CN212866082U - Intelligent monitoring device for foundation pit settlement - Google Patents

Intelligent monitoring device for foundation pit settlement Download PDF

Info

Publication number
CN212866082U
CN212866082U CN202021521181.XU CN202021521181U CN212866082U CN 212866082 U CN212866082 U CN 212866082U CN 202021521181 U CN202021521181 U CN 202021521181U CN 212866082 U CN212866082 U CN 212866082U
Authority
CN
China
Prior art keywords
monitoring
foundation ditch
fixed
fixedly provided
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021521181.XU
Other languages
Chinese (zh)
Inventor
王振峰
徐明霞
李明杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Institute of Technology
Original Assignee
Shaanxi Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Institute of Technology filed Critical Shaanxi Institute of Technology
Priority to CN202021521181.XU priority Critical patent/CN212866082U/en
Application granted granted Critical
Publication of CN212866082U publication Critical patent/CN212866082U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses an intelligent monitoring devices for foundation ditch subsides, including foundation ditch lateral wall and foundation ditch diapire, the last fixed surface of a support section of thick bamboo installs fixed frame, the lower fixed surface of fixed frame installs the scale strip, the interior diapire of fixed frame and the equal fixed mounting of interior roof have a plurality of slip roller, the surface of slip roller is provided with the monitoring conical plate, the right flank fixed mounting of monitoring conical plate has the dead lever, the dead lever is kept away from the one end fixed mounting of monitoring conical plate and is pressed the briquetting. This an intelligent monitoring devices for foundation ditch subsides through setting up cylinder pole, a support section of thick bamboo, spring, monitoring conical plate, scale bar, monitoring lever, camera, position sensor and PLC controller, makes this monitoring devices when monitoring foundation ditch lateral wall vertical settlement, can give the PLC controller through position sensor with signal transmission, and the work of PLC controller control camera to for the monitoring personnel provide the vertical real-time data that is subsides of foundation ditch lateral wall.

Description

Intelligent monitoring device for foundation pit settlement
Technical Field
The utility model relates to a be used for foundation ditch settlement monitoring technical field, specifically be an intelligent monitoring devices for foundation ditch subsides.
Background
Along with the development of the industrial and civil building industry, various complex and large-scale engineering buildings are increased day by day, the construction of the engineering buildings changes the original state of the ground, and applies a certain pressure to the foundation of the building, which inevitably causes the deformation of the foundation and the surrounding stratum, so as to ensure the normal service life of the building and the safety of the building, and provide reliable data and corresponding settlement parameters for the future exploration design construction, and the necessity and the importance of monitoring the settlement of the foundation pit are more obvious.
The vertical settlement at the edge of the foundation pit is an important index of the stability of the foundation pit, most of the existing methods for monitoring the vertical settlement at the edge of the foundation pit are carried out in a mode of manual regular measurement, the vertical settlement at the edge of the foundation pit cannot be monitored in real time, and monitoring personnel cannot effectively give an alarm and process the settlement of the foundation pit in time.
Therefore, an intelligent monitoring device for foundation pit settlement is needed.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an intelligent monitoring devices for foundation ditch subsides to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: an intelligent monitoring device for foundation pit settlement comprises a foundation pit side wall and a foundation pit bottom wall, wherein a mounting plate is fixedly mounted on the upper surface of the foundation pit bottom wall through a threaded mounting nail, a ball head is fixedly mounted on the upper surface of the mounting plate, an adjusting disc is arranged on the surface of the ball head, a fixing box is fixedly mounted on the upper surface of the adjusting disc, a cylindrical rod is fixedly mounted on the upper surface of the fixing box, a supporting cylinder is sleeved on the surface of the cylindrical rod, a limiting disc is fixedly mounted on the surface of the cylindrical rod, the cylindrical rod is in sliding connection with the inner wall of the supporting cylinder through the limiting disc, a fixing frame is fixedly mounted on the upper surface of the supporting cylinder, a scale strip is fixedly mounted on the lower surface of the fixing frame, a plurality of sliding rollers are fixedly mounted on the inner bottom wall and the inner top wall of the fixing frame, a monitoring conical plate is arranged on the surface, one end of the fixing rod, which is far away from the monitoring conical plate, is fixedly provided with a pressing block.
Preferably, the upper surface threaded connection of adjusting disk has a plurality of adjusting bolt, a plurality of adjusting bolt circumference equidistance sets up the upper surface at the adjusting disk, adjusting bolt's bottom and the upper surface overlap joint of mounting panel.
Preferably, the upper surface of the limiting disc is fixedly provided with a spring, the top end of the spring is fixedly connected with the inner top wall of the supporting cylinder, the surface of the cylindrical rod is provided with an opening, and the inner wall of the opening is provided with a bolt.
Preferably, the left side of fixed case fixed mounting respectively has monitoring pole and camera, the left end of monitoring pole and the side overlap joint of scale bar, the lower fixed surface of monitoring pole installs position sensor, the right flank fixed mounting of fixed case has the spirit level.
Preferably, the fixed box is internally provided with a storage battery, a PLC (programmable logic controller) and a data conversion module respectively.
Preferably, the camera and the position sensor are both electrically connected with the PLC.
Advantageous effects
The utility model provides an intelligent monitoring devices for foundation ditch subsides possesses following beneficial effect:
1. this an intelligent monitoring devices for foundation ditch subsides, through setting up the cylinder pole, a support section of thick bamboo, a spring, monitoring conical plate, the scale bar, the monitoring lever, the camera, position sensor and PLC controller, make this monitoring devices when monitoring foundation ditch lateral wall vertical settlement, can give the PLC controller through position sensor with signal transmission, the work of PLC controller control camera, thereby for the monitoring personnel provide the vertical real-time data that is subsides of foundation ditch lateral wall, be convenient for the monitoring personnel to take corresponding measure.
2. This an intelligent monitoring devices for foundation ditch subsides through setting up bulb, adjusting disk, adjusting bolt and spirit level, makes this monitoring devices before the monitoring to the vertical settlement of foundation ditch lateral wall, can adjust the device to the horizontality, makes the data of monitoring more accurate.
Drawings
FIG. 1 is a schematic view of a front cross-sectional structure of the present invention;
FIG. 2 is an enlarged schematic view of the structure at A in FIG. 1;
fig. 3 is an enlarged schematic view of B in fig. 1.
In the figure: 1 foundation ditch lateral wall, 2 foundation ditch diapire, 3 mounting panels, 4 bulb, 5 adjustment disks, 6 cylinder poles, 7 support section of thick bamboo, 8 spacing dishes, 9 scale bars, 10 monitoring taper plates, 11 adjusting bolt, 12 springs, 13 bolts, 14 monitoring rod, 15 cameras, 16 position sensor, 17PLC controller.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: the utility model provides an intelligent monitoring devices for foundation ditch subsides, including foundation ditch lateral wall 1 and foundation ditch diapire 2, there is mounting panel 3 on the upper surface of foundation ditch diapire 2 through threaded mounting nail fixed mounting, the last fixed surface of mounting panel 3 installs bulb 4, the surface of bulb 4 is provided with adjusting disk 5, the last surface threaded connection of adjusting disk 5 has a plurality of adjusting bolt 11, 11 circumference equidistance of a plurality of adjusting bolt set up the upper surface at adjusting disk 5, the bottom of adjusting bolt 11 and the upper surface overlap joint of mounting panel 3.
Fixed surface installs the fixed case of 5 of adjustment disks, and the inside of fixed case is provided with the battery respectively, PLC controller 17 and data conversion module, and the right flank fixed mounting of fixed case has the spirit level, through setting up bulb 4, adjustment disks 5, adjusting bolt 11 and spirit level, makes this monitoring devices before the monitoring to 1 vertical settlement of foundation ditch lateral wall, can adjust the device to the horizontality, makes the data of monitoring more accurate.
The last fixed surface of fixed box installs cylinder pole 6, and the surface cover of cylinder pole 6 is equipped with a support section of thick bamboo 7, and the fixed surface of cylinder pole 6 installs spacing dish 8, and cylinder pole 6 is through spacing dish 8 and the inner wall sliding connection who supports a section of thick bamboo 7, and the last fixed surface of spacing dish 8 installs spring 12, spring 12's top and the interior roof fixed connection who supports a section of thick bamboo 7, and the opening has been seted up on the surface of cylinder pole 6, and the open-ended inner wall is provided with bolt 13.
The fixed surface of the upper surface of the supporting cylinder 7 is fixedly provided with a fixing frame, the lower surface of the fixing frame is fixedly provided with a scale strip 9, the left side surface of the fixing box is respectively and fixedly provided with a monitoring rod 14 and a camera 15, the left end of the monitoring rod 14 is in lap joint with the side surface of the scale strip 9, and the lower surface of the monitoring rod 14 is fixedly provided with a position sensor 16.
The equal fixed mounting of the interior diapire of fixed frame and interior roof has a plurality of slip roller, the surface of slip roller is provided with monitoring conical plate 10, the right flank fixed mounting of monitoring conical plate 10 has the dead lever, the dead lever is kept away from the one end fixed mounting of monitoring conical plate 10 and is pressed the briquetting, camera 15 and position sensor 16 all with PLC controller 17 electric connection, through setting up cylinder pole 6, supporting cylinder 7, spring 12, monitoring conical plate 10, scale bar 9, monitoring lever 14, camera 15, position sensor 16 and PLC controller 17, make this monitoring devices in monitoring time measuring to 1 vertical settlement of foundation ditch lateral wall, can give PLC controller 17 with signal transmission through position sensor 16, PLC controller 17 controls camera 15 work, thereby provide the real-time data of 1 vertical settlement of foundation ditch lateral wall for the monitoring personnel, be convenient for the monitoring personnel to take corresponding measure.
The working principle is as follows: this monitoring devices when installation, install the device at the upper surface of foundation ditch diapire 2 through the screw thread installation nail, through observing the spirit level, adjusting bolt 11, make the device be located horizontal position, make the data of monitoring more accurate, later press down and press the briquetting to make monitoring conical plate 10 insert inside foundation ditch lateral wall 1, then extract bolt 13, carry out the monitoring of vertical settlement to foundation ditch lateral wall 1, when vertical settlement appears in foundation ditch lateral wall 1, foundation ditch lateral wall 1 extrudees monitoring conical plate 10 downwards, when monitoring conical plate 10 drives scale bar 9 and moves downwards, position sensor 16 gives PLC controller 17 with signal transmission, PLC controller 17 control camera 15 work, thereby provide the real-time data of vertical settlement of foundation ditch lateral wall 1 for the monitoring personnel, be convenient for the monitoring personnel to take corresponding measure.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides an intelligent monitoring devices for foundation ditch subsides, includes foundation ditch lateral wall (1) and foundation ditch diapire (2), its characterized in that: the upper surface of the foundation pit bottom wall (2) is fixedly provided with a mounting plate (3) through a threaded mounting nail, the upper surface of the mounting plate (3) is fixedly provided with a ball head (4), the surface of the ball head (4) is provided with a regulating disc (5), the upper surface of the regulating disc (5) is fixedly provided with a fixed box, the upper surface of the fixed box is fixedly provided with a cylindrical rod (6), the surface of the cylindrical rod (6) is sleeved with a supporting cylinder (7), the surface of the cylindrical rod (6) is fixedly provided with a limiting disc (8), the cylindrical rod (6) is in sliding connection with the inner wall of the supporting cylinder (7) through the limiting disc (8), the upper surface of the supporting cylinder (7) is fixedly provided with a fixed frame, the lower surface of the fixed frame is fixedly provided with a scale strip (9), and the inner bottom wall and the inner top wall of the fixed frame are, the surface of slip roller is provided with monitoring conical plate (10), the right flank fixed mounting of monitoring conical plate (10) has the dead lever, the one end fixed mounting that the dead lever kept away from monitoring conical plate (10) has the press block.
2. The intelligent monitoring device for foundation pit settlement according to claim 1, wherein: the upper surface threaded connection of adjustment disk (5) has a plurality of adjusting bolt (11), a plurality of adjusting bolt (11) circumference equidistance sets up the upper surface at adjustment disk (5), the bottom of adjusting bolt (11) and the upper surface overlap joint of mounting panel (3).
3. The intelligent monitoring device for foundation pit settlement according to claim 1, wherein: the upper surface of the limiting disc (8) is fixedly provided with a spring (12), the top end of the spring (12) is fixedly connected with the inner top wall of the supporting cylinder (7), the surface of the cylindrical rod (6) is provided with an opening, and the inner wall of the opening is provided with a bolt (13).
4. The intelligent monitoring device for foundation pit settlement according to claim 1, wherein: the left surface of fixed case fixed mounting respectively has monitoring lever (14) and camera (15), the left end of monitoring lever (14) and the side overlap joint of scale bar (9), the lower fixed surface of monitoring lever (14) installs position sensor (16), the right flank fixed mounting of fixed case has the spirit level.
5. The intelligent monitoring device for foundation pit settlement according to claim 1, wherein: and a storage battery, a PLC (programmable logic controller) (17) and a data conversion module are respectively arranged in the fixed box.
6. The intelligent monitoring device for foundation pit settlement according to claim 4, wherein: the camera (15) and the position sensor (16) are electrically connected with the PLC (17).
CN202021521181.XU 2020-07-28 2020-07-28 Intelligent monitoring device for foundation pit settlement Active CN212866082U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021521181.XU CN212866082U (en) 2020-07-28 2020-07-28 Intelligent monitoring device for foundation pit settlement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021521181.XU CN212866082U (en) 2020-07-28 2020-07-28 Intelligent monitoring device for foundation pit settlement

Publications (1)

Publication Number Publication Date
CN212866082U true CN212866082U (en) 2021-04-02

Family

ID=75218244

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021521181.XU Active CN212866082U (en) 2020-07-28 2020-07-28 Intelligent monitoring device for foundation pit settlement

Country Status (1)

Country Link
CN (1) CN212866082U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112962693A (en) * 2021-04-27 2021-06-15 重庆育才工程咨询监理有限公司 Pier stud basis settlement monitoring device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112962693A (en) * 2021-04-27 2021-06-15 重庆育才工程咨询监理有限公司 Pier stud basis settlement monitoring device

Similar Documents

Publication Publication Date Title
CN212866082U (en) Intelligent monitoring device for foundation pit settlement
CN206990062U (en) A kind of Intelligent water level monitoring device
CN209927176U (en) Solar farmland environment monitoring device
CN209978809U (en) Geological disaster displacement automatic monitoring equipment
CN204439121U (en) Old house Sensor monitoring structure
CN218719883U (en) Agricultural meteorological disaster monitoring device
CN217601533U (en) Building foundation pit deformation monitoring device
CN211260233U (en) Building construction supervision device based on BIM
CN210469568U (en) Based on building energy-saving three-dimensional visual material consumption monitoring device
CN112710351A (en) Hydrology forecasting device based on thing networking
CN109827540A (en) A kind of existing building is using building safety management platform monitoring of structures deformation and its implementation method
CN219434173U (en) Reservoir safety precaution monitoring devices
CN220287080U (en) Intelligent building security monitoring
CN202057440U (en) Solar torsional pressure sensor
CN215447879U (en) Foundation pit slope settlement real-time monitoring device
CN217816004U (en) Fixing device of geological disaster monitoring equipment
CN204165547U (en) A kind of tower mast sedimentation detecting system
CN113936433B (en) High-precision intelligent monitoring station for early warning of hydropower engineering and geological disasters
CN213946927U (en) Energy-saving cement pipe curing box
CN214675425U (en) Intelligent management device for power plant equipment
CN215639583U (en) Informationized water conservancy project water regime measuring device
CN215573355U (en) Noise monitoring device for wisdom building site supervision platform
CN214154687U (en) A high definition video monitoring device for wisdom city thing networking
CN210535308U (en) Water conservancy and hydropower construction engineering management bulletin device
CN218445011U (en) Dust environment's environment measuring device

Legal Events

Date Code Title Description
GR01 Patent grant