CN213597452U - Novel building scaffold - Google Patents

Novel building scaffold Download PDF

Info

Publication number
CN213597452U
CN213597452U CN202022222839.3U CN202022222839U CN213597452U CN 213597452 U CN213597452 U CN 213597452U CN 202022222839 U CN202022222839 U CN 202022222839U CN 213597452 U CN213597452 U CN 213597452U
Authority
CN
China
Prior art keywords
building
wall
vertical frame
electric hoist
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022222839.3U
Other languages
Chinese (zh)
Inventor
冯虎庭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Senrui Construction Engineering Co ltd
Original Assignee
Hubei Senrui Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Senrui Construction Engineering Co ltd filed Critical Hubei Senrui Construction Engineering Co ltd
Priority to CN202022222839.3U priority Critical patent/CN213597452U/en
Application granted granted Critical
Publication of CN213597452U publication Critical patent/CN213597452U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a novel construction scaffold, include: the vertical frame is vertically arranged close to the outer wall of the building; the keel plates are sequentially and fixedly connected with the vertical frame along the height direction of the vertical frame, and are arranged in parallel to a horizontal plane; the wall-attached supports are multiple and are fixedly connected with the outer wall of the building in sequence along the height direction of the building, and one side of each wall-attached support is connected with the sliding rail in a sliding manner; electric hoist, electric hoist's one end with the detachable fixed connection of building, electric hoist's the other end with the detachable fixed connection of grudging post, electric hoist is used for driving the grudging post relatively the building slides in vertical direction, and the grudging post can apply the outer wall upward movement of building, is provided with the multilayer keel board on the grudging post, and constructor all can stand on every layer keel board improves the efficiency of construction.

