CN212686471U - Centralized cleaning bin for construction waste - Google Patents

Centralized cleaning bin for construction waste Download PDF

Info

Publication number
CN212686471U
CN212686471U CN202021014520.5U CN202021014520U CN212686471U CN 212686471 U CN212686471 U CN 212686471U CN 202021014520 U CN202021014520 U CN 202021014520U CN 212686471 U CN212686471 U CN 212686471U
Authority
CN
China
Prior art keywords
storehouse
storehouse body
rubbish
construction waste
bin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021014520.5U
Other languages
Chinese (zh)
Inventor
卢秀庆
郑楠潜
何俊良
余辉
邱土富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Sunshine Third Ring City Service Group Co.,Ltd.
Original Assignee
Shenzhen Sunlight Three Ring Ecological Environment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Sunlight Three Ring Ecological Environment Co ltd filed Critical Shenzhen Sunlight Three Ring Ecological Environment Co ltd
Priority to CN202021014520.5U priority Critical patent/CN212686471U/en
Application granted granted Critical
Publication of CN212686471U publication Critical patent/CN212686471U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/10Waste collection, transportation, transfer or storage, e.g. segregated refuse collecting, electric or hybrid propulsion

Landscapes

  • Refuse Collection And Transfer (AREA)

Abstract

The utility model relates to a building rubbish clean-up equipment especially is a centralized clearance storehouse of building construction rubbish, including the storehouse body, the top intermediate position of the storehouse body closely welds there is the blowing fill, and the inseparable welding of the internal portion intermediate position of storehouse has the baffle, and the baffle divides the internal portion of storehouse into first district of placing and the district is placed to the second, is equipped with the pivot directly over the baffle, rotates between pivot and the storehouse body to be connected, is fixed with the flitch of falling in the pivot, and the underrun bolt fastening of the flitch of falling has the electro-magnet. The utility model discloses an adopt the flitch of falling, utilize the electro-magnet, effectively separate metal type building rubbish and other types of building rubbish, solved because contain a large amount of metal type rubbish in the building rubbish, when collecting the clearance, but can't effectively separate metal type rubbish and other types of rubbish, greatly influence subsequent refuse treatment's problem.

Description

Centralized cleaning bin for construction waste
Technical Field
The utility model relates to a building rubbish clean-up equipment, especially a building construction rubbish concentrates clearance storehouse.
Background
The construction waste refers to residue, waste soil, waste material, residual mud and other wastes generated in the process of constructing, laying, dismantling and repairing various buildings, structures, pipe networks and the like by construction, construction units or individuals, and the construction waste contains a large amount of recyclable substances, so that the construction waste needs to be intensively cleaned, but the construction waste contains a large amount of metal waste, so that the metal waste cannot be effectively separated from other types of waste during collection and cleaning, and the subsequent waste treatment is greatly influenced. In view of this, we propose a building construction rubbish is concentrated and is cleared up storehouse.
SUMMERY OF THE UTILITY MODEL
The utility model discloses an aim at is through proposing a construction waste concentrates clearance storehouse to solve the defect of proposing in the above-mentioned background art.
The utility model adopts the technical scheme as follows: including the storehouse body, the top intermediate position of the storehouse body closely welds there is the blowing fill, the closely welding of the internal portion intermediate position in storehouse has the baffle, the baffle will the internal portion in storehouse is divided into first place the district and the district is placed to the second, be equipped with the pivot directly over the baffle, the pivot with rotate between the storehouse body and connect, be fixed with the flitch of falling in the pivot, the underrun bolt fastening of falling the flitch has the electro-magnet.
As an optimal technical solution of the utility model: a pair of fixing plates is tightly welded on the outer wall of the rotating shaft, and the fixing plates and the material pouring plate are tightly fixed through bolts.
As an optimal technical solution of the utility model: a support plate is tightly welded on the rear side wall of the bin body, a stepping motor is mounted on the support plate through a bolt, and a driving gear is fixed on an output shaft of the stepping motor; and a driven gear is fixed at one end of the rotating shaft penetrating through the rear side wall of the bin body, and the driven gear is meshed with the driving gear.
As an optimal technical solution of the utility model: the middle position of the left side wall of the bin body is tightly welded with a hanging ring, and four corners of the bottom surface of the bin body are provided with walking wheels.
As an optimal technical solution of the utility model: the side walls of the left end and the right end of the bin body are provided with ladder frames through bolts, and the top ends of the ladder frames are parallel and level with the top surface of the bin body.
As an optimal technical solution of the utility model: the front end and the rear end of the top surface of the material pouring plate are respectively and tightly welded with a baffle plate, the lower end of the discharging hopper extends into the bin body, and the material port of the discharging hopper faces the middle position of the material pouring plate.
As an optimal technical solution of the utility model: the utility model discloses a safety cabin, including the storehouse body, install the protection casing through the bolt on the back lateral wall of the storehouse body, backup pad, step motor, driven gear and driving gear all are located the protection casing.
The utility model discloses an adopt and fall the flitch, utilize the electro-magnet, effectively separate metal type building rubbish and other types of building rubbish to utilize step motor control to fall the flitch and rotate, alright in pouring different rubbish into and placing the district, solved because contain a large amount of metal type rubbish in the building rubbish, when collecting the clearance, but can't effectively separate metal type rubbish and other types of rubbish, greatly influence subsequent refuse treatment's problem.
Drawings
Fig. 1 is a schematic overall structure diagram of the preferred embodiment of the present invention;
FIG. 2 is a cross-sectional view of the preferred embodiment of the cartridge body of the present invention;
FIG. 3 is a front view of the preferred embodiment of the cartridge body of the present invention;
fig. 4 is a schematic structural diagram of a material pouring plate in the preferred embodiment of the present invention.
The reference numbers illustrate:
the device comprises a bin body 1, a first placing area 11, a second placing area 12, traveling wheels 13, a material placing hopper 14, a lifting ring 15, a partition plate 2, a supporting plate 3, a stepping motor 31, a driving gear 311, a rotating shaft 32, a driven gear 321, a fixing plate 322, a material pouring plate 33, a baffle 331, an electromagnet 34, a ladder frame 4 and a protective cover 5.
Detailed Description
It should be noted that, in the present application, features of embodiments and embodiments can be combined with each other without conflict, and the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1 to 4, the utility model provides a construction waste concentrates clearance storehouse, including the storehouse body 1, the top intermediate position of the storehouse body 1 closely welds there is blowing hopper 14, and the inside intermediate position of the storehouse body 1 closely welds there is baffle 2, and baffle 2 is divided into the first district 11 of placing and the district 12 is placed to the second with the storehouse body 1 inside, is equipped with pivot 32 directly over baffle 2, rotates between pivot 32 and the storehouse body 1 to be connected, is fixed with down flitch 33 in the pivot 32, and the underrun bolt fastening of down flitch 33 has electro-magnet 34.
In the embodiment, a supporting plate 3 is tightly welded on the rear side wall of the bin body 1, a stepping motor 31 is arranged on the supporting plate 3 through a bolt, and a driving gear 311 is fixed on an output shaft of the stepping motor 31; the pivot 32 passes one of storehouse body 1 rear side wall and serves and be fixed with driven gear 321, and driven gear 321 and driving gear 311 intermeshing control the incline direction of flitch 33 through step motor 31, have alleviateed staff's working strength, can better control flitch 33 of falling simultaneously.
In addition, a pair of fixing plates 322 are tightly welded on the outer wall of the rotating shaft 32, and the fixing plates 322 and the material pouring plate 33 are tightly fixed through bolts, so that the connection between the material pouring plate 33 and the rotating shaft 32 is ensured to be more stable.
Further, the rings 15 are tightly welded in the middle of the left side wall of the bin body 1, the walking wheels 13 are installed at four corners of the bottom of the bin body 1, the rings 15 are conveniently hooked by an external traction device to pull the bin body 1, so that the building garbage can be collected and treated more conveniently, and the adaptability of the device is improved.
Besides, the left and right side walls of the bin body 1 are provided with the ladder frames 4 through bolts, the top ends of the ladder frames 4 are flush with the top surface of the bin body 1, the ladder frames 4 are convenient to install and used for putting collected construction waste into the bin body 1, and therefore the collection and treatment of the waste are faster.
Further, both ends all closely welded have baffle 331 around the top surface of flitch 33, and the lower extreme of blowing hopper 14 is deep into to storehouse body 1, and the feed opening of blowing hopper 14 faces the intermediate position of flitch 33 that falls, prevents effectively that when empting building rubbish, building rubbish directly drops in storehouse body 1, has ensured to carry out careful screening to building rubbish.
In addition, install protection casing 5 through the bolt on the back lateral wall of the storehouse body 1, backup pad 3, step motor 31, driven gear 321 and driving gear 311 all are located protection casing 5, protect step motor 31, have guaranteed that when rainy day, the storehouse body 1 can continue to operate still.
The utility model discloses a centralized cleaning bin for construction waste, when in use, firstly, the bin body 1 is pulled to a predetermined place by using external traction equipment, then, the ladder frame 4 is installed on the bin body 1 by bolts, the stepping motor 31 is opened, the stepping motor 31 rotates corresponding angle when working, the driving gear 311 is driven, the driven gear 321 meshed with the driving gear rotates along with the driving gear, the rotating shaft 32 is driven to rotate, the material pouring plate 33 rotates corresponding angle along with the direction towards the first placing area 11, the power supply on the electromagnet 34 is switched on, magnetic force is generated, at the moment, the construction waste is poured into the bin body 1 through the material placing hopper 14, the construction waste falls on the material pouring plate 33, under the magnetic force action of the electromagnet 34, metal construction waste stops on the material pouring plate 33, nonmetal waste directly falls into the first placing area 11 under the action of gravity, the stepping motor 31 is opened again afterwards, rotate certain angle towards opposite direction, drive the material pouring plate 33 and rotate towards the direction that the district 12 was placed to the second, close the power on the electro-magnet 34, magnetic force disappears, under the effect of gravity, metal class rubbish directly falls into in the district 12 is placed to the second, has solved because contain a large amount of metal class rubbish in the construction waste, when collecting the clearance, but can't effectively separate metal class rubbish and other class rubbish, greatly influences subsequent refuse treatment's problem.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (7)

1. The utility model provides a construction rubbish is concentrated and is cleared up storehouse, includes storehouse body (1), its characterized in that: the welding of the top intermediate position of the storehouse body (1) closely has blowing fill (14), the welding of the inside intermediate position of the storehouse body (1) closely has baffle (2), baffle (2) will the storehouse body (1) is inside to be divided into first place district (11) and second and place district (12), be equipped with pivot (32) directly over baffle (2), pivot (32) with rotate between the storehouse body (1) and connect, be fixed with down flitch (33) in pivot (32), the underrun bolt fastening of down flitch (33) has electro-magnet (34).
2. The centralized cleaning bin for construction waste as claimed in claim 1, wherein: a pair of fixing plates (322) are tightly welded on the outer wall of the rotating shaft (32), and the fixing plates (322) and the material pouring plate (33) are tightly fixed through bolts.
3. The centralized cleaning bin for construction waste as claimed in claim 1, wherein: a supporting plate (3) is tightly welded on the rear side wall of the bin body (1), a stepping motor (31) is mounted on the supporting plate (3) through a bolt, and a driving gear (311) is fixed on an output shaft of the stepping motor (31); a driven gear (321) is fixed at one end of the rotating shaft (32) penetrating through the rear side wall of the bin body (1), and the driven gear (321) is meshed with the driving gear (311).
4. The centralized cleaning bin for construction waste as claimed in claim 1, wherein: the left side wall intermediate position of the storehouse body (1) closely welds rings (15), walking wheel (13) are all installed to the bottom surface four corners position of the storehouse body (1).
5. The centralized cleaning bin for construction waste as claimed in claim 1, wherein: the left and right side walls of the bin body (1) are provided with ladder frames (4) through bolts, and the top ends of the ladder frames (4) are parallel and level with the top surface of the bin body (1).
6. The centralized cleaning bin for construction waste as claimed in claim 1, wherein: the front end and the rear end of the top surface of the material pouring plate (33) are respectively and tightly welded with a baffle (331), the lower end of the discharge hopper (14) extends into the bin body (1), and a material port of the discharge hopper (14) is over against the middle position of the material pouring plate (33).
7. The centralized cleaning bin for construction waste as claimed in claim 3, wherein: the utility model discloses a capsule machine, including the storehouse body (1), install protection casing (5) through the bolt on the back lateral wall of storehouse body (1), backup pad (3), step motor (31), driven gear (321) and driving gear (311) all are located protection casing (5).
CN202021014520.5U 2020-06-04 2020-06-04 Centralized cleaning bin for construction waste Active CN212686471U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021014520.5U CN212686471U (en) 2020-06-04 2020-06-04 Centralized cleaning bin for construction waste

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021014520.5U CN212686471U (en) 2020-06-04 2020-06-04 Centralized cleaning bin for construction waste

Publications (1)

Publication Number Publication Date
CN212686471U true CN212686471U (en) 2021-03-12

Family

ID=74888725

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021014520.5U Active CN212686471U (en) 2020-06-04 2020-06-04 Centralized cleaning bin for construction waste

Country Status (1)

Country Link
CN (1) CN212686471U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113511434A (en) * 2021-07-29 2021-10-19 扬州工业职业技术学院 Office garbage recycling robot
CN114718173A (en) * 2022-04-26 2022-07-08 广东英聚建筑工程有限公司 Municipal drainage system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113511434A (en) * 2021-07-29 2021-10-19 扬州工业职业技术学院 Office garbage recycling robot
CN114718173A (en) * 2022-04-26 2022-07-08 广东英聚建筑工程有限公司 Municipal drainage system
CN114718173B (en) * 2022-04-26 2022-11-29 广东英聚建筑工程有限公司 Municipal drainage system

Similar Documents

Publication Publication Date Title
CN212686471U (en) Centralized cleaning bin for construction waste
CN206537804U (en) A kind of garbage truck dustbin apparatus for being easy to discharge
CN109403290A (en) A kind of environmental protection collecting refuse from open water grinding device
CN214863927U (en) Building rubbish circulation reducing mechanism
CN211677972U (en) Building rubbish reducing mechanism for building bridge
CN112090494A (en) Screening discharge apparatus is smashed in circulation of building rubbish collection for building engineering
CN201362489Y (en) Fully-enclosed self-discharging motor-driven third wheel garbage truck
CN213805792U (en) Novel pipeline dredging robot
CN217888615U (en) Prevent rubbish screening equipment of jam
CN206591504U (en) A kind of river course cleaning plant
CN114382131B (en) High-efficient underwater dredging robot
CN210164190U (en) Building site floor rubbish clearance passageway
CN216703562U (en) Highway service area domestic sewage integration treatment device
CN212960422U (en) Sewage discharge pipe network with prevent blockking up structure
CN212405442U (en) Town road drainage structures
CN101987325A (en) Comprehensive sorting and pretreating integrated equipment of kitchen garbage
CN213245708U (en) Equipment for efficiently excavating Chinese herbal medicines
CN212896732U (en) Town road rainwater inspection shaft structure
CN211922439U (en) District is road garbage collection device for property
CN209901671U (en) Solid waste screening treatment device
CN201815531U (en) Comprehensive sorting and pretreatment integrated device for restaurant-kitchen garbage
CN212468360U (en) Construction waste treatment device
CN112337940A (en) Building construction rubbish reducing mechanism
CN212263823U (en) Environment-friendly mechanical device for screening and recycling solid waste
CN210636511U (en) Mechanical water taking device for water well

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 518000 Units 618 # -620 #, Zhuofeigao Building (Haixiang Square), east of Industrial Avenue and west of Liyuan Road, Shekou Street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: Shenzhen Sunshine Third Ring City Service Group Co.,Ltd.

Address before: 518000 Units 618 # -620 #, Zhuofeigao Building (Haixiang Square), east of Industrial Avenue and west of Liyuan Road, Shekou Street, Nanshan District, Shenzhen City, Guangdong Province

Patentee before: SHENZHEN SUNLIGHT THREE RING ECOLOGICAL ENVIRONMENT CO.,LTD.