CN213868955U - Building water repellent treatment construction equipment - Google Patents

Building water repellent treatment construction equipment Download PDF

Info

Publication number
CN213868955U
CN213868955U CN202021624908.7U CN202021624908U CN213868955U CN 213868955 U CN213868955 U CN 213868955U CN 202021624908 U CN202021624908 U CN 202021624908U CN 213868955 U CN213868955 U CN 213868955U
Authority
CN
China
Prior art keywords
side wall
coiled material
auxiliary roller
support
heating device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021624908.7U
Other languages
Chinese (zh)
Inventor
李忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Yalong Construction Engineering Co ltd
Original Assignee
Yunnan Yalong Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Yalong Construction Engineering Co ltd filed Critical Yunnan Yalong Construction Engineering Co ltd
Priority to CN202021624908.7U priority Critical patent/CN213868955U/en
Application granted granted Critical
Publication of CN213868955U publication Critical patent/CN213868955U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The utility model discloses a building water-proof treatment construction equipment in the technical field of building water-proof treatment, which comprises a bracket and a water-proof coiled material, wherein the top of the front and back side walls of the bracket is provided with a U-shaped groove, a coiled material rotating shaft is movably arranged in the U-shaped groove, the water-proof coiled material is movably arranged on the coiled material rotating shaft, the leftmost side of the front and back side walls of the bracket is fixedly provided with a spring pressing sheet, the back inner side wall of the bracket is fixedly provided with the tail end of a heating device, the head end of the heating device is fixedly connected with one end of a backfire preventer, the other end of the backfire preventer is fixedly provided with a valve, the utility model has simple structure and lower cost, is simple and easy to use by workers, is convenient for actual operation construction, an auxiliary roller can automatically lay the coiled material, the heating device can rapidly and uniformly heat the asphalt surface of the coiled material, and the pressing roller is compacted immediately following the coiled material, the time interval between heating and laying is reduced, so that the laying effect is better.

Description

Building water repellent treatment construction equipment
Technical Field
The utility model relates to a building water repellent technical field specifically is a building water repellent construction equipment.
Background
With the rapid development and progress of economy, China needs to newly build a plurality of important basic projects, such as expressways, bridges, tunnels and the like every year, and the construction of various large civil and commercial buildings increases the workload of waterproof construction. The existing waterproof coiled material laying construction is that workers generally hold a blast burner to heat the waterproof coiled material and lay the waterproof coiled material at a position needing water prevention, and then the waterproof coiled material is compacted through a roller. Because the coiled material face is wide great, consequently need handheld blowtorch horizontal reciprocating heating, thereby it is inhomogeneous to reduce full rate of gluing to heat the effect easily, and the heating is consuming time longer moreover, increases the engineering time and lets the workman be in high temperature environment for a long time, because coiled material heating back temperature is higher, the workman often can wait the temperature for safety to reduce and lay the coiled material again, influences the coiled material and lays the effect, for this reason, we provide a building waterproofing treatment construction equipment.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building water repellent treatment construction equipment to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a building waterproofing treatment construction equipment comprises a support and a waterproofing coiled material, wherein a U-shaped groove is formed in the top of the front side wall and the rear side wall of the support, a coiled material rotating shaft is movably mounted in the U-shaped groove, the waterproofing coiled material is movably mounted on the coiled material rotating shaft, round holes are formed in the centers of the left ends of the front side wall and the rear side wall of the support, a pinch roller rotating shaft is fixedly mounted in each round hole, a pinch roller is movably mounted on the pinch roller rotating shaft, a spring pressing sheet is fixedly mounted at the leftmost side of the front side wall and the rear side wall of the support, a first auxiliary roller, a second auxiliary roller and a third auxiliary roller are movably mounted between the front inner side wall and the rear inner side wall of the support, the first auxiliary roller is arranged in the middle of the bottom of the inner side wall of the support, the second auxiliary roller is arranged on the left side of the first auxiliary roller, the third auxiliary roller is arranged on the left side of the second auxiliary roller, and the rear inner side wall of the support is fixedly mounted with the tail end of a heating device, the heating device is located below the third auxiliary roller, the head end of the heating device is fixedly connected with one end of a backfire preventer, the other end of the backfire preventer is fixedly provided with a valve, the other end of the valve is fixedly connected with a connector, the backfire preventer is fixedly installed on the front side wall of the support, the right center of the bottom of the front side wall and the rear side wall of the support are fixedly provided with supporting rods, the tail ends of the supporting rods are fixedly provided with casters with brakes, and the right side of the support is fixedly provided with a handle.
Preferably, the pinch roller shell is a metal wheel, and cement concrete is filled in the pinch roller.
Preferably, the gas pipeline of the heating device is a stainless steel pipeline.
Preferably, the gas shower nozzle is copper shower nozzle, gas shower nozzle quantity is seven.
Preferably, the brake caster wheels and the support rods are metal wheels and metal rods.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model has the advantages of reasonable design, the utility model has the advantages of simple structure, therefore, the cost is lower, the workman uses simple easy-to-use, make things convenient for the actual operation construction, waterproofing membrane when laying, the coiled material can be laid automatically to the auxiliary roller, heating device can the quick even heating coiled material the pitch face, the pinch roller is closely following its compaction, reduce the heating and lay time interval between, it is better to make the effect of laying, because work need not artifical the completion above, workman's work efficiency has been improved, reduce the engineering time, take the retreat formula method of laying, and the flame direction is forward, therefore the high temperature that flame produced can not influence the construction workman, heating device installs the backfire preventer, can prevent to backfire and produce the explosion, the design of shower nozzle can improve the heating degree of consistency, thereby the dust screen can prevent that pitch or other magazines from getting into gas shower nozzle and plugging up the gas port.
Drawings
FIG. 1 is a schematic view of the overall structure of a construction equipment for water-proofing construction of buildings according to the present invention;
FIG. 2 is a schematic diagram of the positions of the structures on the rear side wall of the construction equipment for waterproof treatment of buildings according to the present invention;
FIG. 3 is a schematic structural view of a heating device of the construction equipment for waterproof treatment of buildings of the present invention;
fig. 4 is the utility model relates to a building water repellent treatment construction equipment's gas shower nozzle's schematic structure view.
In the figure: 1. a support; 2. a U-shaped groove; 3. a coiled material rotating shaft; 4. waterproof coiled materials; 5. a circular hole; 6. a pinch roller rotating shaft; 7. a pinch roller; 8. a first auxiliary roller; 9. a second auxiliary roller; 10. a third auxiliary roller; 11. a heating device; 12. a flashback arrestor; 13. a support bar; 14. braking the caster; 15. a handle; 16. a gas pipeline; 17. a gas port; 18. a gas burner; 19. a dust screen; 20. pressing a spring plate; 21. a valve; 22. a connecting head.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a building water-proof treatment construction equipment comprises a support 1 and a waterproof coiled material 4, wherein the top of the front side wall and the top of the rear side wall of the support 1 are respectively provided with a U-shaped groove 2, a coiled material rotating shaft 3 is movably arranged in the U-shaped groove 2, the waterproof coiled material 4 is movably arranged on the coiled material rotating shaft 3, the left ends of the front side wall and the rear side wall of the support 1 are respectively provided with a round hole 5, a pinch roller rotating shaft 6 is fixedly arranged in the round holes 5, a pinch roller 7 is movably arranged on the pinch roller rotating shaft 6, the leftmost side of the front side wall and the leftmost side wall of the support 1 is fixedly provided with a spring pressing sheet 20, a first auxiliary roller 8, a second auxiliary roller 9 and a third auxiliary roller 10 are movably arranged between the front inner side wall and the rear inner side wall of the support 1, the first auxiliary roller 8 is arranged in the middle of the bottom of the inner side wall of the support 1, the second auxiliary roller 9 is arranged on the left side of the third auxiliary roller 9, the rear inner side wall of the support 1 is fixedly provided with the tail end of a heating device 11, heating device 11 is located the below of third auxiliary roller 10, the head end fixedly connected with one end of tempering prevention ware 12 of heating device 11, the other end fixed mounting of tempering prevention ware 12 has valve 21, the other end fixedly connected with connector 22 of valve 21, tempering prevention ware 12 fixed mounting is on the preceding lateral wall of support 1, the equal fixed mounting of right side center department of the bottom of lateral wall has bracing piece 13 around support 1, the terminal fixed mounting of bracing piece 13 has area brake truckle 14, support 1 right side fixed mounting has handle 15.
The heating device 11 comprises a gas pipeline 16, a gas port 17 is fixedly formed in the left side of the gas pipeline 16, a gas nozzle 18 is fixedly mounted at the gas port 17 of the gas pipeline 16, the gas nozzle 18 horizontally faces the pinch roller 7 leftwards, a detachable dustproof net 19 is movably mounted at the nozzle of the gas nozzle 18, flame sprayed by the gas nozzle 18 can uniformly heat the bottom surface of the waterproof coiled material 4, and the dustproof net 19 is used for preventing the gas pipeline 16 from being blocked by impurities to cause uneven flame;
the shell of the pressing wheel 7 is a metal wheel to adapt to a high-temperature working environment, cement concrete is filled in the pressing wheel 7, the weight of the pressing wheel 7 is increased to compact the waterproof coiled material 4, and the cement concrete is hardly influenced by temperature after being blocked and has low cost;
the gas pipeline 16 of the heating device 11 is a stainless steel pipeline, so that the safety of the gas heating device 11 is improved, the stainless steel can be suitable for the high-temperature working environment, and the gas leakage caused by the breakage of the gas pipeline 16 is prevented;
the gas nozzles 18 are copper nozzles, the number of the gas nozzles 18 is seven, and the gas nozzles 18 distributed dispersedly enable flame to be distributed more uniformly, so that the waterproof roll 4 is heated more sufficiently and uniformly, and the full adhesion rate of the waterproof roll 4 after being laid is higher;
brake truckle 14 and bracing piece 13 are metal wheel and metal pole, prevent to receive the thermal deformation and influence the utility model discloses a work.
The working principle is as follows: when need carry out waterproofing work, install waterproofing membrane 4 on coiled material pivot 3 earlier, valve 21 closes, connector 22 pipe connection gas tank, draw waterproofing membrane 4 to the below of first auxiliary roller 8, then pass from the centre of second auxiliary roller 9 and third auxiliary roller 10, draw below pinch roller 7 at last, open valve 21 and ignite, the flame even heating waterproofing membrane 4's of gas shower nozzle 18 bottom surface pitch, will through handle 15 the utility model discloses draw backward, waterproofing membrane 4 is automatic to be laid subaerial under the pinch roller 7 effect, then pinch roller 7 and spring pressing piece 20 are with waterproofing membrane 4 compaction, it can to close valve 21 after finishing to lay.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a building waterproofing handles construction equipment, includes support (1) and waterproofing membrane (4), its characterized in that: the top of the front side wall and the back side wall of the support (1) are both provided with a U-shaped groove (2), the inside of the U-shaped groove (2) is movably provided with a coiled material rotating shaft (3), a waterproof coiled material (4) is movably arranged on the coiled material rotating shaft (3), the left end centers of the front side wall and the back side wall of the support (1) are both provided with round holes (5), the inside of each round hole (5) is fixedly provided with a pinch roller rotating shaft (6), the pinch roller rotating shaft (6) is movably provided with a pinch roller (7), the leftmost side wall of the front side wall and the back side wall of the support (1) is fixedly provided with a spring pressing sheet (20), a first auxiliary roller (8), a second auxiliary roller (9) and a third auxiliary roller (10) are movably arranged between the front inner side wall and the back inner side wall of the support (1), the first auxiliary roller (8) is arranged in the middle of the bottom of the inner side wall of the support (1), the second auxiliary roller (9) is arranged on the left side of the first auxiliary roller (8), the third auxiliary roller (10) is arranged at the upper left of the second auxiliary roller (9), the rear inner side wall of the bracket (1) is fixedly provided with the tail end of a heating device (11), the heating device (11) is positioned below the third auxiliary roller (10), the head end of the heating device (11) is fixedly connected with one end of a backfire preventer (12), the other end of the backfire preventer (12) is fixedly provided with a valve (21), the other end of the valve (21) is fixedly connected with a connector (22), the backfire preventer (12) is fixedly arranged on the front side wall of the bracket (1), a support rod (13) is fixedly arranged at the right center of the bottom of the front side wall and the rear side wall of the bracket (1), the tail end of the supporting rod (13) is fixedly provided with a caster (14) with a brake, and the right side of the bracket (1) is fixedly provided with a handle (15).
2. The construction equipment for waterproofing a building according to claim 1, wherein: heating device (11) include gas pipeline (16), gas port (17) have been fixed to have seted up in the left side of gas pipeline (16), gas pipeline (16) locate fixed mounting at gas port (17) have gas shower nozzle (18), gas shower nozzle (18) direction level is towards pinch roller (7) left, the spout department movable mounting of gas shower nozzle (18) has detachable dust screen (19).
3. The construction equipment for waterproofing a building according to claim 1, wherein: the shell of the pressing wheel (7) is a metal wheel, and cement concrete is filled in the pressing wheel (7).
4. The construction equipment for waterproofing a building according to claim 1, wherein: the gas pipeline (16) of the heating device (11) is a stainless steel pipeline.
5. The construction equipment for waterproofing a building according to claim 2, wherein: the gas nozzles (18) are made of copper, and the number of the gas nozzles (18) is seven.
6. The construction equipment for waterproofing a building according to claim 1, wherein: the brake caster wheels (14) and the support rods (13) are metal wheels and metal rods.
CN202021624908.7U 2020-08-07 2020-08-07 Building water repellent treatment construction equipment Active CN213868955U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021624908.7U CN213868955U (en) 2020-08-07 2020-08-07 Building water repellent treatment construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021624908.7U CN213868955U (en) 2020-08-07 2020-08-07 Building water repellent treatment construction equipment

Publications (1)

Publication Number Publication Date
CN213868955U true CN213868955U (en) 2021-08-03

Family

ID=77033940

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021624908.7U Active CN213868955U (en) 2020-08-07 2020-08-07 Building water repellent treatment construction equipment

Country Status (1)

Country Link
CN (1) CN213868955U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114293720A (en) * 2021-12-31 2022-04-08 中国建筑第八工程局有限公司 Portable waterproofing membrane spreads and pastes device
CN115324339A (en) * 2022-07-08 2022-11-11 济南四建(集团)有限责任公司 Waterproofing membrane hot melt equipment for civil engineering

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114293720A (en) * 2021-12-31 2022-04-08 中国建筑第八工程局有限公司 Portable waterproofing membrane spreads and pastes device
CN115324339A (en) * 2022-07-08 2022-11-11 济南四建(集团)有限责任公司 Waterproofing membrane hot melt equipment for civil engineering

Similar Documents

Publication Publication Date Title
CN213868955U (en) Building water repellent treatment construction equipment
CN106592430A (en) Cast-in-place winter construction method for hanging basket cantilever
CN208618688U (en) A kind of reinforcement polymer membranes laying apparatus
CN205840219U (en) A kind of clay brick stainless steel perforated support system
CN209556348U (en) Deep basal pit outer wall of basement frame body is to support single side formwork system
CN209686857U (en) Deep basal pit outer wall of basement shape steel bracket diagonal brace single side formwork system
CN203916375U (en) Construction scope of operation spray dust heat sink
CN110965670B (en) Welding-free installation method for horizontal water-stopping steel plate of shear wall
CN105178986B (en) Variable curve mold for lining positioning of earth-sheltered dwelling and construction technology of variable-curve mold
CN214832413U (en) EVA waterproof board convenient to lay fast
CN216516547U (en) Multi-functional pitch waterproofing membrane laying device
CN212405177U (en) Suspended enclosing purlin supporting system
CN210282694U (en) Heat preservation canopy is used in section of jurisdiction production
CN206608617U (en) The heat-insulated fixed support of heat-net-pipeline
CN208131005U (en) Gas cleaning reactor and its top exit structure
CN108518070B (en) Be used for general fine tuning control of cast-in-situ slab reinforcement protective layer turnover
CN110158888A (en) A kind of construction method of steel structure surface brick paving
CN217604371U (en) Waste heat utilization device for smoke box at front end of drying roller
CN213204744U (en) Make things convenient for blowdown pond prevention of seepage construction of rolling to lay auxiliary device with coiled material
CN204435855U (en) A kind of shear wall formwork structure of large volume radiation-proof concrete wall
CN215519504U (en) Thickness adjusting device for concrete protective layer of steel bar net frame and pouring forming structure of thickness adjusting device
CN213390957U (en) External wall heat insulation decorative board
CN109944430A (en) A kind of electric lifting platform construction method for special-shaped exterior walls of buildings operation
CN219654731U (en) Spraying device for underground engineering
CN220048612U (en) Spraying device for fireproof paint

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant