CN213681929U - Road ponding treatment facility for municipal works - Google Patents

Road ponding treatment facility for municipal works Download PDF

Info

Publication number
CN213681929U
CN213681929U CN202021942411.XU CN202021942411U CN213681929U CN 213681929 U CN213681929 U CN 213681929U CN 202021942411 U CN202021942411 U CN 202021942411U CN 213681929 U CN213681929 U CN 213681929U
Authority
CN
China
Prior art keywords
block
sewage tank
sliding
fixed
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021942411.XU
Other languages
Chinese (zh)
Inventor
王伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Huatian Electromechanical Engineering Co ltd
Original Assignee
Kaifeng Hongtai Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kaifeng Hongtai Construction Engineering Co ltd filed Critical Kaifeng Hongtai Construction Engineering Co ltd
Priority to CN202021942411.XU priority Critical patent/CN213681929U/en
Application granted granted Critical
Publication of CN213681929U publication Critical patent/CN213681929U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a road accumulated water treatment device for municipal engineering, which comprises a sewage tank, an L-shaped installation plate block and a lifting platform, wherein the upper surface of the L-shaped installation plate block is fixedly provided with the sewage tank, the bottom inside the sewage tank is fixedly provided with a water pump, both ends of the water pump are fixedly connected with a water pipe, one end of the water pipe is communicated with the bottom inside the sewage tank, the top end of the other end of the water pipe penetrates through the upper surface of the sewage tank and is fixedly connected with a plastic hose, the surface of one side of the sewage tank is fixedly connected with the lifting platform, the upper surface of the lifting platform is penetrated and provided with a slide rail, the inner part of the slide rail is movably provided with a sliding installation block, the device can temporarily store sucked garbage through the dust collector, the pollution to the environment caused by the random release of the garbage is reduced, and the sewage tank is also, therefore, the absorbed sewage can be treated in a centralized way, and the pollution of the water body caused by the random discharge of the accumulated water is avoided.

Description

Road ponding treatment facility for municipal works
Technical Field
The utility model relates to a municipal administration maintenance equipment technical field specifically is a road ponding treatment facility for municipal works.
Background
The existing roads are mainly divided into four types, namely ordinary stone roads, cement concrete roads, asphalt concrete roads and recycled asphalt concrete roads, the road surfaces of the roads are often influenced by underground water, rainwater, heavy-duty vehicles, external natural factors and the like, sunken road pits are often formed, water is easily accumulated in the sunken road pits in rainy days, and the situation of splashing of water can be caused when a motor vehicle drives the pits with accumulated water, so that the normal running of pedestrians, non-motor vehicles and motor vehicles beside the roads can be influenced, the accumulated water in the sunken road pits is not treated in time, the damage of the road surfaces can be accelerated under the condition of heavy-duty vehicle rolling, the road maintenance cost is increased, and therefore, the drainage treatment on the road sections with the accumulated water is needed, but the existing accumulated water treatment equipment has the following problems:
current ponding treatment facility adopts the manual work to utilize the broom to sweep or use the water pump to carry out the suction usually, artifical sweeping will be very waste time when to the great puddle of some areas like this, and work efficiency is poor, the intensity and the cost of artifical work have been increased, and when to some less foundation ditches, adopt the water pump very again not to repay, current ponding needs the manual work to carry out the operation on the road for a long time when handling in addition and sweeps, will increase safe risk like this, current ponding treatment facility does not have the device that rubbish stored in addition, be difficult to deposit when meetting rubbish like this, consequently, the road ponding treatment facility for municipal works is needed urgently to solve the problem that the aforesaid was proposed.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a road ponding treatment facility for municipal works to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
a road accumulated water treatment device for municipal engineering comprises a sewage tank, an L-shaped installation plate block and a lifting platform, wherein the upper surface of the L-shaped installation plate block is fixedly provided with the sewage tank, the bottom inside the sewage tank is fixedly provided with a water pump, two ends of the water pump are both fixedly connected with a water pipe, one end of the water pipe is communicated with the bottom inside the sewage tank, the top end of the water pipe at the other end penetrates through the upper surface of the sewage tank and is fixedly connected with a plastic hose, the surface of one side of the sewage tank is fixedly connected with the lifting platform, the upper surface of the lifting platform is penetrated and provided with a slide rail, the slide rail is movably provided with a sliding installation block, a second electric push rod is fixedly arranged between the lower surface of the sliding installation block and the upper surface of the L-shaped installation plate block, the upper surface of the sliding installation block is penetrated and provided, the utility model discloses a suction pipe, including suction pipe, baffle, sliding mounting piece, fixed connection has the baffle, the top of suction pipe runs through fixedly connected with baffle, just the baffle is located the upper surface of sliding mounting piece, the upper surface of baffle runs through fixedly connected with plastic hose, the fixed suction head that is provided with of lower extreme of suction pipe, there is the filter screen in the inside of suction head through screw threaded connection.
As a further aspect of the present invention: the utility model discloses a garbage can, including L shape installation plate, dustbin, hinge activity, door plant, pull ring and press piece, the last fixed surface of L shape installation plate is provided with the dustbin, the dustbin is located the left side of sewage case, the surface of dustbin one side is provided with the door plant through the hinge activity, the fixed pull ring that is provided with respectively in surface of door plant is pressed the piece, it is connected with the connecting sleeve pole through the bearing rotation to press the surperficial both sides of piece, the fixed surface of dustbin is provided with the fixed block, the fixed block is connected.
As a further aspect of the present invention: the lower surface of L shape installation plate all fixedly mounted all around has first electric putter, every the equal fixedly mounted in bottom of first electric putter has the universal wheel, every the surface of universal wheel one side all is connected with the brake ware through the bearing rotation.
As a further aspect of the present invention: the upper surface of L shape installation plate runs through and sets up the recess, the lower surface of dustbin runs through fixedly to be provided with the connecting tube, just the connecting tube activity is located the inside of recess, the bottom fixed mounting of connecting tube has the dust catcher, the dust catcher is located the lower surface of L shape installation plate.
As a further aspect of the present invention: the surface on the right side of the L-shaped mounting plate is uniformly and fixedly provided with two push-pull handles, the surfaces of the two push-pull handles are fixedly sleeved with rubber ferrules, and the surfaces of the rubber ferrules are uniformly and fixedly provided with a plurality of protruding blocks.
As a further aspect of the present invention: the sliding installation block is connected with the sliding rail in a sliding mode, and the sliding installation block is matched with the sliding rail in size.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses an install the dustbin, can carry out temporary depositing with the rubbish suction through the dust catcher like this, the pollution that rubbish was put in disorder at will and is caused the environment has been reduced, and the device still installs the sewage case, can carry out centralized processing with absorptive sewage like this, avoid ponding to discharge at will and cause the pollution of water, and one side of sewage case is provided with the suction head, can utilize the suction head with the ponding suction like this, thereby replaced the use manual work to clean, like this greatly reduced the intensity and the cost of labor, the inside of suction head still is provided with the one deck filter screen, the phenomenon that can prevent impurity and stop up the suction head like this takes place, in addition the device still installs second electric putter, can carry out the water absorption according to the actual pit depth of depth like this, the practicality of device is improved.
2. In addition, the utility model discloses still through installing first electric putter, can rise or reduce the height of L shape installation plate like this as required, prevent that ponding from leading to the inside into of dustbin deeply, the device still is provided with universal wheel and push-and-pull handle moreover, makes things convenient for operating personnel mobile device to go forward like this more, has also reduced the danger at the road operation.
Drawings
FIG. 1 is a schematic view of an overall three-dimensional front view structure of a road ponding treatment device for municipal works.
FIG. 2 is a schematic view of the overall main section structure of the road ponding treatment equipment for municipal works.
FIG. 3 is a schematic view of a three-dimensional display structure of an L-shaped mounting plate in the road accumulated water treatment equipment for municipal engineering.
Fig. 4 is a schematic view of a three-dimensional display structure of a lifting platform in the road accumulated water treatment equipment for municipal engineering.
FIG. 5 is a schematic view of a part of an enlarged structure at A in the road ponding treatment device for municipal works.
In the figure: the garbage can comprises a garbage can 1, a sewage tank 2, an L-shaped mounting plate 3, a door panel 4, a lifting platform 5, a universal wheel 6, a first electric push rod 7, a second electric push rod 8, a sliding mounting block 9, a baffle 10, a plastic hose 11, a suction pipe 12, a fixed block 13, a dust collector 14, a hinge 15, a rubber ferrule 16, a pull ring 17, a pressing block 18, a connecting ferrule rod 19, a brake 20, a push-pull handle 21, a water pump 22, a connecting pipeline 23, a suction head 24, a water pipe 25, a filter screen 26, a groove 27, a slide rail 28 and screws 29.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1 to 5, in the embodiment of the present invention, a road accumulated water treatment device for municipal engineering comprises a sewage tank 2, an L-shaped mounting plate 3 and a lifting platform 5, wherein the upper surface of the L-shaped mounting plate 3 is fixedly provided with the sewage tank 2, the bottom inside the sewage tank 2 is fixedly provided with a water pump 22, two ends of the water pump 22 are fixedly connected with water pipes 25, one end of the water pipe 25 is communicated with the bottom inside the sewage tank 2, the top end of the other end of the water pipe 25 penetrates through the upper surface of the sewage tank 2 and is fixedly connected with a plastic hose 11, the surface of one side of the sewage tank 2 is fixedly connected with the lifting platform 5, the upper surface of the lifting platform 5 is penetrated with a sliding rail 28, a sliding mounting block 9 is movably arranged inside the sliding rail 28, a second electric push rod 8 is fixedly arranged between the lower surface of the sliding mounting block 9 and the upper surface of the L-shaped mounting plate 3, a suction pipe 12 is movably arranged in the jack, the top end of the suction pipe 12 is fixedly connected with a baffle 10 in a penetrating way, the baffle 10 is positioned on the upper surface of a sliding installation block 9, the upper surface of the baffle 10 is fixedly connected with a plastic hose 11 in a penetrating way, the lower end of the suction pipe 12 is fixedly provided with a suction head 24, the interior of the suction head 24 is connected with a filter screen 26 through a screw 29 and a thread, the device is also provided with a sewage tank 2, so that the absorbed sewage can be treated in a centralized way, the pollution of water caused by the random discharge of the accumulated water is avoided, one side of the sewage tank 2 is provided with the suction head 24, so that the accumulated water can be sucked out by the suction head 24, the cleaning by manpower is replaced, the labor intensity and the cost are greatly reduced, the filter screen 26 is also arranged in the suction head 24, so that the phenomenon that, therefore, the water absorption treatment can be carried out by adjusting the extension degree of the suction head 24 according to the actual depth of the water pit, and the practicability of the device is improved.
Please refer to fig. 1, the fixed surface of the L-shaped installation plate 3 is provided with a dustbin 1, the dustbin 1 is located on the left side of the dustbin 2, the surface of one side of the dustbin 1 is movably provided with a door plate 4 through a hinge 15, the surface of the door plate 4 is respectively fixedly provided with a pull ring 17 and a pressing block 18, the two sides of the surface of the pressing block 18 are rotatably connected with a connecting loop bar 19 through a bearing, the fixed surface of the dustbin 1 is provided with a fixed block 13, the fixed block 13 is connected with the connecting loop bar 19 in a clamping manner, the utility model discloses an install the dustbin 1, can temporarily store the rubbish suction through a dust collector 14, and reduce the pollution to the environment caused by randomly and disorderly placing rubbish.
Please refer to fig. 1 and 2, all fixed mounting has first electric putter 7 around the lower surface of L shape installation plate 3, the equal fixed mounting in bottom of every electric putter 7 has universal wheel 6, the surface of every universal wheel 6 one side all is connected with brake 20 through the bearing rotation, the device is provided with universal wheel 6 and push-and-pull handle 21, make things convenient for operating personnel mobile device to go forward like this, the danger in road operation has also been reduced, the utility model discloses still through installing first electric putter 7, can rise or reduce the height of L shape installation plate 3 like this as required, prevent that ponding from leading to dustbin 1 inside intaking too deeply.
Referring to fig. 2 and 3, a groove 27 is formed through the upper surface of the L-shaped mounting plate 3, a connecting pipe 23 is fixedly formed through the lower surface of the trash can 1, the connecting pipe 23 is movably located inside the groove 27, a dust collector 14 is fixedly mounted at the bottom of the connecting pipe 23, and the dust collector 14 is located on the lower surface of the L-shaped mounting plate 3.
Referring to fig. 2, the push-pull handles 21 are uniformly and fixedly arranged on the right side surface of the L-shaped mounting plate 3, two push-pull handles 21 are arranged, the rubber ferrules 16 are fixedly sleeved on the surfaces of the two push-pull handles 21, the rubber ferrules 16 are soft in texture and can protect the palms of operators from being damaged, and a plurality of protruding blocks are uniformly and fixedly arranged on the surface of the rubber ferrules 16 and are used for increasing friction and preventing sliding in the pushing process.
Referring to fig. 1, the sliding mounting block 9 is slidably connected to the sliding rail 28, and the size of the sliding mounting block 9 is matched with that of the sliding rail 28.
The utility model discloses a theory of operation is: when using the utility model discloses a, at first should promote the device to the place of needs through push-and-pull handle 21 and universal wheel 6, then drive the slidable mounting piece 9 of connection above-mentioned through second electric putter 8 and reciprocate on elevating platform 5, stretch into ponding with the bottom of suction head 24 when moving suitable position, at this moment the inside water pump 22 of sewage case 2 will be with ponding extraction come in, unnecessary impurity rubbish can be separated by filter screen 26 and filtered when the extraction, after the extraction is accomplished, carry out suction to dustbin 1 inside through dust catcher 14 with inside rubbish and deposit temporarily, if meet the darker district of ponding, can drive L shape installation plate 3 through first electric putter 7 and shift up, prevent the inside of dustbin 1 from intaking, later repeat above-mentioned operation and finish ponding, later on according to pressing the block 18 and loosen the block connection between connecting loop bar 19 and the fixed block 13 and open door plant 4 and get inside rubbish and get And (4) treating the sewage, and then treating the sewage in the sewage tank 2.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (6)

1. The utility model provides a road ponding treatment facility for municipal works, includes sewage case (2), L shape installation plate piece (3) and elevating platform (5), its characterized in that: the upper surface of the L-shaped mounting plate block (3) is fixedly provided with a sewage tank (2), the bottom inside the sewage tank (2) is fixedly provided with a water pump (22), two ends of the water pump (22) are fixedly connected with water pipes (25), one end of each water pipe (25) is communicated with the bottom inside the sewage tank (2), the top end of the other end of each water pipe (25) penetrates through the upper surface of the sewage tank (2) and is fixedly connected with a plastic hose (11), the surface of one side of the sewage tank (2) is fixedly connected with a lifting platform (5), the upper surface of the lifting platform (5) is provided with a sliding rail (28) in a penetrating way, a sliding mounting block (9) is movably arranged inside the sliding rail (28), a second electric push rod (8) is fixedly arranged between the lower surface of the sliding mounting block (9) and the upper surface of the L-shaped mounting plate block (3), the upper surface of the sliding mounting block (9) is provided with a, the inside activity of jack is provided with straw (12), fixedly connected with baffle (10) is run through on the top of straw (12), just baffle (10) are located the upper surface of slidable mounting piece (9), fixedly connected with plastic hose (11) is run through on the upper surface of baffle (10), the fixed suction head (24) that is provided with of lower extreme of straw (12), screw (29) threaded connection has filter screen (26) in the inside of suction head (24).
2. The road ponding treatment device for municipal engineering according to claim 1, characterized in that: the utility model discloses a garbage can, including L shape installation plate piece (3), last fixed surface of L shape installation plate piece (3) is provided with dustbin (1), dustbin (1) is located the left side of sewage case (2), the surface of dustbin (1) one side is provided with door plant (4) through hinge (15) activity, the fixed pull ring (17) and the pressure piece (18) of being provided with respectively in surface of door plant (4), the surperficial both sides of pressing piece (18) are connected with connection loop bar (19) through bearing rotation, the fixed surface of dustbin (1) is provided with fixed block (13), fixed block (13) are connected with connection loop bar (19) block.
3. The road ponding treatment device for municipal engineering according to claim 1, characterized in that: the lower surface of L shape installation plate piece (3) all fixed mounting all has first electric putter (7) all around, every the equal fixed mounting in bottom of first electric putter (7) has universal wheel (6), every the surface of universal wheel (6) one side all is connected with brake ware (20) through the bearing rotation.
4. The road ponding treatment device for municipal engineering according to claim 2, characterized in that: the upper surface of L shape installation plate piece (3) runs through and sets up fluted (27), the lower surface of dustbin (1) runs through fixed connecting tube (23) that is provided with, just connecting tube (23) activity is located the inside of recess (27), the bottom fixed mounting of connecting tube (23) has dust catcher (14), dust catcher (14) are located the lower surface of L shape installation plate piece (3).
5. The road ponding treatment device for municipal engineering according to claim 1, characterized in that: push-pull handles (21) are uniformly and fixedly arranged on the surface of the right side of the L-shaped mounting plate block (3), two push-pull handles (21) are arranged, rubber ferrules (16) are fixedly sleeved on the surfaces of the two push-pull handles (21), and a plurality of protruding blocks are uniformly and fixedly arranged on the surfaces of the rubber ferrules (16).
6. The road ponding treatment device for municipal engineering according to claim 1, characterized in that: the sliding installation block (9) is connected with the sliding rail (28) in a sliding mode, and the sliding installation block (9) is matched with the sliding rail (28) in size.
CN202021942411.XU 2020-09-08 2020-09-08 Road ponding treatment facility for municipal works Active CN213681929U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021942411.XU CN213681929U (en) 2020-09-08 2020-09-08 Road ponding treatment facility for municipal works

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021942411.XU CN213681929U (en) 2020-09-08 2020-09-08 Road ponding treatment facility for municipal works

Publications (1)

Publication Number Publication Date
CN213681929U true CN213681929U (en) 2021-07-13

Family

ID=76746839

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021942411.XU Active CN213681929U (en) 2020-09-08 2020-09-08 Road ponding treatment facility for municipal works

Country Status (1)

Country Link
CN (1) CN213681929U (en)

Similar Documents

Publication Publication Date Title
CN103334487B (en) Urban underground round rainwater pipeline dredging device
CN213681929U (en) Road ponding treatment facility for municipal works
CN108560940B (en) High-efficient ceramic tile floor excavation device
CN213268294U (en) Sewer grid plate pull throughs that municipal works were used
CN210177428U (en) Road surface ash removal device for road construction
CN202273257U (en) Door type hydraulic grab bucket trash remover
CN217949303U (en) Hydraulic push rod sewer cleaning robot
CN214245888U (en) A escape canal cleaning device for gardens construction
CN217810433U (en) Road surface gap slip casting patching device with deashing function
CN215330409U (en) Municipal administration public works are led to stifled device with drainage
CN213952472U (en) Underground foreign matter fishing device for municipal works
CN215330343U (en) Water supply and drainage equipment for building construction
CN111719481B (en) Expansion joint cleaning method and cleaning device
CN219863047U (en) Silt cleaning equipment
CN221193645U (en) Water conservancy construction is with ponding extraction equipment
CN217676158U (en) Antiskid of town road engineering design
CN217736484U (en) Pipeline laying device for municipal pipeline
CN221276473U (en) Construction drainage structures of infiltration section road bed
CN215948419U (en) Drainage device for sponge road
CN204822848U (en) Slope rubbish compressor
CN116791722B (en) Cable pit drainage device for power equipment
CN215052561U (en) Cleaning device for accumulated water on hollow pavement
CN212582372U (en) Small-size device of milling in road surface
CN216254380U (en) Turf planting device for municipal works
CN214831703U (en) Road surface compaction device for highway construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20231012

Address after: No. 61, Unit 1, Building 11, No. 53 Yingchun Street, High tech Development Zone, Zhengzhou City, Henan Province, 450000

Patentee after: Zhang Hongwei

Address before: 475500 north side of Fuyuan Road East section, Weishi County, Kaifeng City, Henan Province

Patentee before: Kaifeng Hongtai Construction Engineering Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231026

Address after: Floor 6, building 52, Lianhua street, high tech Industrial Development Zone, Zhengzhou City, Henan Province

Patentee after: Henan Huatian Electromechanical Engineering Co.,Ltd.

Address before: No. 61, Unit 1, Building 11, No. 53 Yingchun Street, High tech Development Zone, Zhengzhou City, Henan Province, 450000

Patentee before: Zhang Hongwei

TR01 Transfer of patent right