CN212835465U - Head structure of construction well - Google Patents

Head structure of construction well Download PDF

Info

Publication number
CN212835465U
CN212835465U CN202021541595.9U CN202021541595U CN212835465U CN 212835465 U CN212835465 U CN 212835465U CN 202021541595 U CN202021541595 U CN 202021541595U CN 212835465 U CN212835465 U CN 212835465U
Authority
CN
China
Prior art keywords
plate
opening
spring
riser
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021541595.9U
Other languages
Chinese (zh)
Inventor
梁学林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021541595.9U priority Critical patent/CN212835465U/en
Application granted granted Critical
Publication of CN212835465U publication Critical patent/CN212835465U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The application discloses capping structure of construction well, including barrel, buffer gear and adjustment mechanism, barrel top and closing cap bottom fixed connection, barrel inner chamber lateral wall rigid coupling has buffer board and closing plate from the bottom up in proper order, the stagnant water steel sheet has been cup jointed to the barrel outer wall, buffer gear includes buffer board, first opening, riser, diaphragm, first spring and roof, buffer board center department is equipped with first opening, buffer board top and riser bottom fixed connection, be equipped with the second opening on the riser, a side end face and the roof sliding connection of riser, riser opposite side end face and diaphragm one side fixed connection. This application is through mutually supporting between buffer board, riser, second opening, diaphragm, third opening, first spring and the roof, cushions the water that oozes from the first opening on the buffer board, and the infiltration is prevented to the sealed board of rethread, and is simple effective.

Description

Head structure of construction well
Technical Field
The application relates to an end enclosure structure, in particular to an end enclosure structure of a building construction well.
Background
The end cap is an element for sealing the end of the container to isolate the internal and external media, and is also called an end cap. The closure head of a cylindrical container is generally a swivel housing. The shape of the seal head surface can be divided into convex, conical, flat and combined shapes. The convex end socket refers to an end socket with a convex outer surface shape, such as a hemispherical, oval, dished and edgeless spherical end socket. Some gas cylinders adopt a combined bottom seal head with an inward convex surface, so that the strength can be ensured, and the requirement for safe use can be met.
In the construction, can set up a lot of construction wells, for example, set up the precipitation well in the foundation ditch, because the water in the foundation ditch needs in time to discharge in order to guarantee construction quality, so need set up the precipitation well in the foundation ditch, be used for discharging ponding, need seal the precipitation well after the engineering is accomplished, precipitation well seals and generally adopts the mode of concrete placement to seal among the prior art, construction period is longer, and simultaneously, the closure effect is poor, under the condition that has higher water pressure, can not seal fast, hardly block the infiltration route completely, lead to easily sealing the failure. Therefore, a head structure of a building construction well is provided aiming at the problems.
Disclosure of Invention
A head structure of a building construction well comprises a cylinder, a buffer mechanism and an adjusting mechanism;
the top end of the cylinder body is fixedly connected with the bottom end of the sealing cover, a buffer plate and a sealing plate are fixedly connected to the side wall of the inner cavity of the cylinder body from bottom to top in sequence, and a water stop steel plate is sleeved on the outer wall of the cylinder body;
the buffer mechanism comprises a buffer plate, a first opening, a vertical plate, a transverse plate, a first spring and a top plate, wherein the first opening is arranged at the center of the buffer plate, the top end of the buffer plate is fixedly connected with the bottom end of the vertical plate, a second opening is arranged on the vertical plate, one side end face of the vertical plate is in sliding connection with the top plate, the other side end face of the vertical plate is fixedly connected with one side of the transverse plate, a third opening is arranged at the center of the transverse plate, the top end of the transverse plate is fixedly connected with one end of the first spring, and the other end of the first spring is fixedly connected with the bottom end of the top;
the adjusting mechanism comprises a connecting rod, a sliding groove, a second spring, a sliding rod, a limiting rod and a supporting plate, the outer side wall of the barrel is fixedly connected with one end of the connecting rod, the other end of the connecting rod is provided with the sliding groove, one side end face of the sliding groove is fixedly connected with one end of the second spring, the other end of the second spring is fixedly connected with one side of the sliding rod, the other side end face of the sliding rod is fixedly connected with the supporting plate, and the top end of the supporting plate is in contact with the water stop steel plate.
Further, the riser has two, two the riser rigid coupling respectively is at the buffer board top of first opening both sides, the second opening has two, two the second opening is established respectively on two risers.
Furthermore, the both sides terminal surface of diaphragm respectively with the opposite side terminal surface fixed connection of two risers, first spring has two, two first spring rigid coupling respectively is on the diaphragm top of third opening both sides, the top of two first springs all with the bottom fixed connection of roof.
Further, the roof is the shape of falling U, two curb plates of roof respectively with two riser sliding connection, two curb plate bottom of roof all than the second opening at the bottom.
Furthermore, the connecting rods are a plurality of which are fixedly connected with the outer side wall of the barrel in an annular array mode, and the number of the sliding rods and the number of the supporting plates are the same as that of the connecting rods.
Further, the connecting rod top is equipped with a plurality of spacing hole, a plurality of spacing hole all communicates with the spout, a plurality of the spout bottom is not run through in spacing hole, the slide bar top is equipped with a spacing groove, spacing groove on spacing hole and the slide bar all with gag lever post sliding connection.
The beneficial effect of this application is: the application provides a take head structure of buffering water pressure and waterproof better building construction well.
Drawings
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present application, and it is obvious for those skilled in the art that other drawings can be obtained according to the drawings without inventive exercise.
FIG. 1 is a schematic overall perspective view of an embodiment of the present application;
FIG. 2 is a schematic diagram of the overall internal structure of an embodiment of the present application;
FIG. 3 is an enlarged view of a portion of the structure of FIG. 2 according to an embodiment of the present disclosure;
fig. 4 is a schematic view of a portion of the enlarged structure at B in fig. 2 according to an embodiment of the present application.
In the figure: 1. the sealing device comprises a barrel body, 2, a buffer plate, 3, a first opening, 4, a vertical plate, 5, a second opening, 6, a transverse plate, 7, a third opening, 8, a first spring, 9, a top plate, 10, a sealing plate, 11, a connecting rod, 12, a sliding groove, 13, a second spring, 14, a sliding rod, 15, a limiting hole, 16, a limiting rod, 17, a supporting plate, 18, a water stop steel plate, 19 and a sealing cover.
Detailed Description
In order to make the technical solutions better understood by those skilled in the art, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only partial embodiments of the present application, but not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
It should be noted that the terms "first," "second," and the like in the description and claims of this application and in the drawings described above are used for distinguishing between similar elements and not necessarily for describing a particular sequential or chronological order. It should be understood that the data so used may be interchanged under appropriate circumstances such that embodiments of the application described herein may be used. Furthermore, the terms "comprises," "comprising," and "having," and any variations thereof, are intended to cover a non-exclusive inclusion, such that a process, method, system, article, or apparatus that comprises a list of steps or elements is not necessarily limited to those steps or elements expressly listed, but may include other steps or elements not expressly listed or inherent to such process, method, article, or apparatus.
In this application, the terms "upper", "lower", "left", "right", "front", "rear", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings. These terms are used primarily to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to a particular orientation or to be constructed and operated in a particular orientation.
Moreover, some of the above terms may be used to indicate other meanings besides the orientation or positional relationship, for example, the term "on" may also be used to indicate some kind of attachment or connection relationship in some cases. The specific meaning of these terms in this application will be understood by those of ordinary skill in the art as appropriate.
Furthermore, the terms "mounted," "disposed," "provided," "connected," and "sleeved" are to be construed broadly. For example, it may be a fixed connection, a removable connection, or a unitary construction; can be a mechanical connection, or an electrical connection; may be directly connected, or indirectly connected through intervening media, or may be in internal communication between two devices, elements or components. The specific meaning of the above terms in the present application can be understood by those of ordinary skill in the art as appropriate.
It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The present application will be described in detail below with reference to the embodiments with reference to the attached drawings.
Referring to fig. 1-4, a head structure of a construction well includes a cylinder 1, a buffer mechanism and an adjusting mechanism;
the top end of the cylinder body 1 is fixedly connected with the bottom end of the sealing cover 19 to facilitate sealing cover, the side wall of the inner cavity of the cylinder body 1 is fixedly connected with the buffer plate 2 and the sealing plate 10 from bottom to top in sequence to facilitate buffering, and the outer wall of the cylinder body 1 is sleeved with the water stop steel plate 18 to facilitate water penetration prevention;
the buffer mechanism comprises a buffer plate 2, a first opening 3, a vertical plate 4, a transverse plate 6, a first spring 8 and a top plate 9, wherein the first opening 3 is arranged at the center of the buffer plate 2, the top end of the buffer plate 2 is fixedly connected with the bottom end of the vertical plate 4 and is convenient to connect, a second opening 5 is arranged on the vertical plate 4, one side end surface of the vertical plate 4 is in sliding connection with the top plate 9 so as to facilitate the sliding of the top plate 9, the other side end surface of the vertical plate 4 is fixedly connected with one side of the transverse plate 6, a third opening 7 is arranged at the center of the transverse plate 6, the top end of the transverse plate 6 is fixedly connected with one end of the first spring 8, and the other end of the first spring 8 is fixedly connected with the;
adjustment mechanism includes connecting rod 11, spout 12, second spring 13, slide bar 14, gag lever post 16 and backup pad 17, the lateral wall of barrel 1 and the one end fixed connection of connecting rod 11 are convenient for connect, the other end of connecting rod 11 is equipped with spout 12, is convenient for connect, a side end face of spout 12 and the one end fixed connection of second spring 13, the other end of second spring 13 and one side fixed connection of slide bar 14, another side end face and the backup pad 17 fixed connection of slide bar 14, the backup pad 17 top contacts with stagnant water steel sheet 18, is convenient for fix a position.
The number of the vertical plates 4 is two, the two vertical plates 4 are fixedly connected to the top ends of the buffer plates 2 on the two sides of the first opening 3 respectively, the number of the second openings 5 is two, and the two second openings 5 are arranged on the two vertical plates 4 respectively; the end surfaces of two sides of the transverse plate 6 are respectively fixedly connected with the end surfaces of the two vertical plates 4, the number of the first springs 8 is two, the two first springs 8 are respectively and fixedly connected with the top ends of the transverse plate 6 at two sides of the third opening 7, and the top ends of the two first springs 8 are respectively and fixedly connected with the bottom end of the top plate 9; the top plate 9 is in an inverted U shape, two side plates of the top plate 9 are respectively connected with the two vertical plates 4 in a sliding mode, and the bottom ends of the two side plates of the top plate 9 are convenient to match with each other compared with the bottom end of the second opening 5; the connecting rods 11 are arranged in a plurality, the connecting rods 11 are fixedly connected with the outer side wall of the barrel 1 in an annular array mode, and the number of the sliding rods 14 and the number of the supporting plates 17 are the same as that of the connecting rods 11, so that the supporting is facilitated; the connecting rod 11 top is equipped with a plurality of spacing hole 15, a plurality of spacing hole 15 all communicates with spout 12, a plurality of spacing hole 15 does not run through spout 12 bottom, the 14 tops of slide bar are equipped with a spacing groove, spacing groove on spacing hole 15 and the slide bar 14 all with gag lever post 16 sliding connection, be convenient for fixed.
When the water-proof sealing device is used, electrical elements appearing in the water-proof sealing device are externally connected with a power supply and a control switch when the water-proof sealing device is used, a supporting plate 17 is pushed according to the size of a construction well, the supporting plate 17 drives a sliding rod 14 to move towards a sliding groove 12 to extrude a second spring 13, when the position is proper, a limiting rod 16 is inserted from a limiting hole 15 at the top end of the sliding groove 12 until the bottom end of the limiting rod 16 enters a limiting groove of the sliding rod 14, the supporting plate 17 is fixed, then cement is poured into a cavity between the supporting plate 17 and the outer wall of a barrel body 1, a proper amount of water-proofing agent is put in the cavity, a water-proof steel plate 18 is welded with the barrel body 1 and the supporting plate 17, then concrete is led into the cavity above a sealing plate 10 in the barrel body 1 for pouring, finally a sealing cover 19 is welded with the barrel body 1, water leakage can be effectively prevented, the top plate 9 is pushed upwards through the second opening 5 in the transverse plate 6, when the top plate 9 rises, water overflows from the third opening 7 in the vertical plate 4 to buffer water pressure layer by layer, the sealing plate 10 above the buffer plate 2 can effectively prevent overflowing water from continuing to leak, the water pressure is buffered, the water leakage is prevented, and the construction well can be quickly sealed.
The application has the advantages that:
1. according to the buffering device, water seeping from the first opening on the buffering plate is buffered through the mutual matching among the buffering plate, the vertical plate, the second opening, the transverse plate, the third opening, the first spring and the top plate, and then water seepage is prevented through the sealing plate, so that the buffering device is simple and effective;
2. this application is rational in infrastructure, make through seting up spout and second spring and can slide between slide bar and the connecting rod, be convenient for adjust the distance of backup pad and barrel, through the cooperation between gag lever post and the spacing hole, can fix the position of backup pad, through utilizing the cavity between backup pad and the barrel to flow back cement and the stagnant water steel sheet in a certain amount of waterproofing agent of ratio and the barrel outside, can effectually prevent the groundwater seepage, the resources are saved of being convenient for, reduce use cost.
It is well within the skill of those in the art to implement, without undue experimentation, the present application is not directed to software and process improvements, as they relate to circuits and electronic components and modules.
The above description is only a preferred embodiment of the present application and is not intended to limit the present application, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims (6)

1. The utility model provides a capping structure of construction well which characterized in that: comprises a cylinder body (1), a buffer mechanism and an adjusting mechanism;
the top end of the cylinder body (1) is fixedly connected with the bottom end of the sealing cover (19), the side wall of the inner cavity of the cylinder body (1) is fixedly connected with a buffer plate (2) and a sealing plate (10) from bottom to top in sequence, and the outer wall of the cylinder body (1) is sleeved with a water stop steel plate (18);
the buffer mechanism comprises a buffer plate (2), a first opening (3), a vertical plate (4), a transverse plate (6), a first spring (8) and a top plate (9), wherein the first opening (3) is arranged at the center of the buffer plate (2), the top end of the buffer plate (2) is fixedly connected with the bottom end of the vertical plate (4), a second opening (5) is arranged on the vertical plate (4), one side end face of the vertical plate (4) is slidably connected with the top plate (9), the other side end face of the vertical plate (4) is fixedly connected with one side of the transverse plate (6), a third opening (7) is arranged at the center of the transverse plate (6), the top end of the transverse plate (6) is fixedly connected with one end of the first spring (8), and the other end of the first spring (8) is fixedly connected with the bottom end of the top plate (9);
adjustment mechanism includes connecting rod (11), spout (12), second spring (13), slide bar (14), gag lever post (16) and backup pad (17), the lateral wall of barrel (1) and the one end fixed connection of connecting rod (11), the other end of connecting rod (11) is equipped with spout (12), a side end face of spout (12) and the one end fixed connection of second spring (13), the other end of second spring (13) and one side fixed connection of slide bar (14), the other side end face and backup pad (17) fixed connection of slide bar (14), backup pad (17) top and stagnant water steel sheet (18) contact.
2. A head structure of a construction well according to claim 1, wherein: riser (4) have two, two riser (4) rigid coupling is on buffer board (2) top of first opening (3) both sides respectively, second opening (5) have two, two second opening (5) are established respectively on two riser (4).
3. A head structure of a construction well according to claim 1, wherein: the both sides terminal surface of diaphragm (6) respectively with the opposite side terminal surface fixed connection of two riser (4), first spring (8) have two, two first spring (8) rigid coupling respectively is on diaphragm (6) top of third opening (7) both sides, the top of two first springs (8) all with the bottom fixed connection of roof (9).
4. A head structure of a construction well according to claim 1, wherein: roof (9) are the shape of falling U, two curb plates of roof (9) respectively with two riser (4) sliding connection, two curb plate bottoms of roof (9) all are lower than second opening (5).
5. A head structure of a construction well according to claim 1, wherein: the connecting rods (11) are fixedly connected with the outer side wall of the barrel body (1) in an annular array mode, and the number of the sliding rods (14) and the number of the supporting plates (17) are the same as that of the connecting rods (11).
6. A head structure of a construction well according to claim 1, wherein: connecting rod (11) top is equipped with a plurality of spacing hole (15), a plurality of spacing hole (15) all communicate with spout (12), a plurality of spout (12) bottom is not run through in spacing hole (15), slide bar (14) top is equipped with a spacing groove, spacing groove on spacing hole (15) and slide bar (14) all with gag lever post (16) sliding connection.
CN202021541595.9U 2020-07-29 2020-07-29 Head structure of construction well Expired - Fee Related CN212835465U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021541595.9U CN212835465U (en) 2020-07-29 2020-07-29 Head structure of construction well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021541595.9U CN212835465U (en) 2020-07-29 2020-07-29 Head structure of construction well

