CN214362938U - Cantilever mould reinforcing bar construction safety support body - Google Patents
Cantilever mould reinforcing bar construction safety support body Download PDFInfo
- Publication number
- CN214362938U CN214362938U CN202120519215.XU CN202120519215U CN214362938U CN 214362938 U CN214362938 U CN 214362938U CN 202120519215 U CN202120519215 U CN 202120519215U CN 214362938 U CN214362938 U CN 214362938U
- Authority
- CN
- China
- Prior art keywords
- frame
- layer
- construction platform
- support frame
- supporting base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model relates to a scaffold technical field, specifically speaking relates to a cantilever mould reinforcing bar construction safety support body. The support frame comprises a support base, four side faces around the support base are provided with fixing frames, the upper portion of the support base is provided with a bottom support frame with an inclination, the center of the upper portion of the support base is provided with a vertical main body support frame, the tops of the bottom support frame and the main body support frame are on the same horizontal plane, the second layer of construction platform comprises a workbench connecting rod and a connecting rod, the structure of the third layer of construction platform is consistent with that of the second layer of construction platform, and the second layer of construction platform and the third layer of construction platform are fixedly connected through the connecting rod. This device can be so that high mound reinforcing bar construction safe effective more, simple convenient.
Description
Technical Field
The utility model relates to a scaffold technical field, specifically speaking relates to a cantilever mould reinforcing bar construction safety support body.
Background
In the traditional high pier steel bar construction, high-altitude safety accidents and high-altitude operation are frequently encountered, and the safety coefficient and the efficiency are low. To this type of problem and combine on-the-spot reality, finally prefabricate a reinforcing bar construction rack, can safe effectual solution this type of problem, let workman's safety of surviving is guaranteed, efficiency is higher.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a cantilever mould reinforcing bar construction safety support body to solve the problem that proposes in the above-mentioned background art.
For realizing above-mentioned purpose, the utility model provides a cantilever mould reinforcing bar construction safety support body, the on-line screen storage device comprises a rack, the rack is cavity terrace with edge frame construction, the rack is by supreme braced frame, second floor construction platform and the third layer construction platform of being respectively down, braced frame is including supporting the base, four sides all are equipped with the mount around the support base, it is equipped with the end support frame that the utensil slopes to support base upper portion, it is equipped with the vertically main part support frame to support base upper portion center, the top of end support frame and main part support frame is on same horizontal plane, second floor construction platform includes the workstation, allies oneself with tie rod and tie rod, third layer construction platform's structure is unanimous with second floor construction platform, it is fixed to be connected through the tie rod between second floor construction platform and the third layer construction platform.
As a further improvement of the technical scheme, the supporting base is of a frame-shaped structure, a gap is formed between the left frame and the right frame of the supporting base, and a transverse reinforcing rod is arranged in the gap.
As a further improvement of the technical scheme, the fixing frame, the bottom supporting frame, the main body supporting frame and the reinforcing rods are all angle steel.
As a further improvement of the technical scheme, the plane of the supporting base and the plane of the workbench are both formed by laying steel plates.
As a further improvement of the technical scheme, guardrails are installed on the peripheries of the second layer construction platform and the third layer construction platform.
As a further improvement of the technical scheme, the guardrail comprises an upper guard plate and a lower guard plate, and the guard plates are arranged on the tie bars of the second-layer construction platform and the third-layer construction platform.
As a further improvement of the technical scheme, a U-shaped plate is arranged on the tie bar, a connecting hole is formed in the side face of the U-shaped plate, a U-shaped rod is arranged in the connecting hole, the U-shaped rod penetrates through the connecting hole and is fixed on the U-shaped plate through a nut, and the guard plate penetrates through the hollow part of the U-shaped plate.
Compared with the prior art, the beneficial effects of the utility model are that: in this cantilever mould reinforcing bar construction safety support body, through the multilayer construction platform that sets up, can be so that the construction is high-efficient, promote construction speed, the guardrail that this device set up can protect constructor personal safety in addition.
Drawings
FIG. 1 is a schematic view of the entire structure of embodiment 1;
FIG. 2 is a schematic view of the structure of a support frame according to embodiment 1;
FIG. 3 is a schematic structural view of a second floor construction platform according to embodiment 1;
FIG. 4 is a schematic structural view of a third floor construction platform according to embodiment 1;
fig. 5 is a schematic structural view of the tie bar, the U-shaped bar and the U-shaped plate of embodiment 1.
The various reference numbers in the figures mean:
100. a rack; 110. a support frame; 111. a support base; 112. a fixed mount; 113. a bottom support frame; 114. a main body support frame; 115. a reinforcing rod; 120. a second layer of construction platform; 121. a work table; 122. a tie bar; 123. a tie bar; 124. a U-shaped plate; 130. a third layer of construction platform; 140. a guardrail; 141. a guard plate; 142. a U-shaped rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and to simplify the description, but do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore should not be construed as limiting the present invention.
Example 1
The utility model provides a cantilever mould reinforcing bar construction safety support body, as shown in fig. 1-5, including rack 100, rack 100 is cavity terrace with edge frame construction, rack 100 is by supreme braced frame 110 that is respectively down, second floor construction platform 120 and third layer construction platform 130, braced frame 110 is including supporting base 111, support base 111 all is equipped with mount 112 in four sides on every side, support base 111 upper portion is equipped with the end support frame 113 of utensil slope, it is equipped with vertically main part support frame 114 to support base 111 upper portion center, the top of end support frame 113 and main part support frame 114 is on same horizontal plane, second floor construction platform 120 includes workstation 121, tie rod 122 and tie rod 123, third layer construction platform 130's structure is unanimous with second floor construction platform 120, it is fixed to be connected through tie rod 123 between second floor construction platform 120 and the third layer construction platform 130.
In order to solve the problem that the structure of the supporting base 111 is not stable enough, a gap is formed between the left frame and the right frame of the frame-shaped supporting base 111, a transverse reinforcing rod 115 is arranged in the gap, and the transverse reinforcing rod 115 is connected with the fixing frame 112, so that the supporting base 111 is stable in structure.
In order to fully utilize the angle steel excess materials on the construction site, the fixing frame 112, the bottom support frame 113, the main body support frame 114 and the reinforcing rods 115 are all made of angle steel, so that the excess materials are fully utilized, and the expenditure is saved.
In order to fully utilize the steel plate excess materials on the construction site, the plane of the supporting base 111 and the plane of the workbench 121 are paved by 2mm steel plates, so that the excess materials are fully utilized, and the expenditure is saved.
In order to solve the potential safety hazard problem of falling in the construction process, guard rails 140 are installed on the peripheries of the second layer construction platform 120 and the third layer construction platform 130.
In order to fix the guard rail 140 more stably, the guard rail 140 includes two upper and lower guard plates 141, the guard plates 141 are mounted on the tie bars 122 of the second layer 120 and the third layer 130, the two upper and lower guard plates 141 can enhance the protection height of the guard rail 140, and the design of the plurality of tie bars 122 also makes the connection between the guard rail 140 and the tie bars 122 more stable.
In order to solve the problem that the guardrail 140 is inconvenient to detach, the tie bar 122 is provided with a U-shaped plate 124, the side surface of the U-shaped plate 124 is provided with a connecting hole, a U-shaped rod 142 is arranged in the connecting hole, the U-shaped rod 142 penetrates through the connecting hole and is fixed on the U-shaped plate 124 through a nut, the guard plate 141 penetrates through the hollow part of the U-shaped plate 124, and the guardrail 140 is convenient to detach from the tie bar 122 through the connection mode of the U-shaped rod 142 and the U-shaped plate 124.
The use method of the cantilever mould steel bar construction safety frame body comprises the following steps: before carrying out pier bar construction, place the reinforcement segment with this cantilever mould bar construction safety support body, whether the inspection platform frame 100 is placed steadily all around, place and can begin the bar construction after accomplishing.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It should be understood by those skilled in the art that the present invention is not limited by the above embodiments, and the description in the above embodiments and the description is only preferred examples of the present invention, and is not intended to limit the present invention, and that the present invention can have various changes and modifications without departing from the spirit and scope of the present invention, and these changes and modifications all fall into the scope of the claimed invention. The scope of the invention is defined by the appended claims and equivalents thereof.
Claims (7)
1. The utility model provides a cantilever mould reinforcing bar construction safety support body, includes rack (100), its characterized in that: the rack (100) is of a hollow prismatic table frame structure, the rack (100) is respectively provided with a support frame (110), a second layer construction platform (120) and a third layer construction platform (130) from bottom to top, the supporting frame (110) comprises a supporting base (111), four side surfaces around the supporting base (111) are respectively provided with a fixing frame (112), the upper part of the supporting base (111) is provided with an inclined bottom supporting frame (113), a vertical main body supporting frame (114) is arranged at the center of the upper part of the supporting base (111), the tops of the bottom support frame (113) and the main body support frame (114) are on the same horizontal plane, the second layer of construction platform (120) comprises a workbench (121), a connecting rod (122) and a tie rod (123), the structure of the third layer of construction platform (130) is consistent with that of the second layer of construction platform (120), the second layer of construction platform (120) and the third layer of construction platform (130) are fixedly connected through a tie bar (123).
2. The cantilever formwork steel bar construction safety frame body of claim 1, characterized in that: the supporting base (111) is of a frame-shaped structure, a gap is formed between the left frame and the right frame of the supporting base (111), and a transverse reinforcing rod (115) is arranged in the gap.
3. The cantilever mould reinforcing bar construction safety support body of claim 2, characterized in that: the fixed frame (112), the bottom support frame (113), the main body support frame (114) and the reinforcing rods (115) are all angle steel.
4. The cantilever mould reinforcing bar construction safety support body of claim 2, characterized in that: the plane of the supporting base (111) and the plane of the workbench (121) are both formed by laying steel plates.
5. The cantilever formwork steel bar construction safety frame body of claim 1, characterized in that: and guardrails (140) are arranged on the peripheries of the second layer construction platform (120) and the third layer construction platform (130).
6. The cantilever formwork steel bar construction safety frame body of claim 5, characterized in that: the guardrail (140) comprises an upper protective plate and a lower protective plate (141), and the protective plates (141) are arranged on the connecting rods (122) of the second-layer construction platform (120) and the third-layer construction platform (130).
7. The cantilever formwork steel bar construction safety frame body of claim 6, characterized in that: the U-shaped plate (124) is arranged on the tie bar (122), a connecting hole is formed in the side face of the U-shaped plate (124), a U-shaped rod (142) is arranged in the connecting hole, the U-shaped rod (142) penetrates through the connecting hole and is fixed to the U-shaped plate (124) through a nut, and the protection plate (141) penetrates through the hollow part of the U-shaped plate (124).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120519215.XU CN214362938U (en) | 2021-03-11 | 2021-03-11 | Cantilever mould reinforcing bar construction safety support body |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120519215.XU CN214362938U (en) | 2021-03-11 | 2021-03-11 | Cantilever mould reinforcing bar construction safety support body |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214362938U true CN214362938U (en) | 2021-10-08 |
Family
ID=77970994
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120519215.XU Expired - Fee Related CN214362938U (en) | 2021-03-11 | 2021-03-11 | Cantilever mould reinforcing bar construction safety support body |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214362938U (en) |
-
2021
- 2021-03-11 CN CN202120519215.XU patent/CN214362938U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210459921U (en) | Construction platform for building construction operation | |
CN214362938U (en) | Cantilever mould reinforcing bar construction safety support body | |
CN215441501U (en) | Cantilever steel structure combined construction hanging basket | |
CN212506752U (en) | Shaped steel support piece convenient to installation is dismantled | |
CN217151113U (en) | Scaffold with freely adjustable height | |
CN210622382U (en) | Building cat ladder for deep basal pit construction | |
CN214170118U (en) | Electric power iron tower convenient to maintenance | |
CN210289068U (en) | Elevator shaft lifting platform | |
CN212129859U (en) | Detachable steel structure aerial work operating platform | |
CN211873780U (en) | Attached safety operation protection platform for building construction | |
CN112727050B (en) | Improved generation attaches wall scaffold structure | |
CN209874424U (en) | Building assembled safety scaffold | |
CN216277000U (en) | Jig frame combined structure for truss assembly | |
CN109056532B (en) | I-beam construction platform | |
CN215857268U (en) | Assembled external construction protection platform | |
CN216518050U (en) | Tunnel tunnel face spouts concrete construction work platform in | |
CN211691396U (en) | Lifting truss under attached lifting scaffold | |
CN210888132U (en) | Building engineering stair are with interim rail guard | |
CN220432275U (en) | Liftable overhaul platform | |
CN217151300U (en) | A assembled platform of unloading safely for construction | |
CN217232608U (en) | Assembled multifunctional scaffold for constructional engineering | |
CN218933797U (en) | High-altitude operation platform device for tower platform beam of steelmaking main plant | |
CN213742267U (en) | Concrete construction operation panel | |
CN219219722U (en) | Steel structure platform | |
CN215671207U (en) | Integrally-assembled overhanging discharging platform for elevator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20211008 |
|
CF01 | Termination of patent right due to non-payment of annual fee |