CN214741338U - Slope tunneling tunnel construction structure - Google Patents

Slope tunneling tunnel construction structure Download PDF

Info

Publication number
CN214741338U
CN214741338U CN202120582455.4U CN202120582455U CN214741338U CN 214741338 U CN214741338 U CN 214741338U CN 202120582455 U CN202120582455 U CN 202120582455U CN 214741338 U CN214741338 U CN 214741338U
Authority
CN
China
Prior art keywords
tunnel
construction
slope
arch
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120582455.4U
Other languages
Chinese (zh)
Inventor
郝再国
胡宏钰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Yongchuang Zhongxin Architectural Design Co ltd
Original Assignee
Beijing Yongchuang Zhongxin Architectural Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Yongchuang Zhongxin Architectural Design Co ltd filed Critical Beijing Yongchuang Zhongxin Architectural Design Co ltd
Priority to CN202120582455.4U priority Critical patent/CN214741338U/en
Application granted granted Critical
Publication of CN214741338U publication Critical patent/CN214741338U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model relates to a slope tunnelling tunnel construction structure, including setting up soil nail wall bank protection on the tunnel slope and setting up the tunnel just lining structure at the tunnel inlayer, soil nail wall bank protection is followed soil nail position and is indulged transversely crisscross the strengthening rib that is equipped with respectively, tunnel slope department is along the tunnel just the outer contour line of digging of lining structure and is equipped with reinforced concrete uide bushing arch, tunnel portal department sets up along the arch camber the intraductal level of difference of uide bushing is provided with big pipe shed, big pipe shed set up the degree of depth and is greater than or equal to 10 m. The utility model discloses a slope tunnelling tunnel construction structure has mainly solved the unable open cut construction's of part underground infrastructure problem, and the safety of protection construction that can be fine can be solved and tunnel construction is carried out under the prerequisite that does not possess the setting shaft at the job site, can improve construction progress reduction of erection time greatly in the construction, also can practice thrift the cost.

Description

Slope tunneling tunnel construction structure
Technical Field
The utility model relates to a tunnel construction field especially relates to a slope tunnelling tunnel construction structure.
Background
In recent years, the state has vigorously developed comprehensive municipal works such as underground comprehensive pipe galleries and the like, most of the works are carried out by adopting an open cut method based on cost control, but the existing underground obstacles are more due to the construction of urban infrastructure, and the works of adopting the open cut method can damage the existing underground obstacles to different degrees.
At present, according to the prior art, measures such as relocation and protection are mostly adopted for the method for treating the underground obstacles, but when part of underground infrastructure cannot be relocated or effectively protected due to site conditions and the particularity of the infrastructure, the foundation pit cannot be used for large-area open cut construction. Therefore, for the construction of the special underground infrastructure, a new construction mode is needed to meet the construction requirements, so that the safe operation of the underground existing infrastructure can be achieved, and meanwhile, the safety of construction operation can be ensured.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the problem that the large tracts of land construction can not be carried out to the part district foundation ditch, studying the safe operation that can effectively guarantee underground existing condition infrastructure, also can guarantee the safe slope tunnelling tunnel construction structure of construction operation simultaneously.
For realizing the above-mentioned purpose, the utility model provides a slope tunnelling tunnel construction structure, including setting up soil nail wall bank protection on the tunnel slope and setting up the tunnel just lining structure at the tunnel inlayer, soil nail wall bank protection is followed soil nail position and is indulged transversely crisscross strengthening rib that is equipped with respectively, tunnel slope department is equipped with reinforced concrete uide bushing arch along the outer contour line of digging of tunnel just lining structure, reinforced concrete uide bushing arch is deepened C30 reinforced concrete guide wall by phi 140 uide bushing and is constituted, tunnel portal department sets up along the arch-forming line the intraductal level of uide bushing is provided with big pipe shed respectively, big pipe shed adopts phi 108 big pipe shed advance support, adjacent big pipe shed hoop interval 300mm, big pipe shed's the setting depth of setting up is greater than or equal to 10 m.
Preferably, the soil nails are made of phi 20 steel bars by grinding.
Preferably, the reinforcing ribs are made of phi 14 reinforcing steel bars, and the spray anchor is C20 concrete with the thickness of 100 mm.
Preferably, the longitudinal and transverse spacing of the reinforcing ribs is not more than 1200 mm.
Preferably, the wall thickness of the guide sleeve is 5mm, and the length of the reinforced concrete guide sleeve arch is set according to the actual size of the reinforced concrete guide arch wall.
Preferably, the wall thickness of the large pipe shed is 6mm, and the circumferential distance is 300 mm.
Preferably, the grouting slurry in the step C is cement slurry or cement-water-glass double-fluid slurry.
Based on the technical scheme, the utility model has the advantages that: by adopting the slope tunneling tunnel construction structure, the safety of protection construction can be good, tunnel construction can be carried out on the premise that a vertical shaft is not arranged on a construction site, the construction progress can be greatly improved, the construction period can be greatly shortened, and the cost can be saved.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the invention and together with the description serve to explain the invention without undue limitation to the invention. In the drawings:
FIG. 1 is a sectional view of a construction structure of a slope tunneling tunnel;
fig. 2 is an elevation view of a construction structure of a slope heading tunnel.
Detailed Description
The technical solution of the present invention is further described in detail by the accompanying drawings and examples.
The utility model provides a slope tunnelling tunnel construction structure, as shown in figure 1 ~ figure 2, wherein show the utility model discloses a preferred embodiment.
The utility model discloses a to part underground infrastructure because of the particularity of site conditions and facility self can't change when moving or effective protection, this section pit just can't carry out the open cut construction of large tracts of land and a slope tunnelling tunnel construction structure that provides.
As shown in fig. 1 and 2, the slope tunneling tunnel construction structure comprises soil nailing wall revetment arranged on a tunnel slope and a tunnel primary lining structure 4 arranged in a tunnel inner layer, wherein reinforcing ribs are respectively arranged on the soil nailing wall revetment in a longitudinally and transversely staggered manner along the soil nailing positions, a reinforced concrete guide sleeve arch is arranged at the tunnel slope along an outer excavation contour line of the tunnel primary lining structure 4, the reinforced concrete guide sleeve arch is formed by a phi 140 guide sleeve 2 penetrating into a C30 reinforced concrete guide wall 1, large pipe sheds 3 are respectively horizontally arranged in the guide sleeve 2 arranged at tunnel portal along an arch raising line, the large pipe sheds 3 are supported by phi 108 large pipe shed advance supports, the circumferential distance between adjacent large pipe sheds 3 is 300mm, and the arrangement depth of the large pipe sheds 3 is not less than 10 m.
Preferably, in the step a, the soil nails are made by grinding steel bars with a diameter of 20, and the longitudinal and transverse intervals of the soil nails are not more than 1200 mm.
Preferably, the reinforcing ribs are made of phi 14 reinforcing steel bars, and the spray anchor is C20 concrete with the thickness of 100 mm.
Particularly, the longitudinal and transverse spacing of the soil nails is not more than 1200 mm. The wall thickness of the guide sleeve 2 is 5mm, and the length of the guide sleeve arch of the reinforced concrete is set according to the actual size of the guide arch wall of the reinforced concrete. The wall thickness of the large pipe shed 3 is 6 mm.
The utility model discloses a slope tunnelling tunnel construction structure can refer to following step and construct:
A. slope protection construction of a slope soil nail wall: adopting the construction of spraying anchor and protecting wall of soil nailing wall, respectively arranging reinforcing ribs along the longitudinal and transverse directions along the soil nailing position;
B. construction of the reinforced concrete guide arch wall: according to the field situation, a reinforced concrete guide sleeve arch is arranged at the slope along the excavation contour line outside the tunnel primary lining structure 4, and the reinforced concrete guide sleeve arch is formed by a phi 140 guide sleeve 2 penetrating into a C30 reinforced concrete guide wall 1; the arranged reinforced concrete guide sleeve arch mainly prevents the slope from sliding laterally, and can support the advanced large pipe shed; the depth of the guide sleeve is set according to the actual size of the reinforced concrete guide arch wall, and the guide sleeve is used for driving the guide wall into a large pipe shed after the construction of the guide wall is finished;
C. advanced grouting support: b, horizontally arranging large pipe sheds 3 in guide sleeves arranged along the arch lifting line at the tunnel door in the step B respectively, wherein the large pipe sheds 3 are supported in advance by phi 108 large pipe sheds, the annular distance is 300mm, and the arranging depth is not less than 10 m;
D. and (3) grouting after the construction is finished, wherein the grouting slurry is cement slurry or cement-water-glass double-liquid slurry, constructing the primary lining structure 4 of the tunnel after the steps are finished, and then checking and accepting the structure.
In the embodiment, the grouting slurry is cement slurry or cement-water-glass double-liquid slurry. The cement slurry is used for daily grouting, and if a sand-containing stratum appears, cement-water-glass double-liquid slurry can be used, and the tunnel primary lining construction can be carried out after grouting is finished.
By adopting the slope tunneling tunnel construction structure, the safety of protection construction can be good, tunnel construction can be carried out on the premise that a vertical shaft is not arranged on a construction site, the construction progress can be greatly improved, the construction period can be greatly shortened, and the cost can be saved.
Finally, it should be noted that the above embodiments are only used for illustrating the technical solutions of the present invention and not for limiting the same; although the present invention has been described in detail with reference to preferred embodiments, it should be understood by those skilled in the art that: the invention can be modified or equivalent substituted for some technical features; without departing from the spirit of the present invention, it should be understood that the scope of the claims is intended to cover all such modifications and variations.

Claims (6)

1. The utility model provides a slope tunnelling tunnel construction structure which characterized in that: including setting up soil nail wall bank protection on the tunnel slope and setting up tunnel primary lining structure (4) at the tunnel inlayer, soil nail wall bank protection is equipped with the strengthening rib along soil nail position longitudinal and transverse crisscross respectively, tunnel slope department is equipped with reinforced concrete uide bushing arch along the outer contour line of digging of tunnel primary lining structure (4), reinforced concrete uide bushing arch is deepened C30 reinforced concrete guide wall (1) by phi 140 uide bushing (2) and is constituted, tunnel portal department sets up along the arch-forming line the level is provided with big pipe-shed (3) in uide bushing (2) respectively, big pipe-shed (3) adopt phi 108 big pipe-shed advance support, adjacent big pipe-shed (3) circumferential spacing 300mm, the degree of depth that sets up of big pipe-shed (3) is more than or equal to 10 m.
2. The structure of claim 1, wherein: the soil nail is made by grinding a phi 20 steel bar.
3. The structure of claim 1, wherein: the reinforcing ribs are made of phi 14 reinforcing steel bars, and the spray anchor is C20 concrete with the thickness of 100 mm.
4. The structure of claim 3, wherein: the longitudinal and transverse spacing of the reinforcing ribs is less than or equal to 1200 mm.
5. The structure of claim 1, wherein: the wall thickness of the guide sleeve (2) is 5mm, and the length of the guide sleeve arch of the reinforced concrete is correspondingly set according to the actual size of the guide arch wall of the reinforced concrete.
6. The structure of claim 1, wherein: the wall thickness of the large pipe shed (3) is 6 mm.
CN202120582455.4U 2021-03-10 2021-03-10 Slope tunneling tunnel construction structure Expired - Fee Related CN214741338U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120582455.4U CN214741338U (en) 2021-03-10 2021-03-10 Slope tunneling tunnel construction structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120582455.4U CN214741338U (en) 2021-03-10 2021-03-10 Slope tunneling tunnel construction structure

Publications (1)

Publication Number Publication Date
CN214741338U true CN214741338U (en) 2021-11-16

Family

ID=78596309

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120582455.4U Expired - Fee Related CN214741338U (en) 2021-03-10 2021-03-10 Slope tunneling tunnel construction structure

Country Status (1)

Country Link
CN (1) CN214741338U (en)

Similar Documents

Publication Publication Date Title
CN102071947B (en) Construction method for soft surrounding rock section of large-span tunnel portal
CN104763433A (en) Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN104120731B (en) A kind of tunnel subsidence protector and construction method thereof
CN102031736A (en) Construction technology for under-passing existing line under complicated geological condition
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN111101540B (en) Construction method for passing existing electric power tunnel on open cut tunnel
CN201801872U (en) Deep foundation pit excavated on corrode geology through combined support
CN207934910U (en) A kind of newly built tunnels closely on across existing tunnel anti-floating reinforcement system
CN111502696A (en) Dense-mesh type advanced support system of underground excavation tunnel and construction method
CN112031814B (en) Cave-entering construction method for crossing shallow-layer high-load highway
CN108131145A (en) A kind of construction method of super-span tunnel excavation support
CN104847362A (en) Large-span subway station underground excavation construction method for hard rock stratum
CN112727466A (en) Construction method for support-free prefabricated assembled type shield tunnel air shaft structure
CN105464685A (en) Cave-pile method bored tunnel waterproof curtain and construction method thereof
CN104653188A (en) Method for arranging large-diameter shield receiving and originating well in underground-excavated air duct
CN104863183B (en) Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction
CN216342131U (en) Shield tunnel invades limit stake and handles reinforced structure
CN104863613B (en) Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method
CN113738399A (en) Underground excavation tunnel large pipe shed guide wall structure and construction method thereof
CN214741338U (en) Slope tunneling tunnel construction structure
CN217518646U (en) Barrier removing tunnel structure for passing through existing station
CN116398165A (en) New tunnel penetrating through existing station at zero distance and construction method thereof
CN214062960U (en) Construction system for shield to pass through irregular barrier below operation station
CN1419020A (en) Method and structure for preventing and protecting near structure settlement by tunnel and isolation piling wall method
CN212296407U (en) Reinforced structure of shield underpass building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211116

CF01 Termination of patent right due to non-payment of annual fee