CN214615578U - High-rise building external support building protection assembly - Google Patents
High-rise building external support building protection assembly Download PDFInfo
- Publication number
- CN214615578U CN214615578U CN202120708664.9U CN202120708664U CN214615578U CN 214615578 U CN214615578 U CN 214615578U CN 202120708664 U CN202120708664 U CN 202120708664U CN 214615578 U CN214615578 U CN 214615578U
- Authority
- CN
- China
- Prior art keywords
- fixed
- fixed pipe
- pipe
- fall way
- protection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Movable Scaffolding (AREA)
Abstract
The application relates to the technical field of building construction, and discloses a high-rise building external support builds protection component, the on-line screen storage device comprises a base, the top of base is through the fixed pipe of bolt fixedly connected with, the side of fixed pipe is provided with the protection rail that is located the base top. This scheme sets up block mechanism through the inside at the fall-pipe, set up the card hole in the side of fixed pipe, cooperation through block mechanism and card hole, make the fall-pipe can reciprocate fast, conveniently adjust the height that shelters from the subassembly, and then conveniently build the support, also be applicable to the support of co-altitude not, the suitability has been improved, and the subassembly that shelters from that sets up can prevent that the object from falling from injuring the staff by a crashing object, improve the security of staff's work, the protection rail that sets up can inject staff's moving range, increase the security of staff's work, and insert with the fixed block through the right angle inserted bar and be connected, and then conveniently protect rail installation and dismantlement.
Description
Technical Field
The application relates to the technical field of building construction, in particular to a high-rise building external support building protection assembly.
Background
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, and requires an external building support to assist construction in the construction process of high-rise buildings;
most of existing building supports are constructed manually, and when the supports are constructed, protection assemblies are needed to protect workers, but the existing protection assemblies are fixed in height and cannot be adjusted, so that the supports are inconvenient to construct.
SUMMERY OF THE UTILITY MODEL
In order to solve the above-mentioned problem of proposing, the application provides a high-rise building external support builds protection component.
The application provides a high-rise building external support builds protection subassembly adopts following technical scheme:
the utility model provides a high-rise building external support builds protection component, includes the base, the fixed pipe of bolt fixedly connected with is passed through at the top of base, the side of fixed pipe is provided with the protection rail that is located the base top, the card hole of arranging along fixed pipe length direction array is seted up to the side of fixed pipe, the inner wall intercommunication of card hole and fixed pipe, just the inside swing joint of fixed pipe has the fall way, the inside of fall way is provided with block mechanism, the fall way passes through block mechanism and card hole and fixed pipe joint, the top of fall way is provided with shelters from the subassembly.
Through adopting above-mentioned technical scheme, set up block mechanism in the inside of fall way, set up the card hole in the side of fixed pipe, through the cooperation in block mechanism and card hole, make the fall way reciprocate fast, conveniently adjust the height that shelters from the subassembly, and then conveniently set up the support, also be applicable to the not support of co-altitude simultaneously, improved the suitability.
Preferably, the number of the fixed pipes is four, the four fixed pipes are uniformly arranged at the top of the base, and the fixed pipes are made of iron-steel alloy.
Through adopting above-mentioned technical scheme, use the fixed pipe that four symmetries set up, when can ensure stably, reduce and dismantle the degree of difficulty, easy to assemble dismantlement.
Preferably, block mechanism includes fixed cover, spring, gleitbretter and kelly, fixed cover is through linking up the inside wall fixed connection of piece and fall way, just the spring with link up the side fixed connection of piece, the other end and the gleitbretter fixed connection of spring, and one side and the kelly fixed connection that the spring was kept away from to the gleitbretter, the other end of kelly runs through the lateral wall of fall way and extends to in the card hole.
Through adopting above-mentioned technical scheme, through the cooperation in block mechanism and card hole, and then the height that can quick adjustment fall way, it is convenient quick to adjust.
Preferably, it includes joint pole and "people" style of calligraphy roof to shelter from the subassembly, the top fixed connection of joint pole and fall way, the inboard and "people" style of calligraphy roof fixed connection of joint pole, just the light is installed at the bottom center of "people" style of calligraphy roof.
Through adopting above-mentioned technical scheme, can prevent that the falling object from pounding the staff by a crashing object through sheltering from the subassembly, improve the security that the staff worked.
Preferably, the side fixedly connected with right angle inserted bar of protection rail, the side fixedly connected with fixed block of fixed pipe, the through-hole has been seted up at the top of fixed block, just through-hole and right angle inserted bar looks adaptation.
Through adopting above-mentioned technical scheme, protection rail can inject staff's home range, increases the security of staff's work to insert through right angle inserted bar and fixed block and be connected, and then conveniently protect rail installation and dismantlement.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the clamping mechanism is arranged in the lifting pipe, the clamping hole is formed in the side face of the fixed pipe, and the lifting pipe can move up and down quickly through the matching of the clamping mechanism and the clamping hole, so that the height of the shielding assembly can be adjusted conveniently, the support can be built conveniently, the lifting pipe is also suitable for supports with different heights, and the applicability is improved;
2. the subassembly that shelters from that sets up can prevent that the object that falls from the high altitude from smashing and hindering the staff, improves the security that the staff worked, and the protection rail that sets up can inject staff's removal scope, increases the security that the staff worked to insert through right angle inserted bar and fixed block and be connected, and then conveniently protect rail installation and dismantlement.
Drawings
Fig. 1 is a schematic structural diagram of the whole of the application example.
Fig. 2 is a schematic structural view of a fixed pipe according to an embodiment of the present invention.
FIG. 3 is a top view of an embodiment of the application.
Fig. 4 is a side view of an embodiment of the application.
Fig. 5 is an enlarged view of the structure at a in fig. 2.
Fig. 6 is an enlarged view of the structure at B in fig. 4.
Description of reference numerals: 1. a base; 2. a fixed tube; 3. a clamping hole; 4. a lifting pipe; 5. a shielding component; 6. a fixed cover; 7. a spring; 8. sliding blades; 9. a clamping rod; 10. a connecting rod; 11. a herringbone top plate; 12. an illuminating lamp; 13. a protective fence; 14. a right-angle inserted link; 15. and (5) fixing blocks.
Detailed Description
The present application is described in further detail below with reference to figures 1-6.
The embodiment of the application discloses high-rise building external support builds protection component. Referring to fig. 1, a high-rise building external support builds protection component, including base 1, the fixed pipe 2 of bolt fixedly connected with is passed through at base 1's top, and fixed pipe 2 has four, and these four fixed pipe 2 symmetries set up, and fixed pipe 2 is made by the iron and steel alloy. The four symmetrically arranged fixed tubes 2 are used, so that the disassembly difficulty is reduced while stability can be ensured, and the disassembly and the assembly are convenient.
Referring to fig. 1 and 4, the side of fixed pipe 2 is provided with the protection rail 13 that is located base 1 top, and the side fixedly connected with right angle inserted bar 14 of protection rail 13, the side fixedly connected with fixed block 15 of fixed pipe 2, and the through-hole has been seted up at the top of fixed block 15, and through-hole and right angle inserted bar 14 looks adaptation. Protection rail 13 can inject staff's displacement range, increases the security that the staff worked to insert through right angle inserted bar 14 and fixed block 15 and be connected, and then conveniently protect the installation of rail 13 and dismantle.
Referring to fig. 1-5, the side of fixed pipe 2 is provided with card hole 3 along 2 length direction array arrangements of fixed pipe, and card hole 3 communicates with the inner wall of fixed pipe 2, and the inside swing joint of fixed pipe 2 has fall way 4, and the inside of fall way 4 is provided with block mechanism, and fall way 4 passes through block mechanism and card hole 3 and fixed pipe 2 joint.
Referring to fig. 5, the clamping mechanism includes a fixed cover 6, a spring 7, a sliding piece 8 and a clamping rod 9, the fixed cover 6 is fixedly connected with the inner side wall of the elevator tube 4 through a connecting block, the spring 7 is fixedly connected with the side edge of the connecting block, the other end of the spring 7 is fixedly connected with the sliding piece 8, one side of the sliding piece 8 far away from the spring 7 is fixedly connected with the clamping rod 9, and the other end of the clamping rod 9 penetrates through the side wall of the elevator tube 4 and extends into the clamping hole 3. Through the cooperation of block mechanism and card hole 3, and then can the height of quick adjustment fall way 4, adjust convenient quick.
Referring to fig. 1, 3 and 4, a shielding assembly 5 is disposed at the top of the elevator pipe 4, the shielding assembly 5 includes a connecting rod 10 and a top plate 11 shaped like a Chinese character 'ren', the connecting rod 10 is fixedly connected to the top of the elevator pipe 4, the inner side of the connecting rod 10 is fixedly connected to the top plate 11 shaped like a Chinese character 'ren', and an illuminating lamp 12 is installed at the center of the bottom of the top plate 11 shaped like a Chinese character 'ren'. Can prevent that the object that falls from high altitude from smashing the staff through sheltering from subassembly 5, improve the security that the staff worked.
The implementation principle of the high-rise building external support building protection assembly is as follows: building a building support on a base 1, adjusting the length of an elevator pipe 4 according to the height of the top of the built support, namely pressing a clamping rod 9 protruding out of a clamping hole 3 inwards to enable the clamping rod 9 to exit from the clamping hole 3, releasing the fixation of the elevator pipe 4 and a fixed pipe 2, then adjusting the elevator pipe 4 up and down, rotating the elevator pipe 4 left and right after adjusting to a proper position to enable the clamping rod 9 in the elevator pipe 4 to be aligned with the clamping hole 3, enabling the clamping rod 9 to be ejected outwards under the action of the elastic force of a spring 7, and further enabling the clamping rod 9 to be inserted into the clamping hole 3 to complete adjustment;
further, the subassembly 5 that shelters from that sets up can prevent that the object that falls from the high altitude from smashing the staff, improves the security that the staff worked, and the moving range of staff can be injectd to the protection rail 13 that sets up, increases the security that the staff worked to through right angle inserted bar 14 and fixed block 15 plug-in connection, and then conveniently protect the installation of rail 13 and dismantle.
It should be noted that, in this document, terms such as "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (5)
1. The utility model provides a high-rise building external support builds protection subassembly, includes base (1), its characterized in that: the utility model discloses a safety protection fence, including base (1), bolt fixedly connected with fixed pipe (2) are passed through at the top of base (1), the side of fixed pipe (2) is provided with protection rail (13) that are located base (1) top, card hole (3) of arranging along fixed pipe (2) length direction array are seted up to the side of fixed pipe (2), card hole (3) and the inner wall intercommunication of fixed pipe (2), just the inside swing joint of fixed pipe (2) has fall way (4), the inside of fall way (4) is provided with block mechanism, fall way (4) are through block mechanism and card hole (3) and fixed pipe (2) joint, the top of fall way (4) is provided with shelters from subassembly (5).
2. A high-rise building external scaffolding protection kit as claimed in claim 1, in which: the number of the fixing pipes (2) is four, the four fixing pipes (2) are symmetrically arranged, and the fixing pipes (2) are made of iron-steel alloy.
3. A high-rise building external scaffolding protection kit as claimed in claim 1, in which: block mechanism is including fixed cover (6), spring (7), gleitbretter (8) and kelly (9), fixed cover (6) is through linking up the inside wall fixed connection of piece and fall way (4), just spring (7) and the side fixed connection who links up the piece, the other end and gleitbretter (8) fixed connection of spring (7), just one side and kelly (9) fixed connection that spring (7) were kept away from in gleitbretter (8), the other end of kelly (9) runs through the lateral wall of fall way (4) and extends to in calorie hole (3).
4. A high-rise building external scaffolding protection kit as claimed in claim 1, in which: shelter from subassembly (5) including linking pole (10) and "people" style of calligraphy roof (11), the top fixed connection of linking pole (10) and fall way (4), the inboard and "people" style of calligraphy roof (11) fixed connection of linking pole (10), just light (12) are installed at the bottom center of "people" style of calligraphy roof (11).
5. A high-rise building external scaffolding protection kit as claimed in claim 1, in which: the side fixedly connected with right angle inserted bar (14) of protection rail (13), the side fixedly connected with fixed block (15) of fixed pipe (2), the through-hole has been seted up at the top of fixed block (15), just through-hole and right angle inserted bar (14) looks adaptation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120708664.9U CN214615578U (en) | 2021-04-08 | 2021-04-08 | High-rise building external support building protection assembly |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120708664.9U CN214615578U (en) | 2021-04-08 | 2021-04-08 | High-rise building external support building protection assembly |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214615578U true CN214615578U (en) | 2021-11-05 |
Family
ID=78400432
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120708664.9U Expired - Fee Related CN214615578U (en) | 2021-04-08 | 2021-04-08 | High-rise building external support building protection assembly |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214615578U (en) |
-
2021
- 2021-04-08 CN CN202120708664.9U patent/CN214615578U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212656515U (en) | Adjustable movable scaffold | |
CN214615578U (en) | High-rise building external support building protection assembly | |
CN211949719U (en) | Building safety protection net | |
CN216866080U (en) | Elevator shaft protection device and system | |
CN215671265U (en) | Make things convenient for edge protection railing of dismouting | |
CN215407835U (en) | Building construction rail structure | |
CN213038913U (en) | Window faces limit entrance to a cave safety protective guard and sets up device | |
CN112211384B (en) | Scaffold for building site | |
CN211171678U (en) | Reinforced slope protection device | |
CN210369986U (en) | Building safety protection equipment | |
CN210396108U (en) | Supporting mechanism for quickly mounting and dismounting concrete formwork | |
CN212743462U (en) | non-French window opening temporary enclosure structure fixing device assembly | |
CN221194376U (en) | Combined type adjustable balcony safety protection plate | |
CN113931354B (en) | Cantilever scaffold and curtain wall integrated structure and construction method | |
CN211007735U (en) | Safety protection net for construction | |
CN219794744U (en) | Shaping edge opening protecting device | |
CN218438093U (en) | Safe civil engineering scaffold convenient to remove | |
CN104975707A (en) | Shed frame and triangular support frame body of shed frame | |
CN218149107U (en) | Curtain board is with general fixed knot structure | |
CN214942646U (en) | Movable balcony faces limit protection instrument | |
CN221194227U (en) | Sustainable use combination dismouting formula L type guardrail | |
CN220100747U (en) | Telescopic floor edge guard rail | |
CN210713761U (en) | Connecting support for building scaffold | |
CN220768786U (en) | Movable scaffold with liftable guard rail | |
CN220377903U (en) | Temporary protection device for roof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20211105 |