disposal soil landslide of claim 3, wherein the hole pitch of each grouting cut-off hole is less than 0.2m, and the depth of each grouting cut-off hole extends at least 1m below the sliding belt.
9. The construction structure for the emergency rescue and disposal of the soil landslide by polymer grouting according to any one of claims 1-8, wherein a backpack drilling machine is adopted for drilling in the whole process.
CN202120858150.1U 2021-04-25 2021-04-25 Construction structure for emergency rescue and disposal of soil landslide through high polymer grouting Active CN214832779U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120858150.1U CN214832779U (en) 2021-04-25 2021-04-25 Construction structure for emergency rescue and disposal of soil landslide through high polymer grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120858150.1U CN214832779U (en) 2021-04-25 2021-04-25 Construction structure for emergency rescue and disposal of soil landslide through high polymer grouting

Publications (1)

Publication Number Publication Date
CN214832779U true CN214832779U (en) 2021-11-23

Family

ID=78768557

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120858150.1U Active CN214832779U (en) 2021-04-25 2021-04-25 Construction structure for emergency rescue and disposal of soil landslide through high polymer grouting

Country Status (1)

Country Link
CN (1) CN214832779U (en)

Similar Documents

Publication Publication Date Title
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN214832780U (en) Construction structure for treating landslide by inducing calcium carbonate precipitation with microbial culture solution
CN101225656B (en) Method for rapidly reinforcing ultra-soft soil superficial layer
CN103437339A (en) Construction method for sealing karst cave near trench wall of underground continuous wall in karst stratum
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN111472346A (en) Construction method for reinforcing soil around pile body of cast-in-place pile
CN105649000A (en) Back pressure backfilling shallow-buried excavation construction method for tunnel undercrossing gully
CN112281879B (en) Anti-seepage film connecting device for water-intercepting curtain and water-intercepting curtain construction method
CN212104042U (en) Underwater anti-sliding bored pile foundation
CN110952533A (en) Underwater anti-slip bored pile foundation and construction method thereof
CN110778328A (en) Loess tunnel entrance section construction method for passing through landslide body
CN113174972B (en) Construction method for treating landslide by high-pressure injection of microbial liquid and calcium carbonate deposition
CN112627212B (en) Water-faced cofferdam inner tube well dewatering dry excavation construction method
CN214832779U (en) Construction structure for emergency rescue and disposal of soil landslide through high polymer grouting
CN110821512B (en) Loess tunnel entrance opening section pre-reinforcing and excavating construction method passing through landslide body
CN113152491A (en) Construction method for emergency rescue disposal of soil landslide through high polymer grouting
CN113266362B (en) Top pipe cover excavation construction method for penetrating through existing dense anchor cable area
CN106049508B (en) A kind of swag type depression earth rock placement structure and construction method
CN211773608U (en) Prefabricated assembled rectangle friction pile dado
CN209654048U (en) A kind of water discharge tunnel tunnel shielding portal pre-buried structure
CN107816068B (en) Construction method of underground diaphragm wall brushing concrete bypass flow detection and treatment device
CN217974213U (en) Gravity wharf for mucky soil foundation
CN216405324U (en) Flexible water drainage device controlled by floating body of check dam
CN217204294U (en) Plugging structure of water overflow node of underground chamber bottom plate post-cast strip
CN114215558B (en) Plugging method for near-flooding civil mining tunnel of tailing pond

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant