CN214575532U - Lifting type steel platform arranged at corridor lighting well position - Google Patents

Lifting type steel platform arranged at corridor lighting well position Download PDF

Info

Publication number
CN214575532U
CN214575532U CN202023123572.9U CN202023123572U CN214575532U CN 214575532 U CN214575532 U CN 214575532U CN 202023123572 U CN202023123572 U CN 202023123572U CN 214575532 U CN214575532 U CN 214575532U
Authority
CN
China
Prior art keywords
lifting
steel
subassembly
welded
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202023123572.9U
Other languages
Chinese (zh)
Inventor
米宏跃
郝晨
张学良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohhot Haiwei Real Estate Co ltd
Zhongtian Construction Group Co Ltd
Original Assignee
Hohhot Haiwei Real Estate Co ltd
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohhot Haiwei Real Estate Co ltd, Zhongtian Construction Group Co Ltd filed Critical Hohhot Haiwei Real Estate Co ltd
Priority to CN202023123572.9U priority Critical patent/CN214575532U/en
Application granted granted Critical
Publication of CN214575532U publication Critical patent/CN214575532U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a set up the lifting type steel platform in vestibule lighting well position, including the slipmat, the top movable mounting of slipmat has the protection component, the fixed recess that is provided with in bottom of protection component, welded mounting has the subassembly that lifts by crane between the recess, the bottom welded mounting who lifts by crane the subassembly has the installation component. The utility model discloses an there is the installation component in the bottom welded mounting of lifting by crane the subassembly, earlier support the triangular supports frame that the second channel-section steel becomes in concrete window lower wall department, the triangular supports frame welded fastening that welds first thick steel sheet supporting platform board and second channel-section steel becomes on the support frame again, the operation platform support body that welds into of first channel-section steel is the operation platform board welding with the second thick steel sheet, will lift by crane the subassembly welding at last and be used for whole hoist and mount on the operation platform board, it not only wastes time and energy to have solved traditional scaffold frame and set up construction technology, and have certain potential safety hazard, cause the problem that the dangerous occurence of failure easily.

Description

Lifting type steel platform arranged at corridor lighting well position
Technical Field
The utility model relates to a building appliances technical field specifically is a set up the liftable formula steel platform in vestibule lighting well position.
Background
"construction platform" that the job site of building daylighting top used, the form of full hall frame erection is adopted in early stage, the construction platform of daylighting top that this kind of method set up needs a large amount of steel pipe support bodies or adjustable shelf, and is with high costs, low efficiency, and the inside region construction and the current of influence daylighting top, in the prior art, according to the position of on-the-spot daylighting vestibule, height and construction load, confirm the full hall support body parameter (pole setting interval, stride and anti-overturning measure) that need set up through the calculation, adopt flitch and full deck template as construction platform on support body upper portion after reaching the height, thereby satisfy the demand of site operation, the work platform of vestibule daylighting well position department sets up and always is a difficult point in the work progress, and in the process of setting up, current vestibule daylighting well position steel platform has many problems or defect:
traditional vestibule lighting well position steel platform is in the in-service use, and current scaffold frame set up construction technology not only wastes time and energy, and has certain potential safety hazard, causes the emergence of dangerous accident easily, does not have the safeguard simultaneously on the operation platform board, the operating personnel of work on operation platform, personal safety can not obtain due guarantee.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a set up the liftable formula steel platform in vestibule lighting well position to solve the problem that provides among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a set up at promotion formula steel platform of vestibule lighting well position, includes the slipmat, the top movable mounting of slipmat has the protection component, the bottom fixed of protection component is provided with the recess, welded mounting has the subassembly of lifting by crane between the recess, the bottom welded mounting who lifts by crane the subassembly has the installation component, the bottom fixed mounting of installation component has spacing subassembly, the fixed surface of installation component is provided with the protective layer.
Preferably, the mounting assembly comprises a second thick steel plate, a first channel steel is welded and mounted at the bottom of the second thick steel plate, a first thick steel plate is welded and mounted at the bottom of the first channel steel, and a second channel steel is welded and mounted at the bottom of the first thick steel plate.
Preferably, the protection component comprises stand columns, a clamping groove is fixedly formed in the tops of the stand columns, a protection frame is fixedly mounted between the stand columns, and a protection net is fixedly arranged inside the protection frame.
Preferably, the lifting assembly comprises a lifting seat, a steel bar hanging ring is welded to the top of the lifting seat, and a lifting groove is fixedly formed in the steel bar hanging ring.
Preferably, the limiting assembly comprises a limiting groove, wherein bulges are arranged in the limiting groove at equal intervals and are made of rubber.
Preferably, the surface of the protective layer is provided with a coating layer, and one side of the coating layer is fixedly provided with a wear-resistant layer.
Compared with the prior art, the beneficial effects of the utility model are that: this set up can promote formula steel platform in vestibule lighting well position has following advantage:
(1) the installation assembly is welded and installed at the bottom of the lifting assembly, a triangular support frame formed by welding second channel steel is supported at the position of a lower wall of a concrete window, then a first thick steel plate supporting platform plate and the triangular support frame formed by welding the second channel steel are welded and fixed on the support frame, the first channel steel is welded into an operation platform frame body and the second thick steel plate is welded into an operation platform plate, and finally the lifting assembly is welded on the operation platform plate for integral hoisting, so that the problems that the traditional scaffold erecting construction technology is time-consuming and labor-consuming, has certain potential safety hazards and easily causes dangerous accidents are solved;
(2) the top of the non-slip mat is movably provided with the protection assembly, so that the protection frame and the protective net can be matched to protect the personal safety of operators, the operators are prevented from falling from the operation platform carelessly in the operation process, meanwhile, the top of the upright post is provided with the clamping groove, and the protection frame and the protective net can be clamped on one layer, so that the protection effect is improved, and the problems that the safety measures are not available on the operation platform plate and the personal safety of the operators working on the operation platform cannot be guaranteed in the prior art are solved;
(3) install through welding between the recess and lift by crane the subassembly, can utilize welding reinforcing bar rings with whole hoist and mount, be provided with in the inside of reinforcing bar rings and lift by crane the groove, make things convenient for external rope fixed, reduce rocking at the in-process of lifting by crane, will lift by crane the seat welding through the welding mode and to operation platform on, guarantee its fastness.
Drawings
Fig. 1 is a front view of the present invention;
fig. 2 is a side view of the present invention;
FIG. 3 is a schematic view of a partial structure of the protection assembly of the present invention;
fig. 4 is a partial structural schematic view of the hoisting assembly of the present invention;
fig. 5 is a schematic view of a partial structure of the limiting component of the present invention;
fig. 6 is a schematic view of a partial structure of the protective layer of the present invention.
In the figure: 1. a guard assembly; 101. a protective net; 102. a card slot; 103. a protective frame; 104. a column; 2. a groove; 3. mounting the component; 301. a first channel steel; 302. a first thick steel plate; 303. a second channel steel; 304. a second thick steel plate; 4. a hoisting assembly; 401. lifting the lifting seat; 402. hoisting a groove; 403. a steel bar hanging ring; 5. a protective layer; 501. a wear layer; 502. a coating layer; 6. a limiting component; 601. a limiting groove; 602. a protrusion; 7. a non-slip mat.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-6, the present invention provides an embodiment: a liftable steel platform arranged at a corridor lighting well position comprises an anti-skid pad 7, wherein a protection assembly 1 is movably arranged at the top of the anti-skid pad 7, the protection assembly 1 comprises stand columns 104, clamping grooves 102 are fixedly arranged at the tops of the stand columns 104, a protection frame 103 is fixedly arranged between the stand columns 104, a protection net 101 is fixedly arranged inside the protection frame 103, and a groove 2 is fixedly arranged at the bottom of the protection assembly 1;
specifically, as shown in fig. 1, fig. 2 and fig. 3, when in use, the protection assembly 1 is movably mounted at the top of the anti-slip mat 7, and can be matched with the protection net 101 by using the protection frame 103 to protect the personal safety of an operator, so as to prevent the operator from falling from the operation platform carelessly during the operation process, meanwhile, the top of the upright post 104 is provided with the clamping groove 102, which can be clamped with the protection frame 103 and the protection net 101 on one layer, so that the protection effect is improved, the problem that the operator working on the operation platform cannot be guaranteed due to the lack of safety measures on the operation platform plate in the prior art is solved, the anti-slip mat 7 is arranged to increase the friction force between the sole of the operator and the operation platform, so as to further improve the protection effect of the operator, the groove 2 is provided, the upright post 104 is inserted into the groove 2 for fixing, and the protection assembly 1 is convenient to detach and assemble, the utilization rate of resources is improved;
a hoisting assembly 4 is welded and installed between the grooves 2, the hoisting assembly 4 comprises a hoisting seat 401, a steel bar hoisting ring 403 is welded and installed at the top of the hoisting seat 401, and a hoisting groove 402 is fixedly arranged inside the steel bar hoisting ring 403;
specifically, as shown in fig. 1 and 4, when the lifting assembly 4 is welded and installed between the grooves 2, the welded steel bar hanging ring 403 can be used for integrally lifting the lifting assembly, a lifting groove 402 is formed in the steel bar hanging ring 403, so that an external rope can be conveniently fixed, the shake in the lifting process is reduced, and the lifting seat 401 is welded on an operation platform in a welding manner, so that the firmness of the lifting assembly is ensured;
the bottom of the hoisting component 4 is welded with the mounting component 3, the mounting component 3 comprises a second thick steel plate 304, the bottom of the second thick steel plate 304 is welded with a first channel steel 301, the bottom of the first channel steel 301 is welded with a first thick steel plate 302, the bottom of the first thick steel plate 302 is welded with a second channel steel 303, the bottom of the mounting component 3 is fixedly provided with a limiting component 6, the limiting component 6 comprises a limiting groove 601, bulges 602 are equidistantly arranged in the limiting groove 601 and are made of rubber, the surface of the mounting component 3 is fixedly provided with a protective layer 5, the surface of the protective layer 5 is provided with a coating layer 502, and one side of the coating layer 502 is fixedly provided with a wear-resistant layer 501;
specifically, as shown in fig. 1, 5 and 6, when in use, the mounting assembly 3 is welded and mounted at the bottom of the hoisting assembly 4, the triangular support frame welded by the second channel steel 303 is supported at the lower wall of the concrete window, then the triangular support frame welded by the first thick steel plate 302 and the second channel steel 303 is welded and fixed on the support frame, the first channel steel 301 is welded into the operation platform frame body and the second thick steel plate 304 are welded as the operation platform plate, and finally the hoisting assembly 4 is welded on the operation platform plate for integral hoisting, so that the problems that the traditional scaffold erecting construction technology is time-consuming and labor-consuming, has certain potential safety hazard and is easy to cause dangerous accidents are solved, the limiting assembly 6 is mounted, the stability of the mounting assembly 3 on the concrete beam at the opening of the window is improved, and the friction force between the limiting groove 601 and the concrete beam at the opening of the window is increased by the arrangement of the bulge 602, and protruding 602 is rubber materials, can protect second channel-section steel 303, prolongs the life of second channel-section steel 303, and through being provided with protective layer 5, the surface of protective layer 5 is provided with dope layer 502, prevents installation component 3 surface oxidation, prolongs the live time of installation component 3, is provided with wearing layer 501, increases the wearability of installation component 3, further prolongs the live time of installation component 3.
The working principle is as follows: when the lifting assembly is used, firstly, the mounting assembly 3 is welded and mounted at the bottom of the lifting assembly 4, a triangular support frame formed by welding second channel steel 303 is supported at the lower wall of a concrete window, then a first thick steel plate 302 supporting platform plate and the triangular support frame formed by welding the second channel steel 303 are welded and fixed on the support frame, a first channel steel 301 is welded into an operation platform frame body and welded with a second thick steel plate 304 as an operation platform plate, and finally the lifting assembly 4 is welded on the operation platform plate for integral hoisting;
secondly, the protection assembly 1 is movably mounted at the top of the non-slip mat 7, the protection frame 103 can be matched with the protection net 101, personal safety of operators can be protected, the operators can be prevented from falling from an operation platform carelessly in the operation process, meanwhile, the top of the upright post 104 is provided with the clamping groove 102, and the protection frame 103 and the protection net 101 can be clamped on one layer, so that the protection effect is improved;
finally, a hoisting assembly 4 is welded and installed between the grooves 2, the whole hoisting can be achieved by welding the steel bar hoisting rings 403, the hoisting grooves 402 are formed in the steel bar hoisting rings 403, external ropes can be conveniently fixed, shaking in the hoisting process is reduced, and the hoisting seat 401 is welded on the operating platform in a welding mode, so that firmness of the operating platform is guaranteed.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein, and any reference signs in the claims are not intended to be construed as limiting the claim concerned.

Claims (6)

1. The utility model provides a set up the liftable formula steel platform in vestibule lighting well position, includes slipmat (7), its characterized in that: the top movable mounting of slipmat (7) has protection component (1), the bottom of protection component (1) is fixed and is provided with recess (2), welded mounting has between recess (2) and lifts by crane subassembly (4), the bottom welded mounting of the subassembly of lifting by crane (4) has installation component (3), the bottom fixed mounting of installation component (3) has spacing subassembly (6), the fixed surface of installation component (3) is provided with protective layer (5).
2. A liftable steel platform to be placed at the location of a corridor lighting well according to claim 1, wherein: the mounting assembly (3) comprises a second thick steel plate (304), a first channel steel (301) is installed at the bottom of the second thick steel plate (304) in a welding mode, a first thick steel plate (302) is installed at the bottom of the first channel steel (301) in a welding mode, and a second channel steel (303) is installed at the bottom of the first thick steel plate (302) in a welding mode.
3. A liftable steel platform to be placed at the location of a corridor lighting well according to claim 1, wherein: the protective assembly (1) comprises stand columns (104), clamping grooves (102) are fixedly arranged at the tops of the stand columns (104), protective frames (103) are fixedly arranged between the stand columns (104), and protective nets (101) are fixedly arranged inside the protective frames (103).
4. A liftable steel platform to be placed at the location of a corridor lighting well according to claim 1, wherein: the lifting assembly (4) comprises a lifting seat (401), a steel bar lifting ring (403) is welded to the top of the lifting seat (401), and a lifting groove (402) is fixedly arranged inside the steel bar lifting ring (403).
5. A liftable steel platform to be placed at the location of a corridor lighting well according to claim 1, wherein: spacing subassembly (6) are provided with arch (602) including spacing groove (601), the inside equidistance of spacing groove (601), and arch (602) are the rubber material.
6. A liftable steel platform to be placed at the location of a corridor lighting well according to claim 1, wherein: the surface of the protective layer (5) is provided with a coating layer (502), and one side of the coating layer (502) is fixedly provided with a wear-resistant layer (501).
CN202023123572.9U 2020-12-23 2020-12-23 Lifting type steel platform arranged at corridor lighting well position Expired - Fee Related CN214575532U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023123572.9U CN214575532U (en) 2020-12-23 2020-12-23 Lifting type steel platform arranged at corridor lighting well position

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023123572.9U CN214575532U (en) 2020-12-23 2020-12-23 Lifting type steel platform arranged at corridor lighting well position

Publications (1)

Publication Number Publication Date
CN214575532U true CN214575532U (en) 2021-11-02

Family

ID=78365781

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023123572.9U Expired - Fee Related CN214575532U (en) 2020-12-23 2020-12-23 Lifting type steel platform arranged at corridor lighting well position

Country Status (1)

Country Link
CN (1) CN214575532U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114809579A (en) * 2022-05-08 2022-07-29 山西三建集团有限公司 Method for erecting lifting construction platform for building formwork system around light well

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114809579A (en) * 2022-05-08 2022-07-29 山西三建集团有限公司 Method for erecting lifting construction platform for building formwork system around light well

Similar Documents

Publication Publication Date Title
CN205772984U (en) A kind of hanging apparatus of monolithic steel truss
CN204626921U (en) A kind of fixed working platform without scaffold construction elevator
CN214575532U (en) Lifting type steel platform arranged at corridor lighting well position
CN217028004U (en) Annular hanging basket suspension device for curtain wall construction of super high-rise building
CN103967263A (en) Novel hydraulic automatic climbing discharging platform
CN219280494U (en) Tower beam temporary consolidation supporting structure for bridge tower stability control
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space
CN208732495U (en) A kind of small gun carriage
CN215443025U (en) Safety construction platform for machine-room-less elevator shaft
CN211499699U (en) Ladder-climbing type operation rack for hanging cage
CN113137047A (en) Safety construction platform for machine-room-less elevator shaft
CN209970667U (en) Roller type photovoltaic glass assembly platform
CN208981152U (en) A kind of fast-type high-speed rail Bridge Pier Construction hanging basket mounting platform
CN210029781U (en) Anti-shaking device for hoisting
CN209957241U (en) Steel hanger
CN103206077B (en) Structure for steel structure roof inner slab installation foot hand cradle
CN212897496U (en) Elevator shaft operating frame device
CN216190195U (en) Rope end combination fixing device
CN218438162U (en) Hanging flower basket strutting arrangement and hanging flower basket support operating system
CN218467055U (en) High-altitude suspension construction platform
CN218810043U (en) Light partition plate assists installation device
CN218539120U (en) High altitude curtain wall glass hoist device
CN211169608U (en) Hanging basket prismatic sheet hoisting device
CN217106217U (en) Climb a support type and change material platform
CN109881880A (en) Double rod type platform becomes Auxiliary equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211102

CF01 Termination of patent right due to non-payment of annual fee