CN106677216B - Access gallery structure and its construction method under deep water - Google Patents

Access gallery structure and its construction method under deep water Download PDF

Info

Publication number
CN106677216B
CN106677216B CN201710032228.2A CN201710032228A CN106677216B CN 106677216 B CN106677216 B CN 106677216B CN 201710032228 A CN201710032228 A CN 201710032228A CN 106677216 B CN106677216 B CN 106677216B
Authority
CN
China
Prior art keywords
slope
sand
gravel
cushion
box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710032228.2A
Other languages
Chinese (zh)
Other versions
CN106677216A (en
Inventor
余义华
章荣发
邓东生
高洪远
郭靖
尹振强
李江
钟保蒙
刘�东
曾坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changjiang Institute of Survey Planning Design and Research Co Ltd
Original Assignee
Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changjiang Institute of Survey Planning Design and Research Co Ltd filed Critical Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority to CN201710032228.2A priority Critical patent/CN106677216B/en
Publication of CN106677216A publication Critical patent/CN106677216A/en
Application granted granted Critical
Publication of CN106677216B publication Critical patent/CN106677216B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses access gallery structure and its construction methods under a kind of deep water, belong to submerged structure technical field of structures.The present invention includes horizontal traffic gallery structure and domatic access gallery structure, and horizontal traffic gallery structure basis is arranged on riverbed, and one end connects with domatic access gallery structure, and the other end connects with underwater protective;The domatic access gallery structure basis is arranged on the slope of dyke, is supported by pile foundation, and one end connects with horizontal traffic gallery, and the other end is connect with ground oodle shop.Degree of safety of the present invention is high, and process is simple, and structurally waterproof effect is good, and speed of application is fast, and settling amount is small.

Description

Access gallery structure and its construction method under deep water
Technical field
The present invention relates to submerged structure technical field of structures, and in particular to be access gallery structure under a kind of deep water, this Invention further relates to the construction method of this structure.
Background technique
After Three Gorges Projects water storage, it is underwater that the preservation of White Crane Ridge Inscription of Fuling Chongqing is submerged in 10-40m all the year round.2 months 2001, really It is fixed to use the underwater protection scheme in former address that historical relic is inscribed and the external world that is, in one protective cover of upper construction of inscribing preservation of White Crane Ridge Inscription It is environmentally isolated, and then realizes protection purpose.White crane beam protects engineering by ground exhibition hall, underwater protective and access gallery three It is grouped as.Access gallery is divided into domatic access gallery and horizontal traffic gallery two parts.Domatic access gallery basis is arranged in The Changjiang dyke built rolls on rockfill slope, and horizontal traffic gallery is arranged on riverbed, every gallery length about 140m, and totally two Item.Access gallery is the important component for connecting ground exhibition hall and underwater protective, peace under white crane beam protection engineering water Quan Xing, applicability directly influence the normal use of underwater protective.
Access gallery is banded structure, 5.0 × 5.8m of normal section outer profile size (wide × high), empty dead size in normal section 3.4 × 4.2m (wide × high), side wall, top plate and bottom plate thickness are 0.8m, and top plate is in both ends arch camber, interior arch radius 0.9m.Bottom plate Inside armpit angle is 300 × 300mm;Domatic access gallery two sides of the bottom set toe of wall, choose clear span 0.7m, thick 0.8m outside, form full envelope The band-like submerged structure of enclosed.The every 11.0m of domatic access gallery sets deformation joint together, and centre does not set construction joint;Horizontal traffic gallery Every 20m sets deformation joint together, and centre sets construction joint;Press structure shape in the junction of domatic access gallery and horizontal traffic gallery Formula smoothly transits, and arrangement of reinforcement is reinforced in end, and domatic access gallery end divides into concrete foundation or vibration pier, do not set connector.
Currently, more conventional access gallery structure is normally at ground or more, plays a part of to connect traffic, be primarily subjected to The live loads such as dead load, geological process, normal use live load and wind load, snow load.The underwater access gallery of white crane beam is narrow Long, stress is complicated, changes in deep water in 10~40m and runs for a long time, gallery structure is in addition to bearing dead load, also subject to inside and outside water Soil pressure, reservoir stormy waves power, buoyancy, shoal materials act on the pressure in outside and accidental impact power, geological process, temperature are answered Power, concrete shrinkage stress etc..
Now there are no the protection structure of submerged structure and the construction methods of this structure.
Summary of the invention
The first object of the present invention is to overcome above-mentioned the deficiencies in the prior art, provides a kind of deepwater environment, complicated stress Under the conditions of access gallery structure under used deep water.
The second object of the present invention is to provide the construction method of access gallery structure under above-mentioned deep water.
To realize above-mentioned first purpose, the present invention adopts the following technical scheme:
Access gallery structure under deep water, including horizontal traffic gallery structure and domatic access gallery structure;The horizontal friendship Vestibule road structure basis is arranged on riverbed, and one end connects with domatic access gallery structure, and the other end connects with underwater protective; The domatic access gallery structure basis is arranged on the slope of dyke, is supported by pile foundation, one end and horizontal traffic gallery knot Structure connects, and the other end is connect with ground oodle shop;The main structure normal section of the horizontal traffic gallery structure is cast in place reinforced bar coagulation Box section made of soil;The main structure normal section of the domatic access gallery structure is case made of cast-in-situ steel reinforced concrete Tee section I;
The horizontal traffic gallery structure include: bedrock surface, concrete cushion, box section, cemented rock, sand rubble and Building stones;The concrete cushion is located on bedrock surface;The box section is located on the middle position of concrete cushion;The slurry Building block stone is located on concrete cushion and is symmetrically arranged in the two sides of box section, and two sides cemented rock is by cemented rock water Flat position and cemented rock ramp position composition;The sand rubble is symmetrically arranged in case between cemented rock and building stones The two sides of tee section;The building stones are made of building stones horizontal position and building stones ramp position, and anti-anchor block stone is embedded in the water of building stones Flat position and the two sides for being symmetrically arranged in box section;
The domatic access gallery structure includes: bedrock surface, sand rubble compensation bed course, box section I, sand rubble I, grouts Block stone I, blotter and precast concrete block;The sand rubble compensation bed course is located on bedrock surface and compensates bed course by sand rubble Horizontal position and sand rubble compensation bed course ramp position composition, the sand rubble compensation roll enrockment under the position of bed course slope Body;The box section I is located on the middle position of sand rubble compensation bed course;The sand rubble I is located at sand rubble compensation bed course The two sides of box section I are gone up and are symmetrically arranged in, and two sides sand rubble I is by sand rubble I horizontal position, sand rubble I upslope Position and sand rubble I downslope position composition, the sand rubble I downslope roll rockfill under position;The concrete Soil block is by horizontal position under horizontal position, precast concrete block on precast concrete block and precast concrete block ramp hyte At horizontal position is located on sand rubble I horizontal position on the precast concrete block, horizontal position under the precast concrete block On blotter, cemented rock has been poured between precast concrete block slope position and sand rubble I upslope position I;Rockfill is rolled under the blotter.
Further, the gradient on cemented rock slope position described in horizontal traffic gallery structure is 1: 2;The building stones are oblique The gradient at slope position is 1: 2;The gradient at precast concrete block slope position described in domatic access gallery structure is 1: 2;It is described The gradient that sand rubble compensates bed course slope position is 1: 2;The gradient at sand rubble I downslope position is 1: 2, on sand rubble I The gradient at slope position is 1: 1.5.
According to the above scheme, the box section I, including gallery side wall, gallery bottom plate and gallery top plate;The gallery side wall Concrete backfill step ladder is provided on the left of inner surface;Plumbing pipe trench is provided on the right side of the gallery side wall inner surface;It is described to give Trench cover is provided with above by-wash;Elevator machine hole is provided among the concrete backfill step ladder and by-wash; The concrete backfill step ladder, elevator machine hole and plumbing pipe trench are located on gallery bottom plate.
Further, the main structure normal section outer profile size is 5.0m × 5.8m (wide × high), headroom having a size of 3.4m × 4.2m (wide × high), gallery side wall, gallery top plate and gallery base plate thickness are 0.80m, and gallery top plate rises at both ends Arch, interior arch radius 0.9m, gallery bottom plate inside armpit angle is 300 × 300mm.
It constructs to access gallery structure under above-mentioned deep water, the working procedure of the horizontal traffic gallery structure, including Following steps: 1) being excavated, and end is excavated to bedrock surface;2) after excavating cleaning to bedrock surface, casting concrete bed course;3) Box section is poured on concrete cushion, the coagulation after box section has poured, using cemented rock in gallery bottom plate two sides Spats locking is carried out on soil padding;4) after spats has locked, the backfill of sand rubble and compaction in layers, pressure are carried out in gallery side wall two sides Real coefficient 0.94, side slope 1: 2 (vertical height: horizontal width);5) after being backfilling and compacted, in the sand metalling last time being backfilling and compacted It fills out 1.5m thickness building stones and grouts the thick anti-anchor block stone of 2m, flushed at the top of the building stones of backfill and the anti-anchor block stone grouted;
The working procedure of the domatic access gallery structure, comprising the following steps: 1) remove dike face precast concrete block and Blotter is excavated, and end is excavated to bedrock surface;2) after being excavated to bedrock surface check of foundation subsoil, using pea gravel concreten to stone roller It presses rockfill to carry out concrete grouting reinforcing, and pours sand rubble compensation bed course;3) box-shaped is poured on sand rubble compensation bed course Section I after box section I has been poured, carries out spats using cemented rock I, and be laid with toe of wall pad in gallery bottom plate two sides in time Layer;4) after spats and toe of wall setting cushion are complete, the above Cast-in-situ Piles in Sand-filling rubble I of bed course, and compaction in layers, compacting system are compensated in sand rubble Number 0.94, side slope 1: 1.5 (vertical height: horizontal width);5) after being backfilling and compacted, 500mm thickness rubble is poured in spats side Then bed course restores 200mm thickness precast concrete block mask by dyke dike face standard in top surface.
Further, the check of foundation subsoil in the working procedure step 2) of domatic access gallery structure is held by the confirmation of geological mapping unit Power layer bedrock surface, designing unit confirm basic plane size, positioning, absolute altitude.
Further, the slip casting bore dia of the grouting and reinforcing in the working procedure step 2) of domatic access gallery structure is 110mm, hole depth are excavation face or less 7m.
Still further, toe of wall bed course in the working procedure step 3) of domatic access gallery structure is from gallery bottom plate two sides It is 0.7m, thickness 0.8m to clear span is extended out.
Also further, the box section construction in the horizontal traffic gallery structure working procedure step 3) uses punching block Plate pours integral together with box section concrete;Domatic access gallery structure construction process 3) in box section I Construction is poured together with box section I concrete integral using steel form, pours box section and box section I concrete Strength grade is C40, and seepage-resistant grade S12, freeze proof grade is D200, and swelling agent used is that ZY type high-performance high-effective concrete is swollen Swollen dose.
The invention has the following advantages:
1, the processing of access gallery structure vault junction is arc-shaped under deep water, can increase rigidity herein, reduce it and answer Power is concentrated.
2, under deep water access gallery main structure construction using steel form poured together with main structure concrete to be formed it is whole Body reduces construction joint quantity, is conducive to accelerate construction progress, and enhancing structure self waterproofing.And main structure concrete is adopted With ZY type high-performance high-efficiency concrete expansion admixture, concrete shrinkage can compensate for, improve structure anti-permeability performance, further enhance structure Self waterproofing.
3, domatic access gallery structure and horizontal traffic gallery structure are embedded in riverbed, river mistake occupied by gallery top Flow area is relatively small, reduces influence of the reservoir stormy waves power to gallery structure, and does not influence the section flood passage.In Three Gorges Reservoir Under the conditions of low water level operation, the navigation of Yangtze River waterway is not influenced, solves navigation to protection engineering bring safety problem.
4, the essential bearing stratum of domatic access gallery structure and horizontal traffic gallery structure is located at horizon d, can significantly reduce Structure sediment amount guarantees that it meets design requirement.
Detailed description of the invention
Fig. 1 is access gallery structure chart under deep water;
Structural box section cross-sectional view based on Fig. 2;
Fig. 3 is that horizontal traffic gallery foundation trench backfills cross-sectional view;
Fig. 4 is that domatic access gallery foundation trench backfills cross-sectional view.
In figure: horizontal traffic gallery structure 1, domatic access gallery structure 2, dyke 3, oodle shop 4, underwater protective 5, river Bed 6, pile foundation 7, gallery bottom plate 01, gallery side wall 02, gallery top plate 02, plumbing pipe trench 04, trench cover 05, elevator machine hole 06, concrete backfill step ladder 07, anti-anchor block stone 11, building stones 12, sand rubble 13, cemented rock 14, concrete cushion 15, box-shaped are cut Face 16, bedrock surface 17, precast concrete block 21, sand rubble compensation bed course 22, rolls rockfill 23, grouts at box section I 16 ' Block stone I24, sand rubble I 25, blotter 26.
Specific embodiment
The present invention will be further explained below with reference to the attached drawings and specific examples.
As shown in Figure 1, access gallery structure under deep water, including horizontal traffic gallery structure 1 and domatic access gallery structure 2;1 basis of horizontal traffic gallery structure is arranged on riverbed 6, and one end connects with domatic access gallery structure 2, the other end with Underwater protective 5 connects;2 basis of domatic access gallery structure is arranged on the slope of dyke 3, and the gradient is 30 °, by pile foundation Plinth 7 supports, and one end connects with horizontal traffic gallery structure 1, and the other end is connect with ground oodle shop 4.
As shown in Fig. 2, the main structure normal section of the horizontal traffic gallery structure 1 and domatic access gallery structure 2 Respectively box section 16 and box section I 16 ' made of cast-in-situ steel reinforced concrete;The box section 16 and box section I 16 ' include 03 plate of gallery bottom plate 01, gallery side wall 02 and gallery top;Coagulation is provided on the left of 02 inner surface of gallery side wall Earthen backfill step ladder 07;Plumbing pipe trench 04 is provided on the right side of 02 inner surface of gallery side wall;The plumbing pipe trench 04 it is upper Side is provided with trench cover 05;Elevator machine hole 06 is provided among the concrete backfill step ladder 07 and by-wash 04;It is described Concrete backfill step ladder 07, elevator machine hole 06 and plumbing pipe trench 04 are located on gallery bottom plate 01.
As shown in figure 3, horizontal traffic gallery structure 1 includes: bedrock surface 17, concrete cushion 15, box section 16, grouts Block stone 14, sand rubble 13 and building stones 12;The concrete cushion 15 is located on bedrock surface 17;The box section 16 is located at coagulation On the middle position of soil padding 15;The cemented rock 14 is located on concrete cushion 15 and is symmetrically arranged in box section 16 Two sides, and two sides cemented rock 14 is made of cemented rock horizontal position and cemented rock slope position (gradient 1: 2);Institute Sand rubble 13 is stated between cemented rock 14 and building stones 12, and is symmetrically arranged in the two sides of box section 16;The building stones 12 It is made of building stones horizontal position and building stones slope position (gradient 1: 2), anti-anchor block stone 11 is embedded in the horizontal position of building stones 12 And it is symmetrically arranged in the two sides of box section 16.
As shown in figure 4, domatic access gallery structure 2 includes: bedrock surface 17, sand rubble compensation bed course 22, box section I 16 ', sand rubble I 25, cemented rock I 24, blotter 26 and precast concrete block 21;The sand rubble compensates bed course 22 In on bedrock surface 17 and by sand rubble compensation bed course horizontal position and sand rubble compensation bed course slope position (gradient 1: 2) group At the sand rubble compensation rolls rockfill 23 under the position of bed course slope;The box section I 16 ' is located at the compensation of sand rubble On the middle position of bed course 22;The sand rubble I 25 is located on sand rubble compensation bed course 22 and is symmetrically arranged in box section I 16 ' two sides, and two sides sand rubble I 25 is by sand rubble I horizontal position, sand rubble I upslope position (gradient 1: 1.5) It is formed with sand rubble I downslope position (gradient 1: 2), the sand rubble I downslope rolls rockfill 23 under position;It is described Precast concrete block 21 is oblique by horizontal position under horizontal position, precast concrete block on precast concrete block and precast concrete block Slope position (gradient 1: 2) forms, and horizontal position is located on 25 horizontal position of sand rubble I on the precast concrete block, described Horizontal position is located on blotter 26 under precast concrete block, on precast concrete block slope position and sand rubble I 25 Cemented rock I 24 has been poured between the position of slope;Rockfill 23 is rolled under the blotter 26.
Wherein, the outer profile size of horizontal traffic gallery structure 1 and the main structure normal section of domatic access gallery structure 2 For 5.0m × 5.8m (wide × high), headroom is having a size of 3.4m × 4.2m (wide × high), gallery side wall, gallery top plate and gallery bottom plate Thickness is 0.80m, and gallery top plate is in both ends arch camber, and interior arch radius 0.9m, gallery bottom plate inside armpit angle is 300 × 300mm.
It constructs to access gallery structure under above-mentioned deep water, according to above-mentioned horizontal traffic gallery of shown in Fig. 3, constructing, 1) working procedure is the following steps are included: excavated, and end is excavated to bedrock surface 17;2) after excavating cleaning to bedrock surface 17, Pour C15 concrete cushion 15;3) according to Fig. 2, box section 16 is poured on C15 concrete cushion 15, box section 16 pours After having built, spats locking is carried out on the concrete cushion 15 of 01 two sides of gallery bottom plate using cemented rock 14;4) spats is locked Afterwards, 02 two sides of gallery side wall carry out sand rubble 13 backfill and compaction in layers, compacting factor 0.94, side slope 1: 2 (vertical height: Horizontal width);5) after being backfilling and compacted, prevent in 13 layers of the sand rubble being backfilling and compacted upper backfill 1.5m thickness building stones 12 with 2m thickness is grouted It is flushed at the top of anchor block stone 11, the building stones 12 of backfill and the anti-anchor block stone 11 grouted.
According to above-mentioned domatic access gallery structure of shown in Fig. 4, constructing, 1) working procedure is the following steps are included: remove dike Face precast concrete block and blotter, are excavated, and end is excavated to bedrock surface 17;2) it is excavated to 17 check of foundation subsoil of bedrock surface Afterwards, concrete grouting reinforcing is carried out to rockfill 23 is rolled using C30 pea gravel concreten, and pours sand rubble compensation bed course 22, Slip casting bore dia is 110mm, and hole depth is to excavate basal surface or less 7m;3) according to Fig. 2, case is poured on sand rubble compensation bed course 22 Tee section I 16 ', after box section I 16 ' has been poured, using the timely spats of 1: 2 cemented rock 24, and at 01 liang of gallery bottom plate Side is laid with and extends out clear span 0.7m, the toe of wall bed course of thick 0.8m;4) after spats and toe of wall setting cushion are complete, bed course is compensated in sand rubble The above Cast-in-situ Piles in Sand-filling rubble I 25 in 22 two sides, and compaction in layers, compacting factor 0.94, (the vertical height: horizontal wide of side slope 1: 1.5 Degree);5) after being backfilling and compacted, 500mm thickness blotter 26 is poured in spats side, then presses 3 dike face standard of dyke in top surface Restore 21 mask of 200mm thickness precast concrete block.
Wherein, in horizontal gallery structure and the work progress of domatic access gallery structure, use strength grade for C40, Seepage-resistant grade is S12, and freeze proof grade is that the concrete of D200 and steel form pour integral, formation box section 16 and case together Tee section I 16 ', swelling agent used is ZY type high-performance high-efficiency concrete expansion admixture in Concrete.
Load Combination is carried out according to the different phase of construction time and runtime, different safety coefficients is selected to be calculated.
Involved effect has dead load, soil pressure, water pressure (design high-water pressure, design when internal force calculating Low water level pressure, design mean water pressure), heating, cooling, Pedestrian Load (unidirectional, two-way), differential settlement, earthquake make With.
The combination of runtime primary load is as shown in table 1.
Table 1
Note: " ★ " expression effect has this kind of load
Three-dimensional modeling calculating is carried out to access gallery structure using general finite meta software, calculates operating condition as shown in table 2
Table 2
The peak value of each control section internal force design value is obtained according to the requirement of Load Combination according to each operating condition subitem internal force, As shown in table 3.
Table 3
According to table 3 as a result, under deep water access gallery structure carry out sectional reinforcement checking computations it is found that gallery structure cross section most The big ratio of reinforcement is 1.42%, structure general safety.

Claims (8)

1.深水下交通廊道结构,其特征在于:包括水平交通廊道结构(1)和坡形交通廊道结构(2);所述水平交通廊道结构(1)基础布置在河床(6)上,一端与坡形交通廊道结构(2)相接,另一端与水下保护体(5)相接;所述坡形交通廊道结构(2)基础布置在堤防(3)的斜坡上,由桩基础(7)支撑,一端与水平交通廊道结构(1)相接,另一端与地面馆(4)连接;所述水平交通廊道结构(1)的主体结构正截面为现浇钢筋混凝土制成的箱形截面(16);所述坡形交通廊道结构(2)的主体结构正截面为现浇钢筋混凝土制成的箱形截面I(16’);1. The deep underwater traffic corridor structure is characterized in that: it comprises a horizontal traffic corridor structure (1) and a slope-shaped traffic corridor structure (2); the foundation of the horizontal traffic corridor structure (1) is arranged on a riverbed (6) one end is connected with the slope-shaped traffic corridor structure (2), and the other end is connected with the underwater protection body (5); the foundation of the slope-shaped traffic corridor structure (2) is arranged on the slope of the embankment (3). , supported by a pile foundation (7), one end is connected with the horizontal traffic corridor structure (1), and the other end is connected with the ground pavilion (4); A box-shaped section (16) made of reinforced concrete; the front section of the main structure of the slope-shaped traffic corridor structure (2) is a box-shaped section I (16') made of cast-in-place reinforced concrete; 所述水平交通廊道结构(1)包括:基岩面(17)、混凝土垫层(15)、箱形截面(16)、浆砌块石(14)、砂碎石(13)和石料(12);所述混凝土垫层(15)位于基岩面(17)上;所述箱形截面(16)位于混凝土垫层(15)的中间位置上;所述浆砌块石(14)位于混凝土垫层(15)上并对称布置于箱形截面(16)的两侧,且两侧浆砌块石(14)均由浆砌块石水平部位和浆砌块石斜坡部位组成;所述砂碎石(13)位于浆砌块石(14)和石料(12)之间,并对称布置于箱形截面(16)的两侧;所述石料(12)由石料水平部位和石料斜坡部位组成,防锚块石(11)镶嵌于石料(12)的水平部位并对称布置于箱形截面(16)的两侧;The horizontal traffic corridor structure (1) includes: a bedrock surface (17), a concrete cushion (15), a box-shaped section (16), a mortar block stone (14), a sand crushed stone (13) and a stone (13). 12); the concrete cushion (15) is located on the bedrock surface (17); the box-shaped section (16) is located in the middle position of the concrete cushion (15); the slurry block stone (14) is located in The concrete cushion (15) is symmetrically arranged on both sides of the box-shaped section (16), and the mortar blocks (14) on both sides are composed of a horizontal part of the mortar block and a slope part of the mortar block; the The sand and crushed stones (13) are located between the mortar block stones (14) and the stones (12), and are symmetrically arranged on both sides of the box-shaped section (16); the stones (12) are composed of a horizontal part of the stone and a slope part of the stone composition, the anchor block stone (11) is inlaid in the horizontal part of the stone material (12) and symmetrically arranged on both sides of the box-shaped section (16); 所述坡形交通廊道结构(2)包括:基岩面(17)、砂碎石补偿垫层(22)、箱形截面I(16’)、砂碎石I(25)、浆砌块石I(24)、碎石垫层(26)和预制混凝土块(21);所述砂碎石补偿垫层(22)位于基岩面(17)上并由砂碎石补偿垫层水平部位和砂碎石补偿垫层斜坡部位组成,所述砂碎石补偿垫层斜坡部位下有碾压堆石体(23);所述箱形截面I(16’)位于砂碎石补偿垫层(22)的中间位置上;所述砂碎石I(25)位于砂碎石补偿垫层(22)上并对称布置于箱形截面I(16’)的两侧,且两侧砂碎石I(25)均由砂碎石I水平部位、砂碎石I上斜坡部位和砂碎石I下斜坡部位组成,所述砂碎石I下斜坡部位下有碾压堆石体(23);所述预制混凝土块(21)由预制混凝土块上水平部位、预制混凝土块下水平部位和预制混凝土块斜坡部位组成,所述预制混凝土块上水平部位位于砂碎石I(25)水平部位上,所述预制混凝土块下水平部位位于碎石垫层(26)上,所述预制混凝土块斜坡部位和砂碎石I(25)上斜坡部位之间浇筑有浆砌块石I(24);所述碎石垫层(26)下有碾压堆石体(23)。The slope-shaped traffic corridor structure (2) includes: a bedrock surface (17), a sand and gravel compensation cushion (22), a box-shaped section I (16'), a sand and gravel I (25), and a mortar block Stone I (24), a gravel cushion (26) and a precast concrete block (21); the sand and gravel compensation cushion (22) is located on the bedrock surface (17) and is compensated by the sand and gravel for the horizontal part of the cushion and the sand and gravel compensation cushion slope part, there is a rolling rockfill body (23) under the sand and gravel compensation cushion slope part; the box-shaped section I (16') is located in the sand and gravel compensation cushion (23); 22) in the middle position; the sand and gravel I (25) is located on the sand and gravel compensation cushion (22) and is symmetrically arranged on both sides of the box-shaped section I (16'), and the sand and gravel I on both sides is symmetrical. (25) are all composed of the horizontal part of the sand and gravel I, the upper slope part of the sand and gravel I, and the lower slope part of the sand and gravel I, and there is a rolling rockfill body (23) under the lower slope part of the sand and gravel I; The precast concrete block (21) is composed of an upper horizontal part of the precast concrete block, a lower horizontal part of the precast concrete block and a slope part of the precast concrete block, and the upper horizontal part of the precast concrete block is located on the horizontal part of the sand and gravel 1 (25), so the The lower horizontal part of the precast concrete block is located on the gravel cushion (26), and a mortar block stone I (24) is poured between the slope part of the precast concrete block and the upper slope part of the sand and gravel I (25); There is a rolling rockfill body (23) under the gravel cushion (26). 2.根据权利要求1所述的深水下交通廊道结构,其特征在于:所述的箱形截面(16)和所述的箱形截面I(16’)均包括廊道底板(01)、廊道侧墙(02)和廊道顶板(03);所述廊道侧墙(02)内表面左侧设置有混凝土回填步梯(07);所述廊道侧墙(02)内表面右侧设置有给排水管沟(04);所述给排水管沟(04)的上方设置有管沟盖板(05);所述混凝土回填步梯(07)和排水管沟(04)中间设置有电梯机坑(06);所述混凝土回填步梯(07)、电梯机坑(06)和给排水管沟(04)位于廊道底板(01)上。2. deep underwater traffic corridor structure according to claim 1, is characterized in that: described box-shaped section (16) and described box-shaped section I (16') all comprise corridor bottom plate (01), A corridor side wall (02) and a corridor top plate (03); a concrete backfilling step (07) is provided on the left side of the inner surface of the corridor side wall (02); the inner surface of the corridor side wall (02) is on the right side A water supply and drainage pipe trench (04) is arranged on the side; a pipe trench cover plate (05) is arranged above the water supply and drainage pipe trench (04); the concrete backfilling step (07) and the drainage pipe trench (04) are arranged in the middle There is an elevator machine pit (06); the concrete backfill step ladder (07), the elevator machine pit (06) and the water supply and drainage pipe trench (04) are located on the corridor floor (01). 3.根据权利要求1或2所述的深水下交通廊道结构,其特征在于:所述浆砌块石(14)斜坡部位的坡度为1∶2;3. The deep underwater traffic corridor structure according to claim 1 or 2, characterized in that: the gradient of the slope part of the slurry block stone (14) is 1:2; 所述石料(12)斜坡部位的坡度为1∶2;The slope of the slope part of the stone material (12) is 1:2; 所述预制混凝土块(21)斜坡部位的坡度为1∶2;The slope of the precast concrete block (21) slope is 1:2; 所述砂碎石补偿垫层(22)斜坡部位的坡度为1∶2;The gradient of the slope part of the sand and gravel compensation cushion (22) is 1:2; 所述砂碎石I(25)下斜坡部位的坡度为1∶2,砂碎石I上斜坡部位的坡度为1∶1.5。The slope of the lower slope of the sand and gravel I (25) is 1:2, and the slope of the upper slope of the sand and gravel I is 1:1.5. 4.权利要求1至3中任一权利要求所述的深水下交通廊道结构的施工方法,其特征在于:4. the construction method of the deep underwater traffic corridor structure described in any one of claim 1 to 3, is characterized in that: 所述水平交通廊道结构(1)的施工工序,包括以下步骤:1)进行开挖,且末端开挖至基岩面(17);2)开挖清理至基岩面(17)后,浇筑混凝土垫层(15);3)在混凝土垫层(15)上浇筑箱形截面(16),箱形截面(16)浇筑完后,采用浆砌块石(14)在廊道底板(01)两侧的混凝土垫层(15)上进行护脚锁定;4)护脚锁定完后,在廊道侧墙(02)两侧进行砂碎石(13)回填并分层压实,压实系数0.94,边坡1∶2;5)回填压实完后,在回填压实的砂碎石(13)层上回填1.5m厚石料(12)和浆砌2m厚防锚块石(11),回填的石料(12)与浆砌的防锚块石(11)顶部齐平;The construction process of the horizontal traffic corridor structure (1) includes the following steps: 1) excavating, and excavating the end to the bedrock surface (17); 2) after excavation and cleaning to the bedrock surface (17), pouring a concrete cushion (15); 3) pouring a box-shaped section (16) on the concrete cushion (15), and after the box-shaped section (16) is poured, a mortar block stone (14) is used on the corridor bottom plate (01). ) on both sides of the concrete cushion (15) to lock the foot guards; 4) After the foot guards are locked, sand and gravel (13) are backfilled on both sides of the corridor side wall (02) and are compacted in layers. Coefficient 0.94, slope 1:2; 5) After backfilling and compacting, backfill 1.5m thick stone (12) and 2m thick anti-anchor block stone (11) on the backfill compacted sand and gravel (13) layer , the backfilled stone (12) is flush with the top of the mortar-laid anchor stone (11); 所述坡形交通廊道结构(2)的施工工序,包括以下步骤:1)拆除堤面预制混凝土块和碎石垫层,进行开挖,且末端开挖至基岩面(17);2)开挖至基岩面(17)验槽后,采用细石混凝土对碾压堆石体(23)进行混凝土注浆加固,并浇筑砂碎石补偿垫层(22);3)在砂碎石补偿垫层(22)上浇筑箱形截面I(16’),箱形截面I(16’)浇筑完后,采用浆砌块石I(24)及时护脚,并在廊道底板(01)两侧铺设墙趾垫层;4)护脚和墙趾垫层铺设完后,在砂碎石补偿垫层(22)以上回填砂碎石I(25),并分层压实,压实系数0.94,边坡1∶1.5;5)回填压实完后,在护脚侧面浇筑500mm厚碎石垫层(26),然后在顶面按堤防(3)堤面标准恢复200mm厚预制混凝土块(21)护面。The construction process of the slope-shaped traffic corridor structure (2) includes the following steps: 1) removing the precast concrete blocks and the gravel cushion on the embankment surface, excavating, and excavating the end to the bedrock surface (17); 2) ) After excavating to the bedrock surface (17) for inspection, use fine stone concrete to reinforce the roller compacted rockfill (23) with concrete grouting, and pour the sand and gravel compensation cushion (22); The box-shaped section I (16') is poured on the stone compensation cushion (22), and after the box-shaped section I (16') is poured, the mortar block stone I (24) is used to protect the feet in time, and the bottom of the corridor (01) ) Lay the wall toe cushion on both sides; 4) After the foot protection and the wall toe cushion are laid, backfill the sand and gravel I (25) above the sand and gravel compensation cushion (22), and then compress it in layers. The coefficient is 0.94, the slope is 1:1.5; 5) After backfilling and compaction, a 500mm thick gravel cushion (26) is poured on the side of the foot guard, and then a 200mm thick precast concrete block is restored on the top surface according to the embankment (3) embankment surface standard (21) FACES. 5.根据权利要求4所述的深水下交通廊道结构的施工方法,其特征在于:所述坡形交通廊道结构(2)施工工序步骤2)中所述注浆加固的注浆孔直径为110mm,孔深为开挖面以下7m。5. The construction method of deep underwater traffic corridor structure according to claim 4, characterized in that: the diameter of the grouting hole for grouting reinforcement described in the slope-shaped traffic corridor structure (2) construction process step 2) It is 110mm, and the hole depth is 7m below the excavation surface. 6.根据权利要求4所述的深水下交通廊道结构的施工方法,其特征在于:所述坡形交通廊道结构(2)施工工序步骤3)中的墙趾垫层自廊道底板(01)两侧向外扩净宽为0.7m,厚为0.8m。6. The construction method of deep underwater traffic corridor structure according to claim 4, is characterized in that: the wall toe cushion in the described slope-shaped traffic corridor structure (2) construction process step 3) is from the corridor bottom plate ( 01) The net width of the outward expansion on both sides is 0.7m, and the thickness is 0.8m. 7.根据权利要求4所述的深水下交通廊道结构的施工方法,其特征在于:所述水平交通廊道结构(1)施工工序步骤3)中的箱形截面(16)施工采用钢模板与箱形截面(16)混凝土一起浇筑成整体;坡形交通廊道结构(2)施工工序步骤3)中的箱形截面I(16’)施工采用钢模板与箱形截面I(16’)混凝土一起浇筑成整体。7. the construction method of deep underwater traffic corridor structure according to claim 4, is characterized in that: the box-shaped section (16) construction in described horizontal traffic corridor structure (1) construction procedure step 3) adopts steel formwork It is poured into a whole together with the box-shaped section (16) concrete; the construction of the box-shaped section I (16') in the slope-shaped traffic corridor structure (2) construction process step 3) adopts the steel formwork and the box-shaped section I (16') The concrete is poured together as a whole. 8.根据权利要求4所述的深水下交通廊道结构的施工方法,其特征在于:所述箱形截面(16)及箱形截面I(16’)混凝土强度等级为C40,抗渗等级为S12,抗冻等级为D200,所用膨胀剂为ZY型高性能高效混凝土膨胀剂。8. the construction method of deep underwater traffic corridor structure according to claim 4, is characterized in that: described box-shaped section (16) and box-shaped section I (16 ') concrete strength grade is C40, and impermeability grade is S12, the frost resistance grade is D200, and the expansion agent used is ZY type high-performance and high-efficiency concrete expansion agent.
CN201710032228.2A 2017-01-16 2017-01-16 Access gallery structure and its construction method under deep water Active CN106677216B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710032228.2A CN106677216B (en) 2017-01-16 2017-01-16 Access gallery structure and its construction method under deep water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710032228.2A CN106677216B (en) 2017-01-16 2017-01-16 Access gallery structure and its construction method under deep water

Publications (2)

Publication Number Publication Date
CN106677216A CN106677216A (en) 2017-05-17
CN106677216B true CN106677216B (en) 2019-06-07

Family

ID=58859428

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710032228.2A Active CN106677216B (en) 2017-01-16 2017-01-16 Access gallery structure and its construction method under deep water

Country Status (1)

Country Link
CN (1) CN106677216B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503360B (en) * 2017-07-20 2020-01-24 中铁十八局集团有限公司 Huge loose rock pile tunnel import is piled and is carried back pressure reinforced structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4657435A (en) * 1985-12-27 1987-04-14 Chang Ming Y Underwater tunnel construction
CN202100263U (en) * 2011-06-22 2012-01-04 中铁二院工程集团有限责任公司 High-backfill open cut tunnel lining structure of high-intensity swelled ground region
CN202577349U (en) * 2012-04-07 2012-12-05 中铁十八局集团有限公司 Large immersed tube tunnel dry dock floor structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4657435A (en) * 1985-12-27 1987-04-14 Chang Ming Y Underwater tunnel construction
CN202100263U (en) * 2011-06-22 2012-01-04 中铁二院工程集团有限责任公司 High-backfill open cut tunnel lining structure of high-intensity swelled ground region
CN202577349U (en) * 2012-04-07 2012-12-05 中铁十八局集团有限公司 Large immersed tube tunnel dry dock floor structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"水下文物原址保护施工技术与造价分析";李雨洁, 李多修;《铁路工程造价管理》;20060925;第25卷(第5期);第22-25页

Also Published As

Publication number Publication date
CN106677216A (en) 2017-05-17

Similar Documents

Publication Publication Date Title
CN103967031B (en) A kind of caisson of consolidated subsoil and stake combination foundation and construction method thereof
CN1837511B (en) Double-rowed cofferdam and method for manufacturing the same
CN104452829B (en) A kind of pile-raft foundation float Structure and construction method
CN103321246B (en) Construction Method of Foundation Pit Using Underground Diaphragm Wall
CN111305027B (en) Rapid repair construction method and repair structure for pavement collapse in karst area
CN110158630A (en) A kind of deep covering layer area large-span arch bridge annular ground continuous wall base
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN113431065A (en) Rapid construction method and structure of occlusive pile and steel sleeve combined cofferdam
CN217078387U (en) Bridge abutment structure of sea-crossing bridge
CN113216124B (en) An anti-seepage cofferdam system for ship lock reconstruction and expansion project
CN115787568A (en) Ecological bank dike design method
CN106677216B (en) Access gallery structure and its construction method under deep water
CN106192880B (en) The box harbour of L-type and its method of construction
CN114837191A (en) Foundation pit support structure and construction method
CN106149624A (en) A kind of gravity type quay being applicable to roadbed of alluvial silt and construction method thereof
CN115710887B (en) Method for reinforcing asphalt core wall dam body located on deep coverage layer
CN216809751U (en) A force transmission plate structure for protecting the structures passing through the embankment under the Binjiang Road
CN204608701U (en) A kind of gravity type quay being applicable to roadbed of alluvial silt
CN205000338U (en) A lattice form reinforced structure for soft soil area foundation ditch hole end
CN210561967U (en) Channel structure for improving flood control standards of existing river embankments
CN210122735U (en) Underground structure anti-floating system based on outward-protruding wing foot plate
CN206512747U (en) Access gallery structure under deep water
CN115217114A (en) Construction method of foundation pit emergency back-pressure platform
CN114059444A (en) Bridge abutment structure of sea-crossing bridge and construction method thereof
CN219951575U (en) Road structure of underpass railway bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant