CN213418357U CN202021006793.5U CN202021006793U CN213418357U CN 213418357 U CN213418357 U CN 213418357U CN 202021006793 U CN202021006793 U CN 202021006793U CN 213418357 U CN213418357 U CN 213418357U
Authority
CN
China
Prior art keywords
waterproof layer
floor
layer
waterproof
sewer pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021006793.5U
Other languages
Chinese (zh)
Inventor
丰阿香
张提波
陈留平
田炯旻
许小俭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Greentown Real Estate Group Co ltd
Original Assignee
Greentown Real Estate Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Greentown Real Estate Group Co ltd filed Critical Greentown Real Estate Group Co ltd
Priority to CN202021006793.5U priority Critical patent/CN213418357U/en
Application granted granted Critical
Publication of CN213418357U publication Critical patent/CN213418357U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sink And Installation For Waste Water (AREA)

Abstract

The utility model relates to a building technical field, in particular to interlayer drainage bathroom building ground waterproof construction, include: the first waterproof layer is laid on a structural floor slab, a sewer pipe is arranged on the structural floor slab, and the first waterproof layer is disconnected at the position corresponding to the sewer pipe and is bent upwards to be in sealing connection with the sewer pipe. The utility model provides a pair of interlayer drainage bathroom building ground waterproof construction, through correspond downcomer department disconnection with first waterproof layer and upwards buckle with downcomer sealing connection prevents the downward seepage of water from the structure floor to improve the water-proof effects between interlayer drainage bathroom building ground and the downcomer.

Description

Floor waterproof structure of interlayer drainage toilet
Technical Field
The utility model relates to a building technical field, in particular to interlayer drainage bathroom building ground waterproof construction.
Background
The toilet is a humid environment, the floor of the toilet is often connected with water, water can leak downwards through a gap between the floor of the toilet and the water drainage pipe after a long time, and the waterproof effect is poor.
SUMMERY OF THE UTILITY MODEL
An embodiment of the utility model provides an interlayer drainage bathroom building ground waterproof construction for solve the poor problem of current interlayer drainage bathroom building ground water-proof effects.
In order to overcome the defect of background art, the embodiment of the utility model provides an interlayer drainage bathroom building ground waterproof construction, include: the first waterproof layer is laid on a structural floor slab, a sewer pipe is arranged on the structural floor slab, and the first waterproof layer is disconnected at the position corresponding to the sewer pipe and is bent upwards to be in sealing connection with the sewer pipe.
Preferably, the first waterproof layer is a single-component polyurethane waterproof layer.
Preferably, the first waterproof layer extends to the edge of the structural floor slab and then bends upwards, and the first waterproof layer is attached to the wall.
Preferably, a second waterproof layer is laid at the joint of the structural floor slab and the wall body, the second waterproof layer is located below the first waterproof layer, and the height of the first waterproof layer located on the wall body is higher than that of the second waterproof layer.
Preferably, an R angle is arranged at the joint of the structural floor slab and the wall, and the second waterproof layer is laid on the R angle.
Preferably, a slope finding layer and a floor are laid above the first waterproof layer, and the floor is connected with the slope finding layer through an adhesive.
The utility model has the advantages that:
the utility model provides a pair of interlayer drainage bathroom building ground waterproof construction, through correspond downcomer department disconnection with first waterproof layer and upwards buckle with downcomer sealing connection prevents the downward seepage of water from the structure floor to improve the water-proof effects between interlayer drainage bathroom building ground and the downcomer.
Additional features and advantages of the invention will be set forth in the description which follows, and in part will be obvious from the description, or may be learned by the practice of the invention. The objectives and other advantages of the invention will be realized and attained by the structure particularly pointed out in the written description and claims hereof as well as the appended drawings.
The technical solution of the present invention is further described in detail by the accompanying drawings and examples.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention.
In the drawings:
fig. 1 is a schematic view of the overall structure of the embodiment of the present invention.
Detailed Description
The preferred embodiments of the present invention will be described in conjunction with the accompanying drawings, and it will be understood that they are presented herein only to illustrate and explain the present invention, and not to limit the present invention.
As shown in fig. 1, the embodiment of the utility model provides a waterproof structure of interlayer drainage bathroom building ground, include: the waterproof structure comprises a first waterproof layer 1, a first waterproof layer and a second waterproof layer, wherein the first waterproof layer 1 is laid on a structural floor slab 2, a sewer pipe 3 is arranged on the structural floor slab 2, and the first waterproof layer 1 is disconnected at a position corresponding to the sewer pipe 3 and is bent upwards to be in sealing connection with the sewer pipe 3; the first waterproof layer 1 is a single-component polyurethane waterproof layer.
The first waterproof layer 1 extends to the edge of the structural floor slab 2 and then is bent upwards, and the first waterproof layer 1 is attached to the wall 4; and a second waterproof layer 5 is laid at the joint of the structural floor slab 2 and the wall 4, the second waterproof layer 5 is positioned below the first waterproof layer 1, and the height of the first waterproof layer 1 positioned on the wall 4 is higher than that of the second waterproof layer 5.
In the embodiment, the first waterproof layer 1 is disconnected and bent upwards corresponding to the sewer pipe 3 to be hermetically connected with the sewer pipe 3, so that water is prevented from leaking downwards from the structural floor slab 2, and the waterproof effect between the floor of the interlayer drainage toilet and the sewer pipe 3 is improved; lay second waterproof layer 5 in structural floor 2 and wall body 4 junction, structural floor 2 and wall body 4 junction set up R angle 8, the second waterproof layer is laid on the R angle 8, prevent structural floor 2 and wall body 4 junction ponding, prevent water from 4 downward seepage of wall body, first waterproof layer 1 covers second waterproof layer 5 completely, further prevents water from 4 downward seepage of wall body, and the water-proof effects of wall angle department is better.
The water drainage method is characterized in that a slope finding layer 6 and a floor 7 are laid above the first waterproof layer 1, the drainage gradient of the slope finding layer 6 on the periphery of the sewer pipe 3 is 0.3% -0.5%, drainage is facilitated, the floor 7 is wet-laid, water seepage from the floor 7 is prevented, the floor 7 is connected with the slope finding layer 6 through a bonding agent, the slope finding layer 6 is fine stone concrete, and the bonding agent is a floor tile bonding agent.
In the above embodiment, the first waterproof layer 1 is pressed on the structural floor 2 by the slope layer 6, and the slope layer 6 protects the first waterproof layer 1.
It will be apparent to those skilled in the art that various changes and modifications may be made without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (6)

1. The utility model provides a waterproof structure of interlayer drainage bathroom building ground which characterized in that includes:
the first waterproof layer is laid on a structural floor slab, a sewer pipe is arranged on the structural floor slab, and the first waterproof layer is disconnected at the position corresponding to the sewer pipe and is bent upwards to be in sealing connection with the sewer pipe.
2. A floor waterproofing structure for a toilet with a space between floor drain according to claim 1, wherein said first waterproof layer is a single-component polyurethane waterproof layer.
3. A floor waterproofing structure for a toilet with a space therebetween according to claim 1, wherein said first waterproof layer is bent upward after extending to the edge of said structural floor, and said first waterproof layer is attached to the wall.
4. The floor waterproofing structure according to claim 3, wherein a second waterproof layer is laid at the joint of the structural floor slab and the wall body, the second waterproof layer is located below the first waterproof layer, and the height of the first waterproof layer on the wall body is higher than that of the second waterproof layer.
5. A floor waterproofing structure according to claim 4, wherein a corner R is provided at the junction of the structural floor and the wall, and the second waterproofing layer is laid on the corner R.
6. The floor waterproofing structure according to claim 1, wherein a slope layer and a floor are laid over the first waterproofing layer, and the floor and the slope layer are connected by an adhesive.
CN202021006793.5U 2020-06-04 2020-06-04 Floor waterproof structure of interlayer drainage toilet Active CN213418357U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021006793.5U CN213418357U (en) 2020-06-04 2020-06-04 Floor waterproof structure of interlayer drainage toilet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021006793.5U CN213418357U (en) 2020-06-04 2020-06-04 Floor waterproof structure of interlayer drainage toilet

Publications (1)

Publication Number Publication Date
CN213418357U true CN213418357U (en) 2021-06-11

Family

ID=76223717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021006793.5U Active CN213418357U (en) 2020-06-04 2020-06-04 Floor waterproof structure of interlayer drainage toilet

Country Status (1)

Country Link
CN (1) CN213418357U (en)

Similar Documents

Publication Publication Date Title
CN213418357U (en) Floor waterproof structure of interlayer drainage toilet
CN208501802U (en) A kind of bathroom caisson internal drainage construction
CN103835421B (en) Leakage-proof floor and anti-seepage construction method
CN213418356U (en) Water drainage structure is prevented in shower room
CN206143935U (en) Bathroom threshold waterproof construction
CN212926518U (en) Water leakage prevention structure at deformation joint of outdoor balcony of building
CN104455757A (en) Downcomer assembly and installation method thereof
CN211735533U (en) Waterproof structure of post-cast strip of underground chamber roof
CN213329126U (en) Waterproof structure of post-cast strip of underground building roof
CN208280330U (en) Steel corridor and concrete structure junction waterproof construction system with height difference
CN210600475U (en) Waterproof construction structure at splicing position of ventilating duct and floor slab
CN216242884U (en) Prevention of seepage water floor blow off pipe
CN207376843U (en) Expansion joint leakage-proof structure
CN112982623A (en) Assembly type construction method for drainage pipeline of high-rise building
CN205171652U (en) Heavy pond of formula that installs additional floor drain
CN212388710U (en) Building ground hole waterproof device
CN2814074Y (en) Device for sealing up pipe in the wall
CN212718618U (en) A prevention of seepage water swivel, prevention of seepage water installation for roofing
CN209873894U (en) Basement waterproof structure
CN210049412U (en) Toilet waterproof structure
CN213329478U (en) Same-floor drainage toilet threshold and ground structure
CN219973390U (en) Flexible leak-proof structure at joint of drain pipe
CN203821666U (en) Anti-leakage floor slab
CN217759213U (en) Floor drain connecting device
CN218667817U (en) Cast-in-place water stop joint mounting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant