CN213569128U - Locomotive air cylinder lifting appliance - Google Patents

Locomotive air cylinder lifting appliance Download PDF

Info

Publication number
CN213569128U
CN213569128U CN202022664948.0U CN202022664948U CN213569128U CN 213569128 U CN213569128 U CN 213569128U CN 202022664948 U CN202022664948 U CN 202022664948U CN 213569128 U CN213569128 U CN 213569128U
Authority
CN
China
Prior art keywords
hanging
air cylinder
locomotive
main
piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022664948.0U
Other languages
Chinese (zh)
Inventor
熊朝山
张建武
胡梅梅
魏洋
丁涛
焦少家
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ziyang Zhongche Electric Locomotive Co ltd
Original Assignee
Ziyang Zhongche Electric Locomotive Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ziyang Zhongche Electric Locomotive Co ltd filed Critical Ziyang Zhongche Electric Locomotive Co ltd
Priority to CN202022664948.0U priority Critical patent/CN213569128U/en
Application granted granted Critical
Publication of CN213569128U publication Critical patent/CN213569128U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model relates to the technical field of installation equipment, in particular to a locomotive air cylinder lifting appliance, which comprises a main lifting piece, wherein the lower part of the main lifting piece is provided with a plurality of circular arc surrounding parts which are attached to an air cylinder, both ends of the surrounding parts are respectively provided with hanging strips, and a separable connecting structure is arranged between the hanging strips; the upper part of the main hanging piece is provided with a hanging structure used for connecting hanging equipment. When the air cylinder is hoisted by the lifting appliance, the air cylinder can keep a vertical angle, and the air cylinder is easier to be attached to a mounting groove; meanwhile, the structure of the hoisting piece can be prevented from interfering with the top cover. The arrangement greatly reduces the working strength of installation personnel, improves the installation efficiency and makes the installation effect more ideal.

Description

Locomotive air cylinder lifting appliance
Technical Field
The utility model relates to a erection equipment technical field, concretely relates to locomotive cylinder hoist.
Background
The reservoir on the locomotive is used to store compressed air for use by the locomotive. The general reservoir sets up the lateral part at the locomotive automobile body, and the automobile body lateral part is provided with the vertical mounting groove of installing the reservoir specially, and the mounting groove top still is provided with the top cap. Because the size and the weight of the air cylinder are large, and the interference influence of the top cover causes the air cylinder to be inconvenient to adjust and install, great difficulty is brought to installation personnel, the air cylinder is usually assembled by consuming great physical power by the installation personnel, 40 minutes are consumed for installing one air cylinder, and the installation effect is not ideal.
Therefore, the existing locomotive air cylinder installation technology has the improvement part, a more reasonable technical scheme needs to be provided, and the defects in the prior art are overcome.
SUMMERY OF THE UTILITY MODEL
In order to solve the prior art defect mentioned in the above-mentioned content, the utility model provides a locomotive reservoir hoist aims at fastening and hanging the reservoir and get, and the supplementary reservoir of installing to the locomotive is hanging the whole angle of getting in-process control reservoir, easy to assemble. Therefore, the labor intensity of installation personnel is greatly reduced, the installation efficiency is improved, and the installation effect is more ideal.
In order to achieve the above object, the utility model discloses the technical scheme who specifically adopts is:
a locomotive air cylinder lifting appliance comprises a main lifting piece, wherein the lower part of the main lifting piece is provided with a plurality of circular arc surrounding parts attached to an air cylinder, two ends of each surrounding part are respectively provided with lifting belts, and a separable connecting structure is arranged between the lifting belts; the upper part of the main hanging piece is provided with a hanging structure used for connecting hanging equipment.
According to the lifting appliance, the air cylinder is attached to the surrounding portion, the air cylinder is tightly held by the hanging strip, and the main lifting piece is lifted by the external suspension mechanism to drive the air cylinder. The air cylinder is kept vertical in the process of moving the air cylinder, so that the air cylinder can be directly attached to the mounting groove.
Further, in order to protect the air cylinder and prevent the surface of the air cylinder from being scratched, the structure of the surrounding part is optimized, and the following specific feasible schemes are provided: one side of the encircling part attached to the air cylinder is provided with a flexible cushion layer.
Furthermore, in order to improve the strength of the lifting appliance, the structure of the main lifting element is reinforced, and the following concrete possible schemes are provided: and reinforcing ribs are arranged at the positions of the surrounding parts arranged at the lower parts of the main hanging parts.
Still further, for the same purpose, the main hanger structure is reinforced, and the following concrete possible schemes are listed: and reinforcing ribs are arranged at the positions of the hanging structures arranged at the upper parts of the main hanging pieces.
Further, the hanging structure is not uniquely determined, and various feasible modes can be adopted, specifically as follows: the hanging structure comprises a hanging hole, a hanging ring or a hook.
Further, in order to avoid interference with a top cover of the locomotive during hoisting, the structure of the main hoisting piece is optimized, and the following feasible schemes are provided: the main hanging piece comprises an inverted L-shaped bearing part, the hanging structure is arranged at the free end of the upper part of the bearing part, and the surrounding part is arranged at the free end of the lower part of the bearing part or the bearing part. The structure that sets up like this can avoid the interference of main piece and top cap of hanging when hoisting the reservoir to the mounting groove.
Furthermore, in order to attach and hold the reservoir tightly, the hanging strip is a flexible belt.
Further, the separable connection structure is not uniquely defined, and a possible solution is given here: the detachable connecting structure comprises a connecting hole correspondingly arranged on the lifting belt and a bolt matched with the connecting hole.
Still further, as a feasible option, the number of the hanging strips respectively arranged at the two ends of the encircling part is more than one. The purpose that sets up like this is the reservoir of being convenient for quick installation on the hoist, and unloads the hoist fast, improves the protection to the reservoir.
Further, the connection structure of the surrounding part and the hanging strip is not determined uniquely, and one of the possible solutions is as follows: the two ends of the encircling part are provided with connecting hole holes, and the hanging strip is connected with the connecting hole holes.
Compared with the prior art, the utility model discloses the beneficial effect who has is:
when the air cylinder is hoisted by the lifting appliance, the air cylinder can keep a vertical angle, and the air cylinder is easier to be attached to a mounting groove; meanwhile, the structure of the hoisting piece can be prevented from interfering with the top cover. The arrangement greatly reduces the working strength of installation personnel, improves the installation efficiency and makes the installation effect more ideal.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required to be used in the embodiments will be briefly described below, it should be understood that the following drawings only show some embodiments of the present invention, and therefore should not be considered as limiting the scope, and for those skilled in the art, other related drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic view of the overall structure of a hanger.
Fig. 2 is a schematic view of the hanger holding the reservoir tightly.
FIG. 3 is a schematic view of the hanger lifting the reservoir to the locomotive installation site.
In the above drawings, the meanings of the respective symbols are: 1. a load bearing part; 2. a hanging structure; 3. hanging holes; 4. reinforcing ribs; 5. an encircling part; 6. a flexible cushion layer; 7. the connecting hole is provided with a hole; 8. a sling; 9. a separable connecting structure; 10. an air reservoir; 11. and a top cover.
Detailed Description
The present invention will be further explained with reference to the drawings and the embodiments.
It should be noted that the description of the embodiments is provided to help understanding of the present invention, but the present invention is not limited thereto. Specific structural and functional details disclosed herein are merely illustrative of example embodiments of the invention. The present invention may, however, be embodied in many alternate forms and should not be construed as limited to the embodiments set forth herein.
Examples
Aiming at the current situations that the installation of the air cylinder 10 in the prior art is time-consuming and labor-consuming and the installation effect is not ideal, the embodiment provides the lifting appliance for installing the locomotive air cylinder 10, and the lifting appliance can practically meet the installation angle of the air cylinder 10 and avoid the interference problem.
Specifically, the scheme disclosed in this embodiment is as follows:
as shown in fig. 1, a locomotive air cylinder lifting appliance comprises a main lifting piece, wherein the lower part of the main lifting piece is provided with a plurality of circular arc-shaped surrounding parts 5 attached to an air cylinder 10, two ends of each surrounding part 5 are respectively provided with a hanging strip 8, and a separable connecting structure 9 is arranged between the hanging strips 8; the upper part of the main hanger is provided with a hanging structure 2 for connecting hanging equipment.
As shown in fig. 2, in the hanger disclosed above, the surrounding portion 5 is attached to the air cylinder 10, the air cylinder 10 is held by the hanging strip 8, and the main hanging compartment is lifted by an external hanging mechanism, so that the air cylinder 10 can be driven. The air cylinder 10 is kept vertical in the process of moving the air cylinder 10, so that the air cylinder 10 can be directly attached to the installation groove.
Preferably, the main hanging part is made of alloy steel materials, and has high strength characteristics in practical application through high-temperature stress relief tempering treatment.
In order to protect the air cylinder 10 and prevent the surface thereof from being scratched, the structure of the surrounding part 5 is optimized, and the following specific feasible schemes are provided: one side of the encircling part 5, which is attached to the air cylinder 10, is provided with a flexible cushion layer 6.
Preferably, the flexible cushion layer 6 is made of felt.
In order to improve the strength of the lifting appliance, the structure of the main lifting element is reinforced, and the following concrete feasible schemes are provided: and reinforcing ribs 4 are arranged at the positions of the surrounding parts 5 arranged at the lower parts of the main hanging parts.
For the same purpose, the main hanger structure is reinforced, and the following concrete possible schemes are listed: and reinforcing ribs 4 are arranged at the positions of the hanging structures 2 arranged at the upper parts of the main hanging pieces.
The suspension structure 2 is not uniquely defined, and can be implemented in various ways, as follows: the hanging structure 2 comprises a hanging hole 3 and a hanging ring or a hook. In this embodiment, 3 bits of hanging holes are provided.
As shown in fig. 3, in order to avoid interference with the roof 11 of the locomotive during hoisting, the structure of the main hoisting member is optimized, and the following possible schemes are provided: the main hanging piece comprises an inverted L-shaped bearing part 1, the hanging structure 2 is arranged at the free end of the upper part of the bearing part 1, and the surrounding part 5 is arranged at the free end of the bearing part 1 or the lower part of the bearing part 1. With the structure thus configured, interference between the main hanger and the top cover 11 can be avoided when the reservoir 10 is hoisted to the installation groove.
In order to fit and hold the reservoir 10 tightly, the hanging strip 8 is a flexible strip.
The separable connecting structure 9 is not uniquely defined, and this embodiment exemplifies a possible scheme: the detachable connecting structure 9 comprises a connecting hole correspondingly arranged on the hanging strip 8 and a bolt matched with the connecting hole.
Preferably, the junction of suspender 8 is provided with the splint of L shape, and the reservoir 10 is laminated to one side of splint, and the splint on another suspender 8 are laminated to the another side, are provided with the through-hole that supplies the bolt to pass through on the splint, and the significance of setting like this lies in, avoids two suspenders 8 to hold the reservoir 10 bolt tightly after connecting and scratch reservoir 10.
As a feasible option, the number of the hanging strips 8 respectively arranged at the two ends of the surrounding part 5 is more than one. The purpose of this arrangement is to facilitate quick installation and removal of the air reservoir on and off the spreader, improving protection of the air reservoir 10.
The connection structure of the embracing part 5 and the hanging strip 8 is not determined uniquely, and the embodiment exemplifies one possible scheme: the two ends of the encircling part 5 are provided with connecting hole holes 7, and the hanging strip 8 is connected with the connecting hole holes 7.
The above embodiments are just examples of the present invention, but the present invention is not limited to the above alternative embodiments, and those skilled in the art can obtain other various embodiments by arbitrarily combining the above embodiments, and any one can obtain other various embodiments by the teaching of the present invention. The above detailed description should not be taken as limiting the scope of the invention, which is defined in the following claims, and which can be used to interpret the claims.

Claims (10)

1. The utility model provides a locomotive cylinder hoist which characterized in that: the air cylinder lifting device comprises a main lifting piece, wherein a plurality of circular arc surrounding parts (5) attached to an air cylinder (10) are arranged at the lower part of the main lifting piece, hanging strips (8) are respectively arranged at two ends of each surrounding part (5), and a separable connecting structure (9) is arranged between the hanging strips (8); the upper part of the main hanging piece is provided with a hanging structure (2) used for connecting hanging equipment.
2. The locomotive air cylinder hanger of claim 1, wherein: one side of the encircling part (5) attached to the air cylinder (10) is provided with a flexible cushion layer (6).
3. The locomotive air cylinder hanger of claim 1, wherein: and reinforcing ribs (4) are arranged at the positions of the surrounding parts (5) arranged at the lower parts of the main hanging parts.
4. The locomotive air cylinder hanger of claim 1, wherein: and reinforcing ribs (4) are arranged at the positions of the hanging structures (2) arranged on the upper parts of the main hanging pieces.
5. The locomotive air cylinder hanger of claim 1, wherein: the hanging structure (2) comprises a hanging hole (3) and a hanging ring or a hook.
6. The locomotive air cylinder lifting appliance according to any one of claims 1 to 5, wherein: the main hanging piece comprises an inverted L-shaped bearing part (1), the hanging structure (2) is arranged at the free end of the upper part of the bearing part (1), and the surrounding part (5) is arranged at the free end of the bearing part (1) or positioned at the lower part of the bearing part (1).
7. The locomotive air cylinder hanger of claim 1, wherein: the hanging strip (8) is a flexible strip.
8. The locomotive reservoir spreader of claim 1 or 7, wherein: the detachable connecting structure (9) comprises a connecting hole correspondingly arranged on the hanging strip (8) and a bolt matched with the connecting hole.
9. The locomotive reservoir spreader of claim 1 or 7, wherein: the number of the hanging strips (8) arranged at the two ends of the encircling part (5) is more than one.
10. The locomotive reservoir spreader of claim 1 or 7, wherein: the two ends of the encircling part (5) are provided with connecting hole holes (7), and the hanging strip (8) is connected with the connecting hole holes (7).
CN202022664948.0U 2020-11-17 2020-11-17 Locomotive air cylinder lifting appliance Active CN213569128U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022664948.0U CN213569128U (en) 2020-11-17 2020-11-17 Locomotive air cylinder lifting appliance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022664948.0U CN213569128U (en) 2020-11-17 2020-11-17 Locomotive air cylinder lifting appliance

Publications (1)

Publication Number Publication Date
CN213569128U true CN213569128U (en) 2021-06-29

Family

ID=76538508

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022664948.0U Active CN213569128U (en) 2020-11-17 2020-11-17 Locomotive air cylinder lifting appliance

Country Status (1)

Country Link
CN (1) CN213569128U (en)

Similar Documents

Publication Publication Date Title
CN202321989U (en) Clamping device for carbon brick
CN213569128U (en) Locomotive air cylinder lifting appliance
CN208982630U (en) External clamping angle steel fixed pulley
CN214114710U (en) Building engineering hoist device
CN212832351U (en) Hoisting tool for installing reactor supporting beam
CN201258224Y (en) Eccentric sling for wind-driven generator group assembling work
CN210133807U (en) Shoulder pole beam assembly for unloading engine room of wind generating set and engine room unloading device
CN106081873A (en) A kind of suspender for changing linear tension electric pole and replacing options
CN207390811U (en) Large span board suspending special combination shoulder pole
CN217517384U (en) Auxiliary fixing device for chain block for bridge
CN211667294U (en) Horseshoe-shaped pipeline supporting piece
CN110510502A (en) A kind of lifting rope component
CN216997302U (en) Lifting hook device for lifting generator stator with lifting weight
CN215645831U (en) Gas tank hoisting accessory
CN213112175U (en) Bridge reinforcing bar burst hoist and mount hoist
CN213802563U (en) Cement electric pole hoisting device
CN212687323U (en) Hoisting system for hoisting converter vaporization cooling system equipment
CN201865360U (en) Polyurethane laminboard installation device
CN214031387U (en) Shoulder pole hoisting structure, hoisting device and hoisting system for steel seal door support
CN208561454U (en) Ring cold machine wheel hoisting structure
CN213505726U (en) Hand plate hoist with guiding device
CN211519469U (en) Overhead power battery hoisting and positioning device
CN205346694U (en) Equipment hoisting machine on small -size pole
CN220412599U (en) Buffer tank lifting device for sewage treatment
CN218403282U (en) Eccentric hoisting accessory of segment roof beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant