Prior art keywords
plate
support column
locating
picture peg
steel construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020836489.7U
Other languages
Chinese (zh)
Inventor
李承�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Dayu Engineering Construction Co ltd
Original Assignee
Beijing Dayu Engineering Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Dayu Engineering Construction Co ltd filed Critical Beijing Dayu Engineering Construction Co ltd
Priority to CN202020836489.7U priority Critical patent/CN212656374U/en
Application granted granted Critical
Publication of CN212656374U publication Critical patent/CN212656374U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a building steel construction that intensity is high, including the support column, the quantity of support column is two, and two support column bilateral symmetry settings, the fixed plate has all been welded to the upper and lower both sides of support column inner chamber, the slot has transversely been seted up to the inside of fixed plate, it has the picture peg to peg graft in the inside of slot. The utility model discloses a fix the inside rethread first locating pin of picture peg disect insertion fixed plate, and the cardboard card is in the inboard of picture peg, be connected with first locating plate and second locating plate at the opposite side, can install a supporting beam between two second locating plates, can strengthen the connection structure intensity between the mutual picture peg, can not produce deformation, further improvement steel construction joint strength and the fastness each other, it is lower to have solved the in-process mounting structure intensity at in-service use simultaneously, can cause the whole problem that takes place deformation of steel construction in the long-time use.

Description

Building steel construction that intensity is high
Technical Field
The utility model relates to a steel construction technical field specifically is a building steel construction that intensity is high.
Background
Compared with the traditional concrete building, the steel structure building has the advantages that the steel plate or the profile steel replaces the reinforced concrete, the strength is higher, the earthquake resistance is better, the components can be manufactured in a factory mode, the site installation is realized, the construction period is greatly reduced, the steel can be repeatedly used, the construction waste can be greatly reduced, the environment is more environment-friendly, the components are widely adopted by countries in the world, the components are applied to industrial buildings and civil buildings, the installation structure strength of the construction steel structure is lower in the actual use process, the deformation of the steel structure can be caused in the long-time use process, and the potential safety hazard is increased.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building steel construction that intensity is high possesses the high advantage of connection structure intensity, and it is lower to have solved at in-process mounting structure intensity of in-service use, can cause the whole problem that takes place deformation of steel construction in the long-time use.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a building steel construction that intensity is high, includes the support column, the quantity of support column is two, and two support column bilateral symmetry sets up, the fixed plate has all been welded to the upper and lower both sides of support column inner chamber, the slot has transversely been seted up in the inside of fixed plate, it has the picture peg to peg graft in the inside of slot, the equal joint in one side both ends that the picture peg is close to each other has the cardboard, there is first locating plate in the outside of cardboard through first bolt fixed mounting, there is the second locating plate in the outside of first locating plate through second bolt fixed mounting, there is a supporting beam one side welding of second locating plate, a supporting beam's front is provided with.
Preferably, the two ends of the cross rod are fixedly provided with sleeves, and the sleeves are positioned on the surface of the support beam and connected through the positioning rods.
Preferably, the front surface of the fixing plate is provided with a first positioning hole, and a first positioning pin penetrates through the first positioning hole and extends to the outside of the inserting plate.
Preferably, the front surface of the clamping plate is provided with a second positioning hole, a second positioning pin penetrates through the inside of the second positioning hole, and one end of the second positioning pin extends to the inside of the inserting plate.
Preferably, the outer side of the supporting column is provided with a mounting hole, and the mounting hole is connected with an external fixed beam.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. the utility model discloses a fix the inside rethread first locating pin of picture peg disect insertion fixed plate, and the cardboard card is in the inboard of picture peg, be connected with first locating plate and second locating plate at the opposite side, can install a supporting beam between two second locating plates, can strengthen the connection structure intensity between the mutual picture peg, can not produce deformation, further improvement steel construction joint strength and the fastness each other, it is lower to have solved the in-process mounting structure intensity at in-service use simultaneously, can cause the whole problem that takes place deformation of steel construction in the long-time use.
2. The utility model discloses an increase sleeve pipe and horizontal pole on a supporting beam's surface, not only can support between two supporting beams, can also increase joint strength, the sleeve pipe can be adjusted as required in a supporting beam surface's position moreover, increases the barrier propterty of steel construction.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a front view of the fixing plate structure of the present invention;
figure 3 is a side view of the clamping plate structure of the present invention.
In the figure: 1. a support pillar; 2. a fixing plate; 3. a slot; 4. inserting plates; 5. clamping a plate; 6. a first positioning plate; 7. a second positioning plate; 8. a support beam; 9. a cross bar; 10. a sleeve; 11. a first positioning hole; 12. and a second positioning hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description herein, it is to be understood that the terms "center," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like are used in the orientations and positional relationships indicated in the drawings to facilitate the description of the patent and to simplify the description, but do not indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and thus are not to be considered limiting of the patent. In the description of the present application, it should be noted that unless otherwise explicitly stated or limited, the terms "mounted," "connected," and "disposed" are to be construed broadly and can, for example, be fixedly connected, disposed, detachably connected, disposed, or integrally connected and disposed. The specific meaning of the above terms in this patent may be understood by those of ordinary skill in the art as appropriate.
Referring to fig. 1-3, a high-strength building steel structure comprises support columns 1, wherein two support columns 1 are provided at the outer sides of the support columns 1, the mounting holes are connected with external fixed beams, the two support columns 1 are arranged in bilateral symmetry, fixed plates 2 are welded at the upper and lower sides of the inner cavity of each support column 1, a first positioning hole 11 is formed in the front surface of each fixed plate 2, a first positioning pin penetrates through the first positioning hole 11 and extends to the outer part of an insert plate 4, a slot 3 is transversely formed in the inner part of each fixed plate 2, an insert plate 4 is inserted into the slot 3, clamp plates 5 are clamped at the two ends of the adjacent sides of the insert plates 4, a second positioning hole 12 is formed in the front surface of each clamp plate 5, a second positioning pin penetrates through the inner part of the second positioning hole 12, one end of the second positioning pin extends to the inner part of the insert plate 4, a first positioning plate 6 is fixedly mounted at the outer sides, the outer side of the first positioning plate 6 is fixedly provided with a second positioning plate 7 through a second bolt, one side of the second positioning plate 7 is welded with a support beam 8, the surface of the support beam 8 is additionally provided with a sleeve 10 and a cross rod 9, so that not only can the two support beams 8 be supported, but also the connection strength can be increased, the position of the sleeve 10 on the surface of the support beam 8 can be adjusted according to needs, the protection performance of a steel structure is improved, the front surface of the support beam 8 is provided with the cross rod 9, both ends of the cross rod 9 are fixedly provided with the sleeve 10, the sleeve 10 is positioned on the surface of the support beam 8 and is connected through a positioning rod, the inserting plate 4 is directly inserted into the fixing plate 2 and is fixed through a first positioning pin, the clamping plate 5 is clamped on the inner side of the inserting plate 4, the other side of the inserting plate is connected with the first positioning, can strengthen the connection structure intensity between the mutual picture peg 4, can not produce deformation, further improvement the mutual connection intensity and the fastness of steel construction, it is lower to have solved simultaneously at in-process mounting structure intensity of in-service use, can cause the whole problem that takes place deformation of steel construction in the long-time use.
The utility model provides an all parts are the parts that general standard spare or technical staff in the field know, its structure and principle all are this technical staff all can learn through the technical manual or learn through conventional experimental method, the standard part that uses in this application file all can purchase from the market simultaneously, each part can all be customized according to the record of description and attached drawing in this application file, the concrete joining mode of each part all adopts conventional means such as ripe bolt in the prior art, rivets, welding, machinery, part and equipment all adopt conventional model in the prior art, no longer make specific statement here.
During the use, fix through the inside rethread first locating pin with picture peg 4 disect insertion fixed plate 2, and 5 cards of cardboard are in the inboard of picture peg 4, be connected with first locating plate 6 and second locating plate 7 at the opposite side, can install a supporting beam 8 between two second locating plates 7, can strengthen the connection structure intensity between the mutual picture peg 4, increase sleeve pipe 10 and horizontal pole 9 through the surface at a supporting beam 8, not only can support between two supporting beam 8, can also increase joint strength, can not produce deformation, further improvement the joint strength and the fastness of steel construction each other.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a building steel construction that intensity is high, includes support column (1), its characterized in that: the quantity of support column (1) is two, and two support column (1) bilateral symmetry sets up, fixed plate (2) have all been welded to the upper and lower both sides of support column (1) inner chamber, slot (3) have transversely been seted up to the inside of fixed plate (2), peg graft in the inside of slot (3) has picture peg (4), the equal joint in one side both ends that picture peg (4) are close to each other has cardboard (5), there is first locating plate (6) in the outside of cardboard (5) through first bolt fixed mounting, there is second locating plate (7) in the outside of first locating plate (6) through second bolt fixed mounting, the welding of one side of second locating plate (7) has supporting beam (8), the front of supporting beam (8) is provided with horizontal pole (9).
2. The high-strength construction steel structure according to claim 1, wherein: the two ends of the cross rod (9) are fixedly provided with sleeves (10), and the sleeves (10) are located on the surface of the supporting beam (8) and connected through positioning rods.
3. The high-strength construction steel structure according to claim 1, wherein: first locating hole (11) have been seted up in the front of fixed plate (2), the inside of first locating hole (11) is run through and is provided with first locating pin and extends to the outside of picture peg (4).
4. The high-strength construction steel structure according to claim 1, wherein: the front surface of the clamping plate (5) is provided with a second positioning hole (12), a second positioning pin penetrates through the inside of the second positioning hole (12), and one end of the second positioning pin extends to the inside of the inserting plate (4).
5. The high-strength construction steel structure according to claim 1, wherein: the mounting hole has been seted up in the outside of support column (1), and the mounting hole is connected with external fixed beam.
CN202020836489.7U 2020-05-19 2020-05-19 Building steel construction that intensity is high Expired - Fee Related CN212656374U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020836489.7U CN212656374U (en) 2020-05-19 2020-05-19 Building steel construction that intensity is high

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020836489.7U CN212656374U (en) 2020-05-19 2020-05-19 Building steel construction that intensity is high

Publications (1)

Publication Number Publication Date
CN212656374U true CN212656374U (en) 2021-03-05

Family

ID=74747192

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020836489.7U Expired - Fee Related CN212656374U (en) 2020-05-19 2020-05-19 Building steel construction that intensity is high

Country Status (1)

Country Link
CN (1) CN212656374U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113931307A (en) * 2021-10-18 2022-01-14 赣州博泰钢结构工程有限公司 Construction steel structure convenient to mount and dismount and use method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113931307A (en) * 2021-10-18 2022-01-14 赣州博泰钢结构工程有限公司 Construction steel structure convenient to mount and dismount and use method thereof

Similar Documents

Publication Publication Date Title
CN110656698B (en) Shock resistance connection structure of concrete beam column
CN209837294U (en) Assembled building steel skeleton is connected
CN212656374U (en) Building steel construction that intensity is high
CN209989942U (en) Building steel structure combination beam convenient to equipment
CN213174153U (en) Improved beam-column connecting structure for steel structure building
CN211037784U (en) Structure of encorbelmenting of building external corner
CN213868312U (en) Convenient assembled building steel construction who dismantles
CN213508914U (en) Steel structure beam column for prefabricated building
CN212001632U (en) Assembled square steel pipe column-H shaped steel roof beam connected node
CN209538483U (en) The mounting structure of energy-saving curtain wall
CN214657731U (en) Novel steel structure support connection structure
CN205296397U (en) Huge node field weld construction platform of box steel truss polylinker
CN218988626U (en) Tower crane attachment structure
CN217175896U (en) Crossbeam reinforcing apparatus for building structure
CN216156797U (en) Reinforced structure for steel structure connection
CN220486727U (en) Connection structure of steel structure post and steel structure roof beam
CN212866835U (en) Mounting member for building construction
CN210828056U (en) Steel construction crossbeam convenient to installation
CN210976068U (en) Connecting joint of precast concrete frame beam column
CN212897179U (en) Improved steel structure supporting beam
CN212956955U (en) Be applied to green assembled light steel house of new rural construction
CN212001583U (en) Steel structure roof structure
CN217601705U (en) High strength building steel structure
CN211973861U (en) Connecting component for assembled steel structure building
CN215053914U (en) Right-angle column splicing structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210305

Termination date: 20210519