CN214495505U - Auxiliary hoisting device for partition board installation - Google Patents
Auxiliary hoisting device for partition board installation Download PDFInfo
- Publication number
- CN214495505U CN214495505U CN202120144825.6U CN202120144825U CN214495505U CN 214495505 U CN214495505 U CN 214495505U CN 202120144825 U CN202120144825 U CN 202120144825U CN 214495505 U CN214495505 U CN 214495505U
- Authority
- CN
- China
- Prior art keywords
- vertical
- sleeve
- moving platform
- fixed pulley
- wire rope
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000005192 partition Methods 0.000 title claims abstract description 33
- 238000009434 installation Methods 0.000 title claims abstract description 23
- 230000007246 mechanism Effects 0.000 claims abstract description 18
- 229910000831 Steel Inorganic materials 0.000 claims description 13
- 239000010959 steel Substances 0.000 claims description 13
- 238000003780 insertion Methods 0.000 claims description 7
- 230000037431 insertion Effects 0.000 claims description 7
- 238000004804 winding Methods 0.000 claims 1
- 230000009194 climbing Effects 0.000 abstract description 8
- 238000009435 building construction Methods 0.000 abstract description 2
- 230000009471 action Effects 0.000 description 3
- 238000010276 construction Methods 0.000 description 3
- 230000002146 bilateral effect Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000004567 concrete Substances 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000001932 seasonal effect Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a supplementary device that lifts of partition plate installation belongs to building construction equipment technical field, including moving platform, its characterized in that: moving platform installation climbing mechanism, climbing mechanism includes the flexible pneumatic cylinder of vertical expansion bracket and the vertical expansion bracket of drive, vertical expansion bracket is including fixing the vertical inserted bar on moving platform, the upper portion cartridge of vertical inserted bar has vertical sleeve pipe, the pneumatic cylinder has the jar pole of vertical flexible, jar pole and vertical bushing, moving platform installs the hoist engine, the reel of hoist engine is equipped with wire rope around being equipped with, the position that moving platform upper portion is close to climbing mechanism is equipped with the corner fixed pulley, the position that vertical sleeve pipe is close to the upper end installs the cross-hanging rod, stretch out from climbing mechanism's the place ahead after wire rope's free end passes through corner fixed pulley and cross-hanging rod direction. This novel area is minimum, facilitates the use, can effectively assist the installation of top layer partition plate.
Description
Technical Field
The utility model belongs to the technical field of the construction, especially, relate to a supplementary device that lifts of partition plate installation.
Background
The prefabricated partition wall board is a reinforced concrete plate type member for building assembly, which is called wall board or wall board for short, and is processed in a prefabrication plant or a building site. The prefabricated concrete wallboard is adopted to build the assembled large-plate building, so that the factory and mechanical construction degree can be improved, the field wet operation is reduced, the field labor is saved, the seasonal influence is overcome, and the building construction period is shortened.
In the great building of floor height, need vertical installation polylith partition plate, top layer partition plate's upper end direct contact shingle, because of traditional lifting device's operating height all is higher than the biggest height of lifting by the hanging object, so top layer partition plate can't be with the help of lifting device auxiliary installation, and in addition, traditional lifting device work area is big, can't get into job site work usually. At present, top layer partition plate must be supported by the support by the multiple constructors who stands on cutting fork lift platform and accomplish and just can accomplish the installation, and is not only consuming time, inefficiency, extravagant manpower, and the work progress difficulty, has the potential safety hazard.
SUMMERY OF THE UTILITY MODEL
Problem to prior art existence, the utility model provides a supplementary device that lifts of partition plate installation of the difficult problem of top layer partition plate installation at present is solved.
The utility model discloses a realize like this, a supplementary device that lifts of partition plate installation, including moving platform, its characterized in that: the mobile platform installs climbing mechanism, climbing mechanism includes vertical expansion bracket and drive the flexible pneumatic cylinder of vertical expansion bracket, vertical expansion bracket is including fixing vertical inserted bar on the mobile platform, the upper portion cartridge of vertical inserted bar has vertical sleeve pipe, the pneumatic cylinder has vertical flexible jar pole, the jar pole with vertical bushing, mobile platform installs the hoist engine, the reel of hoist engine is around being equipped with wire rope, mobile platform upper portion is close to climbing mechanism's position is equipped with the corner fixed pulley, the position that vertical sleeve pipe is close to the upper end installs the peg, wire rope's free end is passed through the corner fixed pulley and the peg direction back certainly climbing mechanism's the place ahead stretches out.
The utility model discloses an effect has:
the utility model discloses simple structure, cost and equipment use and maintenance cost are low. The action of vertical extension of vertical expansion bracket accessible realizes that the upper end of vertical expansion bracket is pushed up and is leaned on the roof, makes this device whole top tightly be fixed in the position that is close to the partition plate installation, and fixed device is as the basis of hanging the partition plate. Compared with the traditional hanging equipment, the hanging equipment has the advantages of extremely small occupied area and convenience in use. On the other hand, wire rope winds at the lateral part of partition plate, and partition plate can make its upper end push against the house roof under the hanging effect of this device, effectively assists the installation of top layer partition plate.
In the above technical scheme, preferably, the two vertical insertion rods are fixed on the upper portion of the front end of the mobile platform in a bilateral symmetry manner, the vertical sleeves capable of moving vertically are respectively sleeved on the two vertical insertion rods, the lower cross beam and the transverse hanging rod are connected between the two vertical sleeves, the lower cross beam and the transverse hanging rod form a lifting frame capable of moving vertically, and the hydraulic cylinder is connected with the lower cross beam.
In the above technical solution, preferably, the hanging fixed pulleys are installed on the transverse hanging rod at the transverse positions corresponding to the corner fixed pulleys.
In the above technical solution, preferably, the free end of the steel wire rope is connected with a hook.
In the above technical solution, preferably, the vertical casing is composed of a lower casing and an upper casing installed at an upper end of the lower casing, and the cross hanging rod is fixed to the upper casing.
In the above technical solution, preferably, the lower end of the upper casing is inserted into the upper end of the lower casing.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a side view of the middle vertical telescopic frame of the present invention.
In the figure, 1, a mobile platform; 2. a hydraulic cylinder; 3. a vertical insertion rod; 4. a vertical sleeve; 4-1, setting a sleeve; 4-2, installing a sleeve; 5. a transverse hanging rod; 6. a lower cross beam; 7. a winch; 8. a wire rope; 9. a corner fixed pulley; 10. hanging a fixed pulley; 11. a partition board.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail with reference to the following embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
For solving the problem of present top layer partition plate installation difficulty, the utility model particularly provides a supplementary device that lifts of partition plate installation, this device simple structure, cost low in use cost, and convenient to use. For further explanation of the structure of the present invention, the following detailed description is made with reference to the accompanying drawings:
referring to fig. 1 and 2, an auxiliary lifting device for partition wall plate installation includes a moving platform 1, specifically, a main body of the moving platform 1 is a rectangular planar frame body formed by welding steel materials, and universal rollers having a self-locking function are installed at lower portions of four corners of the rectangular planar frame body.
The mobile platform 1 is provided with a jacking mechanism, and the jacking mechanism comprises a vertical telescopic frame and a hydraulic cylinder 2 for driving the vertical telescopic frame to stretch. In the embodiment, the hydraulic cylinder 2 is a conventionally known manual hydraulic cylinder, a cylinder body of the hydraulic cylinder 2 is fixed on the movable platform 1 by using a bolt assembly, and a cylinder rod of the hydraulic cylinder 2 is vertically upward.
The vertical expansion bracket comprises a vertical inserted rod 3 fixed on the moving platform, a vertical sleeve 4 is inserted on the upper portion of the vertical inserted rod 3, and a cylinder rod of the hydraulic cylinder 2 is connected with the vertical sleeve 4. Specifically, two vertical insertion rods 3 are fixed on the upper portion of the front end of the moving platform 1 in a bilateral symmetry mode, and the vertical insertion rods 3 are cylindrical rods with the lower ends welded on the moving platform 1. The two vertical inserted rods 3 are respectively sleeved with a vertical sleeve 4 capable of vertically moving, and the vertical sleeve 4 is a cylindrical pipe and is provided with a jack matched with the vertical inserted rod 3. The vertical sleeve 4 is inserted into the vertical inserted bar 3 from the upper end of the vertical inserted bar 3, and the vertical sleeve and the vertical inserted bar form a telescopic bar body. Connect bottom end rail 6 and horizontal peg 5 between two vertical sleeve 4, bottom end rail 6 welds between two vertical sleeve 4 with horizontal peg 5, and horizontal peg 5 is close to the upper end of vertical sleeve 4, and the level of horizontal peg 5 is less than the upper end of vertical sleeve 4. The lower beam 6 is positioned below the cross hanging rod 5. The two vertical sleeves 4, the lower cross beam 6 and the transverse hanging rod 5 form a lifting frame capable of moving vertically, the hydraulic cylinder 2 is connected with the lower cross beam 6, and in the embodiment, the lower cross beam 6 is directly welded at the top end of the cylinder rod of the hydraulic cylinder 2.
The moving platform 1 is mounted with a hoist 7, the hoist 7 being a conventionally known device equipped with a drum that winds a wire rope 8. The upper portion of the mobile platform 1 is provided with a corner fixed pulley 9 close to the jacking mechanism, the corner fixed pulley 9 is installed on the mobile platform 1 through a shaft seat, the shaft seat is a seat plate welded on the mobile platform 1, a shaft hole is machined in the seat plate, a wheel shaft is inserted in the shaft hole, and the corner fixed pulley 9 capable of rotating around the axis of the wheel shaft is installed on the wheel shaft through a bearing. In this embodiment, the corner fixed pulley 9 is a sheave. The free end of the steel wire rope 8 is guided by the corner fixed pulley 9 and the cross hanging rod 5 and then extends out of the front of the jacking mechanism. That is, the wire rope 8 extends from the drum toward the corner fixed pulley 9, is combined with the corner fixed pulley 9, passes around the corner fixed pulley 9, and is redirected upward by the corner fixed pulley 9. In the same way, the lifting mechanism extends out of the front of the lifting mechanism under the guiding action of the cross hanging rod 5. In this embodiment, the hanging fixed pulley 10 is installed on the transverse hanging rod 5 at a position corresponding to the transverse position of the corner fixed pulley 9. The hanging fixed pulley 10 is combined with the steel wire rope 8 instead of the cross hanging rod 5 to reduce friction.
The free end of the steel wire rope 8 is connected with a hook. The steel wire rope 8 is tightly bound on the side part of the partition wall plate 11, the hook is combined with the rear section of the steel wire rope, the steel wire rope 8 is hung on the partition wall plate 11 through the friction force between the steel wire rope 8 and the side part of the partition wall plate 11, and the binding force of the steel wire rope 8 is increased under the action of the gravity of the partition wall plate 11. In this embodiment, through the fenestrate wooden cushion of area of cluster dress area, wooden cushion surface processing is the coarse surface on wire rope 8 to increase and the frictional force between the partition plate.
Because the working stroke of the hydraulic cylinder is limited, the device can be suitable for construction sites with larger floor heights and is convenient to enter from a door with limited height. Vertical sleeve 4 is as vertical detachable, specific: the vertical sleeve 4 consists of a lower sleeve 4-1 and an upper sleeve 4-2 arranged at the upper end of the lower sleeve 4-1, and the cross hanging rod 5 is fixed on the upper sleeve 4-2. The lower end part of the upper sleeve 4-2 is inserted into the upper end of the lower sleeve 4-1. Namely, the lower part of the lower sleeve 4-1 is a step round rod part which is provided with a plug column part which extends downwards and can be inserted into a pipe hole at the upper end of the lower sleeve 4-1.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
The above description is only exemplary of the present invention and should not be taken as limiting the scope of the present invention, as any modifications, equivalents, improvements and the like made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.
Claims (6)
1. The utility model provides a supplementary hoisting device of partition plate installation, includes moving platform (1), its characterized in that: the mobile platform (1) is provided with a jacking mechanism, the jacking mechanism comprises a vertical telescopic frame and a hydraulic cylinder (2) for driving the vertical telescopic frame to stretch, the vertical expansion bracket comprises a vertical inserted bar (3) fixed on the mobile platform, a vertical sleeve (4) is inserted at the upper part of the vertical inserted bar (3), the hydraulic cylinder (2) is provided with a vertically telescopic cylinder rod which is connected with the vertical sleeve (4), the moving platform (1) is provided with a winch, a winding drum of the winch is wound with a steel wire rope (8), a corner fixed pulley (9) is arranged at the upper part of the mobile platform (1) close to the jacking mechanism, a transverse hanging rod (5) is arranged at the position of the vertical sleeve (4) close to the upper end part, the free end of the steel wire rope (8) is guided by the corner fixed pulley (9) and the transverse hanging rod (5) and then extends out of the front of the jacking mechanism.
2. The partition installation auxiliary lifting device of claim 1, wherein: the left and right symmetry of the upper portion of the front end of the moving platform (1) is fixed with two vertical insertion rods (3), vertical sleeves (4) capable of moving vertically are sleeved on the two vertical insertion rods (3), two lower cross beams (6) and transverse hanging rods (5) are connected between the vertical sleeves (4), two vertical sleeves (4), the lower cross beams (6) and the transverse hanging rods (5) form lifting frames capable of moving vertically, and the hydraulic cylinder (2) is connected with the lower cross beams (6).
3. The partition installation auxiliary lifting device of claim 2, wherein: and a hanging fixed pulley (10) is arranged on the transverse hanging rod (5) corresponding to the transverse position of the corner fixed pulley (9).
4. The partition installation auxiliary lifting device of claim 1, wherein: the free end of the steel wire rope (8) is connected with a hook.
5. The partition installation auxiliary lifting device of claim 2, wherein: the vertical sleeve (4) is composed of a lower sleeve (4-1) and an upper sleeve (4-2) arranged at the upper end of the lower sleeve (4-1), and the transverse hanging rod (5) is fixed on the upper sleeve (4-2).
6. The partition installation auxiliary lifting device of claim 5, wherein: the lower end part of the upper sleeve (4-2) is inserted into the upper end of the lower sleeve (4-1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120144825.6U CN214495505U (en) | 2021-01-19 | 2021-01-19 | Auxiliary hoisting device for partition board installation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120144825.6U CN214495505U (en) | 2021-01-19 | 2021-01-19 | Auxiliary hoisting device for partition board installation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214495505U true CN214495505U (en) | 2021-10-26 |
Family
ID=78215796
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120144825.6U Expired - Fee Related CN214495505U (en) | 2021-01-19 | 2021-01-19 | Auxiliary hoisting device for partition board installation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214495505U (en) |
-
2021
- 2021-01-19 CN CN202120144825.6U patent/CN214495505U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110104522B (en) | Traction type construction lifter for folding roof beam and construction method thereof | |
CN110228743B (en) | Overhead two-to-one suspension ratio construction elevator for elevator shaft traction and operation method thereof | |
CN113968543B (en) | Assembled building hoisting accessory | |
CN210048319U (en) | Traction type construction elevator with foldable top beam | |
CN214495505U (en) | Auxiliary hoisting device for partition board installation | |
CN210855047U (en) | Be suitable for transmission material between reverse construction method floor with small-size swing arm formula electric hoist | |
CN210480530U (en) | Elevator shaft traction overhead two-to-one suspension ratio construction elevator | |
CN218893051U (en) | Step stone traction track device | |
CN111115412A (en) | Collapsible arch bridge formula bearing beam subassembly and spandrel girder for well construction elevator | |
CN110606439A (en) | Be suitable for transmission material between reverse construction method floor with small-size swing arm formula electric hoist | |
CN214570286U (en) | Convenient type slat wall installation assists utensil | |
CN113213315B (en) | Transfer method for building partition plate | |
CN210457242U (en) | Detachable hoist engine hoist device | |
CN209816674U (en) | Indoor prestress tensioning jack mounting tool for cast-in-situ box girder box | |
CN209957241U (en) | Steel hanger | |
CN2460501Y (en) | Assembling standard steel structure frame | |
CN219906793U (en) | Detachable fixed elevator | |
CN111196566A (en) | Construction structure and construction method of super high-rise inner climbing tower crane | |
CN218507446U (en) | Simple lifting device for construction of assembled plate wall | |
CN220889544U (en) | Steam pressurized concrete wallboard vertical lathe | |
JPH03195684A (en) | Household elevator | |
CN216711434U (en) | High-lift hoister | |
CN213329962U (en) | Split type lifting scaffold | |
CN210457367U (en) | High-rise ALC wallboard construction equipment | |
CN114906758B (en) | Conversion structure and method for construction elevator foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20211026 |