CN214575462U - Device for drawknot of double-row protection frame outside underground chamber of constructional engineering - Google Patents

Device for drawknot of double-row protection frame outside underground chamber of constructional engineering Download PDF

Info

Publication number
CN214575462U
CN214575462U CN202120326083.9U CN202120326083U CN214575462U CN 214575462 U CN214575462 U CN 214575462U CN 202120326083 U CN202120326083 U CN 202120326083U CN 214575462 U CN214575462 U CN 214575462U
Authority
CN
China
Prior art keywords
sleeve
rod
drawknot
steel pipe
wall body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120326083.9U
Other languages
Chinese (zh)
Inventor
李东
李红伟
唐辉
左小海
李军花
胡海宝
刘牧林
章志明
杨飞
余沛君
陈熹杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Aerospace Construction Engineering Co ltd
Original Assignee
Henan Aerospace Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Aerospace Construction Engineering Co ltd filed Critical Henan Aerospace Construction Engineering Co ltd
Priority to CN202120326083.9U priority Critical patent/CN214575462U/en
Application granted granted Critical
Publication of CN214575462U publication Critical patent/CN214575462U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model discloses a device for drawknot of double rows of protective frames outside an underground chamber of constructional engineering, which is mainly characterized in that a first sleeve is pre-buried in a wall body; one end of the bolt rod is in threaded connection with the first sleeve, and the other end of the bolt rod extends out of the wall body and is connected with the outer frame assembly; the outer frame assembly comprises a second sleeve in threaded connection with the bolt rod, a drawknot steel pipe, a vertical rod, a longitudinal horizontal rod and a transverse horizontal rod; the second sleeve is fixed on the drawknot steel pipe, the vertical rod is connected with the drawknot steel pipe through a buckle, the transverse horizontal rod is connected with the vertical rod through a buckle, and the longitudinal horizontal rod is connected with the transverse horizontal rod through a buckle. The utility model discloses be fixed in the wall body with the drawknot device, make whole braced system more stable, because of not perforating on the wall body, can prevent effectively that the outer wall from seeping water, and the effective reutilization of most subassembly reduces construction cost.

Description

Device for drawknot of double-row protection frame outside underground chamber of constructional engineering
Technical Field
The utility model relates to a drawknot device, concretely relates to device is used to outer double protection frame drawknot of building engineering basement belongs to building engineering safety technical field.
Background
With the increasing number of the basement layers, the three, four or even more layers of the basement become longer and longer, and the outer frame safety protection becomes more important when the basement is constructed. The traditional basement outer frame protective support is mostly provided with throwing supports, namely, the upper end of the traditional basement outer frame protective support is fixed on a steel pipe frame by a fastener, and the lower end of the traditional basement outer frame protective support is randomly supported on a side slope support, so that an effective support system cannot be formed; moreover, because the slope protection concrete has low strength, even the slope surface is not supported, and the angle of the inclined strut is actually too large, the concrete cannot play a role in supporting the slope, and the safety is poor; moreover, as the outer frame is higher and higher; the length of the steel pipe for supporting can not be met, and even if the length meets the requirement, the stability of the steel pipe compression rod piece can not meet the safety requirement. In addition to the above problems, the basement needs to meet the waterproof requirement, the concrete wall should be constructed as an integral whole as much as possible, and the outer wall of the civil air defense basement does not allow holes to be reserved, so that the mode of construction on the ground is difficult to adopt, and the protective frame is fixed and installed by reserving the holes on the wall.
Disclosure of Invention
The utility model aims at providing an outer double protection frame device for drawknot of building engineering underground chamber, when being directed against underground works, simple to operate, the drawknot height, the part can be used many times, can reach the requirement that the people's air defense basement outer wall does not allow the shrinkage pool and prevent the seepage simultaneously.
In order to achieve the purpose, the utility model discloses a device for drawknot of a double-row protective frame outside an underground chamber of building engineering, which comprises a first sleeve, a bolt rod and an outer frame component for supporting an outdoor protective support;
the first sleeve is pre-buried in the wall body;
one end of the bolt rod is in threaded connection with the first sleeve, and the other end of the bolt rod extends out of the wall body and is connected with the outer frame assembly;
the outer frame assembly comprises a second sleeve in threaded connection with the bolt rod, a tie steel pipe, a vertical rod, a longitudinal horizontal rod and a transverse horizontal rod; the second sleeve is fixed on the drawknot steel pipe, the vertical rod is connected with the drawknot steel pipe through a buckle, the transverse horizontal rod is connected with the vertical rod through a buckle, and the longitudinal horizontal rod is connected with the transverse horizontal rod through a buckle.
Further, the second sleeve is welded and fixed on the upper part of the inner wall of the drawknot steel pipe.
Preferably, the thickness of a welding seam between the second sleeve and the inner wall of the drawed steel pipe is not less than 5mm, the width of the welding seam is not less than 12mm, and the length of the welding seam is not less than 40 mm.
Preferably, the first sleeve is a truncated cone-shaped sleeve, and a threaded hole matched with the bolt rod is formed in one end face of the truncated cone-shaped sleeve.
Preferably, the length of the bolt rod extending out of the wall body is more than 100 mm.
The utility model discloses a use method of device for drawknot of outdoor double protection frame of building engineering underground, including following step:
s1: the first sleeve and one end of the bolt rod are connected through threads, and when the basement concrete outer wall is poured, the connected first sleeve is placed in the wall, and the other end of the bolt rod extends out of the wall;
s2: when the upper wall body is poured, the template baffle plate provided with the small hole matched with the outer diameter of the bolt rod is sleeved on the bolt rod, and then a bolt is tightened at one end of the bolt rod extending out of the wall body for fixing the template baffle plate, so that the upper wall body is convenient to pour;
s3: after the upper wall body is poured, the bolts and the template baffle are taken down, the tie steel pipes welded with the second sleeves are in threaded fit connection with the bolt rods, and the external frame assembly is assembled;
s4: after the outer frame assembly is used, the outer frame assembly is disassembled, and the bolt rod is screwed out through the threads for secondary utilization;
s5: and plugging the hole left by the wall body.
Further, the second sleeve is welded and fixed on the upper part of the inner wall of the drawknot steel pipe, and is welded according to the following steps:
a. after the drawknot steel pipe and the second sleeve are placed in a trial mode, two positions where the second sleeve is internally tangent to the inner wall of the steel pipe are found out, and identification is made;
b. marking two grooves on the outer surface of the steel pipe according to marks by using a special tool, wherein the width of each groove is 12-14mm, and the length of each groove is 40-50 mm;
c. the welding rod adopts an E5003 type, and the welding parameters are as follows: the thickness of the welding line is not less than 5mm, the width of the welding line is not less than 12mm, and the length of the welding line is not less than 40 mm;
d. when welding, the special sleeve matched with the steel bar cannot be burnt; slag should be removed in time during welding, the surface of a welding seam should be smooth, the rest height of the welding seam should be in smooth transition, and an arc pit should be filled;
e. and (3) inspecting the quality of the welding seam (including the length, thickness and width of the welding seam, the existence of slag inclusion and the like) in time after welding, and painting anti-rust paint in time after confirming that no fault exists.
Furthermore, a section of the bolt rod extending out of the wall body is provided with threads.
Compare with traditional basement outrigger bracing, the utility model discloses be fixed in the wall body with the drawknot device, make whole braced system more stable, simultaneously, because of not perforating on the wall body, the back is demolishd to the outrigger, and the screw rod hole that the basement outer wall was reserved is repaired easily, adopt water leak-proof shutoff can, effectively prevent the outer wall infiltration. Moreover, most of the components can be effectively reused.
Drawings
Fig. 1 is a schematic structural diagram of the present invention;
FIG. 2 is a schematic view of the first bushing and bolt shank connection of FIG. 1;
FIG. 3 is a schematic view of the welding structure of the second sleeve and the steel drawknot pipe in FIG. 1;
figure 4 is the utility model discloses a fixed die plate baffle's when being used for pouring upper portion wall body schematic diagram.
In the figure: 1. the novel steel pipe wall comprises a first sleeve, 11 threaded holes, 2 bolt rods, 3 second sleeves, 4 steel tie pipes, 5 vertical rods, 6 longitudinal horizontal rods, 7 transverse horizontal rods, 8 wall bodies, 91 bamboo plywood, 92 square timber, 93 butterfly clips, 94 steel pipes and 96 nuts.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
As shown in fig. 1, the device for pulling the double rows of outdoor protection frames of the underground of the constructional engineering comprises a first sleeve 1, a bolt rod 2 and an outer frame assembly for supporting outdoor protection supports;
the first sleeve 1 is pre-embedded in the wall body 8;
one end of the bolt rod 2 is in threaded connection with the first sleeve 1, and the other end of the bolt rod extends out of the wall body 8 and is connected with the outer frame assembly; the length of the bolt rod 2 extending out of the wall body 8 is more than 100 mm;
the outer frame assembly comprises a second sleeve 3 in threaded connection with the bolt rod 2, a tie steel pipe 4, a vertical rod 5, a longitudinal horizontal rod 6 and a transverse horizontal rod 7; the second sleeve 3 is fixed on the drawknot steel pipe 4, the upright stanchion 5 is connected with the drawknot steel pipe 4 through a buckle, the horizontal rod 7 is connected with the upright stanchion 5 through a buckle, and the vertical horizontal rod 6 is connected with the horizontal rod 7 through a buckle.
As shown in fig. 3, further, the second sleeve 3 is welded and fixed on the upper portion of the inner wall of the steel drawtube 4. Through the mode, the welding section can bear tension and pressure, the stability checking calculation of the pressed rod piece is met, and the safety technical requirement of the traditional overground scaffold connecting piece is completely met. Meanwhile, preferably, the thickness of a welding seam between the second sleeve 3 and the inner wall of the drawknot steel pipe 4 is not less than 5mm, the width of the welding seam is not less than 12mm, and the length of the welding seam is not less than 40 mm.
As shown in fig. 2, the first sleeve 1 is preferably a circular truncated cone shaped sleeve, and one of the end faces of the circular truncated cone shaped sleeve is provided with a threaded hole 11 for engaging with the bolt shank 2.
The utility model discloses a use method of device for drawknot of outdoor double protection frame of building engineering underground, including following step:
s1: the first sleeve 1 and one end of the bolt rod 2 are connected through threads, when the basement concrete outer wall body 8 is poured, the connected first sleeve 1 is placed in the wall body 8, and the other end of the bolt rod 2 extends out of the wall body 8;
s2: as shown in fig. 4, when the upper wall 8 is poured, the template baffle plate provided with the small hole matched with the outer diameter of the bolt rod 2 is sleeved on the bolt rod 2, and then a bolt is tightened at one end of the bolt rod 2 extending out of the wall 8 for fixing the template baffle plate, so that the upper wall 8 is convenient to pour; specifically, as shown in fig. 4, the bamboo plywood 91 is used as a fixed formwork baffle, the square timber 92 supports the bamboo plywood 91 on one side of the outer wall of the bamboo plywood 91, penetrates through the bolt rod 2 through the butterfly clamp 93, and fixes the steel pipe 94 for supporting the square timber 92 on one side of the outer wall of the square timber 92; then, a nut 96 is tightened on the bolt rod 2, and a butterfly clamp 93 is fixed;
s3: after the upper wall body 8 is poured, the bolts and the template baffle are taken down, as shown in fig. 1, the tie steel pipes 4 welded with the second sleeves 3 are connected with the bolt rods 2 in a threaded fit manner, and the outer frame assembly is assembled;
s4: after the outer frame assembly is used, the outer frame assembly is disassembled, and the bolt rod 2 is screwed out through the threads for secondary utilization;
s5: and plugging the hole left in the wall body 8.
In the method, except the first sleeve 1 adopted by the drawknot, other parts can be repeatedly used, and the economic benefit is improved.
Further, the second sleeve 3 is welded and fixed on the upper part of the inner wall of the drawknot steel pipe 4, and is welded according to the following steps:
a. after the steel tube 4 and the second sleeve 3 are placed in a trial mode, finding out two positions where the second sleeve 3 is internally tangent to the inner wall of the steel tube 94, and making marks;
b. marking two grooves on the outer surface of the steel pipe 94 according to the marks by using a special tool, wherein the width of each groove is 12-14mm, and the length of each groove is 40-50 mm;
c. the welding rod adopts an E5003 type, and the welding parameters are as follows: the thickness of the welding line is not less than 5mm, the width of the welding line is not less than 12mm, and the length of the welding line is not less than 40 mm;
d. when welding, the special sleeve matched with the steel bar cannot be burnt; slag should be removed in time during welding, the surface of a welding seam should be smooth, the rest height of the welding seam should be in smooth transition, and an arc pit should be filled;
e. and (3) inspecting the quality of the welding seam (including the length, thickness and width of the welding seam, the existence of slag inclusion and the like) in time after welding, and painting anti-rust paint in time after confirming that no fault exists.
Furthermore, a section of the bolt rod 2 extending out of the wall body 8 is provided with threads. Thereby can guarantee effectively to fix the template baffle through screwing up the bolt.
Compare with traditional basement outrigger bracing, the utility model discloses be fixed in wall body 8 with the drawknot device, make whole braced system more stable, simultaneously, because of not perforating on wall body 8, the back is demolishd to the outrigger, and the screw rod hole that the basement outer wall was reserved is repaired easily, adopt water leak-tight shutoff can, effectively prevent the outer wall infiltration. Moreover, most of the components can be effectively reused.

Claims (5)

1. The utility model provides an outdoor double protection of building engineering puts up device for drawknot which characterized in that: the outdoor protective support comprises a first sleeve, a bolt rod and an outer frame assembly for supporting the outdoor protective support;
the first sleeve is pre-buried in the wall body;
one end of the bolt rod is in threaded connection with the first sleeve, and the other end of the bolt rod extends out of the wall body and is connected with the outer frame assembly;
the outer frame assembly comprises a second sleeve in threaded connection with the bolt rod, a tie steel pipe, a vertical rod, a longitudinal horizontal rod and a transverse horizontal rod; the second sleeve is fixed on the drawknot steel pipe, the vertical rod is connected with the drawknot steel pipe through a buckle, the transverse horizontal rod is connected with the vertical rod through a buckle, and the longitudinal horizontal rod is connected with the transverse horizontal rod through a buckle.
2. The device for the drawknot of the double-row protection frame outside the underground chamber of the constructional engineering as claimed in claim 1, wherein: and the second sleeve is welded and fixed on the upper part of the inner wall of the drawknot steel pipe.
3. The device for the drawknot of the double rows of the protection frames outside the underground chamber of the constructional engineering as claimed in claim 2, wherein: the thickness of a welding seam between the second sleeve and the inner wall of the drawed steel pipe is not less than 5mm, the width of the welding seam is not less than 12mm, and the length of the welding seam is not less than 40 mm.
4. The device for pulling the double rows of the protection frames outside the underground chamber of the constructional engineering as claimed in any one of claims 1 to 3, wherein: the first sleeve is a circular truncated cone-shaped sleeve, and a threaded hole matched with the bolt rod is formed in one end face of the circular truncated cone-shaped sleeve.
5. The device for pulling the double rows of the protection frames outside the underground chamber of the constructional engineering as claimed in any one of claims 1 to 3, wherein: the length of the bolt rod extending out of the wall body is more than 100 mm.
CN202120326083.9U 2021-02-05 2021-02-05 Device for drawknot of double-row protection frame outside underground chamber of constructional engineering Active CN214575462U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120326083.9U CN214575462U (en) 2021-02-05 2021-02-05 Device for drawknot of double-row protection frame outside underground chamber of constructional engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120326083.9U CN214575462U (en) 2021-02-05 2021-02-05 Device for drawknot of double-row protection frame outside underground chamber of constructional engineering

Publications (1)

Publication Number Publication Date
CN214575462U true CN214575462U (en) 2021-11-02

Family

ID=78350129

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120326083.9U Active CN214575462U (en) 2021-02-05 2021-02-05 Device for drawknot of double-row protection frame outside underground chamber of constructional engineering

Country Status (1)

Country Link
CN (1) CN214575462U (en)

Similar Documents

Publication Publication Date Title
CN205400024U (en) Instrument formula external scaffolding bolt that can dismantle used repeatedly links wall spare
CN210239103U (en) Novel scaffold wall connecting piece structure
CN203531365U (en) Bolt anchor stiffness wall connecting piece
CN214575462U (en) Device for drawknot of double-row protection frame outside underground chamber of constructional engineering
CN212295578U (en) Diagonal cantilever beam supporting system of scaffold
CN206319597U (en) A kind of cantilever steel girder erecting device
CN206722378U (en) A kind of pull-up manomelia is encorbelmented heavy frame
CN210342642U (en) Scaffold wall connecting piece and scaffold
CN107504036B (en) Internal support device for casing and construction method thereof
CN107447975A (en) Exterior wall scaffold tapered cup nut wall-connecting piece
CN112832496A (en) Device for drawknot of double-row protection frames outside underground chamber of constructional engineering and using method
CN104164889A (en) Demountable tower crane foundation
CN206245709U (en) A kind of outrigger wall-connecting piece
CN214461277U (en) Quick plugging mechanism for overhanging I-steel reserved hole
CN204386140U (en) A kind of recoverable suspension scaffold shaped steel anchor device
CN208966008U (en) A kind of reusable exterior wall steel pipe scaffold wall-connecting piece device
CN205990753U (en) Exterior wall scaffold tapered cup nut wall-connecting piece
CN210164054U (en) Quick butt joint and temporary fixing device for upper and lower layers of steel concrete composite pipe
CN217631200U (en) Scaffold frame is wall spare drawknot device even suitable for brick and concrete structure
CN211080218U (en) Soil nail slip casting leak protection thick liquid device
CN206707283U (en) A kind of unidirectional fishbolt fixed form root device of built-in type
CN212772709U (en) Concrete pipe pillow side form reinforcing apparatus
CN107152161A (en) The drawknot construction method of external scaffolding and wall interconnecting piece
CN214658717U (en) Scaffold wall connecting structure
CN211714556U (en) Building scaffold wall connecting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant