CN117071560A - A kind of prefabricated pipe pile construction positioning support device - Google Patents

A kind of prefabricated pipe pile construction positioning support device Download PDF

Info

Publication number
CN117071560A
CN117071560A CN202311095862.2A CN202311095862A CN117071560A CN 117071560 A CN117071560 A CN 117071560A CN 202311095862 A CN202311095862 A CN 202311095862A CN 117071560 A CN117071560 A CN 117071560A
Authority
CN
China
Prior art keywords
clamping
lifting
pipe pile
hoisting
positioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311095862.2A
Other languages
Chinese (zh)
Inventor
雷金波
钟昊晔
张存健
郭杨
乐腾胜
程金生
颜启龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanchang Hangkong University
Original Assignee
Nanchang Hangkong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanchang Hangkong University filed Critical Nanchang Hangkong University
Priority to CN202311095862.2A priority Critical patent/CN117071560A/en
Publication of CN117071560A publication Critical patent/CN117071560A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention provides a positioning and supporting device for construction of a precast tubular pile, which relates to the technical field of pile foundation construction and comprises the following components: the lifting mechanism comprises a portal frame, a lifting cross beam is arranged in the portal frame, and a lifting hook is arranged at the bottom of the lifting cross beam; the clamping assembly comprises two clamping vertical rods, clamping blocks are arranged at the lower ends of the clamping vertical rods, lifting connecting rods are connected to the tops of the clamping vertical rods, and the two lifting connecting rods are rotatably arranged on the connecting rotating shafts; and the lifting assembly is arranged on the working platform and is connected with the connecting rotating shaft. The device can realize self-adaptive clamping and fixing according to the diameters of different tubular piles, thereby ensuring the stability of tubular pile construction and positioning, greatly improving the working efficiency and positioning precision of tubular pile positioning construction, and having simple operation and convenient use.

Description

一种预制管桩施工定位支撑装置A kind of prefabricated pipe pile construction positioning support device

技术领域Technical field

本发明属于桩基施工技术领域,尤其涉及一种预制管桩施工定位支撑装置。The invention belongs to the technical field of pile foundation construction, and in particular relates to a prefabricated pipe pile construction positioning support device.

背景技术Background technique

随着建筑业水平的不断提升,预制管桩得到了广泛应用,桩基础的承载能力高,能承受竖直荷载,也能承受水平荷载,能抵抗上拔荷载也能承受振动荷载,是应用最广泛的深基础形式。桩基础的施工质量对上部结构的安全和稳定性起到至关重要的作用,其施工过程中的桩位偏差和桩身垂直度将会对其工程整体质量产生重要影响,因此,在预制管桩施工过程中,控制其水平平面内位置偏差和垂直度偏差,是桩基础施工过程中的关键要素。With the continuous improvement of the construction industry, prefabricated pipe piles have been widely used. The pile foundation has a high bearing capacity, can withstand vertical loads, can also withstand horizontal loads, can resist uplift loads and withstand vibration loads, and is the most widely used. Extensive deep base form. The construction quality of the pile foundation plays a vital role in the safety and stability of the superstructure. The pile position deviation and pile verticality during the construction process will have an important impact on the overall quality of the project. Therefore, in the precast pipe During the pile construction process, controlling the position deviation and verticality deviation in the horizontal plane is a key element in the pile foundation construction process.

现有传统桩基础定位通常先采用仪器测设桩基础的中心位置,做好标识,之后吊桩入位,在打桩操作过程中,主要由工人通过观察控制桩身位置,通过上部吊点的起吊,对桩身位置进行调整,由于桩身在吊起过程中,只有桩身上部一个固定点,桩身下部一直处于自由摆动的状态,使得调整桩身的平面位置和桩身的垂直度变得极为困难,对操作工人的施工经验和技术水平要求较高,成桩的平面位置偏差和桩身垂直度通常由工人的技术水平与责任心所决定,施工质量和精度难以把控,易发生桩位偏差过大等不符合规范行为,造成较大的经济和工期损失。The existing traditional pile foundation positioning usually uses instruments to measure the center position of the pile foundation and mark it, and then the piles are lifted into position. During the piling operation, the position of the pile body is mainly controlled by workers through observation and lifting of the upper lifting point. , adjust the position of the pile body. Since the pile body has only one fixed point on the upper part of the pile body during the lifting process, the lower part of the pile body is always in a free swing state, making it difficult to adjust the plane position of the pile body and the verticality of the pile body. It is extremely difficult and requires high construction experience and technical level of operators. The plane position deviation of the pile and the verticality of the pile body are usually determined by the technical level and sense of responsibility of the workers. The construction quality and accuracy are difficult to control, and piles are prone to occur. Excessive position deviation and other non-compliant behaviors will cause greater economic and construction period losses.

发明内容Contents of the invention

本发明实施例的目的在于提供一种预制管桩施工定位支撑装置,旨在解决现有技术中所述的问题。The purpose of the embodiments of the present invention is to provide a prefabricated pipe pile construction positioning support device, aiming to solve the problems described in the prior art.

本发明实施例是这样实现的,一种预制管桩施工定位支撑装置,包括工作平台,所述工作平台的底部设置有移动机构,且所述工作平台转动安装于移动机构上,还包括:The embodiment of the present invention is implemented in this way. A prefabricated pipe pile construction positioning support device includes a working platform. The bottom of the working platform is provided with a moving mechanism, and the working platform is rotationally mounted on the moving mechanism. It also includes:

吊装机构,所述吊装机构包括安装于工作平台上的龙门架,所述龙门架中沿竖直方向滑动安装有吊装横梁,且所述工作平台在吊装横梁竖直投影的区域开设有吊装工位(槽状),所述吊装横梁的底部设置有吊钩;Hoisting mechanism, the hoisting mechanism includes a gantry installed on a working platform, a lifting beam is slidably installed in the gantry in the vertical direction, and the working platform is provided with a lifting station in the area where the lifting beam is vertically projected. (Trough-shaped), the bottom of the lifting beam is provided with a hook;

夹持组件,所述夹持组件用于对吊装于吊钩处的管桩进行自适应夹持,所述夹持组件包括两个对称安装于吊装横梁中的夹持立杆,且所述夹持立杆沿水平方向滑动安装于吊装横梁中,且两个所述夹持立杆均通过弹性复位元件与吊装横梁的内部连接,两个所述夹持立杆的下端均安装有一个夹持块,且两个所述夹持块相对安装于夹持立杆上,两个所述夹持立杆的顶部均转动连接有一个起吊连杆,两个所述起吊连杆远离夹持立杆的一端均转动安装于连接转轴上;以及Clamping assembly, the clamping assembly is used to adaptively clamp the pipe piles hoisted at the hook, the clamping assembly includes two clamping poles symmetrically installed in the hoisting beam, and the clamping The holding pole is slidably installed in the hoisting beam in the horizontal direction, and the two clamping poles are connected to the interior of the hoisting beam through elastic return elements. A clamping pole is installed at the lower end of the two clamping poles. block, and the two clamping blocks are relatively installed on the clamping pole. The tops of the two clamping poles are rotatably connected with a lifting link, and the two lifting links are away from the clamping pole. One end of each is rotatably mounted on the connecting shaft; and

起吊组件,所述起吊组件安装于工作平台上,且所述起吊组件与连接转轴连接,所述起吊组件用于带动夹持组件对管桩的侧壁进行自适应夹持,并同步带动吊装横梁对被夹持住的管桩进行安装定位。Lifting assembly, the lifting assembly is installed on the working platform, and the lifting assembly is connected to the connecting shaft. The lifting assembly is used to drive the clamping assembly to adaptively clamp the side wall of the pipe pile, and to synchronously drive the lifting beam. Install and position the clamped pipe piles.

进一步的技术方案,所述吊装横梁的两侧均转动安装有导向滚轮,且所述龙门架上开设有用于供导向滚轮进行竖直方向上的线性滑动的导向滑槽。In a further technical solution, guide rollers are rotatably installed on both sides of the hoisting beam, and a guide chute is provided on the gantry for linear sliding of the guide rollers in the vertical direction.

进一步的技术方案,所述弹性复位元件可以为复位弹簧或是弹性伸缩杆,且当装置处于自由状态时,所述弹性复位元件的弹性恢复力会使得两个所述夹持立杆的之间的间距最大化。In a further technical solution, the elastic return element can be a return spring or an elastic telescopic rod, and when the device is in a free state, the elastic restoring force of the elastic return element will cause the gap between the two clamping poles to Maximize the spacing.

进一步的技术方案,所述起吊组件包括安装于工作平台上的收卷辊,所述收卷辊连接有驱动电机,通过驱动电机带动收卷辊进行旋转,所述收卷辊上收卷有收卷绳,所述龙门架的顶部安装有定滑轮,且所述收卷绳绕接过定滑轮并与连接转轴连接。In a further technical solution, the lifting assembly includes a rewinding roller installed on the working platform. The rewinding roller is connected to a drive motor, and the drive motor drives the rewinding roller to rotate. There is a rewinding device on the rewinding roller. The winding rope is equipped with a fixed pulley on the top of the gantry, and the winding rope is wound around the fixed pulley and connected to the connecting rotating shaft.

进一步的技术方案,所述连接转轴上安装有吊环,且所述收卷绳的一端通过吊环与连接转轴连接。In a further technical solution, a lifting ring is installed on the connecting rotating shaft, and one end of the winding rope is connected to the connecting rotating shaft through a lifting ring.

进一步的技术方案,所述工作平台的底部还设置有用于对工作平台进行辅助支撑的辅助支撑组件,且所述工作平台的底部两两对称安装有四组辅助支撑组件。In a further technical solution, the bottom of the working platform is also provided with auxiliary support components for auxiliary support of the working platform, and four sets of auxiliary support components are installed symmetrically on the bottom of the working platform.

进一步的技术方案,所述辅助支撑组件包括转动安装于工作平台底壁上的支撑板和第一伸缩元件,且所述第一伸缩元件的活动端与支撑板的侧壁连接,所述支撑板的自由端安装有第二伸缩元件,所述第二伸缩元件的底部连接有支撑底盘。In a further technical solution, the auxiliary support assembly includes a support plate rotatably mounted on the bottom wall of the work platform and a first telescopic element, and the movable end of the first telescopic element is connected to the side wall of the support plate, and the support plate The free end of the second telescopic element is installed with a second telescopic element, and the bottom of the second telescopic element is connected to a supporting chassis.

进一步的技术方案,所述第一伸缩元件和第二伸缩元件均为液压伸缩杆。In a further technical solution, the first telescopic element and the second telescopic element are both hydraulic telescopic rods.

进一步的技术方案,所述移动机构采用承载能力强的履带式移动机构。In a further technical solution, the moving mechanism adopts a crawler-type moving mechanism with strong carrying capacity.

本发明实施例的另一目的在于,提供一种预制管桩施工定位方法,基于上述的预制管桩施工定位支撑装置,包括以下具体步骤:Another object of the embodiment of the present invention is to provide a prefabricated pipe pile construction positioning method. Based on the above-mentioned prefabricated pipe pile construction positioning support device, it includes the following specific steps:

步骤1、先通过第一伸缩元件的伸缩运动带动第二伸缩元件进行转动,从而将第二伸缩元件调节至指定的位置,然后通过控制第二伸缩元件的伸缩量,使得支撑底盘与地面稳定接触,从而对工作平台进行稳定的支撑;Step 1. First, the telescopic movement of the first telescopic element drives the second telescopic element to rotate, thereby adjusting the second telescopic element to the designated position. Then, by controlling the telescopic amount of the second telescopic element, the supporting chassis is in stable contact with the ground. , thereby providing stable support to the working platform;

步骤2、通过起吊组件将吊装横梁下放至指定的高度,然后将吊装工位处的管桩吊装于吊钩上,通过驱动电机带动收卷辊对收卷绳进行收卷,收卷绳会通过吊环带动连接转轴向上运动,连接转轴通过起吊连杆带动两个夹持立杆同时相向运动,夹持立杆带动两个夹持块相互靠近,从而对待吊装的管桩的侧壁进行夹持;Step 2. Lower the hoisting beam to the specified height through the lifting component, then hoist the pipe pile at the hoisting station on the hook, drive the motor to drive the rewinding roller to rewind the rewinding rope, and the rewinding rope will pass through The lifting ring drives the connecting shaft to move upward, and the connecting shaft drives the two clamping poles to move toward each other at the same time through the lifting connecting rod. The clamping pole drives the two clamping blocks to approach each other, thereby clamping the side wall of the pipe pile to be lifted;

步骤3、当管桩的侧壁被夹持固定住后,夹持立杆带动吊装横梁整体向上移动,吊装横梁通过吊钩带动管桩同步上升,即可实现对管桩的起吊,然后将管桩移动至指定的安装位置进行下放;Step 3. After the side wall of the pipe pile is clamped and fixed, the clamping pole drives the lifting beam to move upward as a whole. The lifting beam drives the pipe pile to rise synchronously through the hook, so that the pipe pile can be lifted, and then the pipe is lifted. The piles are moved to the designated installation position for lowering;

步骤4、当管桩下放到位后,吊装横梁在管桩的支撑作用下便不再向下运动,而此时随着收卷绳的继续放卷,弹性复位元件会带动夹持立杆向远离管桩的一侧滑动,夹持立杆带动夹持块自动与管桩脱离,即完成管桩的定位安装。Step 4. When the pipe pile is lowered into place, the lifting beam will no longer move downward under the support of the pipe pile. At this time, as the winding rope continues to be unrolled, the elastic reset element will drive the clamping pole away from the One side of the pipe pile slides, and the clamping pole drives the clamping block to automatically separate from the pipe pile, which completes the positioning and installation of the pipe pile.

有益效果beneficial effects

本发明实施例提供的一种预制管桩施工定位支撑装置,先通过起吊组件将吊装横梁下放至指定的高度,然后将管桩的顶部吊装于吊钩上,再通过起吊组件对管桩进行起吊,在此过程中,由于管桩的重力作用,起吊组件会首先带动连接转轴向上运动,连接转轴通过起吊连杆带动两个夹持立杆同时相向运动,通过夹持立杆带动两个夹持块相互靠近,以实现对待吊装的管桩的侧壁进行夹持,且当夹持块与管桩的侧壁接触后,夹持立杆便不在进行滑动,从而达到根据管桩的直径进行自适应夹持的目的。当管桩的侧壁被夹持固定住后,夹持立杆可带动吊装横梁整体向上移动,吊装横梁通过吊钩带动管桩同步上升,即可实现对管桩的起吊。在进行下放管桩的过程中,由于管桩的重力作用,夹持组件会始终保持稳定的夹持状态,从而保证在进行管桩的定位安装时,管桩不会发生摆动。在进行下放管桩的过程中,由于管桩的重力作用,夹持组件会始终保持稳定的夹持状态,从而保证在进行管桩的定位安装时,管桩不会发生摆动,大大提高了管桩定位施工的工作效率和定位精度。当管桩下放到位后,吊装横梁在管桩的支撑作用下便不再向下运动,而此时随着收卷绳的继续放卷,弹性复位元件会带动夹持立杆向远离管桩的一侧滑动,夹持立杆带动夹持块自动与管桩脱离,即可进行后续的施工操作。该装置能够根据不同的管桩的直径实现自适应夹持和固定,从而保证管桩施工定位时的稳定性,大大提高了管桩定位施工的工作效率和定位精度,操作简单,便于使用。A prefabricated pipe pile construction positioning support device provided by an embodiment of the present invention first lowers the lifting beam to a specified height through a lifting assembly, then hoists the top of the pipe pile on the hanging hook, and then lifts the pipe pile through the lifting assembly. , during this process, due to the gravity of the pipe pile, the lifting component will first drive the connecting shaft to move upward. The connecting shaft drives the two clamping poles to move toward each other at the same time through the lifting connecting rod, and the two clamping poles are driven by the clamping pole. The blocks are close to each other to clamp the side wall of the pipe pile to be hoisted, and when the clamping block contacts the side wall of the pipe pile, the clamping pole will no longer slide, thereby achieving automatic adjustment according to the diameter of the pipe pile. Adapted to clamping purposes. When the side wall of the pipe pile is clamped and fixed, the clamping pole can drive the lifting beam to move upward as a whole. The lifting beam drives the pipe pile to rise synchronously through the hook, so that the pipe pile can be lifted. During the process of lowering the pipe pile, due to the gravity of the pipe pile, the clamping assembly will always maintain a stable clamping state, thereby ensuring that the pipe pile will not swing when positioning and installing the pipe pile. During the process of lowering the pipe pile, due to the gravity of the pipe pile, the clamping assembly will always maintain a stable clamping state, thereby ensuring that the pipe pile will not swing during the positioning and installation of the pipe pile, which greatly improves the efficiency of the pipe pile. Work efficiency and positioning accuracy of pile positioning construction. When the pipe pile is lowered into place, the lifting beam will no longer move downward under the support of the pipe pile. At this time, as the winding rope continues to be unrolled, the elastic reset element will drive the clamping pole away from the pipe pile. Sliding on one side, the clamping pole drives the clamping block to automatically separate from the pipe pile, and subsequent construction operations can be carried out. This device can realize adaptive clamping and fixing according to the diameter of different pipe piles, thereby ensuring the stability of pipe pile positioning during construction, greatly improving the work efficiency and positioning accuracy of pipe pile positioning construction, and is simple to operate and easy to use.

附图说明Description of the drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图示出的结构获得其他的附图。In order to explain the embodiments of the present invention or the technical solutions in the prior art more clearly, the drawings needed to be used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings in the following description are only These are some embodiments of the present invention. For those of ordinary skill in the art, other drawings can be obtained based on the structures shown in these drawings without exerting creative efforts.

图1为本发明实施例提供的一种预制管桩施工定位支撑装置的结构示意图;Figure 1 is a schematic structural diagram of a prefabricated pipe pile construction positioning support device provided by an embodiment of the present invention;

图2为本发明实施例提供的一种预制管桩施工定位支撑装置中的吊装横梁与导向滚轮配合的结构示意图;Figure 2 is a schematic structural diagram of the cooperation between the hoisting beam and the guide roller in a prefabricated pipe pile construction positioning support device provided by an embodiment of the present invention;

图3为本发明实施例提供的一种预制管桩施工定位支撑装置中的夹持组件的结构示意图;Figure 3 is a schematic structural diagram of a clamping component in a prefabricated pipe pile construction positioning support device provided by an embodiment of the present invention;

图4为本发明实施例提供的一种预制管桩施工定位支撑装置中的夹持组件的结局部剖视图;Figure 4 is a sectional view of the end portion of the clamping assembly in a prefabricated pipe pile construction positioning support device provided by an embodiment of the present invention;

图5为本发明实施例提供的一种预制管桩施工定位支撑装置中的辅助支撑组件的结构示意图;Figure 5 is a schematic structural diagram of an auxiliary support component in a prefabricated pipe pile construction positioning support device provided by an embodiment of the present invention;

图6为本发明实施例提供的一种预制管桩施工定位支撑装置中的图1的A处放大图。Figure 6 is an enlarged view of position A in Figure 1 in a prefabricated pipe pile construction positioning support device provided by an embodiment of the present invention.

附图中:工作平台1;移动机构11;吊装工位12;辅助支撑组件2;支撑板21;第一伸缩元件22;第二伸缩元件23;支撑底盘24;吊装机构3;龙门架31;吊装横梁32;吊钩33;导向滚轮34;导向滑槽35;夹持组件4;吊环41;连接转轴42;起吊连杆43;夹持立杆44;弹性复位元件45;夹持块46;起吊组件5;收卷辊51;收卷绳52;定滑轮53。In the drawings: working platform 1; moving mechanism 11; hoisting station 12; auxiliary support assembly 2; support plate 21; first telescopic element 22; second telescopic element 23; support chassis 24; hoisting mechanism 3; gantry 31; Lifting beam 32; hook 33; guide roller 34; guide chute 35; clamping component 4; lifting ring 41; connecting shaft 42; lifting link 43; clamping vertical rod 44; elastic return element 45; clamping block 46; Lifting component 5; rewinding roller 51; rewinding rope 52; fixed pulley 53.

本发明目的的实现、功能特点及优点将结合实施例,参照附图做进一步说明。The realization of the purpose, functional features and advantages of the present invention will be further described with reference to the embodiments and the accompanying drawings.

具体实施方式Detailed ways

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention and are not intended to limit the present invention.

以下结合具体实施例对本发明的具体实现进行详细描述。The specific implementation of the present invention will be described in detail below with reference to specific embodiments.

如图1-4所示,为本发明一个实施例提供的一种预制管桩施工定位支撑装置,包括工作平台1,所述工作平台1的底部设置有移动机构11,且所述工作平台1转动安装于移动机构11上,还包括:As shown in Figures 1-4, a prefabricated pipe pile construction positioning support device provided by one embodiment of the present invention includes a working platform 1. The bottom of the working platform 1 is provided with a moving mechanism 11, and the working platform 1 Rotated on the moving mechanism 11, it also includes:

吊装机构3,所述吊装机构3包括安装于工作平台1上的龙门架31,所述龙门架31中沿竖直方向滑动安装有吊装横梁32,且所述工作平台1在吊装横梁32竖直投影的区域开设有吊装工位12(槽状),所述吊装横梁32的底部设置有吊钩33;Hoisting mechanism 3. The hoisting mechanism 3 includes a gantry 31 installed on the working platform 1. A lifting beam 32 is slidably installed in the gantry 31 in the vertical direction, and the working platform 1 is vertically connected to the lifting beam 32. A lifting station 12 (trough-shaped) is provided in the projected area, and a hook 33 is provided at the bottom of the lifting beam 32;

夹持组件4,所述夹持组件4用于对吊装于吊钩33处的管桩进行自适应夹持,所述夹持组件4包括两个对称安装于吊装横梁32中的夹持立杆44,且所述夹持立杆44沿水平方向滑动安装于吊装横梁32中,两个所述夹持立杆44均通过弹性复位元件45与吊装横梁32的内部连接,两个所述夹持立杆44的下端均安装有一个夹持块46,且两个所述夹持块46相对安装于夹持立杆44上,两个所述夹持立杆44的顶部均转动连接有一个起吊连杆43,两个所述起吊连杆43远离夹持立杆44的一端均转动安装于连接转轴42上;以及The clamping assembly 4 is used to adaptively clamp the pipe piles hoisted at the hook 33. The clamping assembly 4 includes two clamping poles symmetrically installed in the hoisting beam 32. 44, and the clamping poles 44 are slidably installed in the hoisting beam 32 in the horizontal direction. The two clamping poles 44 are connected to the interior of the hoisting beam 32 through elastic reset elements 45. A clamping block 46 is installed at the lower end of the vertical pole 44, and the two clamping blocks 46 are relatively installed on the clamping vertical pole 44. The tops of the two clamping vertical poles 44 are rotatably connected to a lifting device. Connecting rod 43, one end of the two lifting connecting rods 43 away from the clamping pole 44 is rotatably installed on the connecting shaft 42; and

起吊组件5,所述起吊组件5安装于工作平台1上,且所述起吊组件5与连接转轴42连接,所述起吊组件5用于带动夹持组件4对管桩的侧壁进行自适应夹持,并同步带动吊装横梁32对被夹持住的管桩进行安装定位。Lifting component 5, the lifting component 5 is installed on the working platform 1, and the lifting component 5 is connected to the connecting shaft 42. The lifting component 5 is used to drive the clamping component 4 to adaptively clamp the side wall of the pipe pile. Hold, and simultaneously drive the lifting beam 32 to install and position the clamped pipe pile.

在本发明实施例中,通过设置吊装工位12可使得龙门架31的安装位置尽可能地靠近工作平台1的中心处,进而保证进行吊装工作时,装置整体的重心尽可能地靠近工作平台1的中心,从而提升装置的稳定性。使用时,先通过起吊组件5将吊装横梁32下放至指定的高度,然后将管桩的顶部吊装于吊钩33上。然后通过起吊组件5对管桩进行起吊,在此过程中,由于管桩的重力作用,起吊组件5会首先带动连接转轴42向上运动,连接转轴42通过起吊连杆43带动两个夹持立杆44同时相向运动,通过夹持立杆44带动两个夹持块46相互靠近,以实现对待吊装的管桩的侧壁进行夹持,且当夹持块46与管桩的侧壁接触后,夹持立杆44便不在进行滑动,从而达到根据管桩的直径进行自适应夹持的目的。当管桩的侧壁被夹持固定住后,夹持立杆44可带动吊装横梁32整体向上移动,吊装横梁32通过吊钩33带动管桩同步上升,即可实现对管桩的起吊。在进行下放管桩的过程中,由于管桩的重力作用,夹持组件4会始终保持稳定的夹持状态,从而保证在进行管桩的定位安装时,管桩不会发生摆动,大大提高了管桩定位施工的工作效率和定位精度。在进行下放管桩的过程中,由于管桩的重力作用,夹持组件4会始终保持稳定的夹持状态,从而保证在进行管桩的定位安装时,管桩不会发生摆动,大大提高了管桩定位施工的工作效率和定位精度。当管桩下放到位后,吊装横梁32在管桩的支撑作用下便不再向下运动,而此时随着收卷绳的继续放卷,弹性复位元件45会带动夹持立杆44向远离管桩的一侧滑动,夹持立杆44带动夹持块46自动与管桩脱离,即可进行后续的施工操作。In the embodiment of the present invention, by setting the hoisting station 12, the installation position of the gantry 31 can be as close as possible to the center of the working platform 1, thereby ensuring that the center of gravity of the entire device is as close as possible to the working platform 1 during hoisting work. center, thus improving the stability of the device. When in use, the lifting beam 32 is first lowered to a specified height through the lifting assembly 5, and then the top of the pipe pile is hoisted on the hook 33. Then the pipe pile is lifted by the lifting assembly 5. During this process, due to the gravity of the pipe pile, the lifting assembly 5 will first drive the connecting shaft 42 to move upward. The connecting shaft 42 drives the two clamping poles through the lifting connecting rod 43. 44 move toward each other at the same time, and the two clamping blocks 46 are driven close to each other by clamping the vertical rod 44 to clamp the side wall of the pipe pile to be hoisted, and when the clamping block 46 contacts the side wall of the pipe pile, The clamping pole 44 no longer slides, thereby achieving the purpose of adaptive clamping according to the diameter of the pipe pile. When the side wall of the pipe pile is clamped and fixed, the clamping pole 44 can drive the hoisting beam 32 to move upward as a whole. The hoisting beam 32 drives the pipe pile to rise synchronously through the hook 33, so that the pipe pile can be lifted. During the process of lowering the pipe pile, due to the gravity of the pipe pile, the clamping assembly 4 will always maintain a stable clamping state, thereby ensuring that the pipe pile will not swing when positioning and installing the pipe pile, which greatly improves the efficiency of the pipe pile. Work efficiency and positioning accuracy of pipe pile positioning construction. During the process of lowering the pipe pile, due to the gravity of the pipe pile, the clamping assembly 4 will always maintain a stable clamping state, thereby ensuring that the pipe pile will not swing when positioning and installing the pipe pile, which greatly improves the efficiency of the pipe pile. Work efficiency and positioning accuracy of pipe pile positioning construction. When the pipe pile is lowered into place, the hoisting beam 32 will no longer move downward under the support of the pipe pile. At this time, as the winding rope continues to be unrolled, the elastic reset element 45 will drive the clamping pole 44 away. One side of the pipe pile slides, and the clamping pole 44 drives the clamping block 46 to automatically separate from the pipe pile, and subsequent construction operations can be performed.

如图1和图2所示,作为本发明的一种优选实施例,所述吊装横梁32的两侧均转动安装有导向滚轮34,且所述龙门架31上开设有用于供导向滚轮34进行竖直方向上的线性滑动的导向滑槽35。As shown in Figures 1 and 2, as a preferred embodiment of the present invention, guide rollers 34 are rotatably installed on both sides of the lifting beam 32, and the gantry 31 is provided with a hole for the guide rollers 34 to carry out the operation. A linear sliding guide chute 35 in the vertical direction.

在本发明实施例中,在吊装横梁32上下运动的过程中,吊装横梁32可带动导向滚轮34在导向滑槽35中同步进行滑动,从而使得吊装横梁32在上下运动的过程中,不会与龙门架31之间产生相对晃动,保证安装定位时的稳定性。同时,导向滚轮34与导向滑槽35之间为滚动摩擦,部件之间磨损小,不会对吊装横梁32的运动过程产生阻尼作用。In the embodiment of the present invention, during the up and down movement of the hoisting cross beam 32, the hoisting cross beam 32 can drive the guide roller 34 to slide synchronously in the guide chute 35, so that the hoisting cross beam 32 will not interact with the hoisting cross beam 32 during its up and down movement. Relative shaking occurs between the gantry frames 31 to ensure stability during installation and positioning. At the same time, there is rolling friction between the guide roller 34 and the guide chute 35, and the wear between the components is small, which will not produce a damping effect on the movement process of the hoisting beam 32.

如图3和图4所示,作为本发明的一种优选实施例,所述弹性复位元件45可以为复位弹簧或是弹性伸缩杆,且当装置处于自由状态时,所述弹性复位元件45的弹性恢复力会使得两个所述夹持立杆44的之间的间距最大化。As shown in Figures 3 and 4, as a preferred embodiment of the present invention, the elastic return element 45 can be a return spring or an elastic telescopic rod, and when the device is in a free state, the elastic return element 45 The elastic restoring force will maximize the distance between the two clamping poles 44 .

如图1、图3、图4和图6所示,作为本发明的一种优选实施例,所述起吊组件5包括安装于工作平台1上的收卷辊51,所述收卷辊51连接有驱动电机,通过驱动电机带动收卷辊51进行旋转,所述收卷辊51上收卷有收卷绳52,所述龙门架31的顶部安装有定滑轮53,且所述收卷绳52绕接过定滑轮53并与连接转轴42连接。As shown in Figures 1, 3, 4 and 6, as a preferred embodiment of the present invention, the lifting assembly 5 includes a rewinding roller 51 installed on the working platform 1, and the rewinding roller 51 is connected to There is a driving motor, which drives the winding roller 51 to rotate. The winding roller 51 has a winding rope 52 wound on it. A fixed pulley 53 is installed on the top of the gantry 31, and the winding rope 52 It is wound around the fixed pulley 53 and connected to the connecting rotating shaft 42 .

在本发明实施例中,所述连接转轴42上安装有吊环41,且所述收卷绳52的一端连接于吊环41上。使用时,通过驱动电机带动收卷辊51进行收卷绳52的收卷(或放卷),收卷绳52通过吊环41可带动连接转轴42上下运动,从而实现对夹持组件4的调节。In the embodiment of the present invention, a lifting ring 41 is installed on the connecting shaft 42 , and one end of the retracting rope 52 is connected to the lifting ring 41 . During use, the winding roller 51 is driven by the drive motor to wind up (or unwind) the winding rope 52. The winding rope 52 can drive the connecting shaft 42 to move up and down through the lifting ring 41, thereby adjusting the clamping assembly 4.

如图1和图5所示,作为本发明的一种优选实施例,所述工作平台1的底部还设置有用于对工作平台1进行辅助支撑的辅助支撑组件2,且所述工作平台1的底部两两对称安装有四组辅助支撑组件2,从而增加工作平台1在吊装定位时的稳定性。As shown in Figures 1 and 5, as a preferred embodiment of the present invention, the bottom of the working platform 1 is also provided with an auxiliary support assembly 2 for auxiliary support of the working platform 1, and the working platform 1 Four sets of auxiliary support assemblies 2 are installed symmetrically on the bottom, thereby increasing the stability of the working platform 1 during hoisting and positioning.

在本发明实施例中,所述辅助支撑组件2包括转动安装于工作平台1底壁上的支撑板21和第一伸缩元件22,且所述第一伸缩元件22的活动端与支撑板21的侧壁连接,所述支撑板21的自由端安装有第二伸缩元件23,所述第二伸缩元件23的底部连接有支撑底盘24。具体的,所述第一伸缩元件22和第二伸缩元件23均为液压伸缩杆。In the embodiment of the present invention, the auxiliary support assembly 2 includes a support plate 21 rotatably installed on the bottom wall of the working platform 1 and a first telescopic element 22, and the movable end of the first telescopic element 22 is in contact with the support plate 21 The side walls are connected, the free end of the support plate 21 is installed with a second telescopic element 23, and the bottom of the second telescopic element 23 is connected with a support chassis 24. Specifically, the first telescopic element 22 and the second telescopic element 23 are both hydraulic telescopic rods.

在使用时,只需通过控制第二伸缩元件23的伸缩量,使得支撑底盘24与地面稳定接触。在四个支撑底盘24的配合作用下,便可对工作平台1进行稳定的支撑,防止装置整体在进行吊装定位时发生侧翻和倾斜,并且通过对个个相互独立的第二伸缩元件23的及时调节,可始终保持工作平台1处于水平状态,进而保证管桩定位时的水平度,减少依靠人工定位带来的操作误差。同时,在支撑底盘24与地面接触前,通过第一伸缩元件22的伸缩运动可带动第二伸缩元件23进行转动,从而调节支撑底盘24与地面接触的位置,可根据实际工作时的工作区域进行调节,提升装置操作灵活性和环境适应性。When in use, it is only necessary to control the telescopic amount of the second telescopic element 23 so that the supporting chassis 24 is in stable contact with the ground. With the cooperation of the four supporting chassis 24, the working platform 1 can be stably supported to prevent the entire device from rolling over and tilting during hoisting and positioning, and by adjusting the independent second telescopic elements 23 Timely adjustment can always keep the working platform 1 in a horizontal state, thereby ensuring the levelness of the pipe pile positioning and reducing operational errors caused by manual positioning. At the same time, before the support chassis 24 contacts the ground, the telescopic movement of the first telescopic element 22 can drive the second telescopic element 23 to rotate, thereby adjusting the position where the support chassis 24 contacts the ground, which can be adjusted according to the actual working area during work. Adjust to improve the device's operational flexibility and environmental adaptability.

如图1所示,作为本发明的一种优选实施例,所述移动机构11采用履带式移动机构,其承载能力强,且通过性好,便于在施工区域移动和作业。As shown in Figure 1, as a preferred embodiment of the present invention, the moving mechanism 11 adopts a crawler-type moving mechanism, which has strong carrying capacity and good passability, making it easy to move and operate in the construction area.

工作原理:在进行管桩施工定位前,先通过第一伸缩元件22的伸缩运动带动第二伸缩元件23进行转动,从而调节支撑底盘24与地面接触的位置,然后通过控制第二伸缩元件23的伸缩量,使得支撑底盘24与地面稳定接触,便可对工作平台1进行稳定的支撑。使用时,先通过起吊组件5将吊装横梁32下放至指定的高度,然后将管桩的顶部吊装于吊钩33上,便可通过起吊组件5对管桩进行起吊。具体的,通过驱动电机带动收卷辊51对收卷绳52进行收卷,在此过程中,由于管桩的重力作用,收卷绳52会通过吊环41带动连接转轴42向上运动,连接转轴42通过起吊连杆43带动两个夹持立杆44同时相向运动,通过夹持立杆44带动两个夹持块46相互靠近,两个夹持块46会对待吊装的管桩的侧壁进行夹持,且当夹持块46将管桩的侧壁稳定的夹持住以后,夹持立杆44便不在进行滑动,从而达到根据管桩的直径进行自适应夹持的目的。当管桩的侧壁被夹持固定住后,夹持立杆44可带动吊装横梁32整体向上移动,吊装横梁32通过吊钩33带动管桩同步上升,即可实现对管桩的起吊。在进行下放管桩的过程中,由于管桩的重力作用,夹持组件4会始终保持稳定的夹持状态,从而保证在进行管桩的定位安装时,管桩不会发生摆动,大大提高了管桩定位施工的工作效率和定位精度。当管桩下放到位后,吊装横梁32在管桩的支撑作用下便不再向下运动,而此时随着收卷绳的继续放卷,弹性复位元件45会带动夹持立杆44向远离管桩的一侧滑动,夹持立杆44带动夹持块46自动与管桩脱离,即可进行后续的施工操作。Working principle: Before positioning the pipe pile construction, the telescopic movement of the first telescopic element 22 drives the second telescopic element 23 to rotate, thereby adjusting the position of the support chassis 24 in contact with the ground, and then by controlling the movement of the second telescopic element 23. The amount of expansion and contraction ensures that the support chassis 24 is in stable contact with the ground, and the working platform 1 can be stably supported. When in use, the lifting beam 32 is first lowered to a specified height through the lifting assembly 5, and then the top of the pipe pile is hoisted on the lifting hook 33, and then the pipe pile can be lifted through the lifting assembly 5. Specifically, the driving motor drives the winding roller 51 to wind up the winding rope 52. During this process, due to the gravity of the pipe pile, the winding rope 52 drives the connecting shaft 42 to move upward through the lifting ring 41, and the connecting shaft 42 moves upward. The lifting connecting rod 43 drives the two clamping poles 44 to move toward each other at the same time. The clamping poles 44 drive the two clamping blocks 46 to approach each other. The two clamping blocks 46 clamp the side walls of the pipe pile to be lifted. and when the clamping block 46 stably clamps the side wall of the pipe pile, the clamping pole 44 will no longer slide, thereby achieving the purpose of adaptive clamping according to the diameter of the pipe pile. When the side wall of the pipe pile is clamped and fixed, the clamping pole 44 can drive the hoisting beam 32 to move upward as a whole. The hoisting beam 32 drives the pipe pile to rise synchronously through the hook 33, so that the pipe pile can be lifted. During the process of lowering the pipe pile, due to the gravity of the pipe pile, the clamping assembly 4 will always maintain a stable clamping state, thereby ensuring that the pipe pile will not swing when positioning and installing the pipe pile, which greatly improves the efficiency of the pipe pile. Work efficiency and positioning accuracy of pipe pile positioning construction. When the pipe pile is lowered into place, the hoisting beam 32 will no longer move downward under the support of the pipe pile. At this time, as the winding rope continues to be unrolled, the elastic reset element 45 will drive the clamping pole 44 away. One side of the pipe pile slides, and the clamping pole 44 drives the clamping block 46 to automatically separate from the pipe pile, and subsequent construction operations can be performed.

本发明实施例还公开了一种预制管桩施工定位方法,其是基于上述的预制管桩施工定位支撑装置,主要包括以下步骤:Embodiments of the present invention also disclose a prefabricated pipe pile construction positioning method, which is based on the above-mentioned prefabricated pipe pile construction positioning support device and mainly includes the following steps:

步骤1、先通过第一伸缩元件22的伸缩运动带动第二伸缩元件23进行转动,从而将第二伸缩元件23调节至指定的位置,然后通过控制第二伸缩元件23的伸缩量,使得支撑底盘24与地面稳定接触,从而对工作平台1进行稳定的支撑;Step 1: First, the telescopic movement of the first telescopic element 22 drives the second telescopic element 23 to rotate, thereby adjusting the second telescopic element 23 to a designated position, and then controlling the telescopic amount of the second telescopic element 23 to support the chassis. 24 is in stable contact with the ground to provide stable support to the working platform 1;

步骤2、通过起吊组件5将吊装横梁32下放至指定的高度,然后将吊装工位12处的管桩吊装于吊钩33上,通过驱动电机带动收卷辊51对收卷绳52进行收卷,收卷绳52会通过吊环41带动连接转轴42向上运动,连接转轴42通过起吊连杆43带动两个夹持立杆44同时相向运动,夹持立杆44带动两个夹持块46相互靠近,从而对待吊装的管桩的侧壁进行夹持;Step 2: lower the lifting beam 32 to the specified height through the lifting assembly 5, then hoist the pipe pile at the lifting station 12 on the hook 33, and drive the winding roller 51 through the drive motor to wind up the winding rope 52 , the take-up rope 52 will drive the connecting shaft 42 to move upward through the lifting ring 41, and the connecting shaft 42 will drive the two clamping poles 44 to move toward each other at the same time through the lifting link 43, and the clamping pole 44 will drive the two clamping blocks 46 to approach each other. , thereby clamping the side wall of the pipe pile to be lifted;

步骤3、当管桩的侧壁被夹持固定住后,夹持立杆44带动吊装横梁32整体向上移动,吊装横梁32通过吊钩33带动管桩同步上升,即可实现对管桩的起吊,然后将管桩移动至指定的安装位置进行下放;Step 3. After the side wall of the pipe pile is clamped and fixed, the clamping pole 44 drives the lifting beam 32 to move upward as a whole. The lifting beam 32 drives the pipe pile to rise synchronously through the hook 33, so that the pipe pile can be lifted. , and then move the pipe pile to the designated installation location for lowering;

步骤4、当管桩下放到位后,吊装横梁32在管桩的支撑作用下便不再向下运动,而此时随着收卷绳的继续放卷,弹性复位元件45会带动夹持立杆44向远离管桩的一侧滑动,夹持立杆44带动夹持块46自动与管桩脱离,即完成管桩的定位安装。Step 4. After the pipe pile is lowered into place, the lifting beam 32 will no longer move downward under the support of the pipe pile. At this time, as the winding rope continues to be unrolled, the elastic reset element 45 will drive the clamping pole. 44 slides to the side away from the pipe pile, and the clamping pole 44 drives the clamping block 46 to automatically separate from the pipe pile, thereby completing the positioning and installation of the pipe pile.

需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性地包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。It should be noted that in this article, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply that these entities or operations are mutually exclusive. any such actual relationship or sequence exists between them. Furthermore, the terms "comprises," "comprises," or any other variation thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that includes a list of elements includes not only those elements, but also those not expressly listed other elements, or elements inherent to the process, method, article or equipment.

尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, those of ordinary skill in the art will understand that various changes, modifications, and substitutions can be made to these embodiments without departing from the principles and spirit of the invention. and modifications, the scope of the invention is defined by the appended claims and their equivalents.

Claims (10)

1. The utility model provides a prefabricated tubular pile construction location strutting arrangement, includes work platform (1), the bottom of work platform (1) is provided with moving mechanism (11), just work platform (1) rotate and install on moving mechanism (11), its characterized in that still includes:
the lifting mechanism (3), the lifting mechanism (3) comprises a portal frame (31) arranged on the working platform (1), a lifting cross beam (32) is slidably arranged in the portal frame (31) along the vertical direction, and a lifting hook (33) is arranged at the bottom of the lifting cross beam (32);
the clamping assembly (4), the clamping assembly (4) is used for carrying out self-adaptive clamping on the pipe pile hoisted at the lifting hook (33), the clamping assembly (4) comprises two clamping vertical rods (44) symmetrically arranged in the hoisting cross beam (32), the clamping vertical rods (44) are slidably arranged in the hoisting cross beam (32) along the horizontal direction, the two clamping vertical rods (44) are connected with the inside of the hoisting cross beam (32) through elastic reset elements (45), one clamping block (46) is arranged at the lower end of each clamping vertical rod (44), the two clamping blocks (46) are oppositely arranged on the clamping vertical rods (44), the tops of the two clamping vertical rods (44) are rotatably connected with one hoisting connecting rod (43), and one ends of the two hoisting connecting rods (43) far away from the clamping vertical rods (44) are rotatably arranged on the connecting rotating shaft (42); and
lifting by crane subassembly (5), lifting by crane subassembly (5) install on work platform (1), just lifting by crane subassembly (5) are connected with connecting pivot (42), lifting by crane subassembly (5) are used for driving clamping component (4) and carry out self-adaptation centre gripping to the lateral wall of tubular pile to synchronous drive hoist and mount crossbeam (32) and install the location to the tubular pile that is held.
2. The precast tubular pile construction positioning and supporting device according to claim 1, wherein the working platform (1) is provided with a groove-shaped hoisting station (12) in a vertically projected area of the hoisting cross beam (32).
3. The positioning and supporting device for the construction of the prefabricated pipe pile according to claim 1, wherein guide rollers (34) are rotatably mounted on two sides of the hoisting cross beam (32), and guide sliding grooves (35) for the guide rollers (34) to linearly slide in the vertical direction are formed in the portal frame (31).
4. A precast tubular pile construction positioning support device according to claim 1, characterized in that the elastic return element (45) is a return spring or an elastic telescopic rod, and that when the device is in a free state, the elastic restoring force of the elastic return element (45) will bring the distance between the two clamping uprights (44) to a maximum value.
5. The precast tubular pile construction positioning and supporting device according to claim 1, wherein the hoisting assembly (5) comprises a winding roller (51) installed on the working platform (1), the winding roller (51) is connected with a driving motor, a winding rope (52) is wound on the winding roller (51), a fixed pulley (53) is installed at the top of the portal frame (31), and the winding rope (52) bypasses the fixed pulley (53) and is connected with the connecting rotating shaft (42).
6. The precast tubular pile construction positioning and supporting device according to claim 5, wherein the connecting rotating shaft (42) is provided with a hanging ring (41), and one end of the winding rope (52) is connected with the connecting rotating shaft (42) through the hanging ring (41).
7. The precast tubular pile construction positioning and supporting device according to claim 1, wherein an auxiliary supporting component (2) for carrying out auxiliary supporting on the working platform (1) is further arranged at the bottom of the working platform (1), and four groups of auxiliary supporting components (2) are symmetrically arranged at the bottom of the working platform (1) in pairs.
8. The precast tubular pile construction positioning and supporting device according to claim 7, characterized in that the auxiliary supporting assembly (2) comprises a supporting plate (21) and a first telescopic element (22) rotatably mounted on the bottom wall of the working platform (1), the movable end of the first telescopic element (22) is connected with the side wall of the supporting plate (21), a second telescopic element (23) is mounted at the free end of the supporting plate (21), and a supporting chassis (24) is connected to the bottom of the second telescopic element (23).
9. The precast tubular pile construction positioning and supporting device according to claim 8, characterized in that the first telescopic element (22) and the second telescopic element (23) are both hydraulic telescopic rods.
10. A method for positioning a precast tubular pile in construction, characterized in that the apparatus for positioning a precast tubular pile in construction according to any one of claims 1 to 9 comprises the steps of:
step 1, driving a second telescopic element (23) to rotate through telescopic movement of a first telescopic element (22), so that the second telescopic element (23) is adjusted to a designated position, and then enabling a supporting chassis (24) to be in stable contact with the ground through controlling the telescopic amount of the second telescopic element (23), so that a working platform (1) is stably supported;
step 2, lowering a hoisting beam (32) to a specified height through a hoisting assembly (5), hoisting a tubular pile at a hoisting station (12) on a lifting hook (33), driving a winding roller (51) to wind a winding rope (52) through a driving motor, driving a connecting rotating shaft (42) to move upwards through a lifting ring (41), driving two clamping upright rods (44) to move in opposite directions simultaneously through a hoisting connecting rod (43) by the connecting rotating shaft (42), and driving two clamping blocks (46) to be close to each other by the clamping upright rods (44), so that the side wall of the tubular pile to be hoisted is clamped;
step 3, after the side wall of the pipe pile is clamped and fixed, the clamping upright rod (44) drives the lifting beam (32) to integrally move upwards, the lifting beam (32) drives the pipe pile to synchronously rise through the lifting hook (33), namely, the lifting of the pipe pile is realized, and then the pipe pile is moved to a designated mounting position for lowering;
and 4, after the pipe pile is lowered in place, the lifting cross beam (32) does not move downwards under the supporting action of the pipe pile, at the moment, along with the continuous unreeling of the reeling rope (52), the elastic reset element (45) drives the clamping upright rod (44) to slide to one side far away from the pipe pile, and the clamping upright rod (44) drives the clamping block (46) to be automatically separated from the pipe pile, so that the positioning and the installation of the pipe pile are completed.
CN202311095862.2A 2023-08-29 2023-08-29 A kind of prefabricated pipe pile construction positioning support device Pending CN117071560A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311095862.2A CN117071560A (en) 2023-08-29 2023-08-29 A kind of prefabricated pipe pile construction positioning support device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311095862.2A CN117071560A (en) 2023-08-29 2023-08-29 A kind of prefabricated pipe pile construction positioning support device

Publications (1)

Publication Number Publication Date
CN117071560A true CN117071560A (en) 2023-11-17

Family

ID=88709518

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311095862.2A Pending CN117071560A (en) 2023-08-29 2023-08-29 A kind of prefabricated pipe pile construction positioning support device

Country Status (1)

Country Link
CN (1) CN117071560A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117775968A (en) * 2024-01-02 2024-03-29 江苏中慧建筑科技有限公司 A hoisting equipment and construction method for prefabricated PC components
CN119117893A (en) * 2024-11-12 2024-12-13 无锡交通建设工程集团股份有限公司 A lifting device for safe bridge construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117775968A (en) * 2024-01-02 2024-03-29 江苏中慧建筑科技有限公司 A hoisting equipment and construction method for prefabricated PC components
CN119117893A (en) * 2024-11-12 2024-12-13 无锡交通建设工程集团股份有限公司 A lifting device for safe bridge construction

Similar Documents

Publication Publication Date Title
CN117071560A (en) A kind of prefabricated pipe pile construction positioning support device
CN110952550A (en) Suspension self-supporting type piling method and piling machine
CN111305206B (en) Pile driver for civil engineering
CN112323796B (en) A kind of inclined prefabricated pile construction device and construction method thereof
CN111056455B (en) Concrete pouring positioning equipment for iron tower base of communication base station
CN218754822U (en) A combination device for heavy-duty shock-isolation bearing installation
CN114348860A (en) Steel box girder hoisting equipment with automatic leveling function
KR101512283B1 (en) Side sway mitigating apparatus for cable crane
CN218933119U (en) Centering device for reinforcement cage with large burial depth
CN218261641U (en) Anti-swing device convenient for stable lifting for crane
CN217555618U (en) Oil cylinder type quintuplet distance-increasing hoisting and moving device
CN217942432U (en) Integral standard festival shaping frock of tower machine fishplate
CN214935537U (en) Construction equipment for quickly installing roadbed side ditch cover plate
CN109403707A (en) A kind of V-shaped frame hoisting construction auxiliary equipment and construction method
CN113666274A (en) A kind of building intelligent lifting equipment
CN219156328U (en) Pile foundation underpinning low clearance cantilever hoisting device
CN217627231U (en) Novel visual crane
CN215326557U (en) Anti-shaking engineering equipment installation hoisting device
CN114162730A (en) A large-scale hoisting platform for prefabricated construction
CN222907326U (en) A converter auxiliary gun hoisting equipment
CN221700931U (en) Overhead hoist for power transmission and transformation engineering
CN223060564U (en) A movable assembled glass railing lifting and installation device
CN221052590U (en) Pile lifting mechanism of vibrating hammer
CN221680614U (en) A lifting device for construction engineering
CN221876386U (en) Building support hoist device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination