CN212688957U - Prestressed bamboo joint pile splicing and positioning assistor - Google Patents

Prestressed bamboo joint pile splicing and positioning assistor Download PDF

Info

Publication number
CN212688957U
CN212688957U CN202021275187.3U CN202021275187U CN212688957U CN 212688957 U CN212688957 U CN 212688957U CN 202021275187 U CN202021275187 U CN 202021275187U CN 212688957 U CN212688957 U CN 212688957U
Authority
CN
China
Prior art keywords
bamboo joint
pile
holding rod
joint pile
suspension wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021275187.3U
Other languages
Chinese (zh)
Inventor
毕经超
郭云汉
贾同安
王坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Civil Engineering Co Ltd
Original Assignee
China Construction Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Civil Engineering Co Ltd filed Critical China Construction Civil Engineering Co Ltd
Priority to CN202021275187.3U priority Critical patent/CN212688957U/en
Application granted granted Critical
Publication of CN212688957U publication Critical patent/CN212688957U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a prestressing force bamboo joint stake concatenation location assistor comprises anchor clamps system and the straightness detecting system that hangs down, and the anchor clamps system is including adjusting the spanner, adjusts the spanner including fixed continuous keeping silent and holding rod, and the opening width of keeping silent and bamboo joint stake external diameter looks adaptation, the card is established on bamboo joint stake pile body, and the straightness detecting system that hangs down includes suspension wire and sash weight, and suspension wire top ligature is on the holding rod, and the bottom links to each other with the sash weight, hangs down in the bamboo joint stake outside naturally. The utility model discloses a lever principle preparation, the handheld holding rod of workman during the construction, the ribbed reinforcing bar chucking bamboo joint pile surface of keeping silent is fixed with the bamboo joint pile, turn to with the adjusting bolt hole site through the holding rod stable control pile body, it is accurate to guarantee that connecting bolt counterpoints, avoid causing the damage to connecting bolt, two sections pile body straightness that hangs down about guaranteeing through the hammer system, to the control dynamics of pile body when having increased the workman and docked the bamboo joint pile, bamboo joint pile concatenation precision has been improved, the probability that once docks successfully has been strengthened and then has improved the efficiency of construction.

Description

Prestressed bamboo joint pile splicing and positioning assistor
Technical Field
The utility model relates to a bamboo joint stake construction technical field, concretely relates to prestressing force bamboo joint stake concatenation location assistor.
Background
The bamboo joint pile is a novel prestressed thin-wall pipe pile, and is a new pipe pile form, the bamboo joint pile is connected through high-strength bolts and epoxy resin, welding of common pipe piles is avoided, efficiency is high, pipe pile splicing at present is mainly performed manually during bamboo joint pile construction, the length of a single section of the common pipe pile reaches 8-12m, weight is large, 3-4 persons cooperate during pipe pile splicing, a pile body is required to be continuously rotated to enable six high-strength bolts to accurately align with a hole of a previous section of pipe pile, labor is wasted, construction at night is particularly performed, once alignment is inaccurate, the bolts are easily extruded and deformed during splicing to cause damage, loss is caused, supervision and acceptance requirements cannot be met, and construction efficiency is slow.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a prestressing force bamboo joint stake concatenation location assistor to two sections are relatively poor to the precision of counterpointing about during the bamboo joint stake concatenation of solution, and efficiency is slow, leads to the fact the technical problem of damage to connecting bolt easily.
In order to achieve the technical purpose, the utility model adopts the following technical scheme:
a prestress bamboo joint pile splicing and positioning auxiliary device comprises a clamp system and a verticality detection system, wherein the clamp system comprises an adjusting wrench, the adjusting wrench comprises a jaw and a holding rod which are fixedly connected, the opening width of the jaw is matched with the outer diameter of a bamboo joint pile, and the jaw is clamped on the pile body of the bamboo joint pile;
the verticality detection system comprises a suspension wire and a suspension hammer, wherein the top end of the suspension wire is bound on the holding rod, the bottom end of the suspension wire is connected with the suspension hammer and naturally hangs outside the bamboo joint piles, and the bottom end of the suspension wire exceeds the splicing positions of the upper and lower bamboo joint piles and extends for a certain distance.
Preferably, keep silent and be the portal frame that two vertical poles and a horizontal pole are even become, the length of vertical pole is between 0.8-1.2 times of bamboo joint stake external diameter, and this length scope has both guaranteed to keep silent and can conveniently the joint in the tubular pile outside, has improved the stability of joint again, the holding rod is fixed in the middle part that the horizontal pole kept away from vertical pole one side, and in order to improve laborsaving effect, the length of holding rod is not less than 600 mm.
Preferably, an upper reinforcing rib and a lower reinforcing rib are respectively fixed between the vertical rod and the transverse rod and between the holding rod and the transverse rod.
Preferably, adjust the spanner and weld by ribbed steel bar and form to increase the frictional force of keeping silent and tubular pile lateral wall, further improve the stability of joint.
Preferably, the suspension wire is made of a prominent red broad wire.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a lever principle preparation, the workman is handheld the holding rod during construction, and the ribbed steel bar chucking bamboo joint pile surface of keeping silent is fixed with the bamboo joint pile, prevents that the bamboo joint pile from rocking, through holding rod stable control pile body turn to with the adjusting bolt hole site, guarantees that connecting bolt counterpoint is accurate, avoids causing the damage to connecting bolt, guarantees two sections pile body verticality about through the drop hammer system, the utility model discloses increased the control dynamics to the pile body when the workman docks the bamboo joint pile, improved bamboo joint pile concatenation precision, strengthened the probability of once docking success and then improved the efficiency of construction;
2. the utility model discloses simple manufacture, convenient operation, repeatedly usable, extensive applicability, safe and reliable.
Drawings
The above and/or other aspects and advantages of the present invention will become more apparent and more readily appreciated from the detailed description taken in conjunction with the following drawings, which are given by way of illustration only and not by way of limitation, wherein:
fig. 1 is a schematic structural view of the use state of the prestressed bamboo joint pile splicing and positioning auxiliary device related to the utility model;
fig. 2 is the utility model relates to a structural schematic diagram of an adjusting spanner of prestressing force bamboo joint stake concatenation location assistor.
Reference numerals: 1-adjusting wrench, 101-jaw, 102-holding rod, 103-upper reinforcing rib, 104-lower reinforcing rib, 2-suspension wire, 3-suspension hammer and 4-bamboo joint pile.
Detailed Description
Hereinafter, embodiments of a prestressed bamboo joint pile splicing and positioning auxiliary device according to the present invention will be described with reference to the accompanying drawings. The embodiments described herein are specific embodiments of the present invention, and are intended to be illustrative of the concepts of the present invention, which are intended to be illustrative and exemplary, and should not be construed as limiting the scope of the embodiments of the present invention. In addition to the embodiments described herein, those skilled in the art will be able to employ other technical solutions which are obvious based on the disclosure of the claims and the specification of the present application, and these technical solutions include technical solutions which make any obvious replacement or modification for the embodiments described herein.
In the description of the present invention, it should be noted that the terms "upper", "lower", "top", "bottom", "inner", "outer", "horizontal", "longitudinal", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
The drawings in the present specification are schematic views to assist in explaining the concept of the present invention, and schematically show the shapes of the respective portions and the mutual relationships thereof. It should be noted that for the sake of clarity in showing the structures of the various components of the embodiments of the present invention, the drawings are not drawn to the same scale. Like reference numerals are used to denote like parts.
The principles and features of the present invention are described below in conjunction with the following drawings, the illustrated embodiments are provided to explain the present invention and not to limit the scope of the invention. The preferred embodiments of the present invention will be described in further detail below with reference to fig. 1-2:
as shown in fig. 1-2, the utility model discloses an optimal prestressing force bamboo joint pile concatenation location assistor comprises anchor clamps system and the straightness detecting system that hangs down, the anchor clamps system is including adjusting spanner 1, adjust spanner 1 and weld by phi 20mm ribbed steel bar and form, including welded fastening's vice jaw 101 and holding rod 102, vice jaw 101 is the portal frame that two vertical poles and a horizontal pole welded, portal frame's opening width and 4 external diameters of bamboo joint pile are adapted, block on 4 pile bodies of bamboo joint pile, the length of vertical pole is between 0.8-1.2 times of 4 external diameters of bamboo joint pile, this length scope has both guaranteed that vice jaw 101 can conveniently joint in the tubular pile outside, has improved the stability of joint again, holding rod 102 is fixed in the middle part that the horizontal pole kept away from one side of vertical pole, in order to improve laborsaving effect, the length of holding rod 102 is not less than 600 mm;
in order to improve the structural connection stability, phi 12mm ribbed steel bars are respectively welded between the longitudinal rods and the transverse rods and between the holding rod 102 and the transverse rods to serve as an upper reinforcing rib 103 and a lower reinforcing rib 104;
the verticality detection system comprises a suspension wire 2 and a hanging hammer 3, wherein the suspension wire 2 is made of a conspicuous red wide line, the top end of the suspension wire is bound on the holding rod 102, the bottom end of the suspension wire is connected with the hanging hammer 3 and naturally hangs outside the bamboo joint piles 4, and the bottom end of the suspension wire 2 exceeds the splicing positions of the upper and lower bamboo joint piles 4 and extends for a certain distance to meet the requirement that the upper and lower bamboo joint piles 4 are used simultaneously.
The utility model discloses during the specific use, hold this assistor holding rod 102 fixed bamboo joint stake 4 by the workman, prevent that bamboo joint stake 4 from rocking, the 4 surfaces of ribbed steel bar chucking bamboo joint stake of 101 of keeping silent, frictional force when the two contacts ensures that the assistor can the stable control pile body turn to with the adjusting bolt hole site, treat that connecting bolt counterpoints accurate back, release hammerhead system, two sections pile bodies hang down straightness about the inspection, can carry out the pile section concatenation after being errorless.
The above description is only for the preferred embodiment of the present invention, and is not intended to limit the present invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included within the protection scope of the present invention.

Claims (5)

1. The utility model provides a prestressing force bamboo joint stake concatenation location assistor which characterized in that: the clamp comprises a clamp system and a verticality detection system, wherein the clamp system comprises an adjusting wrench (1), the adjusting wrench (1) comprises a jaw (101) and a holding rod (102) which are fixedly connected, the opening width of the jaw (101) is matched with the outer diameter of a bamboo joint pile (4), and the jaw is clamped on a pile body of the bamboo joint pile (4);
the verticality detection system comprises a suspension wire (2) and a hanging hammer (3), wherein the top end of the suspension wire (2) is bound on the holding rod (102), the bottom end of the suspension wire is connected with the hanging hammer (3), and the suspension wire naturally hangs outside the bamboo joint pile (4).
2. The prestressed bamboo joint pile splicing and positioning assistor as claimed in claim 1, is characterized in that: the jaw (101) is a portal frame formed by connecting two longitudinal rods and a transverse rod, the length of each longitudinal rod is 0.8-1.2 times of the outer diameter of the bamboo joint pile (4), and the holding rod (102) is fixed in the middle of one side, far away from the longitudinal rods, of the transverse rod and is not less than 600mm in length.
3. The prestressed bamboo joint pile splicing and positioning assistor as claimed in claim 2, wherein: an upper reinforcing rib (103) and a lower reinforcing rib (104) are respectively fixed between the longitudinal rod and the transverse rod and between the holding rod (102) and the transverse rod.
4. The prestressed bamboo joint pile splicing and positioning assistor as claimed in claim 3, wherein: the adjusting wrench (1) is formed by welding ribbed steel bars.
5. The prestressed bamboo joint pile splicing and positioning assistor as claimed in claim 1, is characterized in that: the suspension wire (2) is made of red wide wire.
CN202021275187.3U 2020-07-03 2020-07-03 Prestressed bamboo joint pile splicing and positioning assistor Active CN212688957U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021275187.3U CN212688957U (en) 2020-07-03 2020-07-03 Prestressed bamboo joint pile splicing and positioning assistor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021275187.3U CN212688957U (en) 2020-07-03 2020-07-03 Prestressed bamboo joint pile splicing and positioning assistor

Publications (1)

Publication Number Publication Date
CN212688957U true CN212688957U (en) 2021-03-12

Family

ID=74895800

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021275187.3U Active CN212688957U (en) 2020-07-03 2020-07-03 Prestressed bamboo joint pile splicing and positioning assistor

Country Status (1)

Country Link
CN (1) CN212688957U (en)

Similar Documents

Publication Publication Date Title
CN212688957U (en) Prestressed bamboo joint pile splicing and positioning assistor
CN215760447U (en) Reinforcing structure for anti-ridge template device and anti-ridge template device
JP4093560B2 (en) Parent rope support
CN216840608U (en) Portable beam mold board reinforced structure
CN213682119U (en) Foundation pile pours and uses steel reinforcement cage fixing device
CN213709488U (en) Precast pile with anti-impact pile head
CN214995260U (en) Positioning steel bar position controller
CN209760855U (en) Safety belt fastening and hanging device for balcony part construction
CN214615043U (en) Prefabricated component reserved steel bar positioning and correcting device
CN213268604U (en) Scalable detachable steel reinforcement cage strutting arrangement
CN209867230U (en) Reinforcing steel bar fixing tool used in process of binding reinforcing steel bar cage
CN210066744U (en) Novel steel structure anchor pier for supporting slope prestressed anchor cable
CN214834665U (en) Anti-tilting structure for upright rod of external frame
CN217870447U (en) Concrete prestressed pipe pile
CN212527557U (en) Nut fastening tool
CN114808937B (en) Construction method for non-welding installation and fixation of hollow square pile core-filling reinforcement cage
CN217255629U (en) Adjustable water pump clamp
CN218208170U (en) Simple pump pipe supporting tool
CN215629886U (en) Novel anti-seismic prestressed high-strength concrete pipe pile
CN217580842U (en) Adjustable's fastener for collar tie beam
CN214033713U (en) Quick positioner of pile foundation steel reinforcement cage
CN220539236U (en) Quick adjusting tool for aluminum die diagonal bracing
CN215052935U (en) PHC tubular pile overlap joint alignment instrument
CN213953030U (en) Roof beam steel bar interval control's instrument among civil air defense engineering
CN212796955U (en) Adjustable oxygen tank supporting and moving device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant