CN213741025U - A fill support for flat area photovoltaic support stake - Google Patents

A fill support for flat area photovoltaic support stake Download PDF

Info

Publication number
CN213741025U
CN213741025U CN202022367494.0U CN202022367494U CN213741025U CN 213741025 U CN213741025 U CN 213741025U CN 202022367494 U CN202022367494 U CN 202022367494U CN 213741025 U CN213741025 U CN 213741025U
Authority
CN
China
Prior art keywords
support
positioning
pile
frames
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022367494.0U
Other languages
Chinese (zh)
Inventor
明小燕
张�杰
周毅
周靖斐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Kunming Engineering Corp Ltd
Original Assignee
PowerChina Kunming Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Kunming Engineering Corp Ltd filed Critical PowerChina Kunming Engineering Corp Ltd
Priority to CN202022367494.0U priority Critical patent/CN213741025U/en
Application granted granted Critical
Publication of CN213741025U publication Critical patent/CN213741025U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Foundations (AREA)
  • Photovoltaic Devices (AREA)

Abstract

The utility model belongs to the technical field of photovoltaic support construction, and mainly relates to a perfusion support for a photovoltaic support pile in a flat area, which comprises a fixing device, an elevation adjusting device and a positioning device, wherein the fixing device is composed of two cross beams and a plurality of longitudinal beams arranged between the cross beams, and the cross beams are rectangular frames; the elevation adjusting device is a supporting platform and is arranged at the joint of the longitudinal beam and the cross beam; the positioning devices are a plurality of positioning frames with fixed intervals, cylindrical steel templates are arranged in the frames, and the positioning frames are symmetrically arranged in the rectangular frame of the cross beam; the longeron set up the both sides at the locating frame, the utility model discloses a cast-in-place support designs according to photovoltaic support and pile foundation size, can be used to 10 pile foundations of single photovoltaic support cast-in-place construction simultaneously, has realized photovoltaic support pile foundation modularization, and the rapidization, the construction of accuracy, it is big effectual to have solved the pile foundation construction degree of difficulty, the difficult problem that construction quality is poor has guaranteed engineering quality and construction progress.

Description

A fill support for flat area photovoltaic support stake
Technical Field
The utility model belongs to the technical field of the photovoltaic support construction, mainly relate to a support that fills for flat area photovoltaic support stake.
Background
The photovoltaic support foundation is used as a support structure of a photovoltaic support structure and is an important component of a photovoltaic power generation system, and the safety, stability and attractiveness of the photovoltaic support foundation directly influence the engineering quality and the engineering appearance of the whole photovoltaic power station. As the construction key work, the construction progress of the construction method plays a decisive role in the progress of the whole project. The conventional construction method of the photovoltaic support pile foundation separately pours each pile foundation, and the pile point coordinates and the pile top elevation need to be checked repeatedly for many times in the construction process, so that the construction progress is slow. Meanwhile, the construction precision is poor, the pile foundation position deviation and the pile top elevation deviation are easy to occur, the situation that part of vertical rods need to be processed and installed again is caused, the construction process is time-consuming and labor-consuming, and the construction quality is general.
Disclosure of Invention
The invention mainly aims to provide a cast-in-place support for a photovoltaic support pile in a flat area, which solves the problems in the prior art.
In order to achieve the above purpose, the invention provides the following technical scheme:
a cast-in-place stand for a flat area photovoltaic support pile, the cast-in-place stand comprising a fixing device, an elevation adjustment device and a positioning device, wherein:
the fixing device is composed of two cross beams and a plurality of longitudinal beams arranged between the cross beams, and the cross beams are rectangular frames;
the elevation adjusting device is a supporting platform and is arranged at the joint of the longitudinal beam and the cross beam;
the positioning device is provided with a plurality of positioning frames with fixed intervals according to the intervals of the upper photovoltaic support columns, cylindrical steel templates are arranged in the frames, and the positioning frames are symmetrically arranged in the beam rectangular frame;
the longitudinal beams are arranged on two sides of the positioning frame.
Further, a steel reinforcement cage is arranged in the steel template.
Further, the supporting table comprises a base, a vertical rod, a column casing and a bolt, the vertical rod is a cylinder and is arranged at the center of the base and perpendicular to the base, the column casing is sleeved on the vertical rod and is provided with a threaded hole corresponding to the bolt, the column casing is fixedly connected to the longitudinal rod on the outer side of the rectangular frame, and the height of the supporting frame body is adjusted through the up-and-down movement of the column casing on the vertical rod.
Furthermore, the longitudinal beams are symmetrically arranged on two sides of the positioning frame, the distance between the longitudinal beams and the positioning frame is 30-35cm, and the distance is set to prevent the cross beam from deforming to influence the height of the supporting pile due to the pressure bearing of the steel formwork when concrete is poured into the steel formwork in the positioning frame.
Furthermore, threaded holes matched with the bolts are formed in the periphery of each positioning frame, the pile foundation reinforcement cage can be fixedly suspended on the bolts through the passing in and out movable connection steel templates of the bolts, and the position and the height of the reinforcement cage can be adjusted through adjusting the suspension position.
Furthermore, be provided with the scale on the pole setting, carry out high accurate regulation and location through the scale.
The utility model discloses a cast-in-place support designs according to photovoltaic support and pile foundation size, can be used to 10 pile foundations of single photovoltaic support to fill the construction simultaneously, has realized photovoltaic support pile foundation modularization, and the rapidity, the construction of accurate, the effectual pile foundation construction degree of difficulty of having solved is big, adjusts the difficulty, and the construction progress is slow, and the difficult problem that construction quality is poor has guaranteed engineering quality and construction progress.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is an enlarged view of part A of the present invention;
wherein: 1. a cross beam; 11. a cross bar; 2. a longitudinal bar; 3. a stringer; 4. a steel form; 5. erecting a rod; 6. a base; 7. a column casing; 8. and (4) bolts.
Detailed Description
The invention will be further described with reference to the accompanying drawings and specific embodiments.
As shown in fig. 1, a perfusion support for a photovoltaic support pile in a flat area comprises a fixing device, an elevation adjusting device and a positioning device, wherein: the fixing device is composed of two cross beams 1 and a plurality of longitudinal beams 3 arranged between the cross beams, wherein the cross beam 1 is a rectangular frame and is composed of longitudinal rods 2 and cross rods 11.
As shown in fig. 2, the elevation adjusting device is a supporting platform, which is arranged at the joint of the longitudinal beam and the cross beam and at the joint of the cross bar at the outer side of the rectangular frame of the longitudinal beam and the cross beam; the ground supporting table comprises a base 6, a vertical rod 5, a column 7 and a bolt 8, the vertical rod 5 is arranged in the center of the base 6 and is perpendicular to the base 6 for the cylinder, the column 7 has a certain thickness, is sleeved on the vertical rod 5 and is provided with a threaded hole corresponding to the bolt 8, the column 7 is fixedly connected to the longitudinal rod 11 outside the rectangular frame, the height of the support frame body is adjusted through the vertical movement of the column 7 in the vertical rod, scales are arranged on the vertical rod 5, and according to the field requirement, the corresponding scales are fixed through the bolt to carry out the accurate adjustment and the positioning of the height, the utility model discloses a ground supporting table is convenient to be disassembled and moved, and can be accurate carry out the adjustment of the height.
Positioner is the locating rack of the several fixed spacing who sets up according to upper portion photovoltaic support column interval, be provided with cylindrical steel form 4 in the frame, be provided with the steel reinforcement cage that is used for firm foundation pile in the steel form, locating rack equidistance symmetry sets up in the rectangle frame, longeron 3 is the symmetry and sets up the both sides at the locating rack, and be 30-35cm with the distance between the locating rack, preferably 32.8 cm, every locating rack is provided with the screw hole that matches with the bolt all around, business turn over swing joint steel form through the bolt, preferred steel form is cylindrical steel sheet, pile foundation steel reinforcement cage can hang and be fixed in on the bolt, hang position adjustment steel reinforcement cage position and height through the adjustment.
The quantity of locating frame is confirmed according to the quantity of the pile foundation of photovoltaic support, two rectangle frame symmetries set up 10 locating frames under the conventionality, install 10 steel form promptly additional, rectangle frame horizontal pole 11 is long 13.2m, 2 long 30.4cm of vertical pole, from the one end of rectangle frame, the equidistance sets up 5 locating frames, every locating frame length is 30.4cm wide, the diameter of steel form is 30cm, 3 long 2.684 meters of longeron, quantity is 8, the symmetric distribution is in the locating frame both sides, and the distance between the locating frame is 32.8 centimetres, the steel form can directly imbed in the locating frame, be provided with the screw hole with bolt matching around every locating frame, business turn over swing joint steel form through the bolt.
During the concrete use, transport each adapting unit to the position that needs to install photovoltaic support, then assemble this filling support, keep flat in ground, pile foundation hole respectively on the ground that the steel form corresponds, according to the on-the-spot condition, adjust ground brace table to suitable height, put into the steel reinforcement cage from steel form department, adjust the position and the height of steel reinforcement cage, then in the downthehole and steel reinforcement cage pouring concrete of pile foundation, treat concrete shaping back, take out this filling support, carry out another group photovoltaic support pile foundation pouring construction.

Claims (5)

1. A perfusion support for a photovoltaic support pile in a flat area, the perfusion support comprising a fixing device, an elevation adjustment device and a positioning device, wherein:
the fixing device is composed of two cross beams and a plurality of longitudinal beams arranged between the cross beams, and the cross beams are rectangular frames;
the elevation adjusting device is a supporting platform and is arranged at the joint of the longitudinal beam and the cross beam;
the positioning device is provided with a plurality of positioning frames with fixed intervals according to the intervals of the upper photovoltaic support columns, cylindrical steel templates are arranged in the frames, and the positioning frames are symmetrically arranged in the beam rectangular frame;
the longitudinal beams are arranged on two sides of the positioning frame.
2. The cast-in-place bracket for the flat area photovoltaic bracket pile as claimed in claim 1, wherein a steel reinforcement cage is arranged in the steel formwork.
3. The grouting support for a photovoltaic support pile in a flat area as claimed in claim 1, wherein the support platform comprises a base, a vertical rod, a column casing and a bolt, the vertical rod is a cylinder and is arranged at the center of the base and perpendicular to the base, the column casing is sleeved on the vertical rod and is provided with a threaded hole corresponding to the bolt, the column casing is fixedly connected to the longitudinal rod at the outer side of the rectangular frame, and the height of the support frame body is adjusted by the vertical movement of the column casing on the vertical rod.
4. The cast-in-place bracket for the flat area photovoltaic bracket pile as claimed in claim 1, wherein the longitudinal beams are symmetrically arranged on both sides of the positioning frame, and the distance between the longitudinal beams and the positioning frame is 30-35 cm.
5. The cast-in-place support for the photovoltaic support piles in the flat areas as claimed in claim 2, wherein each positioning frame is provided with threaded holes matched with bolts at the periphery, the steel formwork is movably connected through the passing in and out of the bolts, the pile foundation reinforcement cage can be fixedly hung on the bolts, and the position and the height of the reinforcement cage can be adjusted through adjusting the hanging position.
CN202022367494.0U 2020-10-22 2020-10-22 A fill support for flat area photovoltaic support stake Active CN213741025U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022367494.0U CN213741025U (en) 2020-10-22 2020-10-22 A fill support for flat area photovoltaic support stake

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022367494.0U CN213741025U (en) 2020-10-22 2020-10-22 A fill support for flat area photovoltaic support stake

Publications (1)

Publication Number Publication Date
CN213741025U true CN213741025U (en) 2021-07-20

Family

ID=76851960

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022367494.0U Active CN213741025U (en) 2020-10-22 2020-10-22 A fill support for flat area photovoltaic support stake

Country Status (1)

Country Link
CN (1) CN213741025U (en)

Similar Documents

Publication Publication Date Title
CN206986719U (en) A kind of bridge floor anti-collision wall reinforcing bar positioning installation apparatus
CN212715972U (en) Prefabricated bed-jig suitable for multiple specification pier stud reinforcing bar
CN203729319U (en) Locating steel frame of pre-buried annularly-distributed ground bolt group
CN202117074U (en) Foundation bed steel structure for positioning and mounting base of tower crane
CN205955239U (en) Calibrated mount is used in lattice column construction
CN205852606U (en) Three dimensions tubular truss assembly moulding bed
CN211572600U (en) High-precision construction structure of wafer plate of King cylinder mould
CN213741025U (en) A fill support for flat area photovoltaic support stake
CN212224683U (en) Positioning device for pre-buried foundation bolt
CN202265906U (en) Fixing device for anchor bolts of embedded type steel tube concrete column feet
CN209837767U (en) Assembled horizontal prefabricated component supports support body
CN202266034U (en) Fixing device for anchor bolts of embedded type diamond combined steel and concrete column feet
CN111648611A (en) Embedded part supporting device and embedded part installation method using embedded part supporting device
CN210421141U (en) Accurate installation fixed bolster of column base crab-bolt
CN208088326U (en) A kind of lag pile formula bearing being used to support pile framing
CN208361753U (en) A kind of tower crane supporting leg anchoring pre-buried structure and tower crane
CN209760786U (en) instrumentization support system for controlling precision of two-dimensional component
CN208056464U (en) A kind of novel lattice column device
CN203008232U (en) Steel truss strut
CN207714150U (en) Assemble holder in adhesion type high-altitude
CN211622195U (en) Adjustable dog bed-jig
CN219387170U (en) Horizontal support system for column formwork construction
CN214116620U (en) Adjustable support for accurate positioning of permanent double-steel-pipe column
CN219430998U (en) Shaping bracket for installing column foot embedded bolts
CN212897571U (en) Stand fixing device and stand fixed bolster

Legal Events