CN210457367U - High-rise ALC wallboard construction equipment - Google Patents

High-rise ALC wallboard construction equipment Download PDF

Info

Publication number
CN210457367U
CN210457367U CN201821441904.8U CN201821441904U CN210457367U CN 210457367 U CN210457367 U CN 210457367U CN 201821441904 U CN201821441904 U CN 201821441904U CN 210457367 U CN210457367 U CN 210457367U
Authority
CN
China
Prior art keywords
light
equipment
running track
construction equipment
hoist
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821441904.8U
Other languages
Chinese (zh)
Inventor
李予新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinotech Jingu Prefabricated Construction Industry Research Center Shenzhen Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201821441904.8U priority Critical patent/CN210457367U/en
Application granted granted Critical
Publication of CN210457367U publication Critical patent/CN210457367U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型提供一种高层ALC墙板施工设备,所述施工设备包括轻型吊篮设备、轻型吊装设备、轻质运行轨道设备,通过一套专用的安装设备对高层ALC外墙板进行高效率的安装,本实用新型与传统的几种安装设备相比,机械设备更加轻质灵活,通过在楼面处铺设配套轻轨,轻质吊篮设备和轻质吊装设备可以通过轻轨移动,大大提高了设备工作面积,施工过程更加省时,安装效率更加高,施工定位更加清楚、明晰、高效,更加省时、省力、省人工。

Figure 201821441904

The utility model provides a high-rise ALC wall panel construction equipment. The construction equipment includes light-duty hanging basket equipment, light-duty hoisting equipment, and light-weight running track equipment. Compared with the traditional installation equipment, the utility model has more lightweight and flexible mechanical equipment. By laying a matching light rail on the floor, the light hanging basket equipment and the light lifting equipment can be moved through the light rail, which greatly improves the equipment. The working area, the construction process is more time-saving, the installation efficiency is higher, the construction positioning is clearer, clearer, more efficient, and more time-saving, labor-saving and labor-saving.

Figure 201821441904

Description

High-rise ALC wallboard construction equipment
Technical Field
The utility model belongs to high-rise building prefabricated wallboard construction field especially relates to a construction equipment of high-rise ALC wallboard.
Background
At present, the construction equipment for building the traditional light external wall panel mainly comprises the following types: a winch, a miniature electric hoist, a tower crane and an automobile crane. Among them, the hoist is a light and small hoisting device for hoisting or pulling heavy objects by winding a steel wire rope or a chain on a winding drum, which is also called a winch. The winch can vertically lift, horizontally or obliquely drag heavy objects; the miniature electric hoist is also called as a civil electric hoist, the electric hoist has a compact structure, and the electric hoist with the motor axis vertical to the axis of the winding drum adopts a worm gear transmission device, so that a wallboard below 1000 kilograms can be lifted; the movable arm of the tower crane is arranged on the rotary crane at the upper part of the high tower body, and the working mechanism comprises four parts of lifting, amplitude variation, rotation and walking; the automobile crane is one kind of crane installed on common or special automobile chassis, and has one rotating drum below the crane arm and one steel cable wound to the drum. When retracting, the winding drum reverses to recover the steel wire rope, and the crane arm retracts under the action of self weight.
Several above-mentioned light wallboard erection equipment: belong to common building site corollary equipment, the equipment function is common function, is not the erection equipment of special design to light wallboard. When the wall board is hoisted by the winch or the electric hoist, the wall board needs to be fixed at the installation position in advance, and then the wall board is dismantled and fixed at another installation position after being installed, so that the dismantling process is complicated. The crane equipment is too heavy, the mechanical cost is too high, the hoisting efficiency is low, the hoisting time is too long, and the command difficulty is large.
SUMMERY OF THE UTILITY MODEL
In order to solve the problems, the utility model provides a high-rise ALC external wall panel installation equipment, the construction equipment includes light hanging flower basket equipment, light hoisting equipment and light orbit, the light orbit sets up in the wall body inboard, light hanging flower basket equipment and light hoisting equipment all set up on the light orbit;
furthermore, the light operation track comprises a first operation track and a second operation track, the first operation track is positioned below the second operation track, the light hoisting equipment is connected above the first operation track, and the light hanging basket equipment is connected with the upper square block of the second operation track;
furthermore, the light hanging basket equipment comprises a lifting platform and an electric walking big arm, the electric walking big arm is arranged above the second running track, the lifting platform is connected with the electric walking big arm, and the lifting platform is positioned on the outer side of the wall body;
furthermore, the lifting platform comprises a fence body, a lifting machine, a steel wire rope, a motor and a safety lock, wherein the fence body is connected with the lifting machine through the steel wire rope, the lifting machine is connected with the motor, the safety lock is arranged at the joint of the fence body and the steel wire rope, and the lifting machine is connected with the electric walking large arm;
furthermore, the electric walking big arm comprises a walking motor, a walking wheel and a first pull rope, the walking motor is connected with the walking wheel, the balancing weight is connected with the first pull rope through a winch, and the other end, opposite to the winch, of the first pull rope is connected with a hoist;
further, the height of the fence body is 2 meters, the number of the steel wire ropes is 4, and the length of each steel wire rope is 30 meters;
furthermore, the light-weight hoisting equipment comprises a second pull rope, a balance weight area, a suspension arm and a traveling wheel, wherein the traveling wheel is connected with a first running track, the balance weight area is connected above the traveling wheel, the balance weight area is connected with the second pull rope through the suspension arm, and the other end, opposite to the balance weight area, of the second pull rope is connected with a winch and a balance weight block;
furthermore, the light running track also comprises a track connecting plate, and the first running track and the second running track are fixedly connected with the ground through the track connecting plate;
the utility model has the advantages as follows:
1. compared with the traditional installation equipment, the mechanical equipment is lighter and more flexible;
2. the utility model lays the matched light rail on the floor, the light hanging basket equipment and the light hoisting equipment can move through the light rail, thereby greatly improving the working area of the equipment, saving more time in the construction process and improving the installation efficiency;
3. the equipment in the light hanging basket of the utility model can control the hoisting equipment of the plate at the same height, and the construction and positioning are clearer, clearer and more clear and efficient;
4. the utility model discloses a light lifting device, equipment fixing is convenient, can with the light hoist and mount assigned position of panel, the efficiency of construction is high, saves time, laborsaving, economizes the manual work.
Drawings
FIG. 1 is a structural diagram of the construction equipment of the present invention;
FIG. 2 is a schematic view of the light hanging basket device of the present invention;
fig. 3 is a schematic view of the light hoisting device of the present invention;
fig. 4 is the light orbit device of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention. On the contrary, the invention is intended to cover alternatives, modifications, equivalents and alternatives which may be included within the spirit and scope of the invention as defined by the appended claims. Furthermore, in order to provide a better understanding of the present invention to the public, certain specific details are set forth in the following detailed description of the invention. It will be apparent to those skilled in the art that the present invention may be practiced without these specific details.
The present invention will be further described with reference to the accompanying drawings and specific examples, which are not intended to limit the present invention. The following are the best embodiments of the present invention:
as shown in FIGS. 1-4, the utility model provides a construction equipment of high-rise ALC wallboard, construction equipment includes light hanging flower basket equipment, light lifting device, light orbit. The light operation track is arranged on the inner side of the wall body, and the light hanging basket equipment and the light hoisting equipment are both arranged on the light operation track.
The light orbit includes first orbit and second orbit, first orbit is located second orbit below, light hoisting equipment connects first orbit top, light hanging flower basket equipment sets up second orbit top, light orbit still include the rail connecting plate, first orbit and second orbit are all through rail connecting plate fixed connection ground.
The light hanging basket equipment comprises a lifting platform and an electric walking big arm, wherein the electric walking big arm is arranged above the second running track, the lifting platform is connected with the electric walking big arm, and the lifting platform is positioned on the outer side of the wall body; the lifting platform comprises a fence body, a lifting machine, a motor wire and a safety lock, wherein the fence body is connected with the lifting machine through a steel wire rope, the lifting machine is connected with the motor, the safety lock is arranged at the joint of the fence body and the steel wire rope, and the lifting machine is connected with the electric walking large arm; the electric walking big arm comprises a first pull rope, a walking motor and a walking wheel, the walking motor is connected with the walking wheel, the balancing weight is connected with the first pull rope through a winch, and the other end, opposite to the winch, of the first pull rope is connected with a hoist; the fence body is 2 meters high, 4 steel wire ropes are provided, and the length of each steel wire rope is 30 meters.
The light hoisting equipment comprises a second pull rope, a balance weight area, a suspension arm and a traveling wheel, the traveling wheel is connected with a first running track, the balance weight area is connected above the traveling wheel, the balance weight area is connected with the second pull rope through the suspension arm, and the second pull rope is opposite to the other end of the balance weight area and is connected with a winch and a balance weight block.

Claims (8)

1.一种高层ALC墙板施工设备,其特征在于,所述施工设备包括轻质吊篮设备(1)、轻质吊装设备(2)和轻质运行轨道(3),所述轻质运行轨道(3)设置在墙体内侧,所述轻质吊篮设备(1)和轻质吊装设备(2)均设置在所述轻质运行轨道(3)上。1. A high-rise ALC wall panel construction equipment, is characterized in that, described construction equipment comprises light weight hanging basket equipment (1), light weight hoisting equipment (2) and light weight running track (3), described light weight running The track (3) is arranged on the inner side of the wall, and the light-weight hanging basket device (1) and the light-weight hoisting device (2) are both arranged on the light-weight running track (3). 2.根据权利要求1所述的施工设备,其特征在于,所述轻质运行轨道(3)包括第一运行轨道(31)和第二运行轨道(32),所述第一运行轨道(31)位于所述第二运行轨道(32)下方,所述轻质吊装设备(2)连接所述第一运行轨道(31)上方,所述轻质吊篮设备(1)连接所述第二运行轨道(32)上方。2. The construction equipment according to claim 1, wherein the light-weight running track (3) comprises a first running track (31) and a second running track (32), the first running track (31) ) is located below the second running track (32), the lightweight lifting device (2) is connected above the first running track (31), and the lightweight hanging basket device (1) is connected to the second running track (31). above the track (32). 3.根据权利要求2所述的施工设备,其特征在于,所述的轻质吊篮设备(1)包括升降平台(4)和电动行走大臂(5),所述电动行走大臂(5)设置在所述第二运行轨道(32)上方,所述升降平台(4)连接所述电动行走大臂(5),所述升降平台(4)位于墙体外侧。3. The construction equipment according to claim 2, characterized in that, the lightweight hanging basket equipment (1) comprises a lifting platform (4) and an electric walking boom (5), the electric walking boom (5) ) is arranged above the second running track (32), the lifting platform (4) is connected to the electric traveling boom (5), and the lifting platform (4) is located outside the wall. 4.根据权利要求3所述的施工设备,其特征在于,所述升降平台(4)包括栏体(41)、提升机(42)、钢丝绳(43)、电机(44)和安全锁(45),所述栏体(41)通过钢丝绳(43)连接所述提升机(42),所述提升机(42)连接电机(44),所述安全锁(45)设置在所述栏体(41)和钢丝绳(43)连接处,所述提升机(42)连接所述电动行走大臂(5)。4. The construction equipment according to claim 3, wherein the lifting platform (4) comprises a fence (41), a hoist (42), a wire rope (43), a motor (44) and a safety lock (45) ), the fence (41) is connected to the hoist (42) through the wire rope (43), the hoist (42) is connected to the motor (44), and the safety lock (45) is arranged on the fence (45). 41) and the wire rope (43) connection, the hoist (42) is connected to the electric walking boom (5). 5.根据权利要求4所述的施工设备,其特征在于,所述电动行走大臂(5)包括行走电机(51)、行走轮和第一拉绳(53),所述行走电机(51)连接行走轮,配重块通过卷扬机连接第一拉绳(53),所述第一拉绳(53)相反于所述卷扬机的另一端连接提升机(42)。5. The construction equipment according to claim 4, characterized in that, the electric traveling boom (5) comprises a traveling motor (51), a traveling wheel and a first pulling rope (53), and the traveling motor (51) The traveling wheel is connected, and the counterweight is connected to a first pull rope (53) through a hoist, and the first pull rope (53) is connected to the hoist (42) opposite to the other end of the hoist. 6.根据权利要求4所述的施工设备,其特征在于,所述栏体(41)高为2米,所述钢丝绳(43)为4根,每根所述钢丝绳(43)长度均为30米。6. The construction equipment according to claim 4, characterized in that, the height of the fence body (41) is 2 meters, the number of the wire ropes (43) is 4, and the length of each wire rope (43) is 30 meters. Meter. 7.根据权利要求1所述的施工设备,其特征在于,所述轻质吊装设备(2)包括第二拉绳(21)、配重区(22)、吊臂(23)和行走轮(24),所述行走轮连接第一运行轨道(31),所述配重区(22)连接在所述行走轮上方,所述配重区(22)通过吊臂(23)连接第二拉绳(21),所述第二拉绳(21)相反于所述配重区(22)的另一端连接卷扬机和配重块。7. The construction equipment according to claim 1, characterized in that, the light-weight hoisting equipment (2) comprises a second pulling rope (21), a counterweight area (22), a boom (23) and a traveling wheel ( 24), the travel wheel is connected to the first running track (31), the counterweight area (22) is connected above the travel wheel, and the counterweight area (22) is connected to the second pulley through the boom (23). A rope (21), the other end of the second pulling rope (21) opposite to the counterweight area (22) is connected to the hoist and the counterweight. 8.根据权利要求7所述的高层ALC墙板施工设备,其特征在于,所述的轻质运行轨道(3)还包括道轨连接板(33),所述第一运行轨道(31)和第二运行轨道(32)均通过道轨连接板(33)固定连接地面。8. high-rise ALC wall panel construction equipment according to claim 7, is characterized in that, described light-weight running rail (3) also comprises rail connecting plate (33), described first running rail (31) and The second running rails (32) are all fixedly connected to the ground through the rail connecting plates (33).
CN201821441904.8U 2018-09-04 2018-09-04 High-rise ALC wallboard construction equipment Expired - Fee Related CN210457367U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821441904.8U CN210457367U (en) 2018-09-04 2018-09-04 High-rise ALC wallboard construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821441904.8U CN210457367U (en) 2018-09-04 2018-09-04 High-rise ALC wallboard construction equipment

Publications (1)

Publication Number Publication Date
CN210457367U true CN210457367U (en) 2020-05-05

Family

ID=70428278

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821441904.8U Expired - Fee Related CN210457367U (en) 2018-09-04 2018-09-04 High-rise ALC wallboard construction equipment

Country Status (1)

Country Link
CN (1) CN210457367U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115744667A (en) * 2022-11-30 2023-03-07 上海宝冶集团有限公司 Hoisting method for curtain wall unit plate of super high-rise building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115744667A (en) * 2022-11-30 2023-03-07 上海宝冶集团有限公司 Hoisting method for curtain wall unit plate of super high-rise building

Similar Documents

Publication Publication Date Title
CN201971572U (en) Movable arm type tower crane with suspension arm possible of being folded for dismounting
CN103086279B (en) Vertical transportation construction method for building construction
CN213171204U (en) Construction equipment hoisting device
CN103832933B (en) A kind of group tower tower crane with auxiliary
CN103303807A (en) Self-lifting type crane for wind generating set
CN106698208A (en) Hoisting equipment and hoisting method for external transportation of super high-rise building
CN203728443U (en) Combined tower crane with main and auxiliary boom structure
CN206562264U (en) A kind of hanging device for transport outside high-rise building
CN210457367U (en) High-rise ALC wallboard construction equipment
CN103101847B (en) Tower type truss installing structure and method without cooperation with altitude hoisting equipment
CN202449763U (en) Simple pneumatic crane
CN114572854A (en) Assembled squat silo roof hoisting system and silo roof hoisting method
CN211338603U (en) Gantry frame of crawler crane
CN210855047U (en) Be suitable for transmission material between reverse construction method floor with small-size swing arm formula electric hoist
CN220283436U (en) Hoisting mechanism, wind power device thereof and full-automatic tower crane
CN207844841U (en) A kind of great diameter and long pile cages decentralization suspender
CN216997400U (en) Double-rocker arm holding rod lifting hook releasing and rope conveying device
CN216711434U (en) High-lift hoister
CN209740540U (en) Safe power control system of double-rocker floor type holding rod
CN104860212B (en) A kind of micro lifter
CN115676617A (en) A truss type steel coil lifting device
CN210150618U (en) A rail row hoisting door machine device
CN219116989U (en) Rail sliding device for hoisting high-rise building surface
CN217894899U (en) Pipeline mobile device for hydraulic engineering
CN101429827A (en) Leaning tower self-stabilization upside-down mounting assembling apparatus and method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220302

Address after: 518052 pengrunda Commercial Plaza, No. 3368, Houhaibin Road, Haizhu community, Yuehai street, Nanshan District, Shenzhen, Guangdong 2625

Patentee after: Sinotech Jingu prefabricated construction industry research center (Shenzhen) Co.,Ltd.

Address before: Room 2803, tower a, Dongfang Ruijing, No. 16, Jianguomenwai street, Chaoyang District, Beijing 100022

Patentee before: Li Yuxin

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200505