Description

Novel building scaffold
Technical Field
The utility model relates to a construction equipment technical field, concretely relates to novel construction scaffolding.
Background
The scaffold is a frame body which is erected at a certain height and attached to a building structure, can climb or descend along with an engineering structure layer by depending on self lifting equipment and devices, generally has only one-layer structure in the scaffold in the prior art, can only be used for constructing one-layer buildings at a time, and is low in construction efficiency.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to overcome above-mentioned technique not enough, provide a novel construction scaffolding, solve the lower technical problem of scaffold frame efficiency of construction that uses among the prior art.
In order to achieve the above technical purpose, the technical scheme of the utility model provide a novel construction scaffold, include:
the vertical frame is vertically arranged close to the outer wall of the building, and one side, opposite to the outer wall of the building, of the vertical frame is provided with a vertically arranged slide rail;
the keel plates are sequentially and fixedly connected with the vertical frame along the height direction of the vertical frame, and are arranged in parallel to a horizontal plane;
the wall-attached supports are multiple and are fixedly connected with the outer wall of the building in sequence along the height direction of the building, and one side of each wall-attached support is connected with the sliding rail in a sliding manner;
the electric hoist, the one end of electric hoist with the detachable fixed connection of building, the other end of electric hoist with the detachable fixed connection of grudging post, the electric hoist is used for the drive the grudging post is relative the building slides in vertical direction.
Furthermore, the wall-attached support comprises triangular support frames, and the triangular support frames are fixed on the lower sides of the keel plates.
Further, attach the wall support and include the leading truck, the one end of leading truck with the outer wall fixed connection of building, the other end of leading truck is provided with two at least pulleys of mutual disposition, the slide rail is the I-steel of vertical arrangement, places in the pulley one-to-one of two mutual dispositions slides in the both sides spout of I-steel.
Further, attach the wall support and still include sleeve pipe, connecting rod, dop and elastic component, sheathed tube one end with the leading truck is articulated, sheathed tube upper end is to being close to the direction slope of grudging post, the lower extreme of connecting rod with the coaxial threaded connection of sleeve pipe, the dop with the upper end threaded connection of connecting rod, the upper end of dop is provided with concave cambered surface, it has set gradually the joint axle to be provided with a plurality of along its direction of height on the grudging post, the axis level of joint axle arranges, but concave cambered surface butt in arbitrary the downside of joint axle, the one end of elastic component with sleeve pipe fixed connection, the other end of elastic component with leading truck fixed connection.
Further, an outer protective net is arranged on one side, far away from the building, of the vertical frame.
Compared with the prior art, the beneficial effects of the utility model include: this novel building scaffold sets up on the outer wall of building when using, through the promotion of electric hoist, the outer wall upward movement of building can be applied in the grudging post, is provided with the multilayer keel board on the grudging post, all can stand constructor on every layer keel board to can realize the synchronous construction of multilayer to the building, improve the efficiency of construction.
Drawings
Fig. 1 is a schematic perspective view of an embodiment of the novel building scaffold provided by the present invention;
FIG. 2 is an enlarged partial schematic view at A of FIG. 1;
fig. 3 is a schematic side view of an embodiment of the novel building scaffold provided by the present invention;
FIG. 4 is an enlarged partial schematic view at B of FIG. 3;
fig. 5 is a schematic view of the connection structure of the downward-looking surface of the wall-attached support.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
It will be understood that when an element is referred to as being "secured to" another element, it can be directly on the other element or intervening elements may also be present. When an element is referred to as being "connected" to another element, it can be directly connected to the other element or intervening elements may also be present. The terms "vertical," "horizontal," "left," "right," and the like as used herein are for illustrative purposes only and do not represent the only embodiments.
Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. The terminology used in the description of the invention herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.
Referring to fig. 1 to 5, the present embodiment provides a novel building scaffold, including: the device comprises a vertical frame 1, a keel plate 2, a wall-attached support 3 and an electric hoist 4.
The vertical frame 1 is vertically arranged close to the outer wall of a building, and one side, opposite to the outer wall of the building 5, of the vertical frame 1 is provided with a vertically arranged slide rail 1 a; the keel plates 2 are arranged in a plurality, the keel plates 2 are sequentially and fixedly connected with the vertical frame 1 along the height direction of the vertical frame 1, and each keel plate 2 is arranged in parallel to a horizontal plane; the wall-attached supports 3 are multiple, the wall-attached supports 3 are sequentially and fixedly connected with the outer wall of the building 5 along the height direction of the building 5, and one side of each wall-attached support 3 is slidably connected with the slide rail 1 a; the one end of electric hoist 4 with the detachable fixed connection of building 5, the other end of electric hoist 4 with the detachable fixed connection of grudging post 1, electric hoist 4 is used for the drive grudging post 1 is relative building 5 slides in vertical direction, grudging post 1 is kept away from one side of building 5 is provided with outer protection network (not shown in the figure).
This novel building scaffold sets up on building 5's outer wall when using, through the promotion of electric hoist 4, the outer wall upward movement of building 5 can be applied in grudging post 1, is provided with multilayer keel board 2 on the grudging post 1, and constructor all can stand on every layer keel board 2 to can realize the synchronous construction of multilayer to building 5, improve the efficiency of construction.
Further, novel construction scaffolding still includes triangular supports 7, every the downside of keel board 2 is fixed with triangular supports 7, triangular supports 7 are right triangle, triangular supports 7 are used for improving keel board 2's bearing strength.
Furthermore, the wall-attached support 3 comprises a guide frame 31, one end of the guide frame 31 is fixedly connected with the outer wall of the building 5, the other end of the guide frame 31 is provided with at least two pulleys 32 which are arranged oppositely, the slide rail 1a comprises two vertically arranged channel steel 1a1, the notches of the channel steel 1a1 are deviated and arranged, the two pulleys 32 which are arranged oppositely are arranged in the two channel steel 1a1 in a one-to-one corresponding sliding manner, the wall-attached support 3 further comprises a sleeve 33, a connecting rod 34, a clamping head 35 and an elastic part 36, the elastic part 36 is a spiral spring, one end of the sleeve 33 is hinged to the guide frame 31, the upper end of the sleeve 33 inclines towards the direction close to the vertical frame 1, the lower end of the connecting rod 34 is connected with the coaxial thread of the sleeve 33, the upper end of the clamping head 35 is provided with a concave arc surface 35a, the vertical frame 1 is provided with a plurality of clamping shafts 8 which are arranged at intervals in sequence along, the axis of the clamping shaft 8 is horizontally arranged, the concave arc surface 35a can be abutted to any lower side of the clamping shaft 8, one end of the elastic piece 36 is fixedly connected with the sleeve 33, the other end of the elastic piece 36 is fixedly connected with the guide frame 31, the clamping shaft 8 is pasted on the outer side of the clamping head 35 to slide upwards in the upward movement process of the stand 1, meanwhile, the upper end of the sleeve 33 is pushed to deflect towards one side close to the stand 1, the elastic piece 36 is stretched at the moment, when the clamping shaft 8 in contact with the clamping head 35 slides to the upper end of the clamping head 35, the clamping head 35 loses the blocking of the clamping shaft 8, under the action of the elastic restoring force of the elastic piece 36, the clamping head 35 deflects to be under the clamping shaft 8 adjacent to the clamping head 35, so that the unidirectional locking is realized, the connecting rod can be rotated to realize the adjustment of the distance between the connecting rod 34 and the two ends of the sleeve 33, the clamping head 35 is in threaded connection with the upper end of the, after the overall length of the link 34 and the sleeve 33 is adjusted, the chuck 35 is rotated so that the axis of the concave arc surface 35a is parallel to the axis of the chuck shaft 8, and the chuck shaft 8 is disposed between the back surfaces of the two channel beams 1a1, so that the chuck shaft 8 does not interfere with the movement of the pulley 32.
In this embodiment, one end of the electric hoist 4 is detachably and fixedly connected with the building 5, specifically, the middle part or the upper part of the hoisting iron chain 4c of the electric hoist 4 is fixed on one metal block 4a, and the metal block 5a is provided with a bolt hole, so that bolts arranged on any floor can be fixedly connected.
The other end of the electric hoist 4 is detachably and fixedly connected with the vertical frame 1, and specifically, a hook 4a at the lower end of a hoisting iron chain 4c of the electric hoist 4 is hooked on any cross beam and groove at the lower part of the vertical frame 1.
In another embodiment, the uppermost end of the hoisting iron chain of the electric hoist is connected to a fixed pulley provided on the roof of the building, and the hook of the hoisting iron chain of the electric hoist is fixedly connected to any position of the vertical frame 1, so that the vertical frame 1 can be hoisted, and the metal block 4a does not need to be provided in this embodiment.
This novel building scaffold sets up on building 5's outer wall when using, through the promotion of electric hoist 4, the outer wall upward movement of building 5 can be applied in grudging post 1, is provided with multilayer keel board 2 on the grudging post 1, and constructor all can stand on every layer keel board 2 to can realize the synchronous construction of multilayer to building 5, improve the efficiency of construction.
The above description of the present invention does not limit the scope of the present invention. Any other corresponding changes and modifications made according to the technical idea of the present invention should be included in the scope of the claims of the present invention.

Claims (5)

1. A novel building scaffold, comprising:
the vertical frame is vertically arranged close to the outer wall of the building, and one side, opposite to the outer wall of the building, of the vertical frame is provided with a vertically arranged slide rail;
the keel plates are sequentially and fixedly connected with the vertical frame along the height direction of the vertical frame, and are arranged in parallel to a horizontal plane;
the wall-attached supports are multiple and are fixedly connected with the outer wall of the building in sequence along the height direction of the building, and one side of each wall-attached support is connected with the sliding rail in a sliding manner;
the electric hoist, the one end of electric hoist with the detachable fixed connection of building, the other end of electric hoist with the detachable fixed connection of grudging post, the electric hoist is used for the drive the grudging post is relative the building slides in vertical direction.
2. The novel construction scaffold as claimed in claim 1, further comprising a triangular support frame, said triangular support frame being fixed to the underside of each keel plate.
3. The novel building scaffold as claimed in claim 1, wherein the wall-attached support comprises a guide frame, one end of the guide frame is fixedly connected with the outer wall of the building, the other end of the guide frame is provided with at least two pulleys arranged oppositely, the slide rail comprises two vertically arranged channel steels, the notches of the two channel steels are arranged oppositely, and the two pulleys arranged oppositely are arranged in the two channel steels in a one-to-one sliding manner.
4. The novel building scaffold as claimed in claim 3, wherein the wall-attached support further comprises a sleeve, a connecting rod, a chuck and an elastic member, one end of the sleeve is hinged to the guide frame, the upper end of the sleeve inclines towards the direction close to the vertical frame, the lower end of the connecting rod is coaxially and threadedly connected with the sleeve, the chuck is threadedly connected with the upper end of the connecting rod, the upper end of the chuck is provided with a concave arc surface, the vertical frame is provided with a plurality of clamping shafts which are sequentially arranged at intervals along the height direction of the clamping shafts, the axes of the clamping shafts are horizontally arranged, the concave arc surface can abut against the lower side of any one of the clamping shafts, one end of the elastic member is fixedly connected with the sleeve, and the other end of the elastic member is fixedly connected with the guide frame.
5. The novel building scaffold as claimed in claim 1, wherein the side of the stand away from the building is provided with an external protective net.
CN202022222839.3U 2020-09-30 2020-09-30 Novel building scaffold Active CN213597452U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022222839.3U CN213597452U (en) 2020-09-30 2020-09-30 Novel building scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022222839.3U CN213597452U (en) 2020-09-30 2020-09-30 Novel building scaffold

Publications (1)

Publication Number Publication Date
CN213597452U true CN213597452U (en) 2021-07-02

Family

ID=76589664

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022222839.3U Active CN213597452U (en) 2020-09-30 2020-09-30 Novel building scaffold

Country Status (1)

Country Link
CN (1) CN213597452U (en)

Similar Documents

Publication Publication Date Title
CN206706591U (en) A kind of horizontal splicing apparatus for packaged type bridges precast pier template
CN202785364U (en) Movable dual-door-type mast hoisting device
CN213597452U (en) Novel building scaffold
CN107601257A (en) Large scale arc special hoisting bar and its application method
CN211114737U (en) A construction operation platform in elevator well for tower crane promotes
CN112982935A (en) Pull-up scaffold for wide-scene balcony and construction method thereof
CN105819352B (en) Lifting device for detachable door type mast building and construction method thereof
CN101143689B (en) Internal climbing tower crane double-beam shape internal climbing foundation and internal climbing jacket frame
CN216807824U (en) Pipeline mobile device for hydraulic engineering
CN211078166U (en) Pipeline vertical hoisting device
CN109516390B (en) Flat-head tower crane convenient for manual carrying and installation and field installation method
CN210340110U (en) Two T board hoisting structure of large-span assembled
CN201459602U (en) Equipment for bridge construction
CN206625532U (en) Elevating construction platform bedframe and base
CN206487128U (en) A kind of Guiding Support Elevating Scaffold
CN205932875U (en) Telescopic landing stage is used to steel construction integration elevator
CN201087080Y (en) Double-beam inner climbing base plate and sleeve rack for inner climbing tower crane
CN219710948U (en) Push-pull platform device for wall attachment position of climbing tower crane
CN221876290U (en) Adjustable gun carriage tool
CN112695996B (en) Self-climbing device in elevator shaft and construction method thereof
CN103711299A (en) Liftable scaffold for building outer wall
CN212406055U (en) Lifting hanging point
CN214575545U (en) Building hoisting top bridge
CN220058774U (en) Split heads hanging basket suspension
CN213595758U (en) Lifting device of inverted lifting frame

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant