CN212683790U - Impact type pile machine support rod aligning installation tool - Google Patents

Impact type pile machine support rod aligning installation tool Download PDF

Info

Publication number
CN212683790U
CN212683790U CN202021184438.7U CN202021184438U CN212683790U CN 212683790 U CN212683790 U CN 212683790U CN 202021184438 U CN202021184438 U CN 202021184438U CN 212683790 U CN212683790 U CN 212683790U
Authority
CN
China
Prior art keywords
impact type
clamping
type pile
pile machine
annular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021184438.7U
Other languages
Chinese (zh)
Inventor
张瑞
赵振庆
梁忠宝
李玉泰
罗明清
李国锋
朱竞伍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Resources Ltd
Original Assignee
PowerChina Resources Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Resources Ltd filed Critical PowerChina Resources Ltd
Priority to CN202021184438.7U priority Critical patent/CN212683790U/en
Application granted granted Critical
Publication of CN212683790U publication Critical patent/CN212683790U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides an impact type stake machine vaulting pole is to mouthful mounting tool belongs to building construction equipment technical field, include: the annular clamping piece is provided with two clamping parts with arc structures, one ends of the two arc clamping parts are connected through a rotating shaft, and the other ends of the two arc clamping parts are disconnected; the supporting pieces are vertically connected to the outer wall of the annular clamping piece, and a plurality of supporting pieces are arranged around the outer wall of the annular clamping piece at intervals; the two clamping pieces are respectively and vertically connected to one disconnected end of the two arc-shaped clamping parts of the annular clamping piece, and the two clamping pieces are arranged at an angle; the utility model discloses an impact type stake machine vaulting pole is to mouthful mounting tool carries out the centre gripping to the vaulting pole through annular holder, can support on the one hand at the pile foundation protects a section of thick bamboo through support piece, and on the other hand makes things convenient for the workman to control, blocks the rotation of vaulting pole to can avoid the vaulting pole to improve the efficiency of being geared to the needs of the job when the mouth.

Description

Impact type pile machine support rod aligning installation tool
Technical Field
The utility model relates to a construction equipment technical field, concretely relates to impacted style stake machine vaulting pole is to mouthful mounting tool.
Background
The impact type pile driver is used for piling operation during building construction, and the adopted support rods are in a multi-section type, so that piling depth is lengthened according to needs.
When carrying out the vaulting pole extension, at first stretch into the pile foundation with one section vaulting pole hoist and mount in protecting a section of thick bamboo, then hoist another section vaulting pole, carry out butt joint with first section vaulting pole, at this in-process, need adopt clamping tool will be located the pile foundation and protect first section vaulting pole in a section of thick bamboo and carry out interim fixed.
In the prior art, a pipe clamp is generally adopted to fix a first section of support rod, however, the existing pipe clamp can only fix the support rod in the vertical axial direction, and the two sections of support rods are in butt joint by adopting threaded connection, so that the first section of support rod is required to be fixed in the circumferential direction to avoid the rotation of the support rod in the butt joint process.
SUMMERY OF THE UTILITY MODEL
Therefore, the to-be-solved technical problem of the utility model lies in overcoming the centre gripping instrument that is used for fixed vaulting pole among the prior art, only can carry out axial direction's from top to bottom fixed to the vaulting pole, the vaulting pole probably takes place pivoted defect at the butt joint in-process to an impact type stake machine vaulting pole is to mouthful mounting tool is provided.
In order to solve the technical problem, the utility model provides an impacted style stake machine vaulting pole is to mouthful mounting tool, include:
the annular clamping piece is provided with two clamping parts with arc structures, one ends of the two arc clamping parts are connected through a rotating shaft, and the other ends of the two arc clamping parts are disconnected;
the supporting pieces are vertically connected to the outer wall of the annular clamping piece, and a plurality of supporting pieces are arranged around the outer wall of the annular clamping piece at intervals;
and the two clamping pieces are respectively and vertically connected to one disconnected end of the two arc-shaped clamping parts of the annular clamping piece, and the two clamping pieces are arranged at an angle.
Preferably, the method further comprises the following steps: and the anti-slip interlayer is arranged on the inner side wall of the annular clamping piece.
Preferably, the anti-slip interlayer is an anti-slip thread arranged on the inner side wall of the annular clamping piece.
Preferably, the anti-slip interlayer is anti-slip rubber connected to the inner side wall of the annular clamping piece.
Preferably, the anti-slip rubber is connected with the inner side wall of the annular clamping piece through a fastening piece.
Preferably, the two supporting parts are respectively arranged at the position of pi/4 radian on two sides of the rotating shaft.
Preferably, the angle between the two clamping pieces is 10 ° ± 5 °.
Preferably, the support member and/or the clamping member are provided with non-slip threads on their outer surfaces.
The utility model discloses technical scheme has following advantage:
1. the utility model provides an impact type stake machine vaulting pole is to mouthful mounting tool carries out the centre gripping to the vaulting pole through annular holder, is provided with the support piece that a plurality of perpendicular connections on the outer wall of annular holder, can support on the pile foundation protects a section of thick bamboo on the one hand through support piece, and on the other hand makes things convenient for the workman to control, blocks the rotation of vaulting pole to can avoid the vaulting pole to improve the efficiency of being geared to the needs of the job in the rotation of being geared to the needs of the job.
2. The utility model provides an impact type stake machine vaulting pole is to mouthful mounting tool serves at one of the mutual disconnection of two arc clamping parts of annular holder, is provided with two clamping pieces that become angle, when carrying out the centre gripping to the vaulting pole, is close to two clamping pieces each other through the snap ring and presss from both sides tightly, can improve the clamp force of annular holder to the vaulting pole, guarantees that the vaulting pole does not slip.
3. The utility model provides an impact type stake machine vaulting pole is to mouthful mounting tool is provided with anti-skidding intermediate layer on the inside wall of annular holder to increase the friction with the vaulting pole, improve the tight effect of clamp to the vaulting pole.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the embodiments or the technical solutions in the prior art will be briefly described below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic perspective view of an embodiment of the utility model of an impact type pile machine stay bar aligning installation tool.
Fig. 2 is an exploded view of fig. 1.
Fig. 3 is a top view of fig. 1.
Fig. 4 is a schematic view of the ring clamp of fig. 1 in an open state.
Description of reference numerals:
1. an annular clamping member; 2. a rotating shaft; 3. a support member; 4. a clamping member; 5. an anti-slip interlayer.
Detailed Description
The technical solution of the present invention will be described clearly and completely with reference to the accompanying drawings, and obviously, the described embodiments are some, but not all embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Furthermore, the technical features mentioned in the different embodiments of the invention described below can be combined with each other as long as they do not conflict with each other.
The embodiment provides a specific implementation manner of an impact type pile machine strut aligning installation tool, as shown in fig. 1, including: annular holder 1, annular holder 1 has the clamping part of two arc structures, and the one end of two arc clamping parts is connected through pivot 2, and the other end disconnection of two arc clamping parts.
As shown in fig. 1, two supporting members 3 and two clamping members 4 are vertically connected to the outer wall of the annular clamping member 1, and the outer surfaces of the supporting members 3 and the clamping members 4 are provided with anti-slip threads.
As shown in fig. 1, two of the supporting members 3 are spaced around the outer wall of the annular clamping member 1; the two clamping pieces 4 are respectively connected to the mutually disconnected ends of the two arc-shaped clamping parts of the annular clamping piece 1, and the two clamping pieces 4 are arranged at an angle.
As shown in fig. 2, the method further includes: and the anti-slip interlayer 5 is arranged on the inner side wall of the annular clamping piece 1.
The anti-slip interlayer 5 may be an anti-slip thread provided on the inner side wall of the annular clamping member 1.
The anti-slip interlayer 5 can also be anti-slip rubber connected to the inner side wall of the annular clamping piece 1, and the anti-slip rubber is connected with the inner side wall of the annular clamping piece 1 through a fastening piece.
As shown in fig. 3, the two supporting members 3 are respectively disposed at pi/4 radians on both sides of the rotating shaft 2.
As shown in fig. 3, the angle between the two clamping pieces 4 is 10 ° ± 5 °.
Application method
In use, as shown in figure 4, the two arcuate clamping portions of the annular clamping member 1 are spread apart, fitted over the struts from the sides and then clamped.
As shown in fig. 3, the two clamping members 4 can be clamped by a clamping ring tool to improve the clamping force of the annular clamping member 1 on the stay bar. The supporting piece 3 and the clamping piece 4 are used for supporting the mouth of the pile foundation casing so as to prevent the support rod from falling; then, the worker can prevent the rotation of the stay bar at the time of aligning by holding the support 3, thereby quickly completing the aligning installation of the stay bar.
It should be understood that the above examples are only for clarity of illustration and are not intended to limit the embodiments. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. And obvious variations or modifications therefrom are within the scope of the invention.

Claims (10)

1. Impact stake machine vaulting pole is to mouthful mounting tool, its characterized in that includes:
the annular clamping piece (1) is provided with two clamping parts with arc structures, one ends of the two arc clamping parts are connected through a rotating shaft (2), and the other ends of the two arc clamping parts are disconnected;
the supporting pieces (3) are vertically connected to the outer wall of the annular clamping piece (1), and a plurality of supporting pieces are arranged around the outer wall of the annular clamping piece (1) at intervals;
and the two clamping pieces (4) are respectively and vertically connected to one disconnected end of the two arc-shaped clamping parts of the annular clamping piece (1), and the two clamping pieces (4) are arranged at an angle.
2. The impact type pile machine strut aligning installation tool of claim 1, further comprising: and the anti-skidding interlayer (5) is arranged on the inner side wall of the annular clamping piece (1).
3. The impact type pile machine stay rod aligning installation tool according to claim 2, characterized in that the anti-slip interlayer (5) is an anti-slip thread provided on the inner side wall of the annular clamping member (1).
4. The impact type pile machine stay rod aligning installation tool according to claim 2, characterized in that the anti-slip interlayer (5) is anti-slip rubber connected to the inner side wall of the annular clamping member (1).
5. The impact type pile machine support rod aligning installation tool according to claim 4, wherein the anti-skid rubber is connected with the inner side wall of the annular clamping piece (1) through a fastening piece.
6. The impact type pile machine strut aligning installation tool according to any one of claims 1 to 5, characterized in that the support members (3) have two, which are respectively arranged at pi/4 radians at both sides of the rotating shaft (2).
7. The tool for installing a strut of an impact type pile machine in a mouth-to-mouth manner according to any one of claims 1 to 5, characterized in that the angle between the two clamping pieces (4) is 10 ° ± 5 °.
8. The tool for installing the stay rod of the impact type pile machine in the opposite direction of the stay rod of the impact type pile machine according to claim 6, wherein the angle between the two clamping pieces (4) is 10 ° ± 5.
9. The impact type pile machine stay rod aligning installation tool according to claim 7, characterized in that the outer surface of the support member (3) and/or the clamping member (4) is provided with anti-skid threads.
10. The impact type pile machine stay rod aligning installation tool according to claim 8, characterized in that the outer surface of the support member (3) and/or the clamping member (4) is provided with anti-skid threads.
CN202021184438.7U 2020-06-23 2020-06-23 Impact type pile machine support rod aligning installation tool Active CN212683790U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021184438.7U CN212683790U (en) 2020-06-23 2020-06-23 Impact type pile machine support rod aligning installation tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021184438.7U CN212683790U (en) 2020-06-23 2020-06-23 Impact type pile machine support rod aligning installation tool

Publications (1)

Publication Number Publication Date
CN212683790U true CN212683790U (en) 2021-03-12

Family

ID=74894119

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021184438.7U Active CN212683790U (en) 2020-06-23 2020-06-23 Impact type pile machine support rod aligning installation tool

Country Status (1)

Country Link
CN (1) CN212683790U (en)

Similar Documents

Publication Publication Date Title
CN204040435U (en) High-altitude steel structure welding Hanging Basket
CN212683790U (en) Impact type pile machine support rod aligning installation tool
CN211398817U (en) Protective device for engineering pipeline construction
CN108016984A (en) A kind of mechanical splice building pipeline lifting fixator
JP4662881B2 (en) Insulated operation rod support structure
JP6338308B1 (en) Support
CN211342954U (en) Water stop hanging device
CN214062336U (en) Building construction template reinforcing and opposite-pulling device
CN211899768U (en) Safety rope suspension member
JP6223874B2 (en) Lifting device and method of attaching and removing pole using the same
CN214656985U (en) Anti-drop joint follow-up protective sleeve
JP6152411B1 (en) Single pipe connection mechanism in scaffold and scaffold comprising the same
JP2017020181A (en) Suspending foothold extension method and extended suspending foothold
CN213085411U (en) Pipe jacking device for movable lifting working platform
CN215658786U (en) Clamp holder for butt joint of steel casing
CN216006664U (en) Public road bridge roof beam construction bracket convenient to it is fixed
CN214479056U (en) Movable combined type telescopic cable support
CN218320426U (en) Hose protection device for jacking mechanism of tower crane
CN216042679U (en) Unsettled pipeline mounting tool
CN215595046U (en) Device for safety protection of door and window opening
JPH08158359A (en) Connecting method for steel pipe pile
CN216408139U (en) Assembled piping lane antidetonation support
CN217618544U (en) Standard top cap assembly clamp
CN214832977U (en) Efficient dismounting device for maintenance of grab bucket of excavator
JPH0813775A (en) Narrow space construction method for external finishing panel and device thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant