CN213452051U - Along with bridge laying gas pipeline structure - Google Patents

Along with bridge laying gas pipeline structure Download PDF

Info

Publication number
CN213452051U
CN213452051U CN202022130701.0U CN202022130701U CN213452051U CN 213452051 U CN213452051 U CN 213452051U CN 202022130701 U CN202022130701 U CN 202022130701U CN 213452051 U CN213452051 U CN 213452051U
Authority
CN
China
Prior art keywords
gas
gas pipe
pipe
bridge
gas pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022130701.0U
Other languages
Chinese (zh)
Inventor
马超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Gas Engineering Design Institute Co ltd
Original Assignee
Nanjing Gas Engineering Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Gas Engineering Design Institute Co ltd filed Critical Nanjing Gas Engineering Design Institute Co ltd
Priority to CN202022130701.0U priority Critical patent/CN213452051U/en
Application granted granted Critical
Publication of CN213452051U publication Critical patent/CN213452051U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型涉及一种随桥敷设燃气管道结构,包括埋设在路面下方的第一燃气管、固定在桥面下方的第二燃气管、连接第一燃气管和第二燃气管的转向弯头、以及防沉降管沟;所述防沉降管沟包括底板、设置在底板上并首尾合围的四个侧壁、以及紧密盖合在侧壁顶部的盖板,所述第一燃气管横向贯穿防沉降管沟相对设置的两个侧壁后连接转向弯头,在防沉降管沟内部空隙内填充干沙;所述第一燃气管与侧壁的连接处设置有钢套管,钢套管紧密套装在侧壁的穿孔内,第一燃气管穿设于钢套管中。本实用新型极大地提高了随桥敷设燃气管的柔性,可对土壤沉降进行有效补偿,避免燃气管道受到剪切力作用,解决因不均匀沉降而产生的燃气管道结构破坏问题。

Figure 202022130701

The utility model relates to a bridge-laying gas pipeline structure, which comprises a first gas pipeline buried under the road surface, a second gas pipeline fixed under the bridge deck, a turning elbow connecting the first gas pipeline and the second gas pipeline, and an anti-settling pipe trench; the anti-settling pipe trench includes a bottom plate, four side walls that are arranged on the bottom plate and are enclosed end-to-end, and a cover plate that is tightly covered on the top of the side walls, and the first gas pipe transversely penetrates the anti-settling pipe The two opposite side walls of the pipe trench are connected to the steering elbow, and dry sand is filled in the inner space of the anti-settling pipe trench; the connection between the first gas pipe and the side wall is provided with a steel sleeve, and the steel sleeve is tightly fitted In the perforation of the side wall, the first gas pipe is inserted into the steel casing. The utility model greatly improves the flexibility of the gas pipes laid along the bridge, can effectively compensate for soil settlement, avoids the gas pipelines being subjected to shear force, and solves the problem of structural damage to the gas pipelines caused by uneven settlement.

Figure 202022130701

Description

Along with bridge laying gas pipeline structure
Technical Field
The utility model relates to a lay gas pipeline structure along with bridge belongs to gas pipeline construction technical field.
Background
Along with the rapid development of the gas industry and urban construction in China, the urban gas supply range is wider and wider, and gas conveying pipelines are distributed all over the country. However, many cities have complex terrains, particularly southern cities, wide water distribution and numerous bridges, the situation that a gas conveying pipeline needs to pass through the water area is difficult to avoid in the gas supply process, and the scheme of laying along with the bridges is widely adopted in many areas due to the advantages of relatively simple construction, low engineering cost, fast construction progress, convenience in inspection and maintenance and the like.
The method comprises the following steps of according to whether a gas pipeline is in contact with the atmosphere or not, dividing the gas pipeline along with a bridge into an overhead laying mode and a pipe trench laying mode, wherein the overhead laying mode is that the pipeline is laid in a reserved pipe hole, erected on a pier or suspended below a side sidewalk of the bridge and the like, the pipe trench laying mode is that the gas pipeline is laid in a reserved pipe trench below a bottom plate of the side sidewalk of the bridge, and the periphery of the pipe trench is filled with dry river sand. However, no matter which type of laying mode is used, once the foundations on the two sides of the bridge are settled, the settling rate of soil is high, the settling amount of soil is large, the settling rate of a bridge pier is low, the settling amount of the bridge pier is small, uneven displacement of the soil can generate a large shearing effect on the gas pipeline, when the shearing force exceeds the yield limit of the gas pipeline, plastic deformation and even fracture of the gas pipeline can be caused, and great potential safety hazards are brought.
SUMMERY OF THE UTILITY MODEL
For solving the above-mentioned problem that prior art exists, the utility model aims to provide a lay gas pipeline structure along with the bridge.
In order to solve the technical problem, the utility model discloses the technical scheme who adopts is:
a structure for laying a gas pipeline along with a bridge comprises a first gas pipe embedded below the road surface, a second gas pipe fixed below the bridge floor, a steering elbow connecting the first gas pipe and the second gas pipe, and an anti-settling pipe ditch embedded below the road surface; the anti-settling pipe ditch comprises a bottom plate, four side walls and a cover plate, wherein the four side walls are arranged on the bottom plate and surround the bottom plate end to end, the cover plate is tightly covered on the tops of the side walls, the first gas pipe transversely penetrates through the two opposite side walls of the anti-settling pipe ditch and then is connected with a steering elbow, and dry sand is filled in a gap inside the anti-settling pipe ditch; the joint of the first gas pipe and the side wall is provided with a steel sleeve, the steel sleeve is tightly sleeved in the through hole of the side wall, the first gas pipe penetrates through the steel sleeve, and an elastic filler is filled in a gap between the first gas pipe and the steel sleeve.
The utility model discloses a further improvement lies in: the bottom plate is a plain concrete cushion layer, and the area of the plain concrete cushion layer exceeds the area of a cavity formed by the surrounding of the side walls.
The utility model discloses a further improvement lies in: the first gas pipe and the steel sleeve are axially and eccentrically arranged, and the first gas pipe is close to the bottom wall of the steel sleeve.
The utility model discloses a further improvement lies in: and a reinforcing sleeve for reinforcing the connection strength is arranged at the joint of the steering elbow and the second fuel pipe, and the reinforcing sleeve penetrates through the road surface filling layer and the end part of the bridge deck.
The utility model discloses a further improvement lies in: the top of the side wall is also provided with a plain concrete top block, and the cover plate covers the plain concrete top block; and a cement mortar sealing layer is arranged at the joint of the plain concrete top block and the cover plate.
Due to the adoption of the technical scheme, the utility model discloses the technological progress who gains is:
the utility model provides a lay gas pipeline structure along with the bridge, greatly improved and laid the flexibility and the reliability of gas pipe along with the bridge, can carry out effective compensation to subsiding of soil, avoid the gas pipeline to receive the effect of shearing force and warp, improved the life of gas pipeline, greatly degree has reduced the leakage risk of gas, has improved the security performance. Through experimental proof, the utility model discloses an effective offset is not less than 10cm, can satisfy the gas pipeline of most of areas and prevent subsiding the user demand, has solved the gas pipeline because of the structure destruction problem of inhomogeneous settlement production. The utility model discloses can improve along with bridge laying gas pipeline department original, whole earthwork excavation volume is few, and it is little to reform transform work load, low cost, and overall structure does not contain vulnerable part, good reliability, long service life.
The utility model discloses a turn to the elbow and connect first gas pipe and second gas pipe, turn to the elbow and form by 90 elbow butt joints, increased the structural flexibility when using 45 elbows to connect, the direction of stress is unanimous, but natural compensation shear stress increases the ability that the gas pipeline bore the shearing force.
The utility model discloses a prevent subsiding the trench and protect first gas pipe, prevent through the apron that upper soil subsides and produce the shearing force to the gas pipe, simultaneously, cavity in the trench has increased the activity space of first gas pipe under stress state, is convenient for release stress. The pipe ditch cavity is filled with dry sand, coats the outer wall of the first gas pipe, and uniformly disperses shearing force and avoids the damage of stress concentration to the pipeline.
Set up the steel casing pipe between first gas pipe and the anti-settling trench lateral wall, adopt eccentric mounting between first gas pipe and the steel casing pipe for anti-settling trench has certain whole settlement safety range. When the settlement amount of the pipe ditch is within the settlement safety range, the first gas pipe is free from the action of shearing force. Elastic filler is filled in gaps between the first gas pipe and the steel sleeve, so that the gas pipeline is effectively supported, rigid contact is avoided, and stress risk of the gas pipeline is reduced.
The utility model discloses a plain concrete bed course is as preventing subsiding the bottom plate of trench, provides the outrigger for the lateral wall on the one hand, and on the other hand has effectively improved the condition of subsiding of soil.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a left side view of the anti-settling trench of FIG. 1;
FIG. 3 is a schematic sectional view taken along line A-A in FIG. 1;
figure 4 is a steering elbow including a horizontal bend.
The device comprises a first gas pipe, a second gas pipe, a base plate, a side wall, a cover plate, a turning elbow, a reinforcing pipe sleeve, a steel sleeve, an elastic filler, a plain concrete top block, a cement mortar sealing layer, a dry sand and a reinforcing pipe sleeve, wherein the first gas pipe, the second gas pipe, the base plate, the side wall, the cover plate.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention, but the present invention may be implemented in other ways than those specifically described herein, and one skilled in the art may similarly generalize the present invention without departing from the spirit of the present invention, and therefore the present invention is not limited to the specific embodiments disclosed below.
The embodiment of the utility model provides a lay gas pipeline structure along with bridge, as shown in fig. 1 ~ 3, including bury underground first gas pipe 1 in the road surface below, fix second gas pipe 2 in the bridge floor below, connect first gas pipe 1 and second gas pipe 2 turn to elbow 6, still including burying underground the pipe ditch that subsides of preventing in the road surface below.
The anti-settling pipe ditch comprises a bottom plate 3, four side walls 4 arranged on the bottom plate 3 and surrounded end to end, and a cover plate 5 covering the tops of the side walls 4. The first gas pipe 1 transversely penetrates through two opposite side walls 4 of the anti-settling pipe ditch and is connected with the second gas pipe 2 through a steering elbow 6, and dry sand 12 is filled in a gap inside the anti-settling pipe ditch. The steering elbow 6 is formed by combining 90-degree elbows, a reinforcing sleeve 7 for enhancing the connection strength is arranged at the joint of the steering elbow 6 and the second fuel pipe 2, the reinforcing sleeve 7 penetrates through a road surface soil filling layer and the end part of the bridge deck, and the length of the reinforcing sleeve 7 extending out of the end part of the bridge deck is not less than 0.25m, preferably 0.3 m. 90 elbows can effectively improve the connection flexibility of gas pipe, reduce the shearing force stress surface.
The bottom plate 3 is the plain concrete bed course, and the plain concrete bed course is hard and difficult deformation, for lateral wall 4 provides stable support, and furthest avoids lateral wall 4 to take place to subside. The area of the plain concrete cushion exceeds the area of a cavity formed by the surrounding of the side walls 4, so that the side walls 4 are not easy to incline.
A steel sleeve 8 is arranged at the joint of the first gas pipe 1 and the side wall 4, the steel sleeve 8 is tightly sleeved in a through hole of the side wall 4, the first gas pipe 1 and the steel sleeve 8 are axially and eccentrically arranged, and the first gas pipe 1 is close to the bottom wall of the steel sleeve 8; elastic filler 9 is filled in a gap between the first fuel gas pipe 1 and the steel sleeve 8, so that stable support is provided for the first fuel gas pipe 1, and rigid contact between the steel sleeve 8 and the first fuel gas pipe 1 is avoided; the elastic filler 9 is preferably a polyurethane foam material, and has the advantages of light weight, good rebound resilience and stable support.
Preferably, a gasket for enhancing the sealing property is arranged between the steel sleeve 8 and the perforation of the side wall 4.
The top of lateral wall 4 still is provided with plain concrete kicking block 10, and apron 5 lid closes in plain concrete kicking block 10 top to the reinforcing is to the support intensity of apron 5, reduces the road surface pressure and to the effect of sinking of preventing subsiding the trench. Plain concrete kicking block 10 is provided with cement mortar sealing layer 11 with the handing-over department of apron 5, and cement mortar pouring realizes sealed in getting into the handing-over gap, avoids inside moisture gets into the trench.
Preferably, the side wall 4 is made of reinforced concrete, the bottom plate 3 and the cover plate 5 are made of plain concrete, and the side wall 4 and the bottom plate 3 can be connected through pouring or can be fixedly connected through mechanical structures such as bolts. The cover plate 5 is also provided with a lifting hook convenient to assemble and disassemble.
When the first gas pipe 1 and the second gas pipe 2 only have height difference, the steering elbow 6 is formed by reversely welding two 90-degree elbows; when the first gas pipe 1 and the second gas pipe 2 have a height difference and a lateral displacement difference, the turning elbow 6 further comprises a horizontal bending part as shown in fig. 4.
The utility model discloses a theory of operation does:
when the upper soil layer is slightly settled, the cover plate and the plain concrete cushion layer can be effectively supported, the pipe ditch can be settled without settlement, and the first gas pipe is not stressed; along with the increase of the soil settlement amount, the pipe ditch capable of settling is subjected to integral settlement, and the first gas pipe is not stressed and deformed within the safe settlement range.
Meanwhile, the steering elbow composed of 90-degree elbows can effectively improve the flexibility of the pipeline and reduce the stress surface of the shearing force.
The above is only the preferred embodiment of the present invention, and all the equivalent changes and modifications made according to the claims of the present invention should be covered by the present invention.

Claims (5)

1.一种随桥敷设燃气管道结构,其特征在于:包括埋设在路面下方的第一燃气管(1)、固定在桥面下方的第二燃气管(2)、连接所述第一燃气管(1)和所述第二燃气管(2)的转向弯头(6)、以及埋设在路面下方的防沉降管沟;所述防沉降管沟包括底板(3)、设置在所述底板(3)上并首尾合围的四个侧壁(4)、以及紧密盖合在所述侧壁(4)顶部的盖板(5),所述第一燃气管(1)横向贯穿所述防沉降管沟相对设置的两个侧壁(4)后连接转向所述弯头(6),在防沉降管沟内部空隙内填充干沙(12);所述第一燃气管(1)与所述侧壁(4)的连接处设置有钢套管(8),所述钢套管(8)紧密套装在所述侧壁(4)的穿孔内,所述第一燃气管(1)穿设于所述钢套管(8)中,在所述第一燃气管(1)与所述钢套管(8)的间隙内填充有弹性填料(9)。1. A structure for laying gas pipelines with a bridge, characterized in that: it comprises a first gas pipe (1) buried under a road surface, a second gas pipe (2) fixed under a bridge deck, and a first gas pipe connected to the first gas pipe. (1) and the turning elbow (6) of the second gas pipe (2), and the anti-settling pipe trench buried under the road surface; 3) The four side walls (4) that are enclosed at the end and end, and the cover plate (5) tightly covered on the top of the side walls (4), the first gas pipe (1) transversely runs through the anti-settling The two opposite side walls (4) of the pipe trench are connected and turned to the elbow (6), and dry sand (12) is filled in the inner space of the anti-settling pipe trench; the first gas pipe (1) is connected to the A steel sleeve (8) is provided at the joint of the side wall (4), the steel sleeve (8) is tightly fitted into the perforation of the side wall (4), and the first gas pipe (1) is pierced through In the steel sleeve (8), an elastic filler (9) is filled in the gap between the first gas pipe (1) and the steel sleeve (8). 2.根据权利要求1所述的一种随桥敷设燃气管道结构,其特征在于:所述底板(3)为素混凝土垫层,所述素混凝土垫层面积超出所述侧壁(4)合围形成的腔体面积。2 . The structure for laying gas pipelines with a bridge according to claim 1 , wherein the bottom plate ( 3 ) is a plain concrete cushion, and the area of the plain concrete cushion exceeds the enclosure of the side walls ( 4 ). 3 . The formed cavity area. 3.根据权利要求1所述的一种随桥敷设燃气管道结构,其特征在于:所述第一燃气管(1)与所述钢套管(8)轴向偏心设置、且所述第一燃气管(1)靠近所述钢套管(8)的底壁。3. A bridge-laying gas pipeline structure according to claim 1, characterized in that: the first gas pipe (1) and the steel casing (8) are axially eccentrically arranged, and the first gas pipe (1) and the steel casing (8) are arranged axially eccentrically The gas pipe (1) is close to the bottom wall of the steel sleeve (8). 4.根据权利要求1所述的一种随桥敷设燃气管道结构,其特征在于:所述转向弯头(6)与所述第二燃气管(2)的连接处设置有用于加强连接强度的加固套管(7),所述加固套管(7)贯穿路面填土层和桥面端部。4. A bridge-laying gas pipeline structure according to claim 1, characterized in that: the connection between the steering elbow (6) and the second gas pipe (2) is provided with a connection strength for strengthening the connection strength. A reinforcement sleeve (7) is provided, and the reinforcement sleeve (7) penetrates the road fill layer and the end of the bridge deck. 5.根据权利要求1所述的一种随桥敷设燃气管道结构,其特征在于:所述侧壁(4)的顶部还设置有素混凝土顶块(10),所述盖板(5)盖合于所述素混凝土顶块(10)上方;所述素混凝土顶块(10)与所述盖板(5)的交接处设置有水泥砂浆密封层(11)。5 . The structure for laying gas pipelines with a bridge according to claim 1 , characterized in that: the top of the side wall ( 4 ) is further provided with a plain concrete top block ( 10 ), and the cover plate ( 5 ) covers A cement mortar sealing layer (11) is provided at the junction of the plain concrete top block (10) and the cover plate (5).
CN202022130701.0U 2020-09-25 2020-09-25 Along with bridge laying gas pipeline structure Expired - Fee Related CN213452051U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022130701.0U CN213452051U (en) 2020-09-25 2020-09-25 Along with bridge laying gas pipeline structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022130701.0U CN213452051U (en) 2020-09-25 2020-09-25 Along with bridge laying gas pipeline structure

Publications (1)

Publication Number Publication Date
CN213452051U true CN213452051U (en) 2021-06-15

Family

ID=76281520

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022130701.0U Expired - Fee Related CN213452051U (en) 2020-09-25 2020-09-25 Along with bridge laying gas pipeline structure

Country Status (1)

Country Link
CN (1) CN213452051U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115560248A (en) * 2022-12-08 2023-01-03 招商局金陵船舶(威海)有限公司 Marine liquefied natural gas filling channel connecting structure and connecting method
CN117596731A (en) * 2023-11-28 2024-02-23 绍兴一叶电子股份有限公司 Heating wire, mounting structure thereof and preparation process

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115560248A (en) * 2022-12-08 2023-01-03 招商局金陵船舶(威海)有限公司 Marine liquefied natural gas filling channel connecting structure and connecting method
CN117596731A (en) * 2023-11-28 2024-02-23 绍兴一叶电子股份有限公司 Heating wire, mounting structure thereof and preparation process

Similar Documents

Publication Publication Date Title
CN103321246B (en) Construction Method of Foundation Pit Using Underground Diaphragm Wall
CN104846840B (en) A kind of shallow embedding reinforcement of soft soil integrated pipe canal device and construction method
CN110777809A (en) A kind of deep foundation pit combined support adjacent to existing buildings and construction method thereof
CN213452051U (en) Along with bridge laying gas pipeline structure
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN109267435A (en) A kind of Tunnel Base and its construction
CN210163910U (en) Pipeline pipe jacking receiving well foundation pit supporting structure
CN219158994U (en) A foundation pit support structure for ultra-deep and large-diameter circular pipe-jacking wells in deep soft soil areas
CN103542174B (en) A kind of Subsidence Land in Coal Mining Area Pipe-lining methods
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN219491009U (en) A Vibration Damping Structure Applicable to Urban Foundation Pit Support
CN102900093B (en) Plate-type double-cable foundation structure of transmission tower
CN211228523U (en) A kind of deep foundation pit combined support adjacent to existing buildings
CN114541459A (en) System for compensating buried pipeline settlement in prefabricated well
CN209941754U (en) High-voltage power pipe culvert in-situ protection structure
CN219568906U (en) A foundation pit support structure for settlement control of connected box culverts in deep fill areas
CN213452052U (en) Along with bridge laying gas pipeline anti-settling device
CN219018369U (en) A portal structure for non-excavation reinforcement of existing cable trenches
CN217556728U (en) An embedded structure for strengthening and widening medium and small span bridges and culverts
CN111305220A (en) Concrete support and structural top plate combined building system based on permanent and temporary combination and construction method thereof
CN207213329U (en) A kind of supporting construction of oil pipeline
CN115787665A (en) Support system and construction method for deep foundation pit in silt geology
CN114960675A (en) A new combined support system for foundation pit support of pipe gallery
CN219045112U (en) Dense small-diameter pipeline passing protection device
CN119491513B (en) Vertical reinforced retaining wall structure of assembled multi-source solid waste fluid state solidified soil and construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210615

CF01 Termination of patent right due to non-payment of annual fee