CN212612916U - Module brick formula inspection pit shaft concrete placement device - Google Patents

Module brick formula inspection pit shaft concrete placement device Download PDF

Info

Publication number
CN212612916U
CN212612916U CN202021337337.9U CN202021337337U CN212612916U CN 212612916 U CN212612916 U CN 212612916U CN 202021337337 U CN202021337337 U CN 202021337337U CN 212612916 U CN212612916 U CN 212612916U
Authority
CN
China
Prior art keywords
frame
adjusting
water conservancy
conservancy diversion
rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021337337.9U
Other languages
Chinese (zh)
Inventor
贾刚龙
王蒋皓辰
韩进军
张成贵
王深
刘杰
李鹏飞
梁少智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
China Construction Seventh Engineering Bureau Installation Engineering Co Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
China Construction Seventh Engineering Bureau Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd, China Construction Seventh Engineering Bureau Installation Engineering Co Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN202021337337.9U priority Critical patent/CN212612916U/en
Application granted granted Critical
Publication of CN212612916U publication Critical patent/CN212612916U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a module brick formula inspection pit shaft concrete placement device, the shape including water conservancy diversion frame and water conservancy diversion frame is umbelliform, and coupling mechanism wears to be equipped with on water conservancy diversion frame upper portion, and water conservancy diversion frame lower part is provided with supporting mechanism, and supporting mechanism cooperatees with the pit shaft, and coupling mechanism is connected with supporting mechanism through adjustment mechanism. The utility model discloses structural design is simple, and the installation is dismantled conveniently, and whole easy operation is swift, and the efficiency of construction is high, and is with low costs, has solved the problem that module brick class inspection pit shaft concrete easily scatters, is difficult for pouring into in the module brick in concrete placement process.

Description

Module brick formula inspection pit shaft concrete placement device
Technical Field
The utility model relates to a technical field of construction especially relates to a module brick formula inspection pit shaft concrete placement device.
Background
At present, in the process of municipal road construction, a cylinder is required to be arranged on an inspection well embedded deeply with rainwater, sewage and the like for facilitating the entering and exiting of the inspection well, an inspection shaft is generally cylindrical, and is built by module bricks and is poured with concrete, but the concrete of the module bricks of the traditional pouring inspection shaft is mostly poured by adopting a chute, and because the wall thickness of the shaft limits the general small size of the brick holes of the module bricks, the concrete is easy to spill during pouring, the concrete is not easy to pour, and the time, the labor and the materials are wasted; if the concrete pump truck is adopted, the cost is high and the method is not economical.
SUMMERY OF THE UTILITY MODEL
The method aims at the problems that the traditional pouring inspection shaft module brick concrete is poured by adopting a chute, and because the wall thickness of a shaft limits that the brick holes of the module are generally small, the concrete is easy to spill and not easy to pour, and the time, the labor and the materials are wasted; if adopt the concrete pump truck, the expense is high, uneconomic technical problem, the utility model provides a module brick formula inspection pit shaft concrete placement device.
In order to solve the above problem, the technical scheme of the utility model is so realized:
the utility model provides a module brick formula inspection pit shaft concrete placement device, is umbelliform including the shape of water conservancy diversion frame and water conservancy diversion frame, and coupling mechanism is worn to be equipped with on water conservancy diversion frame upper portion, and water conservancy diversion frame lower part is provided with supporting mechanism, and supporting mechanism cooperatees with the pit shaft, and coupling mechanism is connected with supporting mechanism through adjustment mechanism.
Preferably, coupling mechanism includes the connecting rod, and the connecting rod runs through water conservancy diversion frame and connecting rod both ends all are connected with supporting mechanism through adjustment mechanism.
Preferably, the supporting mechanism comprises a supporting frame, the supporting frame is arranged at the lower part of the diversion frame and is installed in the shaft through a reinforcing frame, and the reinforcing frame is connected with a connecting rod in the connecting mechanism through an adjusting mechanism.
Preferably, braced frame's shape is cylindrical, and the reinforcement frame includes first strengthening rod and second strengthening rod, and first strengthening rod and second strengthening rod wear to establish in braced frame and first strengthening rod and second strengthening rod are whole to be the cross form, and first strengthening rod and second strengthening rod all are connected with the connecting rod through adjustment mechanism.
Preferably, the adjusting mechanism comprises an adjusting rod, a plurality of adjusting holes are formed in the adjusting rod, and the first reinforcing rod, the second reinforcing rod and the connecting rod respectively penetrate through the corresponding adjusting holes to be connected with the adjusting fastener.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model discloses utilize the umbelliform water conservancy diversion of integral type frame to place on the pit shaft to utilize cylindrical braced frame to support the water conservancy diversion frame, utilize the anchor strut to carry out reinforcement installation on the pit shaft to braced frame, utilize the connecting rod, adjust pole and anchor strut whole and form a reinforcement system, the stability of water conservancy diversion frame concreting in-process has been improved greatly, the overall structure design is simple, the installation is dismantled conveniently, the bulk operation is simple swift, the efficiency of construction is high, low cost, the problem of module brick class inspection pit shaft concrete in concrete placement in-process easily scatter, be difficult for pouring into the module brick is solved.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a top view of fig. 1.
In the figure, 1 is a shaft, 2 is a flow guiding frame, 3 is a supporting frame, 4 is an adjusting rod, 5 is a connecting rod, 6 is a first reinforcing rod, and 7 is a second reinforcing rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without any creative effort belong to the protection scope of the present invention.
As shown in figure 1, a module brick formula inspection pit shaft concrete placement device, the shape that includes water conservancy diversion frame 2 and water conservancy diversion frame 2 is umbelliform, the diameter of water conservancy diversion frame bottom is greater than pit shaft diameter 5CM, coupling mechanism wears to be equipped with on 2 upper portions of water conservancy diversion frame, coupling mechanism includes connecting rod 5, connecting rod 5 runs through water conservancy diversion frame 2, 2 lower parts of water conservancy diversion frame are provided with supporting mechanism, and 5 both ends of connecting rod are all connected with supporting mechanism through adjustment mechanism, supporting mechanism and 1 cooperation of pit shaft utilize supporting mechanism to place the water conservancy diversion frame on the pit shaft and support, coupling mechanism is connected with supporting mechanism through adjustment mechanism.
The supporting mechanism comprises a supporting frame 3, the supporting frame 3 is cylindrical, the cylindrical supporting frame is used for providing circumferential support for the flow guide frame, the supporting frame 3 is arranged at the lower part of the flow guide frame 2, the supporting frame 3 is arranged in the shaft 1 through a reinforcing frame, and the reinforcing frame is connected with a connecting rod 5 in the connecting mechanism through an adjusting mechanism; as shown in fig. 2, the reinforcing frame includes a first reinforcing rod 6 and a second reinforcing rod 7, the first reinforcing rod 6 and the second reinforcing rod 7 are inserted into the support frame 3, the first reinforcing rod 6 and the second reinforcing rod 7 are integrally crossed, the support frame is supported on the shaft by the first reinforcing rod and the second reinforcing rod, and the first reinforcing rod 6 and the second reinforcing rod 7 are both connected with the connecting rod 5 through an adjusting mechanism.
The adjusting mechanism comprises an adjusting rod 4, a plurality of adjusting holes are formed in the adjusting rod 4, a first reinforcing rod 6, a second reinforcing rod 7 and a connecting rod 5 respectively penetrate through the corresponding adjusting holes to be connected with an adjusting fastener, a reinforcing system is integrally formed by the connecting rod, the adjusting rod and the reinforcing frame, the stability of the guide frame in the concrete pouring process is greatly improved, the adjusting rod is pushed by rotating the adjusting fastener, the connecting rod and the reinforcing frame are clamped and fixed on a shaft by the two groups of corresponding adjusting rods, the utility model discloses utilize the integral umbrella-shaped guide frame to be placed on the shaft, and utilize the cylindrical support frame to support the guide frame, the integral structure is simple in design, convenient to install and disassemble, simple and fast in integral operation, high in construction efficiency and low in cost, and the problem that the concrete of the module brick inspection shaft is easy to fall off in the concrete pouring process, Not easy to be poured into the module brick.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (5)

1. The utility model provides a module brick formula inspection pit shaft concrete placement device, its characterized in that, is umbelliform including the shape of water conservancy diversion frame (2) and water conservancy diversion frame (2), and coupling mechanism is worn to be equipped with on water conservancy diversion frame (2) upper portion, and water conservancy diversion frame (2) lower part is provided with supporting mechanism, and supporting mechanism cooperatees with pit shaft (1), and coupling mechanism is connected with supporting mechanism through adjustment mechanism.
2. The modular brick inspection shaft concrete placement device according to claim 1, characterized in that the connection means comprise a connecting rod (5), the connecting rod (5) penetrating the guide frame (2) and both ends of the connecting rod (5) being connected with the support means by means of an adjusting means.
3. The modular brick inspection shaft concrete pouring device according to claim 1 or 2, characterized in that the support means comprise a support frame (3), the support frame (3) being arranged at the lower part of the guide frame (2) and the support frame (3) being mounted in the shaft (1) by means of a reinforcement frame, which is connected with the connecting rods (5) in the connecting means by means of an adjusting means.
4. The modular brick inspection shaft concrete placement device according to claim 3, characterized in that the support frame (3) is cylindrical in shape, the reinforcement frame comprises a first reinforcement bar (6) and a second reinforcement bar (7), the first reinforcement bar (6) and the second reinforcement bar (7) are arranged in the support frame (3) in a penetrating manner, the first reinforcement bar (6) and the second reinforcement bar (7) are in a cross-like shape as a whole, and the first reinforcement bar (6) and the second reinforcement bar (7) are connected with the connecting bar (5) through an adjusting mechanism.
5. The modular brick type inspection shaft concrete pouring device according to claim 4, characterized in that the adjusting mechanism comprises an adjusting rod (4), a plurality of adjusting holes are formed on the adjusting rod (4), and the first reinforcing rod (6), the second reinforcing rod (7) and the connecting rod (5) are respectively connected with the adjusting fastener through the corresponding adjusting holes.
CN202021337337.9U 2020-07-09 2020-07-09 Module brick formula inspection pit shaft concrete placement device Active CN212612916U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021337337.9U CN212612916U (en) 2020-07-09 2020-07-09 Module brick formula inspection pit shaft concrete placement device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021337337.9U CN212612916U (en) 2020-07-09 2020-07-09 Module brick formula inspection pit shaft concrete placement device

Publications (1)

Publication Number Publication Date
CN212612916U true CN212612916U (en) 2021-02-26

Family

ID=74746116

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021337337.9U Active CN212612916U (en) 2020-07-09 2020-07-09 Module brick formula inspection pit shaft concrete placement device

Country Status (1)

Country Link
CN (1) CN212612916U (en)

Similar Documents

Publication Publication Date Title
CN205530344U (en) Utility tunnel is pour to split type no mould
CN208668596U (en) A kind of reinforced concrete girder slab system and prefabricated post assembly node
CN208586722U (en) Precast concrete assembled piping shaft
CN101885208B (en) System for manufacturing novel high-efficiency, energy-saving and environmentally-friendly centrifugal concrete pile
CN212612916U (en) Module brick formula inspection pit shaft concrete placement device
CN109356185A (en) A kind of prefabricated pier foundation of regeneration monolith and its construction method
CN209703510U (en) A kind of template system suitable for the ring-like foundation pile of major diameter manually digging hole
CN208280038U (en) A kind of arch culvert template system
CN109972657A (en) Overall assembled steel reinforced concrete pipe gallery is contained in stake
CN110130271A (en) A kind of construction method of side wall concrete single-sided formwork reinforcement
CN211289237U (en) Mounting structure for construction machinery
CN211340484U (en) Road and bridge crack reinforced structure
CN209585109U (en) The assembled piping lane of pile wall interaction
CN209636834U (en) A kind of prefabricated pier foundation of regeneration monolith
CN209799529U (en) communication tower prefabricated base convenient for wiring
CN205576904U (en) Prestressing force high -strength concrete area stake point tubular pile
CN205348170U (en) In dig method prestressed concrete pipe pile
CN101831910B (en) Construction method of reinforced concrete flange reaming type filling pile
CN217896505U (en) Cross water concrete face flatness control device
CN218406469U (en) Reusable suspended mold supporting system
CN214194658U (en) Prefabricated concrete valve well
CN220266556U (en) Watering positioner is used in municipal construction
CN217267952U (en) Multifunctional tunnel intercepting well
CN208280005U (en) The support reinforcement structure of viaduct pier when a kind of excavation of foundation pit
CN220377344U (en) Hanging die supporting device for mixing tower fan foundation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant