CN213569221U - Petrochemical engineering pipeline installation hoisting accessory - Google Patents

Petrochemical engineering pipeline installation hoisting accessory Download PDF

Info

Publication number
CN213569221U
CN213569221U CN202022217561.0U CN202022217561U CN213569221U CN 213569221 U CN213569221 U CN 213569221U CN 202022217561 U CN202022217561 U CN 202022217561U CN 213569221 U CN213569221 U CN 213569221U
Authority
CN
China
Prior art keywords
hanging beam
cantilever
horizontal hanging
horizontal
upper portion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022217561.0U
Other languages
Chinese (zh)
Inventor
肖然
孙正悦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Fourth Construction Co Ltd
Original Assignee
Sinopec Fourth Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Fourth Construction Co Ltd filed Critical Sinopec Fourth Construction Co Ltd
Priority to CN202022217561.0U priority Critical patent/CN213569221U/en
Application granted granted Critical
Publication of CN213569221U publication Critical patent/CN213569221U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a petrochemical engineering piping erection hoisting accessory, including two slide rails and supports along horizontal extension, be equipped with fixed knot structure bottom the slide rail, support and sliding rail connection, top at the support is equipped with the longeron, below at the longeron be equipped with rather than the horizontal hanging beam in vertically upper portion, the horizontal hanging beam in upper portion and longeron sliding connection, the below at the horizontal hanging beam in upper portion is equipped with the horizontal hanging beam in lower part, the horizontal hanging beam in lower part and the horizontal hanging beam both ends in upper portion adopt the telescopic link to connect, the middle part adopts electric block to connect, below rigid coupling at the horizontal hanging beam in lower part has vertical hanging beam, one end at vertical hanging beam is connected with fixed cantilever, the other end is connected with movable cantilever, movable cantilever and vertical hanging beam sliding connection, movable cantilever is driven by the lead screw, movable cantilever and fixed cantilever inboard all are. The utility model discloses can improve the piping erection and lift by crane efficiency and installation accuracy, effective control hoist and mount cost to can reuse.

Description

Petrochemical engineering pipeline installation hoisting accessory
Technical Field
The utility model relates to a device for piping erection, especially a petrochemical industry engineering piping erection hoisting accessory.
Background
The pipeline just like the blood vessel among the petrochemical industry device, exists in a large number, in the device construction process, needs a large amount of installations, and the petrochemical industry pipeline is in the installation, often needs hoisting accessory to hang the petrochemical industry pipeline to the mounting height and installs. The traditional pipeline installation is lifted by crane and is mostly tied up with the hoist and mount area and operate on petrochemical industry pipeline, then reuse crane or chain block hoist and mount, at the in-process that lifts by crane, takes place to rock easily, can't accurately install petrochemical industry pipeline, has reduced work efficiency to the crane cost is higher, and chain block efficiency is lower.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a solve the technical problem who exists among the well-known technology and provide a petrochemical industry engineering piping erection hoisting accessory, the device can improve piping erection hoisting efficiency and installation accuracy, effective control hoist and mount cost to can reuse.
The utility model discloses a solve the technical scheme that technical problem that exists among the well-known technique took and be: the utility model provides a petrochemical engineering pipeline installation hoisting accessory, includes two parallel, along horizontal extension's slide rail and support of each other the slide rail bottom is equipped with fixed knot and constructs, the support pass through the bottom slider with the slide rail is connected the top of support is equipped with the longeron that three are parallel to each other the below of longeron is equipped with rather than the horizontal hanging beam in vertically upper portion, the horizontal hanging beam in upper portion passes through top slider and three the longeron is connected the below of the horizontal hanging beam in upper portion is equipped with the horizontal hanging beam in lower part, the horizontal hanging beam in lower part with the horizontal hanging beam both ends in upper portion adopt the telescopic link to connect, the middle part adopts electric block to connect, the below rigid coupling of the horizontal hanging beam in lower part has three rather than vertically vertical hanging beam the one end below of vertical hanging beam is connected with fixed cantilever the other end below of vertical hanging beam is connected with movable cantilever perpendicularly, the movable cantilever is connected with the longitudinal hanging beam in a sliding manner, the movable cantilever is driven by a screw rod, the screw rod extends along the longitudinal direction, is in threaded connection with the movable cantilever and is in rotary connection with the fixed cantilever, and a hand wheel is arranged at the free end of the screw rod; the inner sides of the movable cantilever and the fixed cantilever are both provided with clamps.
The longitudinal section of the clamp is arc-shaped.
The fixing structure adopts a clamping structure.
The top sliding block is assembled in a sliding groove, and the sliding groove is formed in the bottom of the longitudinal beam.
The electric hoist is provided with a power supply.
The utility model has the advantages and positive effects that: the direction is limited when the upper transverse hanging beam drives the lower transverse hanging beam to ascend through the electric hoist by matching the telescopic rod, the pipeline to be lifted is fixed on the lower transverse hanging beam by matching the clamp with the lower transverse hanging beam, the problem that the pipeline is deviated and shakes to influence the operation of constructors is avoided when the pipeline is lifted and installed, the construction difficulty is reduced, and the working efficiency is improved. Through the horizontal hanging beam in upper portion, the cooperation of the horizontal hanging beam in lower part and electric block is used, make the pipeline can be driven vertical removal by the horizontal hanging beam in lower part through anchor clamps, through the spout, the cooperation of top slider and the horizontal hanging beam in upper portion is used, make the pipeline can be driven longitudinal movement by the horizontal hanging beam in upper portion, through the slide rail, the cooperation of bottom slider and support is used, make the pipeline can be driven lateral shifting by the support, thereby make the device can drive the pipeline and remove in three-dimensional space, make the piping erection more convenient and laborsaving. To sum up, the utility model discloses can improve the piping erection and lift by crane efficiency and installation accuracy, effective control hoist and mount cost to can reuse.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a side view of FIG. 1;
fig. 3 is a cross-sectional view of the present invention.
In the figure: 1. a support; 2. a fixed structure; 3. a slide rail; 4. a bottom slider; 5. a lower transverse hanging beam; 6. fixing the cantilever; 7. a movable cantilever; 8. a telescopic rod; 9. a stringer; 10. an electric hoist; 11. an upper transverse suspension beam; 12. a longitudinal hanging beam; 13. a top slider; 14. a screw rod; 15. a hand wheel; 16. and (4) clamping.
Detailed Description
For further understanding of the contents, features and effects of the present invention, the following embodiments are exemplified in conjunction with the accompanying drawings as follows:
referring to fig. 1 to 3, a petrochemical engineering pipeline installation and hoisting device comprises two parallel sliding rails 3 extending in a transverse direction and a bracket 1, wherein the bottom of each sliding rail 3 is provided with a fixing structure 2, the bracket 1 is connected with the sliding rails 3 through a bottom sliding block 4, the top of the bracket 1 is provided with three parallel longitudinal beams 9, an upper transverse hanging beam 11 perpendicular to the longitudinal beams 9 is arranged below the longitudinal beams 9, the upper transverse hanging beam 11 is connected with the three longitudinal beams 9 through a top sliding block 13, a lower transverse hanging beam 5 is arranged below the upper transverse hanging beam 11, two ends of the lower transverse hanging beam 5 and the upper transverse hanging beam 11 are connected through a telescopic rod 8, the middle part of the lower transverse hanging beam 11 is connected through an electric hoist 10, three vertical hanging beams 12 perpendicular to the lower transverse hanging beam 5 are fixedly connected below one end of the vertical hanging beam 12, a fixed cantilever 6 is vertically connected below one end of the vertical hanging beam 12, a movable cantilever 7 is vertically connected below the other end of the longitudinal hanging beam 12, the movable cantilever 7 is connected with the longitudinal hanging beam 12 in a sliding manner, the movable cantilever 7 is driven by a screw rod 14, the screw rod 14 extends along the longitudinal direction, is in threaded connection with the movable cantilever 7 and is in rotary connection with the fixed cantilever 6, and a hand wheel 15 is arranged at the free end of the screw rod 14; the inner sides of the movable cantilever 7 and the fixed cantilever 6 are both provided with a clamp 16.
In this embodiment, the clamp 16 has an arc-shaped longitudinal section, so as to be in close contact with the pipe and clamp the pipe. The fixing structure 2 adopts a clasping structure, please refer to fig. 2, which is convenient for fixing. The top slide 13 is assembled in a slide groove provided at the bottom of the longitudinal beam 9. The electric hoist 10 is provided with a power supply, and is convenient to use.
The utility model discloses a theory of operation is:
when in use, the device is firstly moved to a position to be used and is fixed on a steel structure through the fixing structure 2; then the lifting hook of the electric hoist 10 is controlled to descend, and the lower transverse hanging beam 5 is put down; the pipeline to be installed is placed between the fixed cantilever 6 and the movable cantilever 7, the hand wheel 15 is rotated to enable the fixed cantilever 6 and the movable cantilever 7 to be close to each other, the inner side clamps 16 are clamped on two sides of the pipeline to be lifted, and the pipeline to be lifted is fixed between the clamps 16. And controlling the lifting hook of the electric hoist 10 to ascend to drive the lower transverse lifting beam 5 to ascend and drive the pipeline to be lifted to ascend. When the pipeline rises to the height required to be installed, the electric hoist 10 is controlled to stop rising, the pipeline is pushed to move longitudinally, the pipeline is aligned with the pipeline required to be butted, the support 1 is pushed to move transversely, the pipeline is contacted with the pipeline required to be butted, and the butting work of the pipeline is completed.
Although the preferred embodiments of the present invention have been described with reference to the accompanying drawings, the present invention is not limited to the above-mentioned embodiments, which are only illustrative and not restrictive, and those skilled in the art can make many forms without departing from the spirit and scope of the present invention, which is within the scope of the present invention.

Claims (5)

1. The utility model provides a petrochemical engineering pipeline installation hoisting accessory, its characterized in that includes two parallel, along horizontal extension's slide rail and support of each other the slide rail bottom is equipped with fixed knot and constructs, the support pass through the bottom slider with slide linkage the top of support is equipped with three longerons that are parallel to each other the below of longeron is equipped with rather than the horizontal hanging beam in vertically upper portion, the horizontal hanging beam in upper portion passes through top slider and three the longeron is connected the below of the horizontal hanging beam in upper portion is equipped with the horizontal hanging beam in lower part, the horizontal hanging beam in lower part with the horizontal hanging beam both ends in upper portion adopt the telescopic link to connect, the middle part adopts electric block to connect the below rigid coupling of the horizontal hanging beam in lower part has three rather than vertically vertical hanging beam the one end below of vertical hanging beam is connected with fixed cantilever the other end below of vertical hanging beam is connected with movable cantilever perpendicularly, the movable cantilever is connected with the longitudinal hanging beam in a sliding manner, the movable cantilever is driven by a screw rod, the screw rod extends along the longitudinal direction, is in threaded connection with the movable cantilever and is in rotary connection with the fixed cantilever, and a hand wheel is arranged at the free end of the screw rod; the inner sides of the movable cantilever and the fixed cantilever are both provided with clamps.
2. The petrochemical engineering pipeline installation lifting device of claim 1, wherein the clamp has an arc-shaped longitudinal section.
3. The petrochemical engineering pipeline installation lifting device according to claim 1, wherein the fixing structure is a clasping structure.
4. The petrochemical engineering pipeline installation lifting device of claim 1, wherein the top slide block is assembled in a chute, and the chute is disposed at the bottom of the longitudinal beam.
5. The petrochemical engineering pipeline installation lifting device according to claim 1, wherein the electric hoist is provided with a power supply.
CN202022217561.0U 2020-09-30 2020-09-30 Petrochemical engineering pipeline installation hoisting accessory Active CN213569221U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022217561.0U CN213569221U (en) 2020-09-30 2020-09-30 Petrochemical engineering pipeline installation hoisting accessory

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022217561.0U CN213569221U (en) 2020-09-30 2020-09-30 Petrochemical engineering pipeline installation hoisting accessory

Publications (1)

Publication Number Publication Date
CN213569221U true CN213569221U (en) 2021-06-29

Family

ID=76580817

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022217561.0U Active CN213569221U (en) 2020-09-30 2020-09-30 Petrochemical engineering pipeline installation hoisting accessory

Country Status (1)

Country Link
CN (1) CN213569221U (en)

Similar Documents

Publication Publication Date Title
CN210528272U (en) Hoisting equipment for prefabricated parts
CN203959642U (en) Steel plate hoisting implement
CN203045200U (en) Sucker hoisting device and plate welding logistics transporting system
CN201343385Y (en) Concentrated driving finished product checking crane
CN111847261A (en) Heavy-load intelligent carrying travelling crane
CN111779245A (en) Tile paving equipment and tile paving robot
CN112027933A (en) Multi-functional hoisting accessory that construction was used
CN213569221U (en) Petrochemical engineering pipeline installation hoisting accessory
CN112983303B (en) Integrated sucker rod automatic slip and operation process
CN206928916U (en) Stacking tubing string manipulator
CN115339992B (en) Lifting appliance system and lifting method for sleeper die
CN2693735Y (en) In and out kettle crane
CN2693736Y (en) Finished product crane
CN216376545U (en) Aerated brick clamping and hoisting device
CN104632104A (en) Auxiliary extension rod device of truck-mounted drilling rig
CN210313219U (en) Heavy-load intelligent carrying travelling crane
CN204457500U (en) A kind of auxiliary extension bar device of truck-mounted drilling rig
CN202201644U (en) Installation equipment for insulator supporting column of serial compensation platform
CN208308303U (en) Heavy wares translation system
CN207226853U (en) A kind of rigidity positioning hoisting apparatus for bridge crane
CN103612973A (en) Dead weight aerated brick clamp with force amplifying mechanism
CN105438958B (en) Rotating lifting steel-fastening structure component boom hoisting
CN220485143U (en) Building girder steel plate loading attachment
CN215797944U (en) Tubular pile hoisting system
CN219412509U (en) Workover robot

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant