CN213740608U - Truss fixing mechanism on pier stand column - Google Patents

Truss fixing mechanism on pier stand column Download PDF

Info

Publication number
CN213740608U
CN213740608U CN202022189919.3U CN202022189919U CN213740608U CN 213740608 U CN213740608 U CN 213740608U CN 202022189919 U CN202022189919 U CN 202022189919U CN 213740608 U CN213740608 U CN 213740608U
Authority
CN
China
Prior art keywords
truss
hole
sleeve
pier column
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202022189919.3U
Other languages
Chinese (zh)
Inventor
刘举
王雨生
陈沣
高扬
吕轶波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sucgm Ltd
Original Assignee
Sucgm Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sucgm Ltd filed Critical Sucgm Ltd
Priority to CN202022189919.3U priority Critical patent/CN213740608U/en
Application granted granted Critical
Publication of CN213740608U publication Critical patent/CN213740608U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型公开了一种在桥墩立柱上的桁架固定机构,用于将桁架固定于桥墩立柱的两侧,其特征在于所述桁架固定机构包括开设于所述桁架上的安装孔、所述桥墩立柱上的水平预留通孔以及贯穿通过所述安装孔和所述水平预留通孔的销棒,所述销棒的两端部分别套设有支撑套管以同所述安装孔的内壁面和所述水平预留通孔的内壁面贴紧形成支撑,所述支撑套管自所述安装孔延伸至所述水平预留通孔内。本实用新型的优点是:在桁架与桥墩立柱之间采用销棒与支撑套管的组合结构,可有效地将桁架固定在桥墩立柱上,并可在达到承载力的要求下,最大限度的减小销棒直径和重量,从而降低安装难度。

Figure 202022189919

The utility model discloses a truss fixing mechanism on a bridge pier column, which is used for fixing a truss on both sides of a bridge pier column. The horizontal reserved through hole on the column and the pin rod passing through the installation hole and the horizontal reserved through hole, the two ends of the pin rod are respectively sleeved with support sleeves to be the same as the inside of the installation hole. The wall surface and the inner wall surface of the horizontal reserved through hole are in close contact to form a support, and the support sleeve extends from the installation hole into the horizontal reserved through hole. The advantages of the utility model are: the combined structure of pin rods and support sleeves is used between the truss and the pier column, which can effectively fix the truss on the pier column, and can reduce the maximum load under the requirement of bearing capacity. Small pin diameter and weight reduce installation difficulty.

Figure 202022189919

Description

Truss fixing mechanism on pier stand column
Technical Field
The utility model belongs to the technical field of the road bridge, concretely relates to truss fixed establishment on pier stand.
Background
When the urban bridge is cast in place, roads are required to be closed, construction period is long, construction quality is not easy to control, consumption of supports and templates in construction is high, construction cost is high, road traffic capacity of construction points is directly influenced, dust, noise and other pollution are brought to cities when concrete materials are constructed and transported, citizens go out and life quality are seriously influenced, great complaints are often caused, and the requirements of urban construction development cannot be met.
Based on this, in order to shorten construction period, reduce the influence to traffic and resident's life around, prefabricated bent cap is by more and more applied to urban bridge construction in-process, compares with cast in situ bent cap, and prefabricated bent cap has advantages such as prefabricated on a large scale, transportation and simple to operate, obtains more extensive application in the bridge construction field.
Before the prefabricated bent cap is erected, a fixed truss structure needs to be installed on a pier stand column, a through hole is formed in the pier stand column in a structure commonly used at present, a pin rod is arranged in the through hole to fix a truss on the pier stand column, but the pin rod arranged in the whole piece has the problems of heavy weight and high cost, and great difficulty exists in installation.
Disclosure of Invention
The utility model aims at providing a truss fixed establishment on pier stand according to the weak point of above-mentioned prior art, this truss fixed establishment establishes support sleeve through the both ends at the round pin stick cover respectively to under the condition that reaches the bearing capacity requirement, reduced the diameter and the weight of round pin stick greatly, reduced the installation degree of difficulty of round pin stick.
The utility model discloses the purpose is realized accomplishing by following technical scheme:
the utility model provides a truss fixed establishment on pier stand for be fixed in the truss in the both sides of pier stand, its characterized in that truss fixed establishment is including offering in mounting hole on the truss the through-hole is reserved to the level on the pier stand and runs through the mounting hole with the round pin stick of through-hole is reserved to the level, the both ends of round pin stick are overlapped respectively and are equipped with support sleeve with the internal face of mounting hole with the internal face of level reservation through-hole pastes tightly and forms the support, support sleeve certainly the mounting hole extends to in the through-hole is reserved to the level.
The extension length L of the support sleeve in the horizontal reserved through hole of the pier column is 2-3 times of the outer diameter d of the support sleeve, namely, L is more than 2d and less than 3 d.
And a circle of flange is arranged on the outer wall surface of the support sleeve, and the flange is clamped between the pier column and the truss.
The truss is provided with a fixed sleeve, the fixed sleeve comprises a flange plate and a sleeve which are connected with each other, the fixed sleeve is sleeved on the exposed end of the supporting sleeve, and the flange plate is fixedly connected with the truss.
The outer end of the pin rod protrudes out of the fixing sleeve, and a nut is arranged at the outer end of the pin rod and screwed to abut against the fixing sleeve to fix the pin rod.
The utility model has the advantages that: the combined structure of the pin rods and the support sleeves is adopted between the truss and the pier upright column, so that the truss can be effectively fixed on the pier upright column, the diameter and the weight of the pin rods can be reduced to the maximum extent under the condition of meeting the requirement of bearing capacity, and the installation difficulty is reduced.
Drawings
FIG. 1 is a schematic view of a truss of the present invention fixed on a pier column by a fixing mechanism;
fig. 2 is a cross-sectional view taken along line a-a of fig. 1 in accordance with the present invention;
fig. 3 is a schematic, enlarged, side view of the present invention in fig. 2;
fig. 4 is a partially enlarged schematic view B of fig. 1 according to the present invention.
Detailed Description
The features of the present invention and other related features are described in further detail below by way of example with reference to the accompanying drawings, for the understanding of those skilled in the art:
referring to fig. 1-4, the labels in the figures are: the device comprises a truss 1, pier columns 2, prefabricated bent caps 3, a truss fixing mechanism 4, a pin rod 5, a support sleeve 6, a fixing sleeve 7, a nut 8, a horizontal preformed hole 9, a mounting hole 10 and a flange 11.
Example (b): as shown in fig. 1, 2, 3, 4, this embodiment concretely relates to truss fixed establishment on pier stud, this truss fixed establishment 4 is used for installing truss 1 fixed on pier stud 2, truss fixed establishment 4 is including offering the mounting hole 10 on truss 1, offer the level preformed hole 9 on pier stud and run through the round pin 5 through mounting hole 10 and level preformed hole 9, the both ends of round pin 5 overlap respectively and are equipped with support sleeve 6 and form the support with the internal wall of mounting hole 10 and the internal wall of level preformed hole 9 clinging tightly, each support sleeve 6 extends to in the level preformed hole 9 from the mounting hole 10.
As shown in fig. 1, 2, 3 and 4, the pier stud 2 of the present embodiment is used for erecting a prefabricated capping beam 3, and the trusses 1 on both sides of the pier stud 1 are used for guiding and supporting the prefabricated capping beam 3 during the erecting construction. As shown in fig. 1 and 4, two sets of truss fixing mechanisms 4 are provided on each of the pier stud 2, thereby stabilizing the truss 1 on the pier stud 2.
As shown in fig. 2 and 3, the installation holes 10 on the truss 1 correspond to the horizontal preformed holes 9 on the pier stud 2, and the hole diameters of the two holes are the same; the diameter of round pin 5 is less than the aperture of horizontal preformed hole 9 and mounting hole 10, round pin 5 runs through the mounting hole 10 on the truss 1 of one side in proper order, horizontal preformed hole 9 on the pier column 2 and the mounting hole 10 on the truss of opposite side 1, establish support sleeve 6 at the both ends cover of round pin 5, support sleeve 6's external diameter is corresponding to the aperture of horizontal preformed hole 9 and mounting hole 10, consequently can make support sleeve 6 hug closely the internal face of mounting hole 10 and the internal face of horizontal preformed hole 9 after support sleeve 6 is established to the cover at 5 both ends of round pin, form and support the atress. The middle part of the support sleeve 6 is provided with a circle of flange 11 so as to divide the support sleeve 6 into two parts in the length direction, one part extends into the horizontal preformed hole 9 of the pier upright post 2 when being installed, the other part is arranged in the installation hole 10 of the truss 1 when being installed, and the circle of flange 11 is clamped between the inner wall surface of the truss 1 and the outer wall surface of the pier upright post 2 to play a role in fixing and limiting the support sleeve 6; it should be further noted that the extension L of the support sleeve 6 in the horizontal preformed hole 9 is 2-3 times the outer diameter d of the support sleeve 6, i.e. 2d < L < 3d, and is selected such that the mechanical properties of the combination of the support sleeve 6 and the pin 5 reach the mechanical properties of the pin 5 with the same diameter d.
As shown in fig. 2 and 3, the outer end of the support sleeve 6 slightly protrudes out of the truss 1, the truss 1 is provided with a fixing sleeve 7 corresponding to each support sleeve 6, the fixing sleeve 7 comprises a flange and a sleeve which are connected with each other, the sleeve is sleeved on the exposed end of the support sleeve 6, and the flange is fixedly connected with the truss 1 through a bolt; the outer end of the pin rod 5 protrudes out of the fixed sleeve 7, and nuts are respectively sleeved at two ends of the pin rod 5 and screwed to abut against the fixed sleeve to fix the pin rod 5.
As shown in fig. 1 to 4, the installation method of the truss fixing mechanism in the present embodiment includes the following steps:
(1) respectively inserting a support sleeve 6 into each horizontal preformed hole 9 of the pier column 2, so that the front half part of the support sleeve 6 extends into the horizontal preformed hole 9, and a circle of flange 11 on the support sleeve is closely attached to the outer wall surface of the pier column 1;
(2) aligning and sleeving each mounting hole 10 on the truss 1 with each support sleeve 6 to arrange the truss 1 on the support sleeve 6;
(3) the hoisting pin rods 5 are installed, sequentially penetrate through the supporting sleeve 6 on one side, the horizontal preformed hole 9 and the supporting sleeve 6 on the other side, and after the installation is in place, the fixed sleeve 7 is sleeved on the outer side of the truss 1 and is fixed through bolts; a nut is provided on the outer end of the pin 5 and screwed against the fixed sleeve 7 to fix the pin 5.

Claims (5)

1.一种在桥墩立柱上的桁架固定机构,用于将桁架固定于桥墩立柱的两侧,其特征在于所述桁架固定机构包括开设于所述桁架上的安装孔、所述桥墩立柱上的水平预留通孔以及贯穿通过所述安装孔和所述水平预留通孔的销棒,所述销棒的两端部分别套设有支撑套管以同所述安装孔的内壁面和所述水平预留通孔的内壁面贴紧形成支撑,所述支撑套管自所述安装孔延伸至所述水平预留通孔内。1. A truss fixing mechanism on a bridge pier column, for fixing a truss on both sides of a bridge pier column, it is characterized in that the truss fixing mechanism comprises an installation hole opened on the truss, a mounting hole on the pier column. The horizontal reserved through hole and the pin rod passing through the installation hole and the horizontal reserved through hole, the two ends of the pin rod are respectively sleeved with support sleeves to be consistent with the inner wall surface of the installation hole and all the holes. The inner wall surface of the horizontal reserved through hole is closely attached to form a support, and the support sleeve extends from the installation hole into the horizontal reserved through hole. 2.根据权利要求1所述的一种在桥墩立柱上的桁架固定机构,其特征在于所述支撑套管在所述桥墩立柱的所述水平预留通孔内的延伸长度L为所述支撑套管外径d的2-3倍,即,2d<L<3d。2. A truss fixing mechanism on a pier column according to claim 1, wherein the extension length L of the support sleeve in the horizontal reserved through hole of the pier column is the support 2-3 times the outer diameter d of the sleeve, that is, 2d<L<3d. 3.根据权利要求2所述的一种在桥墩立柱上的桁架固定机构,其特征在于所述支撑套管的外壁面上具有一圈凸缘,所述凸缘夹紧设置在所述桥墩立柱与所述桁架之间。3 . The truss fixing mechanism on the pier column according to claim 2 , wherein a ring of flanges is provided on the outer wall of the support sleeve, and the flange is clamped and arranged on the pier column. 4 . between the truss. 4.根据权利要求3所述的一种在桥墩立柱上的桁架固定机构,其特征在于所述桁架上设置有固定套,所述固定套包括相互连接的法兰盘和套筒,所述固定套经所述套筒套装在所述支撑套管的外露端上,并经所述法兰盘同所述桁架固定连接。4. A truss fixing mechanism on a bridge pier column according to claim 3, characterized in that a fixing sleeve is provided on the truss, and the fixing sleeve comprises a flange plate and a sleeve connected to each other, and the fixing sleeve is The sleeve is sleeved on the exposed end of the support sleeve through the sleeve, and is fixedly connected with the truss through the flange. 5.根据权利要求4所述的一种在桥墩立柱上的桁架固定机构,其特征在于所述销棒的外端凸出于所述固定套,在所述销棒的外端部上设置螺母并旋紧抵靠在所述固定套上以固定所述销棒。5. A truss fixing mechanism on a bridge pier column according to claim 4, wherein the outer end of the pin protrudes from the fixing sleeve, and a nut is provided on the outer end of the pin And screw it against the fixing sleeve to fix the pin.
CN202022189919.3U 2020-09-29 2020-09-29 Truss fixing mechanism on pier stand column Withdrawn - After Issue CN213740608U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022189919.3U CN213740608U (en) 2020-09-29 2020-09-29 Truss fixing mechanism on pier stand column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022189919.3U CN213740608U (en) 2020-09-29 2020-09-29 Truss fixing mechanism on pier stand column

Publications (1)

Publication Number Publication Date
CN213740608U true CN213740608U (en) 2021-07-20

Family

ID=76847195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022189919.3U Withdrawn - After Issue CN213740608U (en) 2020-09-29 2020-09-29 Truss fixing mechanism on pier stand column

Country Status (1)

Country Link
CN (1) CN213740608U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112176877A (en) * 2020-09-29 2021-01-05 上海城建市政工程(集团)有限公司 A truss fixing mechanism on a bridge pier column

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112176877A (en) * 2020-09-29 2021-01-05 上海城建市政工程(集团)有限公司 A truss fixing mechanism on a bridge pier column
CN112176877B (en) * 2020-09-29 2025-03-04 上海城建市政工程(集团)有限公司 A truss fixing mechanism on a bridge pier column

Similar Documents

Publication Publication Date Title
CN105908621B (en) It is a kind of to damage controllable Self-resetting precast segment steel-pipe assembly concrete pier and the practice
CN107974933B (en) The precast assembly bridge pier anti-seismic structure and its construction method of built-in replaceable viscous damper and energy consumption reinforcing bar
CN111305046B (en) A connection structure between a hingeless steel truss arch and an arch seat and a construction method thereof
CN213740608U (en) Truss fixing mechanism on pier stand column
CN206722087U (en) A kind of assembly concrete frame structure bracing members bearing
CN206034642U (en) Steel column flange formula splicing joint
CN206157913U (en) Assembled square steel tube concrete post and girder steel connected node
CN110670937B (en) A device and method for strengthening the interval of a transmission tower in service
CN215252270U (en) A new type of fast-assembled bridge pier reinforcement device
CN111042320A (en) Strength connecting device for building steel beam and wall
CN212802718U (en) Scalable folding bearing structure of assembled construction
CN112176877B (en) A truss fixing mechanism on a bridge pier column
CN206467580U (en) A kind of reinforced bridge pier
CN108729546A (en) A kind of dry type beam-to-column joint structure for prefabricated assembling type reinforced concrete building
CN219410506U (en) Thread prefabrication assembly node connection structure
CN105155408B (en) Bridge anti-overturning support and construction method thereof
CN209723215U (en) A kind of assembled architecture dry type beam-column connection
CN204753815U (en) Simple and easy assembly quality of assembled precast concrete post
CN104831746B (en) Preembedded streetlamp part mounting and positioning device
CN110307506A (en) Lamp pole foundation structure and street lamp
CN112227210B (en) Construction method for erecting prefabricated capping beam
CN112854018A (en) Steel truss girder pier top turning method and device
CN221972826U (en) A steel bar installation positioning structure in a steel bar reserved hole of a concrete prefabricated block
CN219773035U (en) Inspection shaft reinforced structure
CN219410594U (en) Reinforcing and supporting device for bridge superstructure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20210720

Effective date of abandoning: 20250304

AV01 Patent right actively abandoned

Granted publication date: 20210720

Effective date of abandoning: 20250304