CN214328861U - Construction device for pile foundation engineering - Google Patents

Construction device for pile foundation engineering Download PDF

Info

Publication number
CN214328861U
CN214328861U CN202120120384.6U CN202120120384U CN214328861U CN 214328861 U CN214328861 U CN 214328861U CN 202120120384 U CN202120120384 U CN 202120120384U CN 214328861 U CN214328861 U CN 214328861U
Authority
CN
China
Prior art keywords
cable
base
pile foundation
pulling buckle
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120120384.6U
Other languages
Chinese (zh)
Inventor
陈景灵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Guangyu Construction Engineering Co ltd
Original Assignee
Guangdong Guangyu Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Guangyu Construction Engineering Co ltd filed Critical Guangdong Guangyu Construction Engineering Co ltd
Priority to CN202120120384.6U priority Critical patent/CN214328861U/en
Application granted granted Critical
Publication of CN214328861U publication Critical patent/CN214328861U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a construction device of pile foundation engineering, which comprises a base, wherein a support frame mechanism and a pile rotating mechanism are arranged on the base, both sides of the support frame mechanism are provided with pressure codes, an adjusting groove is arranged in the base, a first pull plate and a second pull plate are arranged in the adjusting groove, the support frame mechanism comprises a vertical column vertically arranged on the base and a pull frame fixedly arranged on the vertical column through a locking plate, a motor wheel shaft drives a support, a fixed seat and a rotating motor to slowly descend to the ground so as to lead a drill rod to drill into the ground, the pressure codes are pressed on the pressure codes to play the role of gravity support, then the first cable, the second cable, the third cable and the fourth cable are respectively connected and tensioned, a pile foundation driver is started to drive a pile column to construct, the structure is more stable, construction safety accidents of toppling are not easy to happen, and the pile foundation is safer, the positions of the first cable, the second cable, the third cable and the fourth cable are adjusted by utilizing the first pulling plate and the second pulling plate, and the device is more convenient and fast.

Description

Construction device for pile foundation engineering
Technical Field
The utility model belongs to the technical field of engineering equipment and specifically relates to a construction equipment of pile foundation engineering is related to.
Background
In to present pile foundation engineering work progress, require very high to the pile foundation frame, the pile foundation frame holding power in present stage is not enough, and weight need press a lot of pressure to go to the sign indicating number and just can realize, and is comparatively troublesome and inconvenient, and this type of pile foundation frame takes place easily to empty under the not enough condition of pressure simultaneously, and factor of safety is low, consequently, is necessary to provide the construction equipment of the pile foundation engineering that factor of safety is high.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a construction equipment of pile foundation engineering to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
construction equipment of pile foundation engineering, the on-line screen storage device comprises a base, the base on install support frame mechanism and change a mechanism, support frame mechanism both sides all be provided with and press the sign indicating number, the base in be provided with the adjustment tank, the adjustment tank in install first arm-tie and second arm-tie, support frame mechanism include vertical installation in the base stand, through jam plate fixed mounting in the stand on the stand, be located the first fastener and the second fastener of the stand left and right sides, change a mechanism including install in the base on the bolster, be located the lift cylinder on the bolster, with the lift cylinder cup joint lift seat, be located the hack lever on the lift seat, with the hack lever be connected the davit, be located pile driver and the stake on the davit, the davit on be provided with the third fastener.
As a further technical scheme of the utility model, the stand be provided with sliding guide along length direction, sliding guide in be equipped with the motor shaft, the motor shaft be connected with the support, the support pass through the fixing base and be connected with the rotation motor, rotation motor drive be connected with the drilling rod, the drilling rod under the effect of rotating the motor bore into the earth's surface.
As a further technical scheme of the utility model, first arm-tie and second arm-tie in be provided with the fourth respectively and draw to detain and the fifth draws to detain, the institute first draw detain with the fourth draw and be connected with first cable between detaining, the second draw detain with the third draw and be connected with the second cable between detaining, the second draw detain with the fifth draw and be connected with the third cable between detaining, the third draw detain with the fifth draw and be connected with the fourth cable between detaining, third cable, fourth cable and second cable between form the triangle-shaped structure.
As a further technical scheme of the utility model, sliding guide in all be provided with anticollision spring from top to bottom.
As a further technical scheme of the utility model, the adjustment tank in both sides be provided with the stopper.
Compared with the prior art, the beneficial effects of the utility model are that: before piling, firstly, starting a motor wheel shaft to drive the support, the fixing seat and the rotating motor to integrally move up to the optimal position, starting the rotating motor to drive the drill rod to rotate, driving the support, the fixing seat and the rotating motor to slowly descend to the ground while rotating, driving the drill rod to drill into the ground, then pressing and stacking the support to play a role of gravity support, then respectively connecting and tensioning the first cable, the second cable, the third cable and the fourth cable, and then starting the pile driver to drive the pile to carry out pile foundation construction.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Wherein: base 1, stand 2, bolster 3, lift cylinder 4, lift seat 5, fourth cable 6, davit 7, pile driver
8. The device comprises a pile 9, a rack rod 10, a third pull buckle 11, a second cable 12, a second pull buckle 13, a third cable 14, a fourth pull buckle 15, a first pull plate 16, a second pull plate 17, a pressing code 18, a limiting block 20, a first cable 21, a drill rod 22, a rotating motor 23, a sliding guide rail 24, a bracket 25, a motor wheel shaft 26, a locking plate 27, an anti-collision spring 28, a pull frame 29, a first pull buckle 30, a fixed seat 31, an adjusting groove 32 and a fifth pull buckle 33.
Detailed Description
The following describes embodiments of the present invention with reference to the drawings and preferred embodiments.
Referring to fig. 1, the construction device of pile foundation engineering includes a base 1, a support frame mechanism and a pile transfer mechanism are installed on the base 1, a weight 18 is installed on both sides of the support frame mechanism, an adjusting groove 32 is installed in the base 1, a first pull plate 16 and a second pull plate 17 are installed in the adjusting groove 32, the support frame mechanism includes a vertical column 2 vertically installed on the base 1, a pull frame 29 fixedly installed on the vertical column 2 through a locking plate 27, a first pull buckle 30 and a second pull buckle 13 located on both sides of the pull frame 29, the pile transfer mechanism includes a cushion frame 3 installed on the base 1, a lifting cylinder 4 located on the cushion frame 3, a lifting seat 5 sleeved with the lifting cylinder 4, a hack lever 10 located on the lifting seat 5, a boom 7 connected with the hack lever 10, a pile driver 8 located on the boom 7, and a pile 9, the suspension arm 7 is provided with a third pull buckle 11, the upright post 2 is provided with a sliding guide rail 24 along the length direction, the sliding guide rail 24 is internally provided with a motor wheel shaft 26, the motor wheel shaft 26 is connected with a support 25, the support 25 is connected with a rotating motor 23 through a fixed seat 31, the rotating motor 23 is connected with a drill rod 22 in a driving way, the drill rod 22 drills into the ground surface under the action of the rotating motor 23, the first pull plate 16 and the second pull plate 17 are respectively provided with a fourth pull buckle 15 and a fifth pull buckle 33, a first cable 21 is connected between the first pull buckle 30 and the fourth pull buckle 15, a second cable 12 is connected between the second pull buckle 13 and the third pull buckle 11, a third cable 14 is connected between the second pull buckle 13 and the fifth pull buckle 33, and a fourth cable 6 is connected between the third pull buckle 11 and the fifth pull buckle 33, a triangular structure is formed among the third cable 14, the fourth cable 6 and the second cable 12, before pile driving, the motor wheel shaft 26 is started to drive the support 25, the fixed seat 31 and the rotating motor 23 to integrally move up to an optimal position, the rotating motor 23 is started to drive the drill rod 22 to rotate, the motor wheel shaft 26 drives the support 25, the fixed seat 31 and the rotating motor 23 to slowly descend towards the ground while rotating, the drill rod 22 is drilled into the ground, the pressing code 18 is pressed to play a role of gravity support, the first cable 21, the second cable 12, the third cable 14 and the fourth cable 6 are respectively connected and tensioned, the pile driver 8 is started to drive the pile column 9 to carry out pile foundation construction, and therefore the structure is more stable, construction safety accidents of dumping are not easy to happen, and safety is higher, and the first cable 21 is adjusted by the first pull plate 16 and the second pull plate 17, The positions of the second cable 12, the third cable 14 and the fourth cable 6 are more convenient.
Furthermore, the upper side and the lower side in the sliding guide rail 24 are provided with anti-collision springs 28, so that the equipment is prevented from being damaged by collision.
Furthermore, the two sides in the adjusting groove 32 are provided with the limiting blocks 20, so that an anti-collision effect is achieved.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (4)

1. Construction equipment of pile foundation engineering, including base (1), its characterized in that, base (1) on install the carriage mechanism and change a mechanism, carriage mechanism both sides all be provided with and press sign indicating number (18), base (1) in be provided with adjustment tank (32), adjustment tank (32) in install first arm-tie (16) and second arm-tie (17), carriage mechanism including vertical stand (2) of installing on base (1), through jam plate (27) fixed mounting in stand (2) on pull frame (29), be located pull frame (29) left and right sides first fastener (30) and second fastener (13), change a mechanism including install in base (1) on cushion (3), be located lift cylinder (4) on cushion (3), with lift cylinder (4) the lift seat (5) that cup joints, The lifting device comprises a frame rod (10) positioned on a lifting seat (5), a lifting arm (7) connected with the frame rod (10), a pile driver (8) and a pile column (9) positioned on the lifting arm (7), wherein a third pull buckle (11) is arranged on the lifting arm (7).
2. The pile foundation engineering construction device according to claim 1, wherein the upright column (2) is provided with a sliding guide rail (24) along the length direction, a motor wheel shaft (26) is assembled in the sliding guide rail (24), the motor wheel shaft (26) is connected with a support (25), the support (25) is connected with a rotating motor (23) through a fixing seat (31), the rotating motor (23) is connected with a drill rod (22) in a driving mode, and the drill rod (22) is driven by the rotating motor (23) to drill into the ground surface.
3. The pile foundation engineering construction device according to claim 1, wherein a fourth pulling buckle (15) and a fifth pulling buckle (33) are respectively arranged in the first pulling plate (16) and the second pulling plate (17), a first cable (21) is connected between the first pulling buckle (30) and the fourth pulling buckle (15), a second cable (12) is connected between the second pulling buckle (13) and the third pulling buckle (11), a third cable (14) is connected between the second pulling buckle (13) and the fifth pulling buckle (33), a fourth cable (6) is connected between the third pulling buckle (11) and the fifth pulling buckle (33), and a triangular structure is formed among the third cable (14), the fourth cable (6) and the second cable (12).
4. The pile foundation engineering construction device according to claim 2, wherein the slide rail (24) is provided with anti-collision springs (28) at upper and lower sides thereof.
CN202120120384.6U 2021-01-18 2021-01-18 Construction device for pile foundation engineering Active CN214328861U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120120384.6U CN214328861U (en) 2021-01-18 2021-01-18 Construction device for pile foundation engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120120384.6U CN214328861U (en) 2021-01-18 2021-01-18 Construction device for pile foundation engineering

Publications (1)

Publication Number Publication Date
CN214328861U true CN214328861U (en) 2021-10-01

Family

ID=77909710

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120120384.6U Active CN214328861U (en) 2021-01-18 2021-01-18 Construction device for pile foundation engineering

Country Status (1)

Country Link
CN (1) CN214328861U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114778806A (en) * 2022-04-13 2022-07-22 国网江苏省电力有限公司连云港供电分公司 Model test device of slip casting formula screw pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114778806A (en) * 2022-04-13 2022-07-22 国网江苏省电力有限公司连云港供电分公司 Model test device of slip casting formula screw pile
CN114778806B (en) * 2022-04-13 2023-11-14 国网江苏省电力有限公司连云港供电分公司 Model test device of slip casting formula screw pile

Similar Documents

Publication Publication Date Title
CN113062758B (en) Anchor rod construction device for civil engineering
CN214328861U (en) Construction device for pile foundation engineering
CN102587826A (en) Drill arm assembly for multifunctional road pile drilling machine
CN213569218U (en) Combined light crane
CN207211884U (en) A kind of two layers of three-dimensional parking device
CN219327294U (en) Platform lifting device
CN102815649B (en) Bushing-type aerial working platform with depression-prevention tilting device
CN210946504U (en) Support bracket for highway bridge
CN117071560A (en) Positioning and supporting device for construction of prefabricated pipe piles
CN201206097Y (en) Pothole and tilting proof apparatus for lifting machine
CN214832646U (en) Traction drive pile driver and self-propelled traction drive pile driver
CN211773643U (en) Pile driver for civil engineering
CN112127362A (en) Building construction pile driver equipment
CN202544738U (en) Drilling arm assembly of multifunctional road pile drilling machine
CN210499074U (en) Concave bottom lifting type roller device
CN210002402U (en) hydraulic drilling and pile-rotating equipment
CN102815648B (en) Scissor aerial work platform with cavity incline resistant device
CN2542523Y (en) Lifting platform for car
CN215888231U (en) Pile driver for civil engineering of transformer substation
CN102807179B (en) Mast-type aerial work platform with anti-hollow oblique device
CN111591200A (en) Accident car special trailer based on motor control goes up and down
CN220888641U (en) Pile driver with buffer
CN216950239U (en) Drilling mechanism and highway guardrail breakdown van
CN220618342U (en) Workover vehicle
CN218969998U (en) Multi-angle and azimuth integrated pile driver

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant