CN213996037U - Highway bridge waste recovery device - Google Patents

Highway bridge waste recovery device Download PDF

Info

Publication number
CN213996037U
CN213996037U CN202021497264.XU CN202021497264U CN213996037U CN 213996037 U CN213996037 U CN 213996037U CN 202021497264 U CN202021497264 U CN 202021497264U CN 213996037 U CN213996037 U CN 213996037U
Authority
CN
China
Prior art keywords
auger
crusher body
fixedly connected
rolling wheel
rubbing crusher
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021497264.XU
Other languages
Chinese (zh)
Inventor
赵国建
李岁论
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Xinghong Construction Co ltd
Original Assignee
Hangzhou Xinghong Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Xinghong Construction Co ltd filed Critical Hangzhou Xinghong Construction Co ltd
Priority to CN202021497264.XU priority Critical patent/CN213996037U/en
Application granted granted Critical
Publication of CN213996037U publication Critical patent/CN213996037U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a waste recycling technical field especially relates to a public road bridge roof beam waste recycling device. The to-be-solved technical problem of the utility model is not to separate the metal. In order to solve the technical problem, the utility model provides a public road bridge roof beam waste recovery device, including rubbing crusher body, rubbing crusher body's inside is rotated and is connected with a pair of rolling wheel, the piece is smashed to rolling wheel's fixed surface is connected with, rubbing crusher body's below fixedly connected with screen cloth that inclines, first discharge gate has been seted up in rubbing crusher body's left side. The utility model discloses a set up support column, telescopic link, electro-magnet and first material guide rail and make metal in the metal after having been rolled and the cement mixture by the rolling wheel adsorb the electro-magnet on, realize the metal separation. The utility model discloses a cooperation of first promotion auger and screen cloth is circulated to not smashing complete waste material and is smashed, until being separated away by the screen cloth, makes cement smash completely, the reutilization of being convenient for.

Description

Highway bridge waste recovery device
Technical Field
The utility model relates to a waste recycling technical field specifically is a public road bridge roof beam waste recovery device.
Background
Highway bridge construction speed is faster and faster, at highway bridge reconstruction in-process, can cause a large amount of waste material, for example reinforced concrete mixture and various stone slab material class, and these discarded objects are often all directly to be the refuse treatment, have caused the waste of a large amount of resources, and current people can adopt some crushers to carry out the breakage to remaining waste material cement etc. to reach reuse's effect.
The prior patent (publication number: CN210546985U) discloses a waste recycling device for highway bridges, which comprises a U-shaped support and a recycling box body, wherein the tops of two sides of the U-shaped support are respectively fixed with a slewing bearing in a nesting manner, and the inventor finds that the following problems in the prior art are not well solved in the process of realizing the scheme: 1. the metals are not separated (the metal resources contained in the construction waste are not conveniently recycled); 2. the pulverization is incomplete (the pulverized construction waste has uneven particle size and is difficult to transport and reuse).
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a public road bridge roof beam waste recovery device has solved and has not separated the metal.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a public road bridge roof beam waste recovery device, includes rubbing crusher body, rubbing crusher body's inside is rotated and is connected with a pair of rolling wheel, the piece is smashed to the fixed surface of rolling wheel is connected with, the below fixedly connected with screen cloth that inclines of rubbing crusher body, first discharge gate has been seted up in rubbing crusher body's left side, the second discharge gate has been seted up to rubbing crusher body's bottom, rubbing crusher body's back fixedly connected with support column, the left side fixedly connected with telescopic link of support column, the bottom fixedly connected with electro-magnet of telescopic link.
The utility model discloses a crusher, including rubbing crusher body, the first promotion auger of left side fixedly connected with of rubbing crusher body, the third discharge gate has been seted up at the top of first promotion auger, the first material guide rail of inner wall fixedly connected with of third discharge gate, the pivot of first promotion auger runs through the bottom in the first promotion auger outside and with first auger driving motor's output fixed connection.
The right side fixedly connected with second of rubbing crusher body promotes the auger, first feed inlet has been seted up to the bottom that the second promoted the auger right side, the fourth discharge gate has been seted up at the left top of second promotion auger, the inner wall fixedly connected with second guide rail of fourth discharge gate, the pivot that the second promoted the auger runs through the second and promotes the top in the auger outside and with second auger driving motor's output fixed connection.
It is further preferred, two be parallel to each other between the rolling wheel, the pivot one end of rolling wheel is passed through the bearing and is rotated the connection on rubbing crusher inner wall, the other end of rolling wheel all passes rubbing crusher outer wall and sets up the output fixed connection at the first driving motor of this side.
Further preferably, the upper part of the crusher body is of a cuboid structure, and the bottom of the crusher body is of a frustum-shaped structure.
Preferably, the electromagnet is higher than the top of the pipe body of the first lifting auger, and the bottom of the electromagnet is opposite to the first material guide rail.
Preferably, the first discharge port penetrates through a pipe body of the first lifting auger, and the bottom of the first discharge port is connected with the top of the screen.
Further preferably, the bottom of the outer side of the second lifting auger is in lap joint with the ground.
(III) advantageous effects
The utility model provides a public road bridge roof beam waste recovery device possesses following beneficial effect:
(1) the utility model discloses a set up support column, telescopic link, electro-magnet and first material guide rail and make metal in the metal after having been rolled and the cement mixture by the rolling wheel adsorb the electro-magnet on, realize the metal separation.
(2) The utility model discloses a cooperation of first promotion auger and screen cloth is circulated to not smashing complete waste material and is smashed, until being separated away by the screen cloth, makes cement smash completely, the reutilization of being convenient for.
Drawings
FIG. 1 is a front cross-sectional view of the present invention;
fig. 2 is a back view of the present invention;
fig. 3 is a structural diagram of the rolling wheel of the present invention.
In the figure: the crusher comprises a crusher body 1, a rolling wheel 2, a crushing block 3, a screen 4, a first discharge port 5, a second discharge port 6, a support column 7, an expansion link 8, an electromagnet 9, a first lifting auger 10, a third discharge port 11, a first guide rail 12, a first auger driving motor 13, a second lifting auger 14, a first feed port 15, a fourth discharge port 16, a second guide rail 17 and a second auger driving motor 18.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: a highway bridge waste recovery device comprises a crusher body 1, the upper part of the crusher body 1 is of a cuboid structure, the bottom is of a frustum-shaped structure, waste is convenient to discharge, a pair of rolling wheels 2 is rotatably connected inside the crusher body 1, the two rolling wheels 2 are parallel and horizontally arranged, one end of a rotating shaft of each rolling wheel 2 is rotatably connected to the inner wall of the crusher body 1 through a bearing, the other ends of the rolling wheels 2 penetrate through the outer wall of the crusher body 1 and are fixedly connected with the output end of a first driving motor arranged on the side, a crushing block 3 is fixedly connected to the surface of each rolling wheel 2, a screen 4 is obliquely and fixedly connected below the crusher body 1, a first discharge port 5 is formed in the left side of the crusher body 1, the first discharge port 5 penetrates through a pipe body of a first lifting auger 10, the bottom of the first discharge port 5 is connected with the top of the screen 4, a second discharge port 6 is formed in the bottom of the crusher body 1, the back fixedly connected with support column 7 of rubbing crusher body 1, the left side fixedly connected with telescopic link 8 of support column 7, the bottom fixedly connected with electro-magnet 9 of telescopic link 8, electro-magnet 9 is higher than the body top of first promotion auger 10, the bottom and the first material guide rail 12 of electro-magnet 9 are relative, through setting up support column 7, telescopic link 8, electro-magnet 9 and first material guide rail 12 make by the metal after rolling wheel 2 rolls and the metal in the cement mixture adsorb to electro-magnet 9 on, realize the metal separation.
The left side of rubbing crusher body 1 fixedly connected with promotes auger 10 first, and the bottom and the ground overlap joint in the second promotion auger 14 outside, and third discharge gate 11 has been seted up at the top of first promotion auger 10, and the first guide rail 12 of the inner wall fixedly connected with of third discharge gate 11, the pivot of first promotion auger 10 run through the bottom in the first promotion auger 10 outside and with the output fixed connection of first auger driving motor 13.
The right side fixedly connected with second promotion auger 14 of rubbing crusher body 1, first feed inlet 15 has been seted up to the bottom on second promotion auger 14 right side, fourth discharge gate 16 has been seted up at the left top of second promotion auger 14, the inner wall fixedly connected with second guide rail 17 of fourth discharge gate 16, the pivot that the second promoted auger 14 runs through the top in the second promotion auger 14 outside and with the output fixed connection of second auger driving motor 18, the cooperation through first promotion auger 13 and screen cloth 4 is to not smashing complete waste material circulation crushing, until being separated by screen cloth 4, make cement smash completely, be convenient for reuse.
The working principle is as follows: the waste material gets into second promotion auger 14 through first feed inlet 15 and gets into rubbing crusher body 1, the waste material rolls for the first time through rolling wheel 2, drop on screen cloth 4, smash complete waste material and drop out rubbing crusher body 1 from the mesh of screen cloth 4, it gets into first promotion auger 10 and gets into rubbing crusher body 1 once more and smashes not to smash complete waste material, electromagnet 9 adsorbs the metal in the waste material when the waste material is on first material guide rail 12, carrying out rubbing crusher body 1 with metal waste through telescopic link 8, separate.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention.

Claims (6)

1. The utility model provides a public road bridge roof beam waste recovery device, includes rubbing crusher body (1), its characterized in that: the crusher comprises a crusher body (1), a pair of rolling wheels (2) are rotatably connected inside the crusher body (1), a crushing block (3) is fixedly connected to the surface of each rolling wheel (2), a screen (4) is fixedly connected to the lower portion of the crusher body (1) in an inclined manner, a first discharge port (5) is formed in the left side of the crusher body (1), a second discharge port (6) is formed in the bottom of the crusher body (1), a support column (7) is fixedly connected to the back of the crusher body (1), a telescopic rod (8) is fixedly connected to the left side of the support column (7), and an electromagnet (9) is fixedly connected to the bottom of the telescopic rod (8);
the left side of the crusher body (1) is fixedly connected with a first lifting auger (10), the top of the first lifting auger (10) is provided with a third discharge hole (11), the inner wall of the third discharge hole (11) is fixedly connected with a first material guide rail (12), and a rotating shaft of the first lifting auger (10) penetrates through the bottom of the outer side of the first lifting auger (10) and is fixedly connected with the output end of a first auger driving motor (13);
the right side fixedly connected with second of rubbing crusher body (1) promotes auger (14), first feed inlet (15) have been seted up to the bottom that the second promoted auger (14) right side, the second promotes auger (14) left top and has seted up fourth discharge gate (16), the inner wall fixedly connected with second guide rail (17) of fourth discharge gate (16), the pivot that the second promoted auger (14) runs through the second promote the top in the auger (14) outside and with the output fixed connection of second auger driving motor (18).
2. The waste recycling device for road bridges of claim 1, wherein: two be parallel to each other between rolling wheel (2), the pivot one end of rolling wheel (2) is passed through the bearing and is rotated the connection on rubbing crusher body (1) inner wall, the other end of rolling wheel (2) all passes rubbing crusher body (1) outer wall and sets up the output fixed connection at the first driving motor of this side.
3. The waste recycling device for road bridges of claim 1, wherein: the upper part of the crusher body (1) is of a cuboid structure, and the bottom of the crusher body is of a frustum-shaped structure.
4. The waste recycling device for road bridges of claim 1, wherein: the electromagnet (9) is higher than the top of the pipe body of the first lifting packing auger (10), and the bottom of the electromagnet (9) is opposite to the first material guide rail (12).
5. The waste recycling device for road bridges of claim 1, wherein: the first discharge port (5) penetrates through the pipe body of the first lifting auger (10), and the bottom of the first discharge port (5) is connected with the top of the screen (4).
6. The waste recycling device for road bridges of claim 1, wherein: the bottom of the outer side of the second lifting auger (14) is in lap joint with the ground.
CN202021497264.XU 2020-07-24 2020-07-24 Highway bridge waste recovery device Active CN213996037U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021497264.XU CN213996037U (en) 2020-07-24 2020-07-24 Highway bridge waste recovery device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021497264.XU CN213996037U (en) 2020-07-24 2020-07-24 Highway bridge waste recovery device

Publications (1)

Publication Number Publication Date
CN213996037U true CN213996037U (en) 2021-08-20

Family

ID=77287744

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021497264.XU Active CN213996037U (en) 2020-07-24 2020-07-24 Highway bridge waste recovery device

Country Status (1)

Country Link
CN (1) CN213996037U (en)

Similar Documents

Publication Publication Date Title
CN110560235A (en) Building rubbish reducing mechanism with dustproof and metal recycle
CN210876709U (en) Building waste recycling device
CN211274957U (en) Environment-friendly construction waste crushing treatment device
CN210700317U (en) Building foundation engineering waste recycling device
CN107754989A (en) A kind of building rubbish treatment device
CN206613551U (en) A kind of slag recycle device
CN207493750U (en) A kind of stone crusher of adjustable degree of grinding
CN206444702U (en) A kind of building waste recycles reuse means
CN206587821U (en) A kind of building block processing waste material recovery device
CN209379169U (en) A kind of building waste grinding device
CN210097782U (en) Construction site garbage disposal device
CN213996037U (en) Highway bridge waste recovery device
CN202072631U (en) Composite concrete production line
CN106694157A (en) Novel construction waste disposal device
CN213254605U (en) Building rubbish classification equipment
CN210936421U (en) Civil engineering construction waste treatment device
CN212597847U (en) Brick mixes construction waste recovery unit
CN110711643A (en) Building rubbish recovery unit based on electromagnetic conversion
CN214599341U (en) Civil engineering construction waste smashes recovery processing device
CN212681273U (en) A building waste recovery device for high-rise building
CN213468132U (en) Building rubbish reducing mechanism for civil engineering
CN210146095U (en) Municipal administration waste material reducing mechanism
CN210230107U (en) Building rubbish collecting and treating pool
CN213669507U (en) Waste collecting and treating device for traffic engineering highway construction
CN219540435U (en) Concrete crushing and recycling equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant