CN212958755U - Underground tunnel drainage structure - Google Patents

Underground tunnel drainage structure Download PDF

Info

Publication number
CN212958755U
CN212958755U CN202021393141.1U CN202021393141U CN212958755U CN 212958755 U CN212958755 U CN 212958755U CN 202021393141 U CN202021393141 U CN 202021393141U CN 212958755 U CN212958755 U CN 212958755U
Authority
CN
China
Prior art keywords
drainage
laid
layer
ground
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021393141.1U
Other languages
Chinese (zh)
Inventor
韩鹏程
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021393141.1U priority Critical patent/CN212958755U/en
Application granted granted Critical
Publication of CN212958755U publication Critical patent/CN212958755U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model relates to the technical field of road construction, and discloses an underground tunnel drainage structure, which comprises a ground surface, a sandstone layer is laid on the top of the ground surface, a cushion layer is laid on the top of the sandstone layer, a base layer is laid on the top of the cushion layer, a surface layer is laid on the top of the base layer, drainage channels are arranged on both sides of the top of the ground surface, a cover plate is laid on the top of the drainage channels, a supporting body is built on the top of the ground surface, a plurality of through grooves are arranged in the cover plate, and the number of the through grooves is five; the utility model discloses a setting of ground, gravel layer, bed course, basic unit, surface course, drainage canal and apron has solved current drainage structures drainage inefficiency, causes the problem of the inside ponding of tunnel easily, and this drainage structures can effectively improve drainage efficiency, and avoids the inside condition that appears ponding of tunnel to guaranteed that the vehicle is normally current and improved this drainage structures's practicality.

Description

Underground tunnel drainage structure
Technical Field
The utility model relates to a road construction technical field specifically is underground tunnel drainage structures.
Background
Tunnels are buildings that are built underground or underwater or in mountains, and that are used for motor vehicles to travel by laying railways or constructing highways. Can be divided into three categories of mountain tunnels, underwater tunnels and urban tunnels according to the positions of the tunnel bodies. A tunnel traversing from a mountain or under a hill to shorten the distance and avoid a large slope is called a mountain tunnel; an underwater tunnel for crossing a river or channel and passing under a river or sea floor; urban tunnels are used to pass through the ground of a city to meet the requirement of a railway to pass through a large city. The most constructed tunnels in the three categories are mountain tunnels. The tunnel need build drainage structures when the construction, but current drainage structures drainage efficiency is low, causes the inside ponding of tunnel easily to influence the vehicle current, for solving above-mentioned problem, we provide secret tunnel drainage structures.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an underground tunnel drainage structures possesses the efficient advantage of drainage, has solved current drainage structures drainage inefficiency, causes the problem of the inside ponding of tunnel easily.
In order to achieve the above object, the utility model provides a following technical scheme: underground tunnel drainage structures, including ground, the gravel layer has been laid at the top on ground, the bed course has been laid at the top on gravel layer, the basic unit has been laid at the top of bed course, the surface course has been laid at the top of basic unit, the surface course is the pitch layer, the drainage canal has all been seted up to the both sides at ground top, the width of drainage canal is fifty centimetres, the apron has been laid at the top of drainage canal, the width of apron is fifty centimetres, and apron length is eighty centimetres, the apron is made by the concrete.
Preferably, a support body is built on the top of the ground.
Preferably, a plurality of through grooves are formed in the cover plate, and the number of the through grooves is five.
Preferably, the center of the surface layer is convex.
Compared with the prior art, the beneficial effects of the utility model are as follows:
the utility model discloses a setting of ground, gravel layer, bed course, basic unit, surface course, drainage canal and apron has solved current drainage structures drainage inefficiency, causes the problem of the inside ponding of tunnel easily, and this drainage structures can effectively improve drainage efficiency, and avoids the inside condition that appears ponding of tunnel to guaranteed that the vehicle is normally current and improved this drainage structures's practicality.
Drawings
FIG. 1 is a front view of the present invention;
FIG. 2 is a top view of the present invention;
FIG. 3 is a top view of the partial structure of the present invention;
fig. 4 is a partially enlarged view of a portion a in fig. 1 according to the present invention.
In the figure: 1. a ground surface; 2. a sandstone layer; 3. a cushion layer; 4. a base layer; 5. a surface layer; 6. a drainage channel; 7. A cover plate; 8. a support body; 9. a through groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the underground tunnel drainage structure includes a ground 1, a gravel layer 2 is laid on the top of the ground 1, a cushion layer 3 is laid on the top of the gravel layer 2, a base layer 4 is laid on the top of the cushion layer 3, a surface layer 5 is laid on the top of the base layer 4, the surface layer 5 is an asphalt layer, drainage channels 6 are respectively arranged on two sides of the top of the ground 1, the drainage channels 6 are fifty centimeters in width, a cover plate 7 is laid on the top of the drainage channels 6, the cover plate 7 is fifty centimeters in width, the cover plate 7 is eighty centimeters in length, and the cover plate 7 is made of concrete.
Further, the supporting body 8 is built at the top of the ground 1, and the broken stones can be effectively prevented from collapsing by the aid of the supporting body 8.
Further, a plurality of through grooves 9 have been seted up to the inside of apron 7, and the quantity that leads to groove 9 is five, leads to groove 9 through setting up, can effectively make ponding flow in the inside of drainage canal 6.
Furthermore, the center of the surface layer 5 is protruded, and accumulated water can effectively flow to two sides by arranging the protrusion.
The working principle is as follows: when there is ponding tunnel inside, because 1 arch on ground, water can flow to both sides to through the cooperation of logical groove 9 flow in to the inside of ditch 6, can carry out because of the drainage to ponding.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. Underground tunnel drainage structures, including ground (1), its characterized in that: gravel layer (2) has been laid at the top of ground (1), bed course (3) have been laid at the top of gravel layer (2), basic unit (4) have been laid at the top of bed course (3), surface course (5) have been laid at the top of basic unit (4), surface course (5) are the pitch layer, drainage canal (6) have all been seted up to the both sides at ground (1) top, the width of drainage canal (6) is fifty centimetres, apron (7) have been laid at the top of drainage canal (6), the width of apron (7) is fifty centimetres, and apron (7) length is eighty centimetres, apron (7) are made by the concrete.
2. An underground tunnel drainage structure according to claim 1, wherein: and a support body (8) is built at the top of the ground (1).
3. An underground tunnel drainage structure according to claim 1, wherein: a plurality of through grooves (9) are formed in the cover plate (7), and the number of the through grooves (9) is five.
4. An underground tunnel drainage structure according to claim 1, wherein: the center of the surface layer (5) is convex.
CN202021393141.1U 2020-07-15 2020-07-15 Underground tunnel drainage structure Active CN212958755U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021393141.1U CN212958755U (en) 2020-07-15 2020-07-15 Underground tunnel drainage structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021393141.1U CN212958755U (en) 2020-07-15 2020-07-15 Underground tunnel drainage structure

Publications (1)

Publication Number Publication Date
CN212958755U true CN212958755U (en) 2021-04-13

Family

ID=75392957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021393141.1U Active CN212958755U (en) 2020-07-15 2020-07-15 Underground tunnel drainage structure

Country Status (1)

Country Link
CN (1) CN212958755U (en)

Similar Documents

Publication Publication Date Title
CN210916847U (en) Sidewalk floor tile and sidewalk thereof
CN213571359U (en) Natural permeable quarrying paving structure for sponge city
CN102322094A (en) Road surface combined drainage system
CN211922135U (en) Prevent subsiding highway subgrade
CN212958755U (en) Underground tunnel drainage structure
CN218812950U (en) Sponge city brick that permeates water
CN111648199A (en) Water drainage structure system is prevented to city reconstruction road central authorities' median
CN209243482U (en) A kind of town road for receiving water function with face formula
CN214301528U (en) Sponge transformation system for urban river retaining wall
CN205529776U (en) Infiltration structure of waterproof road in road surface
CN212388278U (en) Highway subgrade waterproof construction
CN210216078U (en) Flat stone structure that urban road drainage bituminous paving adopted
CN209568531U (en) A kind of water storage system of discarded Rare-earth Mine
CN209723194U (en) Drainage system of freeway
CN112281573A (en) Municipal road water passing asphalt concrete pavement structure and construction method
CN113152628A (en) V-shaped gully high-fill temporary drainage system and construction method thereof
CN207699976U (en) A kind of curb, the road paving structure using the curb
CN207699962U (en) A kind of road engineering roadbed
CN213772763U (en) Prevent highway subgrade structure that subsides
CN111980131A (en) Construction method for combining wooden plank road with sunken green land
CN213772778U (en) Tunnel antiseep combined type road surface
CN210529901U (en) Ground surface water storage type parking lot
CN210177307U (en) Sponge urban pavement structure
CN220789281U (en) Roadbed for municipal road engineering
CN216445718U (en) Highway subgrade structure capable of preventing subgrade from softening

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant