CN213356666U - Concrete pipe's allocation and transportation device - Google Patents

Concrete pipe's allocation and transportation device Download PDF

Info

Publication number
CN213356666U
CN213356666U CN202022408483.2U CN202022408483U CN213356666U CN 213356666 U CN213356666 U CN 213356666U CN 202022408483 U CN202022408483 U CN 202022408483U CN 213356666 U CN213356666 U CN 213356666U
Authority
CN
China
Prior art keywords
pole
rod
rope
frame
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022408483.2U
Other languages
Chinese (zh)
Inventor
李磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhonghao Jiancheng Construction Co ltd
Original Assignee
Zhonghao Jiancheng Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhonghao Jiancheng Construction Co ltd filed Critical Zhonghao Jiancheng Construction Co ltd
Priority to CN202022408483.2U priority Critical patent/CN213356666U/en
Application granted granted Critical
Publication of CN213356666U publication Critical patent/CN213356666U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a device is transported in transfer of concrete pipe relates to municipal construction equipment's field, including transporting the frame and being used for transporting the connection rope of putting up the connection on the crane davit, transport the first pole that the frame set up including an organic whole, second pole and third pole, first pole and third pole are parallel to each other, the second pole is located between first pole and the third pole, first pole is located directly over the third pole, and connect the rope and be connected with first pole, still be provided with on transporting the frame and carry out the fixed subassembly fixed to the concrete pipe. This application has the advantage that can improve concrete pipe allocation and transportation efficiency.

Description

Concrete pipe's allocation and transportation device
Technical Field
The application relates to the field of municipal construction equipment, in particular to a concrete pipe allocation and transportation device.
Background
The concrete pipe mainly comprises plain concrete pipe, common reinforced concrete pipe, self-stress reinforced concrete pipe and prestressed concrete pipe. Concrete pipes are often used for the transport of fluids such as water, oil and gas. In the municipal construction process, the concrete pipes are often paved, and the concrete pipes are dispatched and transported in the paving process.
In the related art, during the process of transferring the concrete pipe, a plurality of safety ropes need to be bound on the concrete pipe firstly, then the safety ropes are bound on a suspension arm of a crane, and then the crane is used for transferring the concrete pipe.
In view of the above-mentioned related technologies, the inventor found that in order to ensure the safety of the concrete pipe during transportation, a plurality of safety ropes on the concrete pipe need to be bound, and the time spent in the binding process of the plurality of safety ropes is relatively long, which results in low efficiency of transportation of the concrete pipe.
SUMMERY OF THE UTILITY MODEL
In order to make the staff more high-efficient when transporting concrete pipe, this application provides a device is transported in allocation of concrete pipe.
The application provides a transfer device of concrete pipe adopts following technical scheme:
the utility model provides a device is transported in transfer of concrete pipe, is including transporting the frame and being used for transporting the connection rope of putting up the connection on the crane davit with transferring, transfers and transports the frame including integrative first pole, second pole and the third pole that sets up, first pole and third pole are parallel to each other, and the second pole is located between first pole and the third pole, and first pole is located the third pole directly over, and connects rope and first pole and be connected, transfers and still is provided with on the frame and carries out the fixed subassembly fixed to the concrete pipe.
Through adopting above-mentioned technical scheme, carrying out the in-process that the concrete pipe was transferred, the staff only needs to set up the concrete pipe between first pole and third pole, then with fixed subassembly with the concrete pipe fixed can, easy operation and convenience to the transfer efficiency of concrete pipe has been improved.
Optionally, the fixing assembly comprises a fixing rope, one end of the fixing rope is connected with the first rod, a dismounting part for realizing detachable connection between the fixing rope and the third rod is arranged between the other end of the fixing rope and the third rod, and a length adjusting part is further arranged on the fixing rope.
Through adopting above-mentioned technical scheme, fixed rope is when fixing the concrete pipe, and the staff makes fixed rope can dismantle after the concrete pipe and connect on the third pole, can accomplish and fix the concrete pipe.
Optionally, the fixed rope comprises a first portion and a second portion, the first portion is connected with the first rod, the dismounting member is arranged between the second portion and the third rod, the length adjusting member comprises a first mounting seat fixedly connected to the first portion and a second mounting seat fixedly connected to the second portion, a screw rod is fixedly connected to the first mounting seat, a connecting pipe is rotatably connected to the second mounting seat, and the screw rod is in threaded connection with the connecting pipe.
By adopting the technical scheme, the working personnel can change the length of the screw rod in the connecting pipe by screwing the screw rod, so that the length of the fixed rope can be adjusted, and the concrete pipe can be tightened after the fixed rope is fixed.
Optionally, a connecting piece is arranged between the fixed rope and the first rod, and the fixed rope is detachably connected to the first rod through the connecting piece.
Through adopting above-mentioned technical scheme, realized fixing the rope and transferring the dismantlement between the frame and being connected to make things convenient for the staff to the change of fixing the rope.
Optionally, the transferring frame is further provided with a supporting piece.
Through adopting above-mentioned technical scheme, when the staff was laying the concrete pipeline, the support makes things convenient for the staff to the adjustment of concrete pipe, and then makes things convenient for the alignment between two adjacent concrete pipes.
Optionally, the supporting member is arranged to be detachably connected with a supporting rod on the transferring frame.
Through adopting above-mentioned technical scheme, the staff can adjust the concrete pipe in the transfer process through supporting the pole, and when supporting the pole not used, the staff can be dismantled the pole of holding from the transfer frame, conveniently holds putting and transporting of holding the pole.
Optionally, a fixing hole is formed in the transferring frame, and the supporting rod is in threaded connection with the second rod through the fixing hole.
Through adopting above-mentioned technical scheme, the staff will support the pole and twist soon in the fixed orifices, can realize that the fixed orifices installs on transferring the frame, easy operation and convenience.
Optionally, the transferring frame is further fixedly connected with a fixing pipe arranged along the length direction of the transferring frame, the fixing pipe is matched with the supporting rod, and an internal thread is arranged in the fixing pipe.
Through adopting above-mentioned technical scheme, after the pole is dismantled from transferring the frame to the support pole, the staff can fix the support pole in the fixed tube.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the concrete pipe is transported by adopting the transporting frame, and the transporting frame and the concrete pipe are fixed more simply and conveniently, so that the transporting efficiency of workers for the concrete pipe is improved;
2. through set up the holding piece on transferring the frame, when the concrete pipe was laid in transferring, made things convenient for the staff to the adjustment of concrete pipe more.
Drawings
Fig. 1 is a schematic view of a state of a dispatching device in an operating state in the embodiment of the application.
Fig. 2 is a schematic structural diagram of the configuration of the allocation and transportation device in the embodiment of the application.
Fig. 3 is a partial sectional view of a length adjustment member in an embodiment of the present application.
Description of reference numerals: 1. a transferring frame; 11. a first lever; 12. a second lever; 121. a fixing hole; 13. a third lever; 2. A connecting rope; 21. a hoisting ring; 22. pulling a rope; 3. a fixing assembly; 31. fixing a rope; 311. a first part; 312. a second section; 3121. hooking; 32. hanging a ring; 33. a length adjustment member; 331. connecting blocks; 3311. a screw; 332. a fixed block; 3321. a slider; 333. a connecting pipe; 3331. a chute; 4. a connecting member; 41. a connecting hook; 42. a connecting ring; 5. a holding rod; 6. a fixed tube; 7. a concrete pipe.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses a device is transported in allotment of concrete pipe. Referring to fig. 1, the transferring device includes a transferring frame 1 and a connecting rope 2. The transfer frame 1 is used for transferring a concrete pipe 7, and the connecting rope 2 is used for connecting the transfer frame 1 to a boom of a crane.
Referring to fig. 2, the allocation and transportation frame 1 comprises a first rod 11, a second rod 12 and a third rod 13 which are integrally arranged, the first rod 11 and the third rod 13 are parallel to each other, the second rod 12 is positioned between the first rod 11 and the third rod 13, and the allocation and transportation frame 1 is in a 'U' shape.
The connecting rope 2 comprises a hanging ring 21 and three pull ropes 22, one ends of the three pull ropes 22 are fixedly connected with the hanging ring 21, one ends of the three pull ropes 22 far away from the hanging ring 21 are fixedly connected to one surface of the first rod 11 far away from the third rod 13, and connecting points of the three pull ropes 22 and the first rod 11 are arranged at equal intervals along the length direction of the first rod 11.
The adjusting and transporting frame 1 is also provided with a fixing component 3 for fixing the concrete pipe 7. Fixed subassembly 3 includes fixed rope 31, and fixed rope 31 one end is kept away from second pole 12 end connection with first pole 11, and the other end rigid coupling of fixed rope 31 has couple 3121, and the rigid coupling has the link 32 with couple 3121 cooperation use on the terminal surface of second pole 12 is kept away from to third pole 13. And a length adjusting member 33 is provided on the fixing rope 31.
When the concrete pipe 7 is transferred, the worker first hooks the hanging ring 21 of the connecting rope 2 to the arm of the crane, and then moves the transfer frame 1 by the crane, so that the concrete pipe 7 is positioned between the first pole 11 and the third pole 13 of the transfer frame 1, and the concrete pipe 7 is lapped on the third pole 13. Then the hook 3121 of the fixing rope 31 is hooked on the hook 32 of the third rod 13, and then the length of the fixing rope 31 is shortened and tightened by using the length adjuster 33, and then the concrete pipe 7 is adjusted to a designated position by a crane.
Referring to fig. 2 and 3, the fixing rope 31 includes a first portion 311 and a second portion 312, the first portion 311 is connected to the first rod 11, and the hook 3121 is fixed to the second portion 312. The length adjusting member 33 is disposed between the first portion 311 and the second portion 312, the length adjusting member 33 includes a connecting block 331, the connecting block 331 is fixedly connected to the first portion 311 at an end far away from the first rod 11, and a screw rod 3311 is coaxially and fixedly connected to a surface of the connecting block 331 far away from the first portion 311.
The length adjustment member 33 further includes a fixing block 332 having a circular cross section and a connection pipe 333 having a circular cross section, the fixing block 332 is fixedly connected to the second portion 312, and a plurality of annular sliders 3321 are integrally provided on an outer circumferential surface of the fixing block 332. The connecting pipe 333 is sleeved on the fixing block 332, the connecting pipe 333 and the fixing block 332 are connected in a sliding manner, the inner circumferential surface of the connecting pipe 333 is provided with a plurality of sliding grooves 3331 matched with the sliding grooves 3321, the sliding blocks 3331 are respectively embedded in the sliding grooves 3321, and the sliding blocks 3331 and the sliding grooves 3321 are connected in a sliding manner. The screw 3311 of the connecting block 331 is disposed through the connecting tube 333, and the screw 3311 is in threaded connection with the connecting tube 333.
When the worker adjusts the length of the fixing rope 31, the worker controls the length of the screw 3311 extending into the connecting pipe 333 by screwing the screw 3311 of the connecting block 331, thereby adjusting the length of the fixing rope 31.
Referring to fig. 2, in order to allow the fixing rope 31 of the deployment device to be well adapted when facing different types of concrete pipes 7, a connecting member 4 is provided between the first portion 311 of the fixing rope 31 and the first rod 11. The connecting member 4 includes a connecting ring 42 fixed to the first lever 11, and a connecting hook 41 fixed to the first portion 311 of the fixing rope 31 for cooperating with the connecting ring 42. The coupling hook 41 is hooked on the coupling ring 42.
In the process of paving the concrete pipes 7, a plurality of concrete pipes 7 are generally required to be aligned and spliced together, and the concrete pipes 7 are very labor-consuming in the alignment process only by the operation of a crane, so that the concrete pipes 7 are conveniently aligned in the paving process.
The adjusting and transporting frame 1 is further provided with a holding rod 5, a fixing hole 121 matched with the holding rod 5 is formed in a second portion 312 of the corresponding adjusting and transporting frame 1, the holding rod 5 is connected in the fixing hole 121 in the second rod 12 in a threaded mode, and the holding rod 5 is perpendicular to the second portion 312. When concrete pipe 7 was mated formation and is aimed at, the staff can adjust concrete pipe 7 through holding pole 5 to make concrete pipe 7 more convenient when mating formation and aim at.
On transfer frame 1 on the third pole 13 keep away from the one side of first portion 311 on the rigid coupling have fixed pipe 6, fixed pipe 6 lays along the length direction of third pole 13, and fixed pipe 6 sets up to and supports 5 adaptations of pole. Internal threads are formed in the fixed pipe 6, the holding rod 5 can be detached from the second rod 12 when not in use and then is arranged in the fixed pipe 6 in a penetrating manner, so that the holding rod 5 is arranged on the second rod 12 on the transferring frame 1 in a penetrating manner. The holding rod 5 and the adjusting and transporting frame 1 are positioned in the same plane, so that the adjusting and transporting device is more space-saving.
The implementation principle of the concrete pipe 7 allocation and transportation device in the embodiment of the application is as follows: before the concrete pipe 7 is transferred, an operator takes out the holding rod 5 in the fixed pipe 6 and fixes the holding rod on the transfer frame 1, then the operator hooks the hanging ring 21 on the transfer device on the hanging arm of the crane, then the hanging arm of the crane drives the transfer device to move, so that one end of the concrete pipe 7 to be transferred, which is far away from the splicing end, penetrates through the opening on the transfer frame 1 to be arranged between the first rod 11 and the second rod 12 and then is erected on the third rod 13 on the transfer frame 1, then the hook 3121 on the fixed rope 31 is hooked on the hanging ring 32 on the third rod 13, and then the fixed rope 31 is tightened through the length adjusting piece 33.
The staff transfers concrete pipe 7 to appointed place through the crane, and after concrete pipe 7 arrived appointed place, the staff separated couple 3121 and link 32 on the fixing rope 31, relied on transfer frame 1 to bear concrete pipe 7 this moment, and the concatenation end of concrete pipe 7 can lose the interference of fixing rope 31, and later the staff adjusts the alignment back through holding up pole 5 to concrete pipe 7, and the crane is that concrete pipe 7 lands completely afterwards, and it can to dismantle the transfer device again.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a device is transported in allotment of concrete pipe which characterized in that: transfer frame (1) and be used for transferring connecting rope (2) of transporting frame (1) connection on the crane davit including transferring, transfer frame (1) including integrative first pole (11), second pole (12) and third pole (13) that set up, first pole (11) are parallel to each other with third pole (13), second pole (12) are located between first pole (11) and third pole (13), first pole (11) are located third pole (13) directly over, and connect rope (2) and be connected with first pole (11), still be provided with on transferring frame (1) and carry out fixed subassembly (3) fixed concrete pipe (7).
2. The apparatus of claim 1, wherein: the fixing assembly (3) comprises a fixing rope (31), one end of the fixing rope (31) is connected with the first rod (11), a dismounting part for realizing detachable connection between the fixing rope (31) and the third rod (13) is arranged between the other end of the fixing rope (31) and the third rod (13), and a length adjusting part (33) is further arranged on the fixing rope (31).
3. The apparatus of claim 2, wherein: fixed rope (31) include first portion (311) and second portion (312), first portion (311) are connected with first pole (11), the dismouting piece sets up between second portion (312) and third pole (13), length adjustment spare (33) include the first mount pad of rigid coupling on first portion (311) to and the second mount pad of rigid coupling on second portion (312), the rigid coupling has screw rod (3311) on the first mount pad, it is connected with connecting pipe (333) to rotate on the second mount pad, screw rod (3311) threaded connection is in connecting pipe (333).
4. The apparatus of claim 2, wherein: a connecting piece (4) is arranged between the fixed rope (31) and the first rod (11), and the fixed rope (31) is detachably connected to the first rod (11) through the connecting piece (4).
5. The apparatus of claim 1, wherein: the transferring frame (1) is also provided with a supporting piece.
6. The apparatus of claim 5, wherein: the supporting piece is detachably connected with a supporting rod (5) on the transferring frame (1).
7. The apparatus of claim 6, wherein: a fixing hole (121) is formed in the transferring frame (1), and the holding rod (5) is in threaded connection with the second rod (12) through the fixing hole (121).
8. The apparatus of claim 6, wherein: transfer and transport still the rigid coupling on frame (1) and have along transferring fixed pipe (6) that frame (1) length direction laid, fixed pipe (6) and support pole (5) adaptation, and be provided with the internal thread in fixed pipe (6).
CN202022408483.2U 2020-10-26 2020-10-26 Concrete pipe's allocation and transportation device Active CN213356666U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022408483.2U CN213356666U (en) 2020-10-26 2020-10-26 Concrete pipe's allocation and transportation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022408483.2U CN213356666U (en) 2020-10-26 2020-10-26 Concrete pipe's allocation and transportation device

Publications (1)

Publication Number Publication Date
CN213356666U true CN213356666U (en) 2021-06-04

Family

ID=76132324

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022408483.2U Active CN213356666U (en) 2020-10-26 2020-10-26 Concrete pipe's allocation and transportation device

Country Status (1)

Country Link
CN (1) CN213356666U (en)

Similar Documents

Publication Publication Date Title
CN205689895U (en) Heavy caliber compound pipeline complex pipeline boil on the nape opposite the mouth adjusting means
CA2860604A1 (en) Boom mounted coiled tubing guide and method for running coiled tubing
CN211056577U (en) Pipe gallery tubular product hoisting accessory
CN107055309A (en) PK prestressed concrete overlapped slabs suspender and the hanging method using the suspender
CN110253195B (en) High-precision pipeline butt joint device
CN110086120B (en) Anti-bundle tightening device for electrified dismounting insulator string, dismounting device and dismounting method
CN213356666U (en) Concrete pipe's allocation and transportation device
US6405802B1 (en) Subsea flowline jumper handling apparatus
CN114180456A (en) Hoisting posture adjusting method for giant laterally inclined truss structure
KR101811363B1 (en) Device for replacing roller sets
US9009976B2 (en) Method and apparatus for energy chain installation
CN207599140U (en) A kind of descending pipelines into ditch device
CN213575898U (en) Pipe joint installation device
US20150354194A1 (en) Methods and systems for pulling pipe
CN111946900B (en) Pipe joint installation device and method
CN210306464U (en) High-precision pipeline butt-joint structure
CN115182551A (en) Vertical laying method for pipeline
CN108130859B (en) Beam end installation method of stay cable
CN217232809U (en) Swift mounting tool of steel construction wall purlin
CN216945846U (en) Pipeline hoisting clamping tool
CN220467285U (en) Portable lifting appliance suitable for reinforced concrete steel bellmouth pipe
KR101622381B1 (en) Facilities and method for pulling installation of cable using cable guiding device
CN214879771U (en) Hoisting device and functional ship with same
CN220537304U (en) Hoisting device for stably hoisting prefabricated pipeline
CN213112209U (en) Rigging for hoisting concrete pipe

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant