CN213233454U - Bored concrete pile operation platform on water - Google Patents
Bored concrete pile operation platform on water Download PDFInfo
- Publication number
- CN213233454U CN213233454U CN202021659577.0U CN202021659577U CN213233454U CN 213233454 U CN213233454 U CN 213233454U CN 202021659577 U CN202021659577 U CN 202021659577U CN 213233454 U CN213233454 U CN 213233454U
- Authority
- CN
- China
- Prior art keywords
- operation platform
- staple bolt
- hoop
- bored concrete
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Revetment (AREA)
Abstract
An overwater operation platform for a cast-in-place pile comprises a hoop, wherein the hoop and the cast-in-place pile are connected into a whole; the hoop is fixed with a supporting plate on the left and right, horizontal supports are fixed on the front and back of the supporting plate, the horizontal supports and the vertical supports form an operation platform frame, a bamboo springboard is installed on the horizontal portion of the operation platform frame to form an operation channel, and dense mesh type safety vertical nets are arranged around the operation platform frame to form safety protection. The utility model provides a pair of bored concrete pile operation platform on water can provide fixed operation point for bored concrete pile operation on water, stability when guaranteeing personnel's operation.
Description
Technical Field
The utility model relates to an operation platform, especially a bored concrete pile operation platform on water.
Background
After the underwater cast-in-place pile is cast above the water surface, the part of the operation on the water surface generally uses a ship as a temporary operation platform, and the operation efficiency of operators is influenced because the ship cannot provide a stable operation point.
Disclosure of Invention
The utility model aims to solve the technical problem that a bored concrete pile operation platform on water is provided, the solution can provide fixed operation point for bored concrete pile operation on water, stability when guaranteeing personnel's operation.
In order to solve the technical problem, the utility model discloses the technical scheme who adopts is:
an overwater operation platform for a cast-in-place pile comprises a hoop, wherein the hoop and the cast-in-place pile are connected into a whole; the hoop is fixed with a supporting plate on the left and right, horizontal supports are fixed on the front and back of the supporting plate, the horizontal supports and the vertical supports form an operation platform frame, a bamboo springboard is installed on the horizontal portion of the operation platform frame to form an operation channel, and dense mesh type safety vertical nets are arranged around the operation platform frame to form safety protection.
The staple bolt includes half staple bolt on a left side and half staple bolt on a right side, is the arc steel sheet that matches with the bored concrete pile in the middle of half staple bolt on a left side and half staple bolt on a right side, and the both sides of half staple bolt on a left side and half staple bolt on a right side are rectangular steel sheet.
The support plate is an L-shaped steel plate.
The utility model relates to a bored concrete pile operation platform on water has following technological effect:
1) the anchor ear and the supporting plate are installed on the cast-in-place pile, so that the quick lap joint of the operation platform can be realized, a fixed operation point is formed on water, the stability of personnel during operation is guaranteed, and the construction efficiency is improved.
2) The device is arranged on the cast-in-place pile, a supporting point does not need to be arranged on the ground, and the advantage of the operation of the cast-in-place pile in the area with large span of the water area is particularly remarkable.
Drawings
The invention will be further explained with reference to the following figures and examples:
fig. 1 is a front view of the present invention.
Fig. 2 is a left side view of the present invention.
Fig. 3 is a top view of the present invention.
In the figure: staple bolt 1, backup pad 2, horizontal support 3, vertical support 4, bamboo springboard 5, net 6 is found to the safety.
Detailed Description
As shown in fig. 1-3, a cast-in-place pile overwater operation platform comprises a hoop 1, a support plate 2, a horizontal support 3, a vertical support 4, a bamboo springboard 5 and a safety vertical net 6.
The support plates 2 are common L-shaped steel plates, the number of the common steel plates is two, and the two common steel plates are welded with the hoop 1 in a bilateral symmetry mode.
The horizontal supports 3 are horizontal steel pipes, and the two horizontal steel pipes are welded on the support plate 2 from left to right. The other horizontal supports 3 are connected with the two horizontal supports 3 through steel pipe connecting fasteners.
The vertical supports 4 are vertical steel pipes, and the vertical steel pipes are connected with the horizontal steel pipes through steel pipe connecting fasteners to form an operation platform frame integrally. The operation platform frame is provided with a bamboo springboard 5 to form an operation channel, and the adjacent edge part of the channel is provided with a dense mesh type safety vertical net 6 to form safety protection.
Claims (3)
1. The utility model provides a bored concrete pile operation platform on water which characterized in that: comprises a hoop (1), the hoop (1) and a filling pile (7) are connected into a whole; the hoop (1) is fixed with the supporting plate (2) from left to right, the supporting plate (2) is fixed with the horizontal support (3) from front to back, the horizontal support (3) and the vertical support (4) form an operation platform frame, the horizontal part of the operation platform frame is provided with the bamboo springboard (5) to form an operation channel, and the periphery of the operation platform frame is provided with the dense mesh type safety vertical net (6) to form safety protection.
2. A cast-in-place pile marine work platform as claimed in claim 1, wherein: staple bolt (1) is including half staple bolt on a left side and half staple bolt on a right side, is the arc steel sheet that matches with bored concrete pile (7) in the middle of half staple bolt on a left side and the half staple bolt on a right side, and the both sides of half staple bolt on a left side and half staple bolt on a right side are the rectangle steel sheet.
3. A cast-in-place pile marine work platform as claimed in claim 1, wherein: the supporting plate (2) is an L-shaped steel plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021659577.0U CN213233454U (en) | 2020-08-11 | 2020-08-11 | Bored concrete pile operation platform on water |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021659577.0U CN213233454U (en) | 2020-08-11 | 2020-08-11 | Bored concrete pile operation platform on water |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213233454U true CN213233454U (en) | 2021-05-18 |
Family
ID=75893868
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021659577.0U Active CN213233454U (en) | 2020-08-11 | 2020-08-11 | Bored concrete pile operation platform on water |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213233454U (en) |
-
2020
- 2020-08-11 CN CN202021659577.0U patent/CN213233454U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN2923824Y (en) | Inlaid section-steel waist-beam | |
CN213233454U (en) | Bored concrete pile operation platform on water | |
CN205999844U (en) | A kind of novel wave block | |
CN210439674U (en) | Special formwork for construction of breast wall of dike dam | |
CN214832370U (en) | Interim bank protection device is used in construction of environmental hydraulic engineering | |
CN211499866U (en) | A regularization faces limit protection for assembly type structure | |
CN210134411U (en) | Steel-pipe pile diversion guiding device that divides water | |
CN206385532U (en) | It is a kind of to be used for the piling template of CFG | |
CN210134420U (en) | Composite hoop for trestle steel pipe pile parallel connection | |
CN214423126U (en) | Steel temporary bridge for high-pile wharf construction | |
CN212507270U (en) | Detachable pavement for protecting and binding reinforcing steel bars | |
CN209194355U (en) | A kind of hood type anticollision device, collision-prevention device of pier | |
CN209620764U (en) | Assembled moves construction guard fender | |
CN214614105U (en) | Mounting device for inner support of row piles | |
CN213297175U (en) | Detachable pump line fixing device in steel construction | |
CN207073110U (en) | A kind of bucket foundation Larsen steel sheet pile combined type can generation breakwater | |
CN208592819U (en) | A kind of wind-force tower planar plate members storage combination unit | |
CN207919594U (en) | A kind of telescopic steel-pipe pile connects under water is | |
CN207985110U (en) | A kind of naval vessel lightening hole protective device | |
CN206971230U (en) | The supporting construction of Horizontal steelwork bracing in deep basal pit assembled type steel support system | |
CN218027781U (en) | Novel swift finished product lattice column waterstop piece | |
CN210118137U (en) | Shield constructs quick-witted chamber device that starts | |
CN206360392U (en) | Attachment type raise scaffold periphery protecting wire net | |
CN215760890U (en) | Interim protector of wing wall | |
CN211773571U (en) | Adjustable underwater connection system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |