CN214531921U - Tool type mould hanging device - Google Patents

Tool type mould hanging device Download PDF

Info

Publication number
CN214531921U
CN214531921U CN202120151180.9U CN202120151180U CN214531921U CN 214531921 U CN214531921 U CN 214531921U CN 202120151180 U CN202120151180 U CN 202120151180U CN 214531921 U CN214531921 U CN 214531921U
Authority
CN
China
Prior art keywords
screw rod
hole
bolt
reserved
penetrating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120151180.9U
Other languages
Chinese (zh)
Inventor
陈德刚
胡亮
张勇
向康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Construction Engineering Co Ltd
Original Assignee
Wuhan Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Construction Engineering Co Ltd filed Critical Wuhan Construction Engineering Co Ltd
Priority to CN202120151180.9U priority Critical patent/CN214531921U/en
Application granted granted Critical
Publication of CN214531921U publication Critical patent/CN214531921U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a tool type mould hanging device, which comprises a crossbeam and a steel mould which are connected into a whole by welding, wherein a screw rod hole is reserved on the crossbeam and the steel mould; screwing a bolt into the bottom of the screw rod, penetrating the bolt into the gasket, and penetrating the screw rod into the screw rod hole reserved in the cross beam and the steel die; the supporting beam is transversely placed on a reserved hole on the structural floor slab, a screw rod penetrating from the lower part of the hole to the upper part of the hole penetrates into the supporting beam, a gasket is penetrated and then a bolt is screwed for fastening, and the adjusting bolt is used for applying prestress to enable the steel mould to be tightly contacted with the structural floor slab so as to prevent slab staggering and slurry leakage. The utility model is simple in operation, the shaping is of high quality, used repeatedly, has practiced thrift engineering cost when having guaranteed the shaping quality greatly.

Description

Tool type mould hanging device
Technical Field
The utility model relates to a concrete structure reserves entrance to a cave construction technical field, concretely relates to mould device is hung to instrument formula.
Background
In the construction process of the building engineering, holes such as a pump pipe hole, a wire releasing hole and the like of the ground can be reserved for meeting construction requirements, and plugging is carried out after the structure construction is finished. According to the traditional method for plugging the hole, a support frame is erected at the bottom of the hole, a template is paved, then concrete is poured, the operation is complex, the forming is easy to stagger, and the turnover utilization rate is low; the tool type die lifting device is invented by research and experiments aiming at the practical problem.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a mould device is hung to instrument formula, easy operation, the shaping is of high quality, and used repeatedly has practiced thrift engineering cost when having guaranteed the shaping quality greatly.
In order to achieve the above purpose, the utility model adopts the following technical scheme: a tool type mould hanging device comprises a cross beam and a steel mould which are connected into a whole through welding, wherein a screw rod hole is reserved on the cross beam and the steel mould; screwing a bolt into the bottom of the screw rod, penetrating the bolt into the gasket, and penetrating the screw rod into the screw rod hole reserved in the cross beam and the steel die; the supporting beam is transversely placed on a reserved hole on the structural floor slab, a screw rod penetrating from the lower part of the hole to the upper part of the hole penetrates into the supporting beam, a gasket is penetrated and then a bolt is screwed for fastening, and the adjusting bolt is used for applying prestress to enable the steel mould to be tightly contacted with the structural floor slab so as to prevent slab staggering and slurry leakage.
Further, a sleeve is sleeved on the section of the screw rod between the steel die and the support beam, and a release agent is coated on the periphery of the sleeve.
By last, the utility model discloses a mould device is hung to instrument formula possesses following beneficial effect at least: the method is simple to operate, good in forming quality and capable of being used repeatedly, and engineering cost is saved while forming quality is greatly guaranteed.
Drawings
The accompanying drawings, which are included to provide a further understanding of the application and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the application and together with the description serve to explain the application and not to limit the application. In the drawings:
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic diagram of the utility model after the installation.
In the figure: 1-structural floor slab; 2-a cross beam; 3-a support beam; 4-a gasket; 5-bolt; 6-a screw rod; 7-a sleeve; 8-steel molding;
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, embodiments of the present invention will be described in further detail with reference to fig. 1-2.
As shown in fig. 1-2, a tool type die hanging device comprises a cross beam 2 and a steel die 8 which are connected into a whole by welding, all loads are borne by an original structure floor 1, and screw rod holes are reserved on the cross beam 2 and the steel die 8; the bottom of the screw rod 6 is screwed in a bolt 5 and then penetrates into the gasket 4, and then the screw rod 6 penetrates into a screw rod hole reserved between the cross beam 2 and the steel die 8; a supporting beam 3 is transversely placed on a reserved hole on the structural floor slab 1, a screw rod 6 penetrating to the upper side of the hole from the lower side of the hole penetrates the supporting beam 3, a gasket 4 is penetrated and then a bolt 5 is screwed for fastening, and the device applies prestress through an adjusting bolt 5 to enable a steel mould 8 to be tightly contacted with the structural floor slab 1, so that slab staggering and slurry leakage are prevented.
The utility model discloses the cover is equipped with sleeve pipe 7 on this section lead screw 6 that is located between steel mould 8 and a supporting beam 3 to brush the release agent in sleeve pipe 7 periphery.
Instrument formula hang mould device, concrete implementation step as follows:
step 1, adhering foam rubber to the periphery of the bottom surface of the hole;
step 2, chiseling and cleaning the laitance on the side surface of the opening, and brushing cement slurry on the side surface of the opening for one layer;
step 3, blanking and processing each component shown in the figure 1;
step 4, welding and connecting the beam 2 and the steel die 8 into a whole;
step 5, drilling a screw rod hole in the beam 2 and the steel die 8 according to the position shown in the figure 1;
step 6, screwing the bottom of a screw rod 6 into a bolt 5, penetrating the screw rod into a gasket 4, penetrating the screw rod 6 into a screw rod hole reserved in the cross beam 2 and a steel die 8, penetrating a sleeve 7, and coating a release agent;
step 7, transversely placing the support beam 3 on the opening;
step 8, penetrating the screw rod 6 into the support beam 3, penetrating the gasket 4, screwing the bolt 5, tightening and applying prestress, and finishing the installation as shown in fig. 2;
and 9, pouring concrete.
It should be noted that the embodiments described in this application are only examples to illustrate the spirit of the invention. Various modifications, additions and substitutions for the specific embodiments described may be made by those skilled in the art without departing from the spirit of the invention or exceeding the scope of the invention as defined in the accompanying claims.

Claims (2)

1. A tool type die hanging device is characterized by comprising a cross beam (2) and a steel die (8) which are connected into a whole through welding, wherein screw rod holes are reserved on the cross beam (2) and the steel die (8); a bolt (5) is screwed into the bottom of the screw rod (6), then the screw rod (6) penetrates into the gasket (4), and then the screw rod (6) penetrates into a screw rod hole reserved in the cross beam (2) and the steel die (8); a supporting beam (3) is transversely placed on a reserved hole on a structural floor slab (1), a screw rod (6) penetrating to the upper side of the hole from the lower side of the hole penetrates the supporting beam (3), a gasket (4) is penetrated and then a bolt (5) is screwed in for fastening, and prestress is applied through the adjusting bolt (5) to enable a steel die (8) to be tightly contacted with the structural floor slab (1), so that slab staggering and slurry leakage are prevented.
2. The tool type die lifting device according to claim 1, wherein a sleeve (7) is sleeved on the section of the screw rod (6) between the steel die (8) and the support beam (3), and a release agent is coated on the periphery of the sleeve (7).
CN202120151180.9U 2021-01-20 2021-01-20 Tool type mould hanging device Active CN214531921U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120151180.9U CN214531921U (en) 2021-01-20 2021-01-20 Tool type mould hanging device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120151180.9U CN214531921U (en) 2021-01-20 2021-01-20 Tool type mould hanging device

Publications (1)

Publication Number Publication Date
CN214531921U true CN214531921U (en) 2021-10-29

Family

ID=78345998

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120151180.9U Active CN214531921U (en) 2021-01-20 2021-01-20 Tool type mould hanging device

Country Status (1)

Country Link
CN (1) CN214531921U (en)

Similar Documents

Publication Publication Date Title
CN103233479B (en) Method for pouring concrete cup foundation
CN208792737U (en) For hanging the detachable connecting part of external platform hanging girder steel
CN111827670B (en) Reinforcing tool for floor hole hanging die and construction method thereof
CN214531921U (en) Tool type mould hanging device
CN215254592U (en) Portable opening template fastening and sealing device
CN204800838U (en) A built -up plate for parapet production
CN205822780U (en) Floor setting-out hole is reserved and blocks mould
CN205024827U (en) Prefabricated plate and roof beam connection structure
CN203499212U (en) Hoisting structure for curved aluminum circular tube
CN213971755U (en) Lintel integrated prefabricated combined type water and electricity switch control box die
CN213233548U (en) Control device for improving flatness of appearance of basement exterior wall construction joint
CN218438232U (en) Drainage riser combination hangs hole mould
CN204645627U (en) A kind of un-bonded prestressed steel strand Special hole mold
CN211286666U (en) Die adjusting embedded part and aluminum alloy template diagonal bracing device
CN207063528U (en) Hang die device in antiseep hole
CN216340983U (en) Construction hangs template installation limiter
CN2893057Y (en) Construction pipeline headhole casing
CN204435867U (en) Air-conditioning duct preformed hole exempts from form removal tool
CN204152205U (en) Decoration exposed concrete construction method split bolt punch die used
CN204662885U (en) European Architecture concrete decoration carved on paste moulding construction equipment
CN2394990Y (en) Prefabricate hole die for high stored building pipeline
CN215907411U (en) Finished product mould for plugging floor slab hanging hole
CN214739003U (en) Prefabricated heat preservation decorates integration wallboard
CN217949740U (en) Bathroom hangs mould and props reinforcement instrument to propping
CN210685404U (en) Anti-leakage turnover eccentric sleeve applied to construction of concrete shear wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant