CN214192336U - Tower crane safety channel capable of lifting along with climbing frame - Google Patents
Tower crane safety channel capable of lifting along with climbing frame Download PDFInfo
- Publication number
- CN214192336U CN214192336U CN202120039182.9U CN202120039182U CN214192336U CN 214192336 U CN214192336 U CN 214192336U CN 202120039182 U CN202120039182 U CN 202120039182U CN 214192336 U CN214192336 U CN 214192336U
- Authority
- CN
- China
- Prior art keywords
- tower crane
- steel basketry
- basketry net
- set firmly
- iron sheet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000009194 climbing Effects 0.000 title claims description 20
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims abstract description 40
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 34
- 239000010959 steel Substances 0.000 claims abstract description 34
- 229910052742 iron Inorganic materials 0.000 claims abstract description 20
- 238000007689 inspection Methods 0.000 abstract description 5
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Landscapes
- Jib Cranes (AREA)
Abstract
The embodiment of the application belongs to the tower crane field, a tower crane escape way who climbs frame promotion is disclosed in following, include the steel basketry net as the bottom plate, set firmly the iron sheet that just is parallel to each other in steel basketry net upper surface left and right sides, a plurality of main square tube that are used for fixed steel basketry net and iron sheet, set firmly the cubic logical door at steel basketry net upper surface front end, set firmly the ring that is used for drawknot wire rope in cubic logical door bottom left and right sides, set firmly a plurality of fixing bolt that just passes main square tube at steel basketry net upper surface front end, and with climb a welded tie point, cubic logical door is by the hinge, a plurality of cubic logical and keeper are constituteed. The tower crane escape way of this application follows and climbs the frame and promote together, and operating personnel (for example driver, dimension guarantor personnel, inspection person etc.) only need from climb a layer get into tower crane inner channel can, need not set up too much passageway, reduce the potential safety hazard, and make things convenient for tower crane operating personnel tower crane from top to bottom.
Description
Technical Field
The application belongs to the tower crane field, especially relates to a follow tower crane escape way that climbs a promotion.
Background
General building site can set up the escape way to the tower crane tower body in the floor, and the driver need get into the tower crane tower body from low floor, then climbs the driver's cabin, and the driver need climb higher floor, and need set up a plurality of escape ways, has extravagant material and inconvenient tower crane operation personnel (for example driver, dimension guarantor, inspection person etc.) tower crane from top to bottom, and has more potential safety hazard scheduling problem.
SUMMERY OF THE UTILITY MODEL
An object of this application is to provide a follow tower crane escape way that climbs a promotion, aim at solving current inconvenient tower crane operation personnel (for example driver, dimension guarantor personnel, inspection person etc.) tower crane from top to bottom, have more potential safety hazard scheduling problem.
The embodiment of the application provides a follow tower crane escape way that climbs a promotion, include as the steel basketry net of bottom plate, set firmly at the steel basketry net upper surface left and right sides and the parallel iron sheet of each other, be used for fixing the steel basketry net with many main square expert of iron sheet, set firmly the square expert door of steel basketry net upper surface front end, set firmly be used for drawknot wire rope's ring, set firmly of the square expert door bottom left and right sides steel basketry net upper surface front end just passes a plurality of fixing bolt of main square expert and with climb a welded tie point, the square expert door comprises hinge, many times square expert and keeper.
Further, 16 main square tubes for fixing the steel basketry and the iron sheet are included.
Further, 3 of the secondary square tube are included.
Furthermore, 6 sheets of iron sheets are arranged, and 3 sheets of iron sheets are respectively arranged on the left side and the right side of the upper surface of the steel basketry net.
Further, 5 fixing bolts are included.
Further, 6 of the connection points are included.
Compared with the prior art, the embodiment of the application has the advantages that:
the tower crane escape way who climbs frame promotion can be fixed with escape way on climbing the frame to following and climb the frame and promote together, and operating personnel (for example driver, dimension guarantor personnel, inspection person etc.) only need from climbing the frame layer get into the tower crane inner channel can, need not set up too much passageway, reduce the potential safety hazard, and make things convenient for tower crane operating personnel tower crane from top to bottom.
Drawings
Fig. 1 is a schematic structural diagram of a tower crane safety passage lifted along with a climbing frame according to an embodiment of the present application;
fig. 2 is a schematic structural view of a tower crane safety passage lifted along with a climbing frame at another view angle provided in the embodiment of the present application;
in the figure: 1. a steel fence mesh; 2. iron sheet; 3. a main square tube; 4. a square through door; 41. a hinge; 42. a second square tube; 43. a door bolt; 5. a circular ring; 6. fixing the bolt; 7. and connecting points.
Detailed Description
In order to make the technical problems, technical solutions and advantageous effects to be solved by the present application clearer, the present application is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the present application and are not intended to limit the present application.
The following detailed description of the implementations of the present invention is made with reference to the accompanying drawings:
as shown in fig. 1 and 2, the embodiment of the present application provides a tower crane safety passageway lifted along with a climbing frame, which is lifted along with the climbing frame, and is used in the field of tower cranes, and the tower crane safety passageway comprises a steel basketry 1 as a bottom plate, i.e. a steel basketry as a base on which an operator (e.g. a driver, etc.) stands.
The tower crane safety channel further comprises iron sheets 2 which are fixedly arranged on the left side and the right side of the upper surface of a steel fence net 1 and are parallel to each other, a plurality of main square passages 3 used for fixing the steel fence net 1 and the iron sheets 2, an cubic through door 4 fixedly arranged at the front end of the upper surface of the steel fence net 1, circular rings 5 which are fixedly arranged on the left side and the right side of the bottom end of the cubic through door 4 and are used for tying a steel wire rope, a plurality of fixing bolts 6 fixedly arranged at the front end of the upper surface of the steel fence net 1 and penetrate through the main square passages 3, and a plurality of connection points 7 welded with a climbing frame, wherein the cubic through door 4 is composed of a hinge 41, a plurality of secondary square passages 42 and a door bolt 43.
It can be understood that the tower crane safety passageway is a passageway with two openings, one of the two openings is used for being welded with the climbing frame and finally lifted along with the climbing frame, the other opening is an opposite upper opening of the steel basketry net 1, and an operator enters the safety passageway through the secondary passageway door 4 and stands on the steel basketry net 1.
A tower crane safety passageway that rises along with climbing frame includes 16 the main square tube 3 that is used for fixing steel basketry net 1 with iron sheet 2, with the fixed steel basketry net 1 of main square tube 3 for bottom plate/base are more firm, with the fixed iron sheet 2 of main square tube 3, also make the support of left and right sides more fixed, further make iron sheet 2 set firmly on steel basketry net 1.
A follow tower crane escape way that climbs frame promotion includes 3 inferior square tube 42. 3 secondary square tubes 41, 1 hinge 41 and 1 door bolt 43 form a secondary square tube 4, and the secondary square tube 4 is connected with the steel basketry 1 and is fixedly connected with the main square tube 3 of the fixed iron sheet 2.
A tower crane safety passage lifted along with a climbing frame is provided with 6 iron sheets 2, and the left side and the right side of the upper surface of a steel basketry net 1 are respectively provided with 3 iron sheets.
The utility model provides a follow tower crane escape way that climbs frame promotion includes 5 fixing bolt 6 and 6 tie point 7 is together fixed with escape way and climbing frame through set screw 6 and tie point 7.
Here, the left, right, up, and down are based on fig. 1.
The utility model provides a follow tower crane escape way that climbs a promotion, this escape way fixes on climbing a frame, follows and climbs a frame and climb, and operating personnel (for example driver, dimension guarantor personnel, inspection person etc.) only need from climbing a frame layer get into tower crane inner channel can, need not set up too much passageway, reduce the potential safety hazard, and make things convenient for tower crane operating personnel tower crane from top to bottom.
It should be noted that connection references (e.g., attached, coupled, connected, etc.) are to be construed broadly and may include intermediate members between a connection of elements and relative movement between elements. Thus, connection references do not necessarily imply that two elements are directly connected/coupled and in a fixed relationship to each other. The use of "for example" throughout this specification should be interpreted broadly and used to provide non-limiting examples of embodiments of the disclosure, and the disclosure is not limited to such examples. It is intended that all matter contained in the above description or shown in the accompanying drawings shall be interpreted as illustrative only and not limiting. Changes in detail or structure may be made without departing from the disclosure.
The above-mentioned embodiments are only used for illustrating the technical solutions of the present application, and not for limiting the same; although the present application has been described in detail with reference to the foregoing embodiments, it should be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; such modifications and substitutions do not substantially depart from the spirit and scope of the embodiments of the present application and are intended to be included within the scope of the present application.
Claims (6)
1. The utility model provides a follow tower crane escape way that climbs frame promotion, its characterized in that includes steel basketry net (1) as the bottom plate, sets firmly iron sheet (2) that just are parallel to each other in steel basketry net (1) upper surface left and right sides, be used for fixing steel basketry net (1) with many main square tube (3) of iron sheet (2), set firmly inferior square logical door (4) of steel basketry net (1) upper surface front end, set firmly be used for drawknot wire rope's ring (5) in inferior square logical door (4) bottom left and right sides, set firmly steel basketry net (1) upper surface front end just passes a plurality of fixing bolt (6) of main square tube (3) and with climb a plurality of tie point (7) of frame welded, inferior square logical door (4) comprise hinge (41), many inferior square tube (42) and door bolt (43).
2. The tower crane safety passageway lifted by following climbing frame according to claim 1, characterized by comprising 16 main square tubes (3) for fixing the steel basketry (1) and the iron sheet (2).
3. The tower crane safety channel lifted along with the climbing frame according to claim 2, characterized by comprising 3 secondary square passages (42).
4. The tower crane safety channel lifted by following the climbing frame according to claim 3, characterized in that 6 sheets of iron sheet (2) are provided, and 3 sheets are provided on the left and right sides of the upper surface of the steel basketry net (1).
5. The tower crane safety channel lifted along with the climbing frame according to any one of claims 1 to 4, characterized by comprising 5 fixing bolts (6).
6. A tower crane safety corridor according to claim 5, characterized by comprising 6 said connection points (7).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120039182.9U CN214192336U (en) | 2021-01-07 | 2021-01-07 | Tower crane safety channel capable of lifting along with climbing frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120039182.9U CN214192336U (en) | 2021-01-07 | 2021-01-07 | Tower crane safety channel capable of lifting along with climbing frame |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214192336U true CN214192336U (en) | 2021-09-14 |
Family
ID=77634274
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120039182.9U Expired - Fee Related CN214192336U (en) | 2021-01-07 | 2021-01-07 | Tower crane safety channel capable of lifting along with climbing frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214192336U (en) |
-
2021
- 2021-01-07 CN CN202120039182.9U patent/CN214192336U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204899274U (en) | Prefabricated concrete structure goes along with sb. to guard him frame outward | |
CN214192336U (en) | Tower crane safety channel capable of lifting along with climbing frame | |
CN205591529U (en) | Attached lifting scaffold | |
CN210316599U (en) | A curtain ring rail for roofing truss beam position | |
CN209482687U (en) | A kind of Super High exterior frame column construction operation platform | |
CN206957175U (en) | A kind of planar dimension and adjustable for height operating platform | |
CN107795133B (en) | Integral protective frame platform and construction method thereof | |
CN202729645U (en) | Tower crane with elevator | |
CN206487129U (en) | Safety hanging cradle for industrial premises Construction of Steel Structure | |
CN214034706U (en) | Tower crane pedestrian safety passage used on attached lifting scaffold | |
CN213391361U (en) | Color steel plate prefabricated house capable of improving wind resistance | |
CN212295591U (en) | All-steel scaffold board | |
CN210549018U (en) | Eccentric arc-shaped ring corridor section high-altitude lifting tool | |
CN207986495U (en) | A kind of Bridge High-pier main reinforcement hanging apparatus | |
CN208071094U (en) | A kind of superimposed sheet and cladding panel girder steel suspender | |
CN204357138U (en) | Simple steel structure hoisting frame | |
CN206928683U (en) | A kind of lifeline standing rigging | |
CN207243242U (en) | Suspender | |
CN201686458U (en) | Movable operating platform used for quickly processing welding seam at end opening of steel box girder | |
CN207108259U (en) | Special lifting appliance for lifting steel structure module system | |
CN201554254U (en) | Communication tower and communication tower platform | |
CN206636152U (en) | Double-deck scaffold in simple type room | |
CN105712213B (en) | AP1000 nuclear power superposed type dome lifting and fixing construction methods | |
CN214195481U (en) | Elevator shaft protection platform | |
CN203905432U (en) | Hydraulic lifting retractable type platform device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210914 |
|
CF01 | Termination of patent right due to non-payment of annual fee |