Publications (1)

Publication Number Publication Date
CN212835465U true CN212835465U (en) 2021-03-30

Family

ID=75124914

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021541595.9U Expired - Fee Related CN212835465U (en) 2020-07-29 2020-07-29 Head structure of construction well

Country Status (1)

Country Link
CN (1) CN212835465U (en)

Similar Documents

Publication Publication Date Title
CN212835465U (en) Head structure of construction well
CN212742929U (en) Outer plug type assembled station connecting device
CN207944329U (en) The bent cap of precast assembly and the horizontal splicing seams grouting exhaust structure of pier stud
CN214843515U (en) Monitoring devices for hydraulic engineering
CN210597906U (en) Roof greening layer drainage structure
CN211423978U (en) Automatic oxygen filling device
CN215977503U (en) Ground fire hydrant with leakage-proof function
CN211821732U (en) Natural gas storage tank
CN214091023U (en) Building templates link for civil engineering
CN111733984A (en) Outer plug type assembled station connecting device
CN210916970U (en) Deck-type steel pipe arch bridge structure
CN209760610U (en) Grouting sleeve
CN107859076B (en) Flexible waterproof device for joint of anchor rod and bottom plate and construction method thereof
CN112362501A (en) Seepage-proofing structure and stress seepage coupling shear box with same
CN207781736U (en) pressure frame sealing structure
CN205676354U (en) The graphite powder in the bolt anchoring hole of a kind of bottom brick of molten tin bath fills pressurizing unit
CN210802871U (en) Calibration device for liquid level switch
CN207557541U (en) A kind of TE plates seal box
CN214695183U (en) Beam bottom leveling supporting device
CN110049381A (en) A kind of base station
CN216405673U (en) PP module is collected to rainwater
CN217204210U (en) Bearing platform template
CN212026513U (en) Municipal works drainage open channel construction fixing device
CN217483613U (en) Hydraulic engineering liquid level monitoring device
CN213773423U (en) Water sealing device for dewatering well of underground structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